CN110387884B - Construction method for preventing inrush of ultra-deep foundation pit - Google Patents

Construction method for preventing inrush of ultra-deep foundation pit Download PDF

Info

Publication number
CN110387884B
CN110387884B CN201910526968.0A CN201910526968A CN110387884B CN 110387884 B CN110387884 B CN 110387884B CN 201910526968 A CN201910526968 A CN 201910526968A CN 110387884 B CN110387884 B CN 110387884B
Authority
CN
China
Prior art keywords
reinforcing layer
foundation pit
water
layer
underground continuous
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910526968.0A
Other languages
Chinese (zh)
Other versions
CN110387884A (en
Inventor
潘伟强
曹骥
王建秀
龙冠宏
朱雁飞
裴烈烽
陈思慧
王彦杰
诸颖
魏林春
李�昊
严振祥
陈怡�
郭彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tunnel Engineering Co Ltd
Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Original Assignee
Shanghai Tunnel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Tunnel Engineering Co Ltd filed Critical Shanghai Tunnel Engineering Co Ltd
Priority to CN201910526968.0A priority Critical patent/CN110387884B/en
Publication of CN110387884A publication Critical patent/CN110387884A/en
Application granted granted Critical
Publication of CN110387884B publication Critical patent/CN110387884B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Foundations (AREA)

Abstract

The invention relates to a construction method for preventing a surge of an ultra-deep foundation pit, wherein the bottom of the foundation pit to be excavated is close to a pressure-bearing water layer, and the construction method comprises the following steps: arranging an underground continuous wall around an area of a foundation pit to be excavated; pouring a waterproof reinforcing layer at the bottom of the underground continuous wall by using MJS, wherein the periphery of the waterproof reinforcing layer is attached to the underground continuous wall; pouring a depressurization reinforcing layer at the bottom of a foundation pit to be excavated above the waterproof reinforcing layer by using MJS, wherein the periphery of the depressurization reinforcing layer is attached to the underground continuous wall; and excavating a foundation pit and correspondingly erecting a supporting structure. The method effectively solves the problem of potential surge of confined water during the excavation of the ultra-deep foundation pit, has small influence on the surrounding environment during construction, cannot cause the settlement of surrounding buildings, and can ensure the construction quality and the construction efficiency.

Description

Construction method for preventing inrush of ultra-deep foundation pit
Technical Field
The invention relates to the field of building construction, in particular to a construction method for preventing inrush of an ultra-deep foundation pit.
Background
Along with the rapid development of cities, more and more urban underground space resources are developed and utilized to meet the living needs of human beings, particularly, underground rail transit is being built in various big cities as if so, however, when ultra-deep foundation pits need to be excavated and buildings with extremely high settlement control requirements are arranged around the ultra-deep foundation pits, the process operations which can cause serious deformation of the surrounding environment of the foundation pits, such as confined water precipitation, high-pressure jet grouting reinforcement and the like, cannot be carried out, however, the maximum excavation depth of the foundation pits reaches below the confined water layer, the safety coefficient of anti-surging of the bottom of the foundation pit is very low on the premise of not adopting confined water control, the excavation cannot be carried out, and great potential safety hazards exist, so that the construction is influenced.
Disclosure of Invention
The invention aims to overcome the defects of the prior art, provides a construction method for preventing the inrush of the ultra-deep foundation pit, solves the problem of the hidden danger of confined water inrush during the excavation of the ultra-deep foundation pit, has small influence on the surrounding environment during construction, cannot cause the settlement of surrounding buildings, and can ensure the construction quality and the construction efficiency.
The technical scheme for realizing the purpose is as follows:
the invention provides a construction method for preventing a surge of an ultra-deep foundation pit, wherein the bottom of the foundation pit to be excavated is close to a pressure-bearing water layer, and the construction method comprises the following steps:
s11, arranging an underground continuous wall around an area of a foundation pit to be excavated;
s12, pouring a waterproof reinforcing layer at the bottom of the underground continuous wall by using the MJS, wherein the periphery of the waterproof reinforcing layer is attached to the underground continuous wall;
s13, pouring a depressurization reinforcing layer at the bottom of the foundation pit to be excavated above the waterproof reinforcing layer by using MJS, wherein the periphery of the depressurization reinforcing layer is attached to the underground continuous wall;
s14, excavating a foundation pit and correspondingly erecting a supporting structure.
The invention adopts the construction method for preventing the inrush of the ultra-deep foundation pit to construct the ultra-deep foundation pit, and the underground continuous wall is arranged in the area to be excavated, and a pressure reduction reinforcing layer and a water-proof reinforcing layer are respectively arranged between the underground continuous walls and at the position close to the bottom of the foundation pit and the position at the bottom of the underground continuous walls, so that the pressure reduction reinforcing layer can offset the bearing force of the confined water to increase gravity to prevent the confined water from gushing suddenly, the waterproof reinforcing layer can form a waterproof curtain at the bottom of the underground continuous wall to form second protection, the water quantity between the waterproof reinforcing layer and the pressure reduction reinforcing layer can be controlled, further excavating the foundation pit to avoid confined water inrush in the excavation process, effectively solving the problem of confined water inrush hidden danger in the ultra-deep foundation pit excavation, and the influence on the surrounding environment is small during construction, the settlement of surrounding buildings cannot be caused, and the construction quality and the construction efficiency can be ensured.
The construction method for preventing the inrush current of the ultra-deep foundation pit is further improved in that when the waterproof reinforcing layer is poured, the construction method further comprises the following steps:
and pouring the bottom of the waterproof reinforcing layer to a position below the bottom of the underground continuous wall, wherein the part of the waterproof reinforcing layer lower than the underground continuous wall supports the bottom of the underground continuous wall.
The invention further improves the construction method for preventing the inrush of the ultra-deep foundation pit, and before forming the waterproof reinforcing layer by using MJS, the construction method also comprises the following steps:
calculating the bottom elevation of the waterproof reinforcing layer according to the set depth of the foundation pit to be excavated and the elevation position of the pressure-bearing water layer, wherein the calculation formula is as follows:
Σ h.gamma.s ≧ Fs.gamma.w.H, in which
h is the thickness (m) of each layer of soil between the bottom of the foundation pit and the top surface of the confined water layer,
gamma s from the bottom of the foundation pit to the top of the confined aquiferAverage weight of soil in each layer (kN/m)3),
H is the height (m) of the confined water head above the top surface of the confined aquifer,
gamma.w is the water gravity (kN/m)3) Taking 10kN/m3
And Fs is the anti-surge safety coefficient of the foundation pit, and is 1.00.
The construction method for preventing the inrush of the ultra-deep foundation pit is further improved in that when the bottom elevation of the waterproof reinforcing layer is calculated, the construction method further comprises the following steps:
the thickness of the decompression reinforcing layer is 3m, and the thickness of the waterproof reinforcing layer is 10 m.
The construction method for preventing the inrush of the ultra-deep foundation pit is further improved in that when the bottom elevation of the waterproof reinforcing layer is calculated, the construction method further comprises the following steps:
calculating the water jacking force of the pressure-bearing water layer,
Pw=(-H3+H4)*γw*Fs=(-H3+H4)*10.0*1.0;
calculating the soil layer pressure between the bottom of the foundation pit and the top surface of the confined water layer,
Ps=∑hi×γsi=(-H2+H1)*γs1+(H2-H3)*γs2
wherein H1 is the elevation of the bottom of the foundation pit,
h2 is the bottom elevation of the reduced pressure reinforcement layer,
h3 is the bottom elevation of the water-blocking reinforcing layer,
h4 is the initial water level elevation of the pressure water layer,
gammas 1 is the weight of the reduced-pressure reinforcement layer,
γ s2 is the gravity of the soil layer.
The construction method for preventing the inrush of the ultra-deep foundation pit is further improved in that gamma s in a pressure calculation formula from the bottom of the foundation pit to the top surface of the pressure-bearing water layer1Take 20kN/m3,γs2Take 19.4kN/m3
Expanding to obtain Ps 3 × 20+ (H2-H3) × 19.4;
and 3 × 20+ (H2-H3) × 19.4 ≧ (-H3+ H4) × 10.0 × 1.0 is used for obtaining the value range of H3 so as to determine the bottom elevation of the water-resisting reinforcing layer.
The construction method for preventing the inrush of the ultra-deep foundation pit is further improved in that before the foundation pit is excavated, the construction method further comprises the following steps:
and (3) drilling a dewatering well leading to the space between the depressurization reinforcing layer and the water-resisting reinforcing layer, extracting the confined water between the depressurization reinforcing layer and the water-resisting reinforcing layer by using the dewatering well, and observing the change condition of the water level of the confined water between the depressurization reinforcing layer and the water-resisting reinforcing layer, thereby inspecting the water-resisting effect of the depressurization reinforcing layer and the water-resisting reinforcing layer.
The construction method for preventing the inrush of the ultra-deep foundation pit is further improved in that when the foundation pit is provided with the supporting structure, the method further comprises the following steps:
and sequentially erecting inner supports inside the foundation pit along with the excavation depth of the foundation pit so as to reinforce two side walls of the foundation pit.
The construction method for preventing the inrush of the ultra-deep foundation pit is further improved in that the MJS is an omnibearing high-pressure jet grouting method.
Drawings
FIG. 1 is a flow chart of the construction method for preventing the inrush current in the ultra-deep foundation pit according to the invention.
FIG. 2 is a schematic view of foundation pit reinforcement in the construction method for preventing the inrush current in the ultra-deep foundation pit according to the present invention.
FIG. 3 is a schematic diagram of the foundation pit position corresponding to the confined water layer in the construction method for preventing the inrush of the ultra-deep foundation pit according to the present invention.
Detailed Description
The invention is further described with reference to the following figures and specific examples.
Referring to fig. 1, the present invention provides a construction method for preventing a gush of an ultra-deep foundation pit, by installing an underground diaphragm wall in an area to be excavated, and a pressure reduction reinforcing layer and a water-proof reinforcing layer are respectively arranged between the underground continuous walls and at the position close to the bottom of the foundation pit and the position at the bottom of the underground continuous walls, so that the pressure reduction reinforcing layer can offset the bearing force of the confined water to increase gravity to prevent the confined water from gushing suddenly, the waterproof reinforcing layer can form a waterproof curtain at the bottom of the underground continuous wall to form second protection, the water quantity between the waterproof reinforcing layer and the pressure reduction reinforcing layer can be controlled, further excavating the foundation pit to avoid confined water inrush in the excavation process, effectively solving the problem of confined water inrush hidden danger in the ultra-deep foundation pit excavation, and the influence on the surrounding environment is small during construction, the settlement of surrounding buildings cannot be caused, and the construction quality and the construction efficiency can be ensured. The construction method for preventing the inrush current of the ultra-deep foundation pit according to the present invention will be described with reference to the accompanying drawings.
Referring to fig. 1, fig. 1 is a flowchart of a construction method for preventing a sudden inrush of an ultra-deep foundation pit according to the present invention. The construction method for preventing the inrush current in the ultra-deep foundation pit according to the present invention will be described with reference to fig. 1.
As shown in fig. 1, 2 and 3, the construction method for preventing the inrush of the ultra-deep foundation pit of the present invention, the bottom of the foundation pit 11 to be excavated is close to the confined water layer 21, and the construction method includes the following steps:
s11, arranging an underground continuous wall 112 around the area of the foundation pit 11 to be excavated; then, step S12 is executed
Step S12, pouring a waterproof reinforcing layer 13 at the bottom position of the underground continuous wall 112 by using MJS, and attaching the periphery of the waterproof reinforcing layer 13 to the underground continuous wall 112; then, step S13 is executed
Step S13, utilizing MJS to pour a pressure reduction reinforcing layer 12 at the bottom of the foundation pit 11 to be excavated above the waterproof reinforcing layer 13, and the periphery of the pressure reduction reinforcing layer 12 is attached to the underground continuous wall 112; then, step S14 is executed
And S14, excavating the foundation pit 11 and correspondingly erecting a supporting structure.
The waterproof reinforcing layer 13 can block the bottom of the underground continuous wall 112 to prevent pressure-bearing water from entering a space between the waterproof reinforcing layer 13 and the underground continuous wall 112, the content and pressure of the pressure-bearing water in the space can be better controlled to prevent the pressure-bearing water from excessively flowing into the space between the underground continuous walls 112, the depressurization reinforcing layer 12 is poured at the bottom of the foundation pit 11 to be excavated, the pressure above the pressure-bearing water is increased by the depressurization reinforcing layer 12 to compensate the pressure of the excavated soil of the foundation pit 11 after excavation, and the pressure-bearing water can be pressed to prevent the pressure-bearing water from suddenly flowing to break the bottom of the foundation pit 11; the soil layer is located between the waterproof reinforcing layer 13 and the depressurization reinforcing layer 12, the surrounding of the underground continuous wall 112, the waterproof reinforcing layer 13 and the depressurization reinforcing layer 12 prevents the communication between the soil layer and the pressure-bearing water layer between the waterproof reinforcing layer 13 and the depressurization reinforcing layer 12, and avoids the situation that the groundwater in the pressure-bearing water layer counts into the soil layer and the pressure-bearing water layer between the waterproof reinforcing layer 13 and the depressurization reinforcing layer 12, so that the water content in the soil layer between the waterproof reinforcing layer 13 and the depressurization reinforcing layer 12 is ensured to be constant, the pressure of the depressurization reinforcing layer 12 is lower, the linkage effect of the waterproof reinforcing layer 13 and the depressurization reinforcing layer 12 is realized, the pressure of the pressure-bearing water is controlled more accurately, the bottom of the foundation pit 11 is ensured not to gush suddenly, and the stability of the main structure can be ensured.
Specifically, when pouring water proof back up coat 13, still include: the bottom of the waterproof reinforcing layer 13 is poured to a position below the underground continuous wall 112, and the part of the waterproof reinforcing layer 13 lower than the underground continuous wall 112 supports the bottom of the underground continuous wall 112, so that the bottom of the underground continuous wall 112 can be blocked, and the confined water is prevented from flowing between the depressurization reinforcing layer 12 and the waterproof reinforcing layer 13 to a large extent.
Preferably, the MJS is an all-around high-pressure jet grouting method, and the method has small influence on surrounding main body structures and can effectively prevent ground settlement.
As a preferred embodiment of the present invention, before forming the water-blocking reinforcing layer 13 using MJS, the method further includes:
calculating the bottom elevation of the waterproof reinforcing layer 13 according to the set depth of the foundation pit 11 to be excavated and the elevation position of the pressure-bearing water layer 21, wherein the calculation formula is as follows:
Σ h.gamma.s ≧ Fs.gamma.w.H, in which
h is the thickness (m) of each layer of soil between the bottom of the foundation pit and the top surface of the confined water layer,
gamma s is the average gravity (kN/m) of each layer of soil between the bottom of the foundation pit and the top surface of the confined aquifer3),
H is the height (m) of the confined water head above the top surface of the confined aquifer,
gamma.w is the water gravity (kN/m)3) Taking 10kN/m3
And Fs is the anti-surge safety coefficient of the foundation pit, and is 1.00.
Preferably, when calculating the bottom elevation of the water-resisting reinforcing layer 13, the method further includes:
the thickness of the decompression reinforcing layer is 3m, and the thickness of the waterproof reinforcing layer is 10 m.
Further, when calculating the bottom elevation of the water-resisting reinforcing layer 13, the method further includes:
calculating the water jacking force of the pressure-bearing water layer 21,
Pw=(-H3+H4)*γw*Fs=(-H3+H4)*10.0*1.0;
calculating the soil layer pressure between the bottom of the foundation pit 11 and the top surface of the confined water layer 21,
Ps=∑hi×γsi=(-H2+H1)*γs1+(H2-H3)*γs2
wherein H1 is the elevation of the bottom of the foundation pit,
h2 is the bottom elevation of the reduced pressure reinforcement layer,
h3 is the bottom elevation of the water-blocking reinforcing layer,
h4 is the initial water level elevation of the pressure water layer,
gammas 1 is the weight of the reduced-pressure reinforcement layer,
γ s2 is the gravity of the soil layer.
Specifically, gamma s in the pressure calculation formula from the bottom of the foundation pit to the top surface of the confined water layer1Take 20kN/m3,γs2Take 19.4kN/m3And (-H2+ H1) the thickness of the decompression reinforcing layer is 3 m;
expanding to obtain Ps 3 × 20+ (H2-H3) × 19.4;
3X 20+ (H2-H3) 19.4 ≧ -H3+ H4) 10.0X 1.0,
the H2 is known data, H1+3 is known data, H4 is also known data, a value range of H3 can be obtained through an inequality, and a proper numerical value is selected to determine the bottom elevation of the waterproof reinforcing layer.
Further, before excavating foundation ditch 11, still include:
and (2) constructing a dewatering well leading to the space between the depressurization reinforcing layer 12 and the water-resisting reinforcing layer 13, extracting the confined water between the depressurization reinforcing layer 12 and the water-resisting reinforcing layer 13 by using the dewatering well, and observing the change condition of the water level of the confined water between the depressurization reinforcing layer 12 and the water-resisting reinforcing layer 13, so that the water-resisting effect of the depressurization reinforcing layer 12 and the water-resisting reinforcing layer 13 is tested, the construction safety is further ensured, and the condition that the settlement threat to the peripheral buildings cannot be caused can be ensured.
Further, when erecting bearing structure to foundation ditch 11, still include:
multiple horizontal inner supports 111 are sequentially erected inside the foundation pit 11 along with the excavation depth of the foundation pit 11 to reinforce two side walls of the foundation pit 11, so that influence on surrounding buildings due to collapse inside the foundation pit 11 is prevented.
The specific embodiment of the invention is as follows:
taking the barrier removing wells on two sides of a rail transit station as an example, a foundation pit to be constructed is a barrier removing well, the peripheral building of the foundation pit is the station, so that the requirement on ground settlement is extremely high, the settlement range is not more than 2mm and not more than 5mm, the elevation of the top surface of a pressure-bearing water layer of a construction area is-23.92 to-26.31 m, the deepest excavation depth of the foundation pit reaches 23.6m and is very close to the pressure-bearing water layer, and according to field geological exploration data and water exploration feedback, the pressure-bearing water lowering depth needs to reach 13.6m to meet the safety requirement of foundation pit excavation, and four foundation pits need to be excavated in the project;
calculating the bottom elevation of the waterproof reinforcing layer according to the condition that the sigma H & gamma s is more than or equal to Fs & gamma w & H, wherein the thickness of the waterproof reinforcing layer is 10m, the thickness of the pressure reduction reinforcing layer is 3m, and the influence of the confined water in the first confined water layer 211, the second confined water layer 212 and the partition layer 213 in the confined water layer 21 is considered simultaneously during calculation;
for the second confined water layer 212, the water pressure is Pw (-H3+ H4) × 10.0 × 1.0, where H4 has an actual value of-1.50 m, so Pw (-H3-1.50) × 10.0 × 1.0 and the soil pressure is Ps ∑ Hi×γsiBased on actual H1, H2-H1 +3 and the site ground level of 3.79m, H3 and the actual installed depth are calculated as 3 × 20+ (H2-H3) × 19.4, in meters as shown in the following table:
Figure GDA0003208379930000061
Figure GDA0003208379930000071
aiming at the first pressure-bearing water layer 211, the elevation of the first pressure-bearing water layer 211 is-24.58 m, and the water pressure is
Pw is (24.58-1.50). times.10.0. times.1.0 is 230.80kPa, and the soil pressure is shown in the above table
1#:Ps=∑hi×γsi=3*20+(24.58-22.047)*19.4=109.14kPa,
2#:Ps=∑hi×γsi=3*20+(24.58-22.363)*19.4=103.01kPa,
3#:Ps=∑hi×γsi=3*20+(24.58-22.271)*19.4=104.79kPa,
4#:Ps=∑hi×γsi=3*20+(24.58-22.096)*19.4=108.19kPa,
The depth of the water level of the confined water layer needing to be reduced is obtained through calculation, and is shown in the following table:
Figure GDA0003208379930000072
according to the data, the absolute elevation of the top surface of the confined water in the confined water layer is determined to be-36 m to-37 m and then reach a balance point, and the elevation of the ground on site is +3.79m, so that the depth of the bottom of the waterproof reinforcing layer needs to reach 40.384m to 41.016m, namely about 2m to 3m below the underground continuous wall;
the bottom of the underground continuous wall 112 is positioned above the bottom of the second confined water layer 212, so that the confined water layer 21 cannot be completely cut off, the water-proof reinforcing layer 13 covers the bottom of the underground continuous wall 112 to seal the bottom of the underground continuous wall 112, so that confined water cannot permeate from the lower part of the underground continuous wall 112, according to the calculated data, the top of the water-proof reinforcing layer 13 is arranged at a position 4m above the bottom of the underground continuous wall 112, the bottom of the water-proof reinforcing layer 13 is arranged at a position 1-4m below the bottom of the underground continuous wall 112, the depressurization reinforcing layer 12 is poured to a position 3m below the bottom of the foundation pit 11 from the bottom of the foundation pit 11 to be excavated, and the depressurization reinforcing layer 12 and the water-proof reinforcing layer 13 are sprayed by adopting a phi 2000mmMJS construction method;
constructing a precipitation well in the range of an interlayer formed by the depressurization reinforcing layer 12 and the water-resisting reinforcing layer 13 to verify the confined water-resisting effect, respectively arranging a precipitation well at two angular points of each foundation pit 11, and verifying the water-resisting effect of the water-resisting reinforcing layer through water pumping quantity;
the water suction pump is utilized to pump water and observe the height of the water surface of the confined water, and the water level observation time interval is as follows: 1 ', 5', 10 ', 15', 20 ', 25', 30 ', 40', 50 ', 60', 90 'and 120', observing once every 30min later, observing once every 60min after 480 ', observing once every 2h after 1200', stopping pumping water after the water level is stable, observing and recovering the water level after stopping, carrying out the same pumping test at time intervals, detecting the high precision and the high density of the water level by adopting an automatic water level collector, and adjusting in time when the flow change observed twice before and after and exceeds +/-5%;
after the surface of the confined water reaches the design requirement, a foundation pit 11 is excavated, an inner support 111 is arranged inside the foundation pit 11, and the inner collapse of the foundation pit 11 is prevented from affecting the stability of surrounding buildings.
While the present invention has been described in detail and with reference to the embodiments thereof as illustrated in the accompanying drawings, it will be apparent to one skilled in the art that various changes and modifications can be made therein. Therefore, certain details of the embodiments are not to be interpreted as limiting, and the scope of the invention is to be determined by the appended claims.

Claims (7)

1. A construction method for preventing sudden surge of an ultra-deep foundation pit is characterized in that the bottom of the foundation pit to be excavated is close to a pressure-bearing water layer, and the construction method comprises the following steps:
s11, arranging an underground continuous wall around the area of the foundation pit to be excavated;
s12, pouring a waterproof reinforcing layer at the bottom of the underground continuous wall by using MJS, pouring the bottom of the waterproof reinforcing layer to a position below the bottom of the underground continuous wall, wherein the part of the waterproof reinforcing layer lower than the underground continuous wall supports the bottom of the underground continuous wall, so that confined water is prevented from entering a space between the waterproof reinforcing layer and the underground continuous wall, and the peripheral edge of the waterproof reinforcing layer is attached to the underground continuous wall;
s13, pouring a depressurization reinforcing layer at the bottom of the foundation pit to be excavated above the waterproof reinforcing layer by using MJS, attaching the periphery of the depressurization reinforcing layer to the underground continuous wall, drilling a dewatering well leading to the depressurization reinforcing layer and the waterproof reinforcing layer, extracting confined water between the depressurization reinforcing layer and the waterproof reinforcing layer by using the dewatering well, and observing the change condition of the water level of the confined water between the depressurization reinforcing layer and the waterproof reinforcing layer, thereby inspecting the waterproof effect of the depressurization reinforcing layer and the waterproof reinforcing layer;
s14, excavating the foundation pit and correspondingly erecting a supporting structure.
2. The construction method for preventing the inrush current in the ultra-deep foundation pit according to claim 1, wherein before the forming of the water-blocking reinforcing layer using the MJS, the construction method further comprises:
calculating the bottom elevation of the waterproof reinforcing layer according to the set depth of the foundation pit to be excavated and the elevation position of the pressure-bearing water layer, wherein the calculation formula is as follows:
Σ h.gamma.s ≧ Fs.gamma.w.H, in which
h is the thickness (m) of each layer of soil between the bottom of the foundation pit and the top surface of the confined water layer;
gamma s is the average gravity (kN/m) of each layer of soil between the bottom of the foundation pit and the top surface of the confined aquifer3);
H is the height (m) of the confined water head above the top surface of the confined aquifer;
gamma.w is the water gravity (kN/m)3) Taking 10kN/m3
And Fs is the anti-surge safety coefficient of the foundation pit, and is 1.00.
3. The construction method for preventing the inrush current in the ultra-deep foundation pit according to claim 2, wherein when calculating the bottom elevation of the water-blocking reinforcing layer, the method further comprises:
the thickness of setting step-down reinforcing layer is 3m, sets up the thickness of water proof reinforcing layer is 10 m.
4. The construction method for preventing the inrush current in the ultra-deep foundation pit according to claim 3, wherein when calculating the bottom elevation of the water-blocking reinforcing layer, the method further comprises:
calculating the water jacking force of the pressure-bearing water layer,
Pw=(-H3+H4)*γw*Fs=(-H3+H4)*10.0*1.0;
calculating the soil layer pressure between the bottom of the foundation pit and the top surface of the confined water layer,
Ps=∑hi×γsi=(-H2+H1)*γs1+(H2-H3)*γs2
wherein H1 is foundation pit bottom elevation, H2 is depressurization reinforcing layer's bottom elevation, H3 is water proof reinforcing layer's bottom elevation, H4 is confined water layer initial water level elevation, gammas1For reducing the severity of the reinforcing layer,. gamma.s2Is the heavy soil layer.
5. The method as claimed in claim 4, wherein γ s is calculated by pressure between the bottom of the pit and the top of the pressurized water layer1Take 20kN/m3,γs2Take 19.4kN/m3
Expanding to obtain Ps 3 × 20+ (H2-H3) × 19.4;
and 3 × 20+ (H2-H3) × 19.4 ≧ (-H3+ H4) × 10.0 × 1.0 is used for obtaining the value range of H3 so as to determine the bottom elevation of the water-resisting reinforcing layer.
6. The construction method for preventing the inrush current in the ultra-deep foundation pit according to claim 1, further comprising, when the supporting structure is erected for the foundation pit:
and sequentially erecting inner supports inside the foundation pit along with the excavation depth of the foundation pit so as to reinforce two side walls of the foundation pit.
7. The construction method for preventing the inrush of the ultra-deep foundation pit as set forth in claim 1, wherein the MJS is an all-around high-pressure jet grouting method.
CN201910526968.0A 2019-06-18 2019-06-18 Construction method for preventing inrush of ultra-deep foundation pit Active CN110387884B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910526968.0A CN110387884B (en) 2019-06-18 2019-06-18 Construction method for preventing inrush of ultra-deep foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910526968.0A CN110387884B (en) 2019-06-18 2019-06-18 Construction method for preventing inrush of ultra-deep foundation pit

Publications (2)

Publication Number Publication Date
CN110387884A CN110387884A (en) 2019-10-29
CN110387884B true CN110387884B (en) 2021-11-19

Family

ID=68285805

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910526968.0A Active CN110387884B (en) 2019-06-18 2019-06-18 Construction method for preventing inrush of ultra-deep foundation pit

Country Status (1)

Country Link
CN (1) CN110387884B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112081176B (en) * 2020-09-11 2022-02-01 北京住总集团有限责任公司 Pressure-bearing water layer vertical shaft construction method based on non-dewatering drainage
CN112554216A (en) * 2020-11-08 2021-03-26 上海市隧道工程轨道交通设计研究院 Construction method for carrying out horizontal partition treatment on confined water in foundation pit engineering
CN112609707A (en) * 2020-12-09 2021-04-06 中铁二十局集团第六工程有限公司 Foundation pit leakage water treatment method
CN112832278A (en) * 2020-12-30 2021-05-25 中铁二十局集团第一工程有限公司 Foundation pit, water-resisting structure and construction method thereof
CN112813985B (en) * 2021-01-04 2023-03-17 上海市机械施工集团有限公司 Shallow gas protection method for foundation pit
CN113235612A (en) * 2021-05-17 2021-08-10 中铁二十四局集团有限公司 Deep foundation pit supporting construction method for soft soil foundation high-pressure-bearing water environment adjacent to high-speed rail

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094431A (en) * 2009-12-14 2011-06-15 上海市基础工程有限公司 Horizontal plugging construction method for subway station construction confined water
CN103122635A (en) * 2013-01-30 2013-05-29 上海市政工程设计研究总院(集团)有限公司 Foundation pit confined water resistant system and uprush stability judging method thereof
CN105155564A (en) * 2015-08-07 2015-12-16 中建三局第二建设工程有限责任公司 Anti-inrushing construction method for weak water-resisting layer of deep foundation pit
CN206368368U (en) * 2016-12-06 2017-08-01 上海浦东建筑设计研究院有限公司 A kind of supporting construction suitable for non-closed foundation ditch
CN109137949A (en) * 2018-09-06 2019-01-04 中铁第勘察设计院集团有限公司 Deep soft stratum combined type foundation pit Water outburst treatment construction and method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094431A (en) * 2009-12-14 2011-06-15 上海市基础工程有限公司 Horizontal plugging construction method for subway station construction confined water
CN103122635A (en) * 2013-01-30 2013-05-29 上海市政工程设计研究总院(集团)有限公司 Foundation pit confined water resistant system and uprush stability judging method thereof
CN105155564A (en) * 2015-08-07 2015-12-16 中建三局第二建设工程有限责任公司 Anti-inrushing construction method for weak water-resisting layer of deep foundation pit
CN206368368U (en) * 2016-12-06 2017-08-01 上海浦东建筑设计研究院有限公司 A kind of supporting construction suitable for non-closed foundation ditch
CN109137949A (en) * 2018-09-06 2019-01-04 中铁第勘察设计院集团有限公司 Deep soft stratum combined type foundation pit Water outburst treatment construction and method

Also Published As

Publication number Publication date
CN110387884A (en) 2019-10-29

Similar Documents

Publication Publication Date Title
CN110387884B (en) Construction method for preventing inrush of ultra-deep foundation pit
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN104831762B (en) Deep basal pit artesian water precipitation dynamic monitoring system and monitoring method
CN108457285B (en) Ultra-deep pit-in-pit open type dewatering construction method
CN109322330A (en) A kind of light and dark digging combination Metro Station Structure avoiding housing demolition and its construction method
CN104032760A (en) Foundation pit construction tube well dewatering method
CN104676110A (en) On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit
CN108612117A (en) A kind of seabed water-retaining structure across municipal tunnel greatly and construction method
CN101560770A (en) Novel deep building foundation pit supporting system
CN104404974A (en) High-pressure-bearing water and thick sand and pebble formation deep foundation pit grouting bottom-sealing structure and construction technology thereof
CN106436788A (en) Foundation reinforcement and inclination correction method for friction piles of high-rise building
CN110093941A (en) Deep foundation pit precipitation construction method
CN107964971B (en) A kind of precipitation method of the subway station using the construction of PBA engineering method
CN106436717A (en) Impervious curtain river-near foundation pit adopting dewatering wells and design method
CN205999897U (en) A kind of seepage proof curtain using dewatering well borders on the river foundation ditch
CN108153988B (en) Method for determining design parameters of deep horizontal water-stop curtain of foundation pit of strongly permeable stratum
CN209760299U (en) light and shade of avoiding house to tear open and move is dug and is combined subway station structure
CN116378752A (en) Automatic water draining and pressure reducing device and method for karst tunnel large karst cave under heavy rainfall condition
WO2018188529A1 (en) Covering earth balancing and safe receiving method for large-diameter tunnel boring machine
CN112854268B (en) Construction method for jacking and dewatering frame bridge in karst area and geological exploration and treatment method
CN212405161U (en) Foundation pit supporting system
CN211257900U (en) Control structure of confined water in existing basement storey-adding construction
CN204435321U (en) A kind of steam power station water intaking open channel
CN203475453U (en) Deeply-buried type bearing platform curtain structure of bridge
CN111851548A (en) Dewatering inclined shaft in deep foundation pit and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20221109

Address after: No. 1099, No. 5, Wan Ping Nan Road, Xuhui District, Shanghai

Patentee after: SHANGHAI TUNNEL ENGINEERING Co.,Ltd.

Patentee after: SHANGHAI TUNNEL ENGINEERING & RAIL TRANSIT DESIGN AND Research Institute

Address before: No. 1099, No. 5, Wan Ping Nan Road, Xuhui District, Shanghai

Patentee before: SHANGHAI TUNNEL ENGINEERING Co.,Ltd.

TR01 Transfer of patent right