CN110385562A CN201811318265.0A CN201811318265A CN110385562A CN 110385562 A CN110385562 A CN 110385562A CN 201811318265 A CN201811318265 A CN 201811318265A CN 110385562 A CN110385562 A CN 110385562A
Authority
CN
China
Prior art keywords
spray box
nozzle
outer panel
processing method
nozzle plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811318265.0A
Other languages
Chinese (zh)
Other versions
CN110385562B (en
Inventor
杨有进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Simac Engineering (china) Co Ltd
Original Assignee
Simac Engineering (china) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Simac Engineering (china) Co Ltd filed Critical Simac Engineering (china) Co Ltd
Priority to CN201811318265.0A priority Critical patent/CN110385562B/en
Publication of CN110385562A publication Critical patent/CN110385562A/en
Application granted granted Critical
Publication of CN110385562B publication Critical patent/CN110385562B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Metal Rolling (AREA)
  • Coating With Molten Metal (AREA)

Abstract

The invention discloses a kind of preheating sections, whole cold section of spray box processing method, comprising: material processing is produced nozzle plate, two outer panels and back shroud by selection material;Multiple nozzle plates are installed to form multiple nozzles using mounting plate;First time welding is carried out after the nozzle plate and outer panel are assembled, welding process pushes down nozzle plate using counterweight, and the outer panel is fixed on the mounting plate;By back shroud assembly rear end position on outer panel;Weld outer panel and nozzle plate again, using from it is intermediate forward, the welding manner at rear both ends carry out, until being welded into preheating section spray box or eventually cold section of spray box.The present invention not only can control the precision and welding deformation of components, but also reduce the scale error of components, it is ensured that the equipment precision under mass production environment, this method repeatability is strong, can preferably improve manufacturing speed while ensuring quality.

Description

Preheating section, eventually cold section of spray box processing method
Technical field
The present invention relates to a kind of machining manufacture of spray box more particularly to a kind of cold rolling vertical type continuous annealing units and galvanized machine Group annealing furnace preheating section, eventually cold section of spray box processing method.
Background technique
Cold rolling vertical type continuous annealing unit and galvanizing unit annealing furnace preheating section spray box and whole cold section of spray box are that the important of unit sets Standby, the flatness and openings of sizes of nozzle are directly related to preheating speed and the cooling velocity of strip.The length of spray box is longer, all 10m or more is reached, the flatness and welding deformation of nozzle are difficult to control.Spray box height is low, using usual manner weld joint on inner side It can not weld.
Therefore, how to design that a kind of preheating section that can solve above-mentioned technical problem, cold section of spray box production method is this eventually The project that inventor concentrates on studies.
Summary of the invention
The purpose of the present invention is to provide a kind of preheating sections, whole cold section of spray box processing method, both can control components Precision and welding deformation, and reduce the scale error of components, it is ensured that the equipment precision under mass production environment, the party Method repeatability is strong, can preferably improve manufacturing speed while ensuring quality.
To achieve the goals above, the present invention provides a kind of preheating section, eventually cold section of spray box processing method comprising following step It is rapid:
(1) material is selected, nozzle plate, two outer panels and back shroud are produced into material processing;
(2) multiple nozzle plates are installed to form multiple nozzles using mounting plate;
(3) first time welding is carried out after assembling the nozzle plate and outer panel, welding process pushes down nozzle plate using counterweight, And the outer panel is fixed on the mounting plate;
(4) by back shroud assembly rear end position on outer panel;
(5) outer panel and nozzle plate are welded again, using from it is intermediate forward, the welding manner at rear both ends carry out, until being welded into Preheat spray box or eventually cold spray box.
Preferably, the material in the step (1) uses Yuanping City's plate.
Preferably, material is processed nozzle plate material, two outer panels using laser cutting, drilling by the step (1) And back shroud.
Preferably, in the nozzle plate material being cut at pre- flanging position spray twice bending line, in flanging according to The bending line carries out flanging, forms nozzle plate.
Preferably, the flanging angle of the nozzle plate is detected using angular mould, and flanging angle guarantees single-nozzle The width error of plate is ± 0.5mm.
Preferably, the mounting plate in the step (2) makes according to the difference of height of each nozzle, and in mounting plate On amplify sample, i.e., crossed on mounting plate according to the size of spray box, mark assembly center line, the nozzle position of spray box Set line and outside printed line.
Preferably, when assembling the nozzle plate and outer panel, specific steps include:
A, the mounting plate is surveyed and is put down, make to be placed on the spray formed between each two neighboring nozzle plate on mounting plate The flatness of mouth position is≤2mm;
B, the position setting between adjacent two pieces of nozzle plates can control the control block of nozzle width;
C, according to the requirement for height of the nozzle, height adjusting block is added respectively in the two sides for being close to the control block, with adjustment Existing ladder height is poor between nozzle;
D, increase in the two sides of the outside printed line for the block against outer panel.
Preferably, in the step (3), first to outer panel and each nozzle plate after the nozzle plate and outer panel have assembled Between weld joint on inner side welded.
Preferably, the step (5) welds outer panel and nozzle plate by the way of welding simultaneously along the right and left.
Preferably, the spray box is pushed down using clump weight or fashioned iron in the whole welding process.
After adopting the above scheme, preheating section of the present invention, whole cold section of spray box processing method are designed by above-mentioned procedure of processing, by The long, accuracy of manufacture in the length of cold rolling vertical type continuous annealing unit and galvanizing unit annealing furnace preheating section spray box and whole cold section of spray box It is required that it is high, and all using thin plate box structure, without any type steel support, therefore the present invention uses laser in the blanking of components Blanking, molding, improve dimension control, welding procedure, assembly technology etc., both can control the essence of components Degree and welding deformation, and reduce the scale error of components, it is ensured that the equipment precision under mass production environment.The processing side Method repeatability is strong, while ensuring quality, can preferably improve manufacturing speed.
Detailed description of the invention
Fig. 1 is cold rolling vertical type continuous annealing unit of the present invention and galvanizing unit annealing furnace preheating section spray box forward sight structural schematic diagram;
Fig. 2 is cold rolling vertical type continuous annealing unit of the present invention and galvanizing unit annealing furnace preheating section spray box overlooking structure diagram;
Fig. 3 is the A-A of Fig. 2 to schematic cross-sectional view;
Before Fig. 4 is cold rolling vertical type continuous annealing unit of the present invention and the mounting plate of galvanizing unit annealing furnace preheating section spray box process Depending on structural schematic diagram;
Fig. 5 bows for the mounting plate of cold rolling vertical type continuous annealing unit of the present invention and galvanizing unit annealing furnace preheating section spray box process Depending on structural schematic diagram;
Fig. 6 is cold rolling vertical type continuous annealing unit of the present invention and galvanizing unit annealing furnace cold section of spray box forward sight structural schematic diagram eventually;
Fig. 7 is cold rolling vertical type continuous annealing unit of the present invention and galvanizing unit annealing furnace cold section of spray box overlooking structure diagram eventually.
Specific embodiment
The present invention is illustrated below according to attached drawing illustrated embodiment.This time disclosed embodiment can consider in all sides Face is to illustrate, without limitation.The scope of the present invention is not illustrated to be limited by following implementation, only by claims Shown in range, and including having all deformations in the same meaning and scope of the claims with scope of the claims.
Preheating section, eventually cold section of spray box processing method of the present invention are illustrated combined with specific embodiments below.
Shown in referring to figs. 1 to Fig. 3, cold rolling vertical type continuous annealing unit and galvanizing unit annealing furnace preheating section spray box processing of the present invention Method includes the following steps:
(1) material is selected, because the inherent strain of Yuanping City's plate is less than roll bending, in order to reduce stress deformation, therefore material selection is former Plate, using laser cutting, drilling processes multiple nozzle plate materials, two outer panels 1 and back shroud 2 for material, using sharp Light cutting stock precision is high, and can be very good to guarantee the degree of deformation of blanking, provides good elder generation for assembly and subsequent welding Precondition sprays twice bending line in each nozzle plate material being cut into, why sprays bending in advance at pre- flanging position Line is because former flat thin is easily deformed, it is difficult to control size, in order to guarantee the flanging compact dimensions precision of nozzle plate 3, roll over When side according to bending line carry out flanging, formed nozzle plate 3, it is ensured that flanging molding when, control errors ± 0.5mm with It is interior, guarantee in a large amount of flanging process, to provide the molding of high quality, the flanging angle of nozzle plate 3 uses angular mould It is detected, reinforcing rib 8 is welded on each nozzle plate 3;
(2) in order to ensure assembly precision, multiple nozzle plates 3 is installed together to form multiple nozzles 4 using mounting plate 5, are adopted The scale error of components can be cut down with the assembly that mounting plate 5 carries out spray box.Because there are differences in height for the size of nozzle 4, and Back shroud 2 is plate.We have designed and produced mounting plate 5(according to the difference of height of nozzle 4 and have seen Fig. 4, Fig. 5 institute according to this configuration Show).And sample is amplified on mounting plate 5, i.e., it is crossed on mounting plate 5 according to the size of spray box, marks spray box Assembly center line, nozzle location line and outside printed line.In assembling nozzle plate 3 and outer panel 1, specific steps include:
A, mounting plate 5 is surveyed and is put down, make to be placed on 4, nozzle formed between each two neighboring nozzle plate 3 on mounting plate 5 The flatness set is≤2mm;
B, in order to guarantee the size of nozzle 4 and the spacing of two nozzles 4, the position setting between adjacent two pieces of nozzle plates 3 can To control the control block 6 of 4 width of nozzle;
C, according to the requirement for height of nozzle 4, height adjusting block 7 is added respectively in the two sides for being close to control block 6, to adjust nozzle 4 Between existing ladder height it is poor;
D, the two sides of printed line increase for the block against outer panel 1 on the outside, prevent 1 positioning of outer panel or deformation;
(3) first time welding is carried out after assembling nozzle plate 3 and outer panel 1, welding process pushes down nozzle plate 3 using counterweight, And outer panel 1 is fixed on mounting plate 5, because spray box height is very low, only 350mm height, so in nozzle plate 3 and outer Side plate 1 first welds the weld joint on inner side between outer panel 1 and each nozzle plate 3 after having assembled, because spray box is symmetrical structure, The weld seam on both sides is symmetrical, if made by the way of directly welding in production, will lead to spray box plane after molding can not Reach requirement, and the flatness of nozzle 4 is overproof, therefore used in welding and be symmetrically welded progress, and control welding direction, It can be very good to guarantee welding quality;
(4) by the assembly of back shroud 2 rear end position on outer panel 1;
(5) outer panel 1 and nozzle plate 3 are welded again, because spray box is longer, length reaches 10m or more, and two sides are shunk in order to prevent Inconsistent, using being symmetrically welded, i.e., spray box two sides carry out welding using two workers simultaneously, and from it is intermediate forward, rear both ends weld The mode of connecing carries out, until being welded into preheating spray box.
Spray box is pushed down by progress using clump weight or fashioned iron in the whole welding process.
By above-mentioned steps, cold rolling vertical type continuous annealing unit and galvanizing unit annealing furnace preheating spray box is made.
With reference to shown in Fig. 6 and Fig. 7, cold rolling vertical type continuous annealing unit and galvanizing unit annealing furnace of the present invention cold section of spray box processing eventually Method, most of step is identical as the step of preheating spray box processing method described in above-mentioned Fig. 1 to Fig. 3, and something in common is no longer superfluous State, be a difference in that: spacing of the present invention eventually between the nozzle of cold section of spray box is bigger than the spacing between preheating section nozzle, weld seam Length is longer.
Cold rolling vertical type continuous annealing unit and galvanizing unit annealing furnace preheating section spray box processing method of the present invention, cold section of spray box adds eventually Work method is designed by above-mentioned procedure of processing, due to cold rolling vertical type continuous annealing unit and galvanizing unit annealing furnace preheating section spray box and end The length of cold section of spray box is long, the accuracy of manufacture require it is high, and all using thin plate box structure, without any type steel support, because This present invention uses laser blanking, molding in the blanking of components, to the side such as dimension control, welding procedure, assembly technology Face is improved, and not only can control the precision and welding deformation of components, but also reduces the scale error of components, it is ensured that batch Measure the equipment precision under working condition.Processing method repeatability is strong, while ensuring quality, can preferably improve system Make speed.
Those skilled in the art after considering the specification and implementing the invention disclosed here, will readily occur to of the invention its Its embodiment.This application is intended to cover any variations, uses, or adaptations of the invention, these modifications, purposes or Person's adaptive change follows general principle of the invention and including undocumented common knowledge in the art or usual Technological means.The description and examples are only to be considered as illustrative, and true scope and spirit of the invention are pointed out by claim.
It should be understood that the invention is not limited to the embodiment method, the structures that are described above, and in the accompanying drawings The precision architecture shown, and various modifications and changes may be made without departing from the scope thereof.The scope of the present invention is only by appended Claim limit.

Claims (10)

1. a kind of preheating section, eventually cold section of spray box processing method, which comprises the steps of:
(1) material is selected, nozzle plate, two outer panels and back shroud are produced into material processing;
(2) multiple nozzle plates are installed to form multiple nozzles using mounting plate;
(3) first time welding is carried out after assembling the nozzle plate and outer panel, welding process pushes down nozzle plate using counterweight, And the outer panel is fixed on the mounting plate;
(4) by back shroud assembly rear end position on outer panel;
(5) outer panel and nozzle plate are welded again, using from it is intermediate forward, the welding manner at rear both ends carry out, until being welded into Preheating section spray box or eventually cold section of spray box.
2. preheating section according to claim 1, eventually cold section of spray box processing method, which is characterized in that in the step (1) Material uses Yuanping City's plate.
3. preheating section according to claim 2, eventually cold section of spray box processing method, which is characterized in that the step (1) uses Laser cutting, drilling processes nozzle plate material, two outer panels and back shroud for material.
4. preheating section according to claim 3, eventually cold section of spray box processing method, which is characterized in that in the nozzle being cut into Twice bending line is sprayed on plate material at pre- flanging position, carries out flanging according to the bending line in flanging, forms nozzle plate.
5. preheating section according to claim 4, eventually cold section of spray box processing method, which is characterized in that the folding of the nozzle plate Corner degree is detected using angular mould, and flanging angle guarantees that the width error of single-nozzle plate is ± 0.5mm.
6. preheating section according to claim 1, eventually cold section of spray box processing method, which is characterized in that in the step (2) Mounting plate makes according to the difference of height of each nozzle, and sample is amplified on mounting plate, i.e., the root on mounting plate It crosses according to the size of spray box, marks the assembly center line, nozzle location line and outside printed line of spray box.
7. preheating section according to claim 6, eventually cold section of spray box processing method, which is characterized in that assembling the nozzle When plate and outer panel, specific steps include:
A, the mounting plate is surveyed and is put down, make to be placed on the spray formed between each two neighboring nozzle plate on mounting plate The flatness of mouth position is≤2mm;
B, the position setting between adjacent two pieces of nozzle plates can control the control block of nozzle width;
C, according to the requirement for height of the nozzle, height adjusting block is added respectively in the two sides for being close to the control block, with adjustment Existing ladder height is poor between nozzle;
D, increase in the two sides of the outside printed line for the block against outer panel.
8. preheating section according to claim 1, eventually cold section of spray box processing method, which is characterized in that in the step (3), First the weld joint on inner side between outer panel and each nozzle plate is welded after the nozzle plate and outer panel have assembled.
9. preheating section according to claim 1, eventually cold section of spray box processing method, which is characterized in that the step (5) uses The mode welded simultaneously along the right and left welds outer panel and nozzle plate.
10. preheating section according to claim 1, eventually cold section of spray box processing method, which is characterized in that in entire welding process It is middle to be pushed down the spray box using clump weight or fashioned iron.
CN201811318265.0A 2018-11-07 2018-11-07 Preheating section and final cooling section spray box processing method Active CN110385562B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811318265.0A CN110385562B (en) 2018-11-07 2018-11-07 Preheating section and final cooling section spray box processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811318265.0A CN110385562B (en) 2018-11-07 2018-11-07 Preheating section and final cooling section spray box processing method

Publications (2)

Publication Number Publication Date
CN110385562A true CN110385562A (en) 2019-10-29
CN110385562B CN110385562B (en) 2021-07-16

Family

ID=68284859

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811318265.0A Active CN110385562B (en) 2018-11-07 2018-11-07 Preheating section and final cooling section spray box processing method

Country Status (1)

Country Link
CN (1) CN110385562B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004217979A (en) * 2003-01-14 2004-08-05 Nippon Steel Corp Forcible convection type cooling method for steel strip in continuous type heat treatment facility and its apparatus
CN2866518Y (en) * 2006-01-18 2007-02-07 宝山钢铁股份有限公司 Fast cooling spraying box capable of suppressing strap steel vibration for continuous annealing
CN201250280Y (en) * 2008-08-14 2009-06-03 宝山钢铁股份有限公司 Hot galvanizing aerosol cooling spray box
CN101643833A (en) * 2009-08-20 2010-02-10 中冶南方(武汉)威仕工业炉有限公司 Method for manufacturing rapid cooling spray box of annealing furnace of cold rolling vertical type continuous annealing machine set
CN201873735U (en) * 2010-11-24 2011-06-22 佛山市高明基业冷轧钢板有限公司 Unit with functions of continuous hot galvanizing and continuous annealing
CN104651599A (en) * 2015-03-17 2015-05-27 中冶南方(武汉)威仕工业炉有限公司 Spray box device for inhibiting vibration of strip steel in gas cooling process
CN105074020A (en) * 2013-02-25 2015-11-18 杰富意钢铁株式会社 Continuous annealing device and continuous hot-dip galvanising device for steel strip

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004217979A (en) * 2003-01-14 2004-08-05 Nippon Steel Corp Forcible convection type cooling method for steel strip in continuous type heat treatment facility and its apparatus
CN2866518Y (en) * 2006-01-18 2007-02-07 宝山钢铁股份有限公司 Fast cooling spraying box capable of suppressing strap steel vibration for continuous annealing
CN201250280Y (en) * 2008-08-14 2009-06-03 宝山钢铁股份有限公司 Hot galvanizing aerosol cooling spray box
CN101643833A (en) * 2009-08-20 2010-02-10 中冶南方(武汉)威仕工业炉有限公司 Method for manufacturing rapid cooling spray box of annealing furnace of cold rolling vertical type continuous annealing machine set
CN201873735U (en) * 2010-11-24 2011-06-22 佛山市高明基业冷轧钢板有限公司 Unit with functions of continuous hot galvanizing and continuous annealing
CN105074020A (en) * 2013-02-25 2015-11-18 杰富意钢铁株式会社 Continuous annealing device and continuous hot-dip galvanising device for steel strip
CN104651599A (en) * 2015-03-17 2015-05-27 中冶南方(武汉)威仕工业炉有限公司 Spray box device for inhibiting vibration of strip steel in gas cooling process

Also Published As

Publication number Publication date
CN110385562B (en) 2021-07-16

Similar Documents

Publication Publication Date Title
CN101524804B (en) Steel member manufacturing method
KR101810607B1 (en) Tubular beam with single center leg
US6770840B2 (en) Method of butt-welding hot-rolled steel materials by laser beam and apparatus therefor
CN102896480A (en) Manufacture method for double-curve H-shaped steel
CN109131566B (en) Lapping structure of automobile cross beam and longitudinal beam and welding method of cross beam and longitudinal beam
US3199174A (en) Method of eliminating buckling deformation of beams
JP4702166B2 (en) Method and apparatus for cooling shape steel
CN104175014A (en) Accurate welding forming device and precise machining method for large thin-walled member
AU734139B2 (en) Method of butt-welding hot-rolled steel materials by laser beam and apparatus therefor
KR20020079311A (en) T-shaped sections and method for producing said t-shaped section
CN110385562A (en) Preheating section, eventually cold section of spray box processing method
CN113084343A (en) Elevator composite panel welding device and method
TW202113089A (en) Rectangular steel pipe and method for manufacturing same, and building structure
JP4858411B2 (en) Steel cooling method
KR101064173B1 (en) Cooling device of T-shaped steel hot rolling line, T-steel manufacturing equipment, and manufacturing method
CN114101391B (en) Orthopedic method for large-size low-rigidity piece for spaceflight and liquid rocket
CN101300087B (en) Steel plate for welding
CN104827241A (en) Manufacturing method of blanks for producing steel-zirconium composite boards
JPH08174111A (en) Production of brazing panel with curved face
CN110479767A (en) A kind of straightening machine base and production method
CN111702481A (en) Traction beam assembling device and method
JP3680652B2 (en) Manufacturing method of H-section steel
JP3695289B2 (en) Parallel flange channel steel with constant outer method and manufacturing method thereof
CN212634972U (en) Continuous production line for ultra-high-strength lightweight automobile chassis longitudinal beam
JP2007260836A (en) Section steel machining method and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant