CN110331848A CN201910479560.2A CN201910479560A CN110331848A CN 110331848 A CN110331848 A CN 110331848A CN 201910479560 A CN201910479560 A CN 201910479560A CN 110331848 A CN110331848 A CN 110331848A
Authority
CN
China
Prior art keywords
platform
wall
hanger
sucker
mounting plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910479560.2A
Other languages
Chinese (zh)
Other versions
CN110331848B (en
Inventor
张旭东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Shengye Construction Project Management Co ltd
Original Assignee
SINO RISING-SUN CONSTRUCTION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SINO RISING-SUN CONSTRUCTION GROUP Co Ltd filed Critical SINO RISING-SUN CONSTRUCTION GROUP Co Ltd
Priority to CN201910479560.2A priority Critical patent/CN110331848B/en
Publication of CN110331848A publication Critical patent/CN110331848A/en
Application granted granted Critical
Publication of CN110331848B publication Critical patent/CN110331848B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/001Safety or protective measures against falling down relating to scaffoldings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
  • Emergency Lowering Means (AREA)

Abstract

The invention discloses a kind of high-rise building Construction of Steel Structure platforms, including platform floor, the both ends welding platform hanger of platform floor, guardrail is welded between the both ends of platform hanger, mounting plate is welded between the side and guardrail of platform floor, adsorbing mechanism is installed on mounting plate, the top of platform hanger is installed by hanging ring, rolling-up mechanism is installed in platform hanger, one end of safety rope is wound on rolling-up mechanism, the other end of safety rope is fixedly connected with the outer wall of safety belt, and the belt fastener matched is installed between the both ends of safety belt.Device is fallen in high building exterior by hanging ring, platform hanger and guardrail carry out encirclement protection to the construction space on platform floor, when construction, it is fitted tightly on high building exterior wall by adsorbing mechanism, increases adsorption capacity between operation platform and high building, avoid wind blows that operation platform is caused to shake, improve safety, safety rope avoids safety rope from dragging and trips construction personnel on platform floor, further increase safety by rolling-up mechanism automatic deploying and retracting.

Description

A kind of high-rise building Construction of Steel Structure platform
Technical field
The present invention relates to building facility technical field, specially a kind of high-rise building Construction of Steel Structure platform.
Background technique
High-rise building is more and more with the development of the times, and it is flat that Construction of Steel Structure can usually be arranged after the completion of high building is built Platform, operation platform usually pass through on the tower crane that lifting rope is suspended at the top of high building, construct for external wall, are such as cleaned, pacified External drainpipe and light etc. are filled, current Construction of Steel Structure platform only passes through lifting rope and carries out suspension fixation, in construction, construction Platform is frequently subjected to wind blows and shakes, and is easy to bring security risk, also, can usually connect by safety rope on operation platform Connect safety belt, when construction worker by safety belt be fixed on carry out security protection, still, current safety rope is in pine always Relaxation state, safety rope easily drag on platform, are easy to be tripped by safety rope when construction personnel does not pay attention to, thus it is proposed that a kind of high Building construction steel structure operation platform is for solving the above problems.
Summary of the invention
The purpose of the present invention is to provide a kind of high-rise building Construction of Steel Structure platforms, to solve to mention in above-mentioned background technique Out the problem of.
To achieve the above object, the invention provides the following technical scheme: a kind of high-rise building Construction of Steel Structure platform, including Platform floor, the both ends of the platform floor are fixedly welded platform hanger, and guardrail is welded between the both ends of the platform hanger, described It is fixedly welded mounting plate between the side and guardrail of platform floor, adsorbing mechanism, the platform floor are installed on the mounting plate The other side and both ends respectively between guardrail and platform hanger through bolt mounting bracket, the fixed peace in the top of the platform hanger Hanging ring is filled, rolling-up mechanism is installed in the platform hanger, one end of safety rope is wound on the rolling-up mechanism, the safety rope The other end is fixedly connected with the outer wall of safety belt, and the belt fastener matched is installed between the both ends of the safety belt.
Preferably, multiple through-holes are provided on the platform floor, the platform hanger is U-shaped structure, the platform floor Both ends and platform hanger between branch put up X-type structure, the bracket between side and guardrail of the platform floor far from mounting plate At W type structure.
Preferably, the adsorbing mechanism includes fixed column, and one end of the fixed column is fixedly connected on the outside of mounting plate On wall, it is fixedly attached sealing shroud in the fixed column, turning set is taken over a job stopper rod between the sealing shroud both ends, the piston rod One end is through sealing shroud and mounting plate and handle is fixedly mounted, and is taken over a job on the piston rod in the sealing shroud by helicitic texture set Plug, the piston outer wall fit closely the inner wall of sealing shroud, and the fixed column is socketed with sucker far from one end of mounting plate, described The end face of the inside fixed connection and sealing set of sucker, and sealing shroud end face is provided with the suction hole of connection sucker inner cavity, the fixation The outer wall of column is socketed turning set by helicitic texture, and multiple operations are fixedly mounted close to one end outer wall of mounting plate in the turning set Platen is fixedly mounted in the other end of bar, the turning set.
Preferably, the sealing shroud inner cavity and piston are to match rectangular parallelepiped structure, and the sucker is pyramidal structure, and is inhaled The miner diameter end fixed connection and sealing set of disk, the bigger diameter end of the sucker run through the outer wall of fixed column, and the sealing shroud is far from sucker One end end face and fixed column outer wall between be provided with perforative venthole, multiple half chous are fixedly mounted on the end face of the platen The friction block of structure.
Preferably, the rolling-up mechanism includes accommodating groove, is provided with accommodating groove in the platform hanger, and the two of the accommodating groove Hold turning set to receive the both ends of spool, be fixedly connected with and wind one end of safety rope on the Scroll, the safety rope it is another One end runs through the inner wall of platform hanger and is fixedly connected with safety belt, and the both ends of the Scroll are socketed clockwork spring, and the both ends of clockwork spring It is respectively fixedly connected with the inner wall of Scroll outer wall and accommodating groove.
Compared with prior art, the beneficial effects of the present invention are: being provided with multiple through-holes on platform floor, platform hanger U Type structure reduces the own wt of platform floor and platform hanger, thus the lifting rope pressure of smaller operation platform, and platform floor Gap between platform hanger and railing carries out closure protection by bracket, and bracket carries out lifting support to platform floor, subtracts The bending stress that chain-wales bottom plate is subject to improves platform integral strength;When high building exterior wall is the smooth flats such as ceramic tile or glass When, operation platform is firmly adsorbed on external wall by the sucker in adsorbing mechanism, when exterior wall is the rough planes such as cement When, exterior wall is compressed by platen, the friction block of multiple semiglobes is fixedly mounted on the end face of platen, to increase platen and outer Frictional force between wall offsets windage, so that operation platform is more stable, improves safety;Safety belt bandage construction personnel's body After upper, construction personnel is protected, avoids dropping, and safety rope is both convenient for construction personnel by rolling-up mechanism automatic deploying and retracting Construction walking, and avoid safety rope from dragging and trip construction personnel on platform floor, further increase safety.
Detailed description of the invention
Fig. 1 is schematic structural view of the invention;
Fig. 2 is left view the schematic diagram of the section structure at adsorbing mechanism of the present invention;
Fig. 3 is top view cross section structural schematic diagram at rolling-up mechanism of the present invention;
Fig. 4 is main view the schematic diagram of the section structure at rolling-up mechanism of the present invention
In figure: 1 platform floor, 2 platform hangers, 3 guardrails, 4 mounting plates, 5 adsorbing mechanisms, 51 fixed columns, 52 sealing shrouds, 53 are inhaled Disk, 54 piston rods, 55 pistons, 56 suction holes, 57 turning sets, 58 operating sticks, 59 platens, 6 safety ropes, 7 rolling-up mechanisms, 71 storages Slot, 72 Scrolls, 73 clockwork springs, 8 safety belts, 9 belt fasteners, 10 hanging rings, 11 brackets.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Fig. 1-4 is please referred to, the present invention provides a kind of technical solution: a kind of high-rise building Construction of Steel Structure platform, including it is flat Platform bottom plate 1, the both ends of platform floor 1 are fixedly welded platform hanger 2, weld guardrail 3, platform floor 1 between the both ends of platform hanger 2 Side and guardrail 3 between be fixedly welded mounting plate 4, adsorbing mechanism 5, the other side of platform floor 1 and two are installed on mounting plate 4 Respectively between guardrail 3 and platform hanger 2 through bolt mounting bracket 11, the top of platform hanger 2 is fixedly mounted hanging ring 10, puts down at end Rolling-up mechanism 7 is installed in platform hanger 2, one end of safety rope 6 is wound on rolling-up mechanism 7, the other end of safety rope 6 is fixedly connected with peace The outer wall of full band 8 installs the belt fastener 9 matched between the both ends of safety belt 8.Device is fallen in high building exterior by hanging ring 10, Platform hanger 2 and guardrail 3 carry out encirclement protection to the construction space on platform floor 1, meanwhile, 1 surrounding of platform floor is led to respectively Cross mounting plate 4 and bracket 11 carry out closure protection, when construction, be fitted tightly over by adsorbing mechanism 5 ceramic tile on high building exterior wall, Glass or cement wall surface etc. increase adsorption capacity between operation platform and high building, avoid wind blows that operation platform is caused to shake, mention High security, and with 8 bandage construction personnel of safety belt after, construction personnel is protected, avoids dropping, and safety rope 6 is logical 7 automatic deploying and retracting of rolling-up mechanism is crossed, is not only constructed walking convenient for construction personnel, but also safety rope is avoided to drag to trip on platform floor 1 and apply Worker person further increases safety.
It is provided with multiple through-holes on platform floor 1, platform hanger 2 is U-shaped structure, reduces platform floor 1 and platform hanger 2 Own wt, thus the lifting rope pressure of smaller operation platform;Bracket 11 between the both ends and platform hanger 2 of platform floor 1 is at X-type Structure, the bracket 11 between side of the platform floor 1 far from mounting plate 4 and guardrail 3 is at W type structure, thus to 1 peace of platform floor Gap between platform hanger 2 and railing 3 carries out closure protection, and bracket 11 carries out lifting support to platform floor 1, reduces platform bottom The bending stress that plate 1 is subject to improves intensity.
Adsorbing mechanism 5 includes fixed column 51, and one end of fixed column 51 is fixedly connected on the lateral wall of mounting plate 4, fixed It is fixedly attached sealing shroud 52 in column 4, turning set is taken over a job stopper rod 54 between 52 both ends of sealing shroud, and one end of piston rod 54 is through sealing Simultaneously handle is fixedly mounted in set 52 and mounting plate 4, is socketed piston 55, piston by helicitic texture on the piston rod 54 in sealing shroud 52 55 outer walls fit closely the inner wall of sealing shroud 52, and fixed column 51 is socketed with sucker 53 far from one end of mounting plate 4, sucker 53 it is interior The end face of side fixed connection and sealing set 52, and 52 end face of sealing shroud is provided with the suction hole 56 of connection 53 inner cavity of sucker, fixed column 51 Outer wall pass through helicitic texture and be socketed turning set 57, multiple operations are fixedly mounted close to one end outer wall of mounting plate 4 in turning set 57 Platen 59 is fixedly mounted in the other end of bar 58, turning set 57, when high-rise outer is ceramic tile or glass, is driven by operating stick 58 Turning set 57 rotates, so that turning set 57 is mobile to mounting plate 4, sucker 53 is exposed, and sucker 53 is tightly attached on ceramic tile or glass, and Piston rod 54 is rotated by handle, so that piston 55 moves in sealing shroud 52, to draw in sucker 53 by suction hole 56 The gas of chamber, to avoid windage, terminates so that forming negative pressure in sucker 53 to be tightly fixed on high building in construction Afterwards, piston rod 54 is rotated by handle, so that piston 55 close to sucker 53, is then formed in gas indentation sucker 53 in sealing shroud 52 Positive pressure is detached from high building exterior wall convenient for sucker 53, when exterior wall is the rough planes such as cement, drives turning set by operating stick 58 57 rotations, so that turning set 57 presses to exterior wall, then platen 59 compresses exterior wall, and multiple half chous are fixedly mounted on the end face of platen 59 The friction block of structure offsets windage to increase frictional force between platen 59 and exterior wall, improves safety.
52 inner cavity of sealing shroud and piston 55 are to match rectangular parallelepiped structure, avoid piston 55 that piston rod 54 is followed to rotate;It inhales Disk 53 is pyramidal structure, and the miner diameter end fixed connection and sealing set 52 of sucker 53, the bigger diameter end of sucker 53 run through fixed column 51 Outer wall adsorbs high building exterior wall convenient for sucker 53, opens between the outer wall of one end end face and fixed column 51 of the sealing shroud 52 far from sucker 53 There is perforative venthole, so that sealing shroud 52 is connected to far from one end inner cavity of sucker 53 with ambient atmosphere, equilibrium air pressure, convenient for living Plug 55 is mobile.
Rolling-up mechanism 7 includes accommodating groove 71, and accommodating groove 71 is provided in platform hanger 2, and the both ends of accommodating groove 71 rotate socket The both ends of Scroll 72, are fixedly connected with and wind one end of safety rope 6 on Scroll 72, and the other end of safety rope 6 runs through platform The inner wall of hanger 2 is simultaneously fixedly connected with safety belt 8, and the both ends of Scroll 72 are socketed clockwork spring 73, and the both ends of clockwork spring 73 are fixed respectively The inner wall of Scroll 72 outer wall and accommodating groove 71 is connected, when construction personnel's walking is constructed, safety rope 6 is drawn out accommodating groove 71, receives Spool 72 rotates so that clockwork spring 73 puts aside elastic potential energy, and in the relaxation of safety rope 6, clockwork spring 73 drives the winding winding peace of Scroll 72 Full rope 6, so that safety rope 6 remains tension.
Working principle: the present invention is in use, fallen device in high building exterior by hanging ring 10, platform hanger 2 and guardrail 3 are right Construction space on platform floor 1 carries out encirclement protection, meanwhile, 1 surrounding of platform floor pass through respectively mounting plate 4 and bracket 11 into Row blocks protection, when high-rise outer is ceramic tile or glass, drives turning set 57 to rotate by operating stick 58, so that turning set 57 Mobile to mounting plate 4, sucker 53 is exposed, and sucker 53 is tightly attached on ceramic tile or glass, and rotates piston rod 54 by handle, so that Piston 55 moves in sealing shroud 52, so that the gas of 53 inner cavity of sucker is drawn by suction hole 56, so that being formed in sucker 53 Negative pressure is to be tightly fixed on high building, to avoid windage, after construction, rotates piston rod 54 by handle, So that piston 55 close to sucker 53, then forms positive pressure in gas indentation sucker 53 in sealing shroud 52, is detached from high building convenient for sucker 53 Exterior wall drives turning set 57 to rotate, so that turning set 57 is pressed to when exterior wall is the rough planes such as cement by operating stick 58 Exterior wall, then platen 59 compresses exterior wall, the friction block of multiple semiglobes is fixedly mounted on the end face of platen 59, to increase platen Frictional force between 59 and exterior wall offsets windage, so that operation platform is more stable, improves safety, safety belt 8 passes through belt Button 9 quickly tightens with construction personnel, and when construction personnel's walking is constructed, safety rope 6 is drawn out accommodating groove 71, and 72 turns of Scroll Dynamic so that clockwork spring 73 puts aside elastic potential energy, in the relaxation of safety rope 6, clockwork spring 73 drives the winding winding safety rope 6 of Scroll 72, makes It obtains safety rope 6 and remains tension, avoid safety rope from dragging and trip construction personnel on platform floor 1, further increase peace Quan Xing.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (5)

1. a kind of high-rise building Construction of Steel Structure platform, including platform floor (1), it is characterised in that: the platform floor (1) Both ends are fixedly welded platform hanger (2), weld guardrail (3) between the both ends of the platform hanger (2), the platform floor (1) It is fixedly welded mounting plate (4), is equipped with adsorbing mechanism (5) on the mounting plate (4), the platform bottom between side and guardrail (3) The other side and both ends of plate (1) pass through bolt mounting bracket (11), the platform between guardrail (3) and platform hanger (2) respectively Hanging ring (10) are fixedly mounted in the top of hanger (2), install rolling-up mechanism (7) in the platform hanger (2), the rolling-up mechanism (7) one end of safety rope (6) is wound on, the other end of the safety rope (6) is fixedly connected with the outer wall of safety belt (8), the peace The belt fastener (9) matched is installed between the both ends of full band (8).
2. a kind of high-rise building Construction of Steel Structure platform according to claim 1, it is characterised in that: the platform floor (1) multiple through-holes are provided on, the platform hanger (2) is U-shaped structure, the both ends of the platform floor (1) and platform hanger (2) Between bracket (11) at X-type structure, the platform floor (1) is far from the bracket (11) between the side and guardrail (3) of mounting plate (4) At W type structure.
3. a kind of high-rise building Construction of Steel Structure platform according to claim 1, it is characterised in that: the adsorbing mechanism It (5) include fixed column (51), one end of the fixed column (51) is fixedly connected on the lateral wall of mounting plate (4), the fixation It is fixedly attached sealing shroud (52) in column (4), turning set is taken over a job stopper rod (54) between sealing shroud (52) both ends, the piston rod (54) one end is through sealing shroud (52) and mounting plate (4) and handle is fixedly mounted, the piston rod in the sealing shroud (52) (54) piston (55) are socketed by helicitic texture on, piston (55) outer wall fits closely the inner wall of sealing shroud (52), described Fixed column (51) is socketed with sucker (53) far from the one end of mounting plate (4), the inside fixed connection and sealing set of the sucker (53) (52) end face, and sealing shroud (52) end face is provided with the suction hole (56) of connection sucker (53) inner cavity, the fixed column (51) Outer wall is socketed turning set (57) by helicitic texture, and one end outer wall of the turning set (57) close to mounting plate (4) is fixedly mounted Platen (59) are fixedly mounted in the other end of multiple operating sticks (58), the turning set (57).
4. a kind of high-rise building Construction of Steel Structure platform according to claim 3, it is characterised in that: the sealing shroud (52) Inner cavity and piston (55) are to match rectangular parallelepiped structure, and the sucker (53) is pyramidal structure, and the miner diameter end of sucker (53) is solid Surely sealing shroud (52) are connected, the bigger diameter end of the sucker (53) runs through the outer wall of fixed column (51), and the sealing shroud (52) is separate It is provided with perforative venthole between one end end face of sucker (53) and the outer wall of fixed column (51), consolidates on the end face of the platen (59) Dingan County fills the friction block of multiple semiglobes.
5. a kind of high-rise building Construction of Steel Structure platform according to claim 1, it is characterised in that: the rolling-up mechanism (7) include accommodating groove (71), be provided with accommodating groove (71) in the platform hanger (2), the both ends turning set of the accommodating groove (71) The both ends of spool (72) are received, are fixedly connected with and wind one end of safety rope (6), the safety rope on the Scroll (72) (6) the other end runs through the inner wall of platform hanger (2) and is fixedly connected safety belt (8), the both ends socket of the Scroll (72) Clockwork spring (73), and the both ends of clockwork spring (73) are respectively fixedly connected with the inner wall of Scroll (72) outer wall and accommodating groove (71).
CN201910479560.2A 2019-06-04 2019-06-04 High building steel construction platform Expired - Fee Related CN110331848B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910479560.2A CN110331848B (en) 2019-06-04 2019-06-04 High building steel construction platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910479560.2A CN110331848B (en) 2019-06-04 2019-06-04 High building steel construction platform

Publications (2)

Publication Number Publication Date
CN110331848A true CN110331848A (en) 2019-10-15
CN110331848B CN110331848B (en) 2021-07-02

Family

ID=68140208

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910479560.2A Expired - Fee Related CN110331848B (en) 2019-06-04 2019-06-04 High building steel construction platform

Country Status (1)

Country Link
CN (1) CN110331848B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113700282A (en) * 2020-05-21 2021-11-26 广东博智林机器人有限公司 Hanging flower basket mechanism and outer wall treatment facility
CN114837100A (en) * 2022-06-17 2022-08-02 中国一冶集团有限公司 Template installation mechanism is used in construction of bridge anticollision barrier

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005105795A (en) * 2003-10-01 2005-04-21 Yoichi Yoshida Base rope support device for curved temporary scaffolding
CN201250566Y (en) * 2008-08-28 2009-06-03 佳木斯大学 Vacuum suction cup-type windowing fixer
CN105536172A (en) * 2016-01-30 2016-05-04 国网技术学院 Falling prevention device for pole tower and safe construction method for electric pole tower
CN206873901U (en) * 2017-06-15 2018-01-12 中冶建工集团有限公司 For fixing the wall-attached device of hanging basket
CN207918373U (en) * 2018-01-09 2018-09-28 高建文 For personnel's carrying overhauling the cage of exterior wall
CN208137399U (en) * 2018-04-21 2018-11-23 温州盛瓯机电信息技术有限公司 A kind of building hanging basket

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005105795A (en) * 2003-10-01 2005-04-21 Yoichi Yoshida Base rope support device for curved temporary scaffolding
CN201250566Y (en) * 2008-08-28 2009-06-03 佳木斯大学 Vacuum suction cup-type windowing fixer
CN105536172A (en) * 2016-01-30 2016-05-04 国网技术学院 Falling prevention device for pole tower and safe construction method for electric pole tower
CN206873901U (en) * 2017-06-15 2018-01-12 中冶建工集团有限公司 For fixing the wall-attached device of hanging basket
CN207918373U (en) * 2018-01-09 2018-09-28 高建文 For personnel's carrying overhauling the cage of exterior wall
CN208137399U (en) * 2018-04-21 2018-11-23 温州盛瓯机电信息技术有限公司 A kind of building hanging basket

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113700282A (en) * 2020-05-21 2021-11-26 广东博智林机器人有限公司 Hanging flower basket mechanism and outer wall treatment facility
CN113700282B (en) * 2020-05-21 2022-12-06 广东博智林机器人有限公司 Hanging flower basket mechanism and outer wall treatment facility
CN114837100A (en) * 2022-06-17 2022-08-02 中国一冶集团有限公司 Template installation mechanism is used in construction of bridge anticollision barrier

Also Published As

Publication number Publication date
CN110331848B (en) 2021-07-02

Similar Documents

Publication Publication Date Title
CN110331848A (en) A kind of high-rise building Construction of Steel Structure platform
CN102100953B (en) Remote control type fire extinguishing apparatus for high-rise building
CN208749070U (en) Construction hanging basket
CN106422107A (en) Falling-preventing safety protection device
CN109132962A (en) The detachable self-priming anti-fall stage apparatus of the included pooling feature of curtain wall transformation
CN202506005U (en) Parachute-type descent self-rescue device
CN205419580U (en) A hoist and mount system for dismantling tower crane overlength pull rod
KR20130000893U (en) rope ladder for saving human life
CN213416063U (en) Overhead hanging basket for steel reinforcement framework
CN106139430A (en) High-rise life saving, disaster relief system
CN112049022A (en) T-shaped hogging moment tensioning and clamping hanging cage of personnel safety protection mechanism for bridge construction
CN105536164A (en) Rescue net for preventing jumping from building
CN106495066A (en) A kind of used hanging basket of construction
CN205555973U (en) Lifting device
CN2853098Y (en) High-altitude lifesaving device
CN108277972A (en) A kind of safety-type hanging basket of construction
CN106629438A (en) Pneumatic device for hanging basket
CN203154633U (en) Building
CN102600563A (en) Escape device for high buildings
CN202263311U (en) Drawbridge-type descent control device bracket
CN110224334A (en) A kind of repairing frame of electric power maintenance
CN107893618A (en) Expanded type escape window
CN201668883U (en) Building escape system
CN203158956U (en) Building for preventing ladder cage of construction lift from falling
CN203158962U (en) Anti-falling system of construction elevator

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230117

Address after: No. 135, Jiashan Avenue, Mingguang City, Chuzhou, Anhui Province 239400

Patentee after: Anhui Shengye Construction Project Management Co.,Ltd.

Address before: 239000 No. 89 Huayuan West Road, Chuzhou City, Anhui Province

Patentee before: SINO RISING-SUN CONSTRUCTION GROUP Co.,Ltd.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210702