CN110320835A - A kind of building automation distributed system and method - Google Patents
A kind of building automation distributed system and method Download PDFInfo
- Publication number
- CN110320835A CN110320835A CN201910550844.6A CN201910550844A CN110320835A CN 110320835 A CN110320835 A CN 110320835A CN 201910550844 A CN201910550844 A CN 201910550844A CN 110320835 A CN110320835 A CN 110320835A
- Authority
- CN
- China
- Prior art keywords
- linkage
- subsystem
- communication node
- automatic
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Programme-control systems
- G05B19/02—Programme-control systems electric
- G05B19/04—Programme control other than numerical control, i.e. in sequence controllers or logic controllers
- G05B19/042—Programme control other than numerical control, i.e. in sequence controllers or logic controllers using digital processors
- G05B19/0428—Safety, monitoring
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B2219/00—Program-control systems
- G05B2219/20—Pc systems
- G05B2219/24—Pc safety
- G05B2219/24024—Safety, surveillance
Abstract
The present invention relates to a kind of building automation distributed system and method, which includes: at least one set of automatic building control system;At least one communication node, each communication node are arranged in a one-to-one correspondence with every group of automatic building control system;Cloud platform is communicated to connect with each communication node.Technical solution provided by the invention, by the way that communication node, cloud platform is arranged, the automatic building control system linkage control for monitoring multiple dispersions in region is got up, both the communication interconnection between building and building had been realized, the monitoring and management of the distribution, long-range to building multiple in region are realized again, and to make the higher building automation wisdom cell of integrated level, city is laid a good foundation.
Description
Technical field
The present invention relates to field of intelligent control technology, and in particular to building automation distributed system and method.
Background technique
Automatic building control system generally comprises following system: comprehensive wiring system, telephone system, has computer network system
Line TV and satellite TV system, safety defense monitoring system, card system, broadcast notification system, automatic building control system, hotel's pipe
Reason system, Property Management System, intelligent building management system (integrated control platform) and data center machine room construction etc..
Automatic building control system can be operated with multithreading, including but not limited to: air-conditioning and Cooling and Heat Source, become distribution, send plumbing
The subsystems such as air draft, security protection, fire-fighting, illumination make the wisdom building of each subsystems linkage work.At full speed in Internet of Things development
Today, wisdom building Ethernet (wired), Internet of Things (wireless) technology for widening under, by it is trans-regional communication become possible.Often
One building automatic building control system communicates with each other to form closed loop, makes the higher building automation wisdom cell of integrated level, city.
Existing routine automatic building control system is the control system of closed loop, main with the linkage control of other building
It completes to repair by artificially adjusting, the degree of automation is not high, and human input is big, and user experience is bad.
Summary of the invention
To be overcome the problems, such as present in the relevant technologies at least to a certain extent, the present invention provides a kind of building automation distribution
Formula system and method, to solve the problems, such as that automatic building control system can not automatic linkage control in the prior art.
According to a first aspect of the embodiments of the present invention, a kind of building automation distributed system is provided, comprising:
At least one set of automatic building control system;
At least one communication node, each communication node are arranged in a one-to-one correspondence with every group of automatic building control system;
Cloud platform is communicated to connect with each communication node.
Preferably, the automatic building control system is specifically used for according to building automation strategy execution automatic operation, the automatic control
Operation includes the training of linkage scheme, and the linkage scheme training includes:
The selection linkage logic in the building automation strategy, according to automatic building control system described in the linkage logical triggering
In subsystem link, complete training;
If the training is effective, the linkage logic is sent to the cloud platform by the communication node, and,
When the cloud platform adjusts the linkage logic, the adjusted of the cloud platform transmission is received by the communication node
Dynamic logic, and updating the linkage logic in the building automation strategy is the linkage logic adjusted;And/or
If the training is invalid, linkage logic is reselected in the building automation strategy, and according to reselecting
Linkage logic execute subsequent step.
Preferably, the subsystem in the automatic building control system according to the linkage logical triggering links, complete
At training, comprising:
The testing result of the subsystem in normally open is obtained, and by testing result storage into log, wherein
Different testing results is stored into identical or different log;
If the testing result be it is abnormal, according to subsystem itself described in the linkage logical triggering and/or with the son
There are other subsystems of interaction relation to execute predetermined registration operation for system;
Predetermined registration operation is being executed, and after abnormal releasing, by predetermined registration operation process storage into log, is completing training,
Wherein, the predetermined registration operation is one or more, and if multinomial, then the predetermined registration operation process storage of different item is to identical or different
Log in.
Preferably, if every group of automatic building control system includes the subsystem of multiple and different types, the system also includes:
Multiple groups private network, the subsystem of the corresponding type of every group of private network;
Same type subsystem in different automatic building control systems accesses corresponding one group of private network.
Preferably, the cloud platform includes: multiple private servers, the corresponding one group of private network of each private server, with
Multiple automatic building control systems, which are triggered, by each private server carries out integrated linkage.
Preferably, the system, further includes:
Monitoring center, and/or, remote user access terminal is communicated to connect with the cloud platform.
Preferably,
The communication node is relay node;
The communication node is communicated to connect by base station and the cloud platform;And/or
The communication node is communicated to connect by Ethernet and the cloud platform.
Preferably, the building automatic system includes at least one subsystem, each subsystem with corresponding communication section
Point communication connection, the subsystem include at least one in following item:
Fire-fighting detection and alert sub-system, safety monitoring subsystem, environmental monitoring subsystem.
According to a second aspect of the embodiments of the present invention, a kind of building automation distributed method is provided, comprising:
Each automatic building control system receives the control instruction that cloud platform is sent by respective communication node, according to
Control instruction executes automatic operation;And/or
The result after executing automatic operation is sent to the cloud platform by respective communication node;
Wherein, the automatic building control system be at least one set, the communication node be at least one, every group of building automation system
System is arranged in a one-to-one correspondence with each communication node.
Preferably, the automatic operation, including linkage scheme are trained, and the linkage scheme training includes:
The selection linkage logic in the building automation strategy, according to automatic building control system described in the linkage logical triggering
In subsystem link, complete training;
If the training is effective, the linkage logic is sent to the cloud platform by the communication node, and,
When the cloud platform adjusts the linkage logic, the adjusted of the cloud platform transmission is received by the communication node
Dynamic logic, and updating the linkage logic in the building automation strategy is the linkage logic adjusted;And/or
If the training is invalid, linkage logic is reselected in the building automation strategy, and according to reselecting
Linkage logic execute subsequent step.
Preferably, the subsystem in the automatic building control system according to the linkage logical triggering links, complete
At training, comprising:
The testing result of the subsystem in normally open is obtained, and by testing result storage into log, wherein
Different testing results is stored into identical or different log;
If the testing result be it is abnormal, according to subsystem itself described in the linkage logical triggering and/or with the son
There are other subsystems of interaction relation to execute predetermined registration operation for system;
Predetermined registration operation is being executed, and after abnormal releasing, by predetermined registration operation process storage into log, is completing training,
Wherein, the predetermined registration operation is one or more, and if multinomial, then the predetermined registration operation process storage of different item is to identical or different
Log in.
The technical solution that the embodiment of the present invention provides can include the following benefits:
By the way that communication node, cloud platform is arranged, the automatic building control system linkage control for monitoring multiple dispersions in region is risen
Come, had not only realized the communication interconnection between building and building, but also realize distribution to building multiple in region, long-range
Monitoring and management, to make the higher building automation wisdom cell of integrated level, city is laid a good foundation.
It should be understood that above general description and following detailed description be only it is exemplary and explanatory, not
It can the limitation present invention.
Detailed description of the invention
The drawings herein are incorporated into the specification and forms part of this specification, and shows and meets implementation of the invention
Example, and be used to explain the principle of the present invention together with specification.
Fig. 1 is a kind of schematic diagram of building automation distributed system shown according to an exemplary embodiment;
Fig. 2 is a kind of schematic block diagram of automatic building control system shown according to an exemplary embodiment;
Fig. 3 is a kind of flow chart of building automation distributed method shown according to an exemplary embodiment;
Fig. 4 is a kind of flow chart of linkage scheme training method shown according to an exemplary embodiment.
Specific embodiment
Example embodiments are described in detail here, and the example is illustrated in the accompanying drawings.Following description is related to
When attached drawing, unless otherwise indicated, the same numbers in different drawings indicate the same or similar elements.Following exemplary embodiment
Described in embodiment do not represent all embodiments consistented with the present invention.On the contrary, they be only with it is such as appended
The example of device and method being described in detail in claims, some aspects of the invention are consistent.
Fig. 1 is a kind of schematic diagram of building automation distributed system shown according to an exemplary embodiment, such as Fig. 1 institute
Show, which includes:
At least one set of automatic building control system 101;
At least one communication node 102, each communication node 102 are arranged in a one-to-one correspondence with every group of automatic building control system 101;
Cloud platform 103 is communicated to connect with each communication node 102.
Preferably, the system, further includes:
Monitoring center 104, and/or, remote user access terminal 105 is communicated to connect with the cloud platform 103.
Preferably, the remote user access terminal 105 is mounted on the terminal device of user, and the terminal device includes
But it is not limited to: desktop computer, laptop, tablet computer, mobile phone etc..
It is understood that the corresponding communication node of every group of building automation subsystem, every group of building automation subsystem are logical
It crosses exclusive communication node and cloud platform and carries out data interaction.The benefit being arranged in this way is that every group of automatic building control system is all one
A independent system, the data interaction between cloud platform are not influenced by the equipment in other channels, ensure that communication quality, together
When, by communication node and cloud platform, every group of automatic building control system realizes communication interconnection again, and cloud platform can be to every group of building
Robot control system(RCS) realizes linkage control and distributed management, and user experience is good, satisfaction is high.
It is understood that technical solution provided in this embodiment, by the way that communication node, cloud platform is arranged, by monitoring section
The automatic building control system linkage control of multiple dispersions in domain is got up, and has not only realized the communication interconnection between building and building, but also real
The monitoring and management of the distribution, long-range to building multiple in region are showed, to make the higher building automation intelligence of integrated level
Intelligent cell, city are laid a good foundation.
Preferably, the communication node 102 is relay node;The communication node 102 passes through base station and the cloud platform
103 communication connections;And/or the communication node 102 is communicated to connect by Ethernet and the cloud platform 103.
It is understood that automatic building control system and cloud may be implemented by base station in technical solution provided in this embodiment
The wired connection of automatic building control system and cloud platform may be implemented by Ethernet in the wireless connection of platform.Automatic building control system
With a variety of connection types of cloud platform, the stability and reliability of system ensure that.
It should be noted that the building automatic system 101 include at least one subsystem, each subsystem with it is corresponding
Communication node 102 communicate to connect, the subsystem include in following item at least one of:
Fire-fighting detection and alert sub-system, safety monitoring subsystem, environmental monitoring subsystem.
As shown in Figure 1, apartment A, hotel B, office building C have affiliated each subsystem (for example, fire-fighting detection and alarm
Subsystem, safety monitoring subsystem, environmental monitoring subsystem etc.), by certain wireless data transmission form between each building, such as
Automatic building control system is imported cloud platform by NB-IoT networking mode access base station, and/or, it is passed by cable datas such as Ethernets
Defeated form imports cloud platform after automatic building control system is accessed network.
Preferably, every group of automatic building control system 101 may include the subsystem of multiple and different types, such as: fire-fighting detection
With alert sub-system, safety monitoring subsystem, environmental monitoring subsystem, air-conditioning and Cooling and Heat Source monitoring subsystem, discharge water monitoring
Subsystems such as subsystem, change monitoring power distribution subsystem, supply and exhaust monitoring subsystem, fire-fighting monitoring subsystem, illumination etc..
It is understood that each subsystem is communicated to connect with corresponding communication node, be conducive to get through obstructed building
Communication connection between the subsystems of robot control system(RCS), the exclusive subsystem of forming region.By to each automatic building control system
The fractionation and recombination of subsystems integrate the exclusive subsystems linkage of creation, not only ensure that the long-range monitoring of remote distributed, but also
Region control subsystem supervision is provided.
Preferably, the system also includes:
Multiple groups private network, the subsystem of the corresponding type of every group of private network;
Same type subsystem in different automatic building control systems accesses corresponding one group of private network.
Preferably, the cloud platform 103 includes: multiple private servers, the corresponding one group of private network of each private server,
Integrated linkage is carried out to trigger multiple automatic building control systems by each private server.
Referring to fig. 2, in multiple automatic building control systems in monitoring region, the subsystem of some automatic building control system can be with
It is interconnected with the subsystem of the same type of other automatic building control systems, forming region manages private network, can mention for requirement report position
For necessary information, fire-fighting detection and alert sub-system b such as fire-fighting detection and the alert sub-system a, hotel B of apartment A are write
The subsystems such as the fire-fighting detection of word building C and alert sub-system c interconnection, to realize that the fire-fighting to each automatic building control system detects
With the linkage control of alert sub-system, and fractionation and recombination to automatic building control system structure in region, the exclusive son of creation is integrated
System interlink not only ensure that the long-range monitoring of remote distributed, but also provide region control subsystem supervision.
Preferably, the automatic building control system 101 is specifically used for according to building automation strategy execution automatic operation, it is described from
Control operation includes the training of linkage scheme, and the linkage scheme training includes:
The selection linkage logic in the building automation strategy, according to automatic building control system described in the linkage logical triggering
In subsystem link, complete training;
If the training is effective, the linkage logic is sent to the cloud platform by the communication node, and,
When the cloud platform adjusts the linkage logic, the adjusted of the cloud platform transmission is received by the communication node
Dynamic logic, and updating the linkage logic in the building automation strategy is the linkage logic adjusted;And/or
If the training is invalid, linkage logic is reselected in the building automation strategy, and according to reselecting
Linkage logic execute subsequent step.
It should be noted that the building automation strategy includes multiple linkage logics, it is pre-stored in automatic building control system, with
For being called when the training of linkage scheme.
If subsystems are operated according to the linkage logic of selection, target can be reached, then determine training effectively,
Otherwise determine that training is invalid.If training is effectively, cloud platform can required precision according to control logic and accuracy requirement, into one
Step corrects the linkage logic.After cloud platform adjusts the linkage logic, it is also necessary to which linkage logic adjusted is passed through communication
Node is issued automatic building control system again and is trained, and is effective to verify linkage logic adjusted.If training result is effective,
Otherwise the linkage logic for then saving selection is given up, to guarantee the reliability of system interlink control.
Preferably, the subsystem in the automatic building control system according to the linkage logical triggering links, complete
At training, comprising:
The testing result of the subsystem in normally open is obtained, and by testing result storage into log, wherein
Different testing results is stored into identical or different log;
If the testing result be it is abnormal, according to subsystem itself described in the linkage logical triggering and/or with the son
There are other subsystems of interaction relation to execute predetermined registration operation for system;
Predetermined registration operation is being executed, and after abnormal releasing, by predetermined registration operation process storage into log, is completing training,
Wherein, the predetermined registration operation is one or more, and if multinomial, then the predetermined registration operation process storage of different item is to identical or different
Log in.
In order to make it easy to understand, including: now that fire-fighting detection and alert sub-system, security protection are supervised with automatic building control system referring to fig. 4
For controlling subsystem, automatic fire control subsystem, this linkage scheme training method that the present embodiment proposes is illustrated as follows:
Step S21, the fire fighting detector of fire-fighting detection and alert sub-system is at normally open, with real-time monitoring week
Surrounding environment;
Step S22, when a fire, fire fighting detector judges whether it is fire, if so, will test result is archived in day
In will B, otherwise, it will test result and be archived in log A;
Step S23, after the fire that automatic building control system receives fire fighting detector output determines signal, output order is issued
It alarms to the fire protection warning device of fire-fighting detection and alert sub-system;
Step S24, safety monitoring subsystem output security protection permission is lifted a ban, the drainage of starting evacuating personnel and fire realtime graphic
Output;
Step S25, safety monitoring subsystem analyzes the real-time condition of fire image, judges the preparation of fire-fighting equipment, from
Dynamic fire-fighting subsystem starting;
If step S26, automatic fire control subsystem starts, the fire extinguishing of safety monitoring subsystem real-time monitoring automatic fire control subsystem
Situation (image, toxic gas, environmental monitoring etc.), after confirmation fire is eliminated, automatic building control system releases alarm of fire, achieves day
In will C, the training program 1 of linkage logic 1 is completed;
If step S27, automatic fire control subsystem is inactive, automatic building control system skips linkage logic, and Xiang Guanfang 119 is sent out
Fire alarm out requests foreign aid, sounds all clear after completing fire extinguishing, and archival log D completes the training program 1 of linkage logic 1;
If step S28, the described training is effective, server of cloud platform backs up the linkage logic 1, and is adjusting the linkage
Automatic building control system re -training is sent to after logic 1;
If step S29, the described training is invalid, linkage logic 2 is reselected in the building automation strategy, returns to step
Rapid S21 executes subsequent step.
It is understood that technical solution provided in this embodiment, by the way that communication node, cloud platform is arranged, by monitoring section
The automatic building control system linkage control of multiple dispersions in domain is got up, and has not only realized the communication interconnection between building and building, but also real
The monitoring and management of the distribution, long-range to building multiple in region are showed, to make the higher building automation intelligence of integrated level
Intelligent cell, city are laid a good foundation.
Fig. 3 is a kind of flow chart of building automation distributed method shown according to an exemplary embodiment, such as Fig. 3 institute
Show, this method comprises:
Step S11, each automatic building control system receives the control instruction that cloud platform is sent by respective communication node, with
Automatic operation is executed according to the control instruction;And/or
Step S12, the result after executing automatic operation is sent to by each automatic building control system by respective communication node
The cloud platform;
Wherein, the automatic building control system be at least one set, the communication node be at least one, every group of building automation system
System is arranged in a one-to-one correspondence with each communication node.
It is understood that the corresponding communication node of every group of building automation subsystem, every group of building automation subsystem are logical
It crosses exclusive communication node and cloud platform and carries out data interaction.The benefit being arranged in this way is that every group of automatic building control system is all one
A independent system, the data interaction between cloud platform are not influenced by the equipment in other channels, ensure that communication quality, together
When, by communication node and cloud platform, every group of automatic building control system realizes communication interconnection again, and cloud platform can be to every group of building
Robot control system(RCS) realizes linkage control and distributed management, and user experience is good, satisfaction is high.
It is understood that technical solution provided in this embodiment, by the way that communication node, cloud platform is arranged, by monitoring section
The automatic building control system linkage control of multiple dispersions in domain is got up, and has not only realized the communication interconnection between building and building, but also real
The monitoring and management of the distribution, long-range to building multiple in region are showed, to make the higher building automation intelligence of integrated level
Intelligent cell, city are laid a good foundation.
Preferably, the automatic operation, including linkage scheme are trained, and the linkage scheme training includes:
The selection linkage logic in the building automation strategy, according to automatic building control system described in the linkage logical triggering
In subsystem link, complete training;
If the training is effective, the linkage logic is sent to the cloud platform by the communication node, and,
When the cloud platform adjusts the linkage logic, the adjusted of the cloud platform transmission is received by the communication node
Dynamic logic, and updating the linkage logic in the building automation strategy is the linkage logic adjusted;And/or
If the training is invalid, linkage logic is reselected in the building automation strategy, and according to reselecting
Linkage logic execute subsequent step.
Preferably, the subsystem in the automatic building control system according to the linkage logical triggering links, complete
At training, comprising:
The testing result of the subsystem in normally open is obtained, and by testing result storage into log, wherein
Different testing results is stored into identical or different log;
If the testing result be it is abnormal, according to subsystem itself described in the linkage logical triggering and/or with the son
There are other subsystems of interaction relation to execute predetermined registration operation for system;
Predetermined registration operation is being executed, and after abnormal releasing, by predetermined registration operation process storage into log, is completing training,
Wherein, the predetermined registration operation is one or more, and if multinomial, then the predetermined registration operation process storage of different item is to identical or different
Log in.
In order to make it easy to understand, including: now that fire-fighting detection and alert sub-system, security protection are supervised with automatic building control system referring to fig. 4
For controlling subsystem, automatic fire control subsystem, this linkage scheme training method that the present embodiment proposes is illustrated as follows:
Step S21, the fire fighting detector of fire-fighting detection and alert sub-system is at normally open, with real-time monitoring week
Surrounding environment;
Step S22, when a fire, fire fighting detector judges whether it is fire, if so, will test result is archived in day
In will B, otherwise, it will test result and be archived in log A;
Step S23, after the fire that automatic building control system receives fire fighting detector output determines signal, output order is issued
It alarms to the fire protection warning device of fire-fighting detection and alert sub-system;
Step S24, safety monitoring subsystem output security protection permission is lifted a ban, the drainage of starting evacuating personnel and fire realtime graphic
Output;
Step S25, safety monitoring subsystem analyzes the real-time condition of fire image, judges the preparation of fire-fighting equipment, from
Dynamic fire-fighting subsystem starting;
If step S26, automatic fire control subsystem starts, the fire extinguishing of safety monitoring subsystem real-time monitoring automatic fire control subsystem
Situation (image, toxic gas, environmental monitoring etc.), after confirmation fire is eliminated, automatic building control system releases alarm of fire, achieves day
In will C, the training program 1 of linkage logic 1 is completed;
If step S27, automatic fire control subsystem is inactive, automatic building control system skips linkage logic, and Xiang Guanfang 119 is sent out
Fire alarm out requests foreign aid, sounds all clear after completing fire extinguishing, and archival log D completes the training program 1 of linkage logic 1;
If step S28, the described training is effective, server of cloud platform backs up the linkage logic 1, and is adjusting the linkage
Automatic building control system re -training is sent to after logic 1;
If step S29, the described training is invalid, linkage logic 2 is reselected in the building automation strategy, returns to step
Rapid S21 executes subsequent step.
It is understood that technical solution provided in this embodiment, by the way that communication node, cloud platform is arranged, by monitoring section
The automatic building control system linkage control of multiple dispersions in domain is got up, and has not only realized the communication interconnection between building and building, but also real
The monitoring and management of the distribution, long-range to building multiple in region are showed, to make the higher building automation intelligence of integrated level
Intelligent cell, city are laid a good foundation.
It is understood that same or similar part can mutually refer in the various embodiments described above, in some embodiments
Unspecified content may refer to the same or similar content in other embodiments.
It should be noted that in the description of the present invention, term " first ", " second " etc. are used for description purposes only, without
It can be interpreted as indication or suggestion relative importance.In addition, in the description of the present invention, unless otherwise indicated, the meaning of " multiple "
Refer at least two.
Any process described otherwise above or method description are construed as in flow chart or herein, and expression includes
It is one or more for realizing specific logical function or process the step of executable instruction code module, segment or portion
Point, and the range of the preferred embodiment of the present invention includes other realization, wherein can not press shown or discussed suitable
Sequence, including according to related function by it is basic simultaneously in the way of or in the opposite order, Lai Zhihang function, this should be of the invention
Embodiment person of ordinary skill in the field understood.
It should be appreciated that each section of the invention can be realized with hardware, software, firmware or their combination.Above-mentioned
In embodiment, software that multiple steps or method can be executed in memory and by suitable instruction execution system with storage
Or firmware is realized.It, and in another embodiment, can be under well known in the art for example, if realized with hardware
Any one of column technology or their combination are realized: having a logic gates for realizing logic function to data-signal
Discrete logic, with suitable combinational logic gate circuit specific integrated circuit, programmable gate array (PGA), scene
Programmable gate array (FPGA) etc..
Those skilled in the art are understood that realize all or part of step that above-described embodiment method carries
It suddenly is that relevant hardware can be instructed to complete by program, the program can store in a kind of computer-readable storage medium
In matter, which when being executed, includes the steps that one or a combination set of embodiment of the method.
It, can also be in addition, each functional unit in each embodiment of the present invention can integrate in a processing module
It is that each unit physically exists alone, can also be integrated in two or more units in a module.Above-mentioned integrated mould
Block both can take the form of hardware realization, can also be realized in the form of software function module.The integrated module is such as
Fruit is realized and when sold or used as an independent product in the form of software function module, also can store in a computer
In read/write memory medium.
Storage medium mentioned above can be read-only memory, disk or CD etc..
In the description of this specification, reference term " one embodiment ", " some embodiments ", " example ", " specifically show
The description of example " or " some examples " etc. means specific features, structure, material or spy described in conjunction with this embodiment or example
Point is included at least one embodiment or example of the invention.In the present specification, schematic expression of the above terms are not
Centainly refer to identical embodiment or example.Moreover, particular features, structures, materials, or characteristics described can be any
One or more embodiment or examples in can be combined in any suitable manner.
Although the embodiments of the present invention has been shown and described above, it is to be understood that above-described embodiment is example
Property, it is not considered as limiting the invention, those skilled in the art within the scope of the invention can be to above-mentioned
Embodiment is changed, modifies, replacement and variant.
Claims (11)
1. a kind of building automation distributed system characterized by comprising
At least one set of automatic building control system;
At least one communication node, each communication node are arranged in a one-to-one correspondence with every group of automatic building control system;
Cloud platform is communicated to connect with each communication node.
2. system according to claim 1, which is characterized in that
The automatic building control system is specifically used for according to building automation strategy execution automatic operation, and the automatic operation includes linkage
Scheme training, the linkage scheme training include:
The selection linkage logic in the building automation strategy, according in automatic building control system described in the linkage logical triggering
Subsystem links, and completes training;
If the training is effective, the linkage logic is sent to the cloud platform by the communication node, and, in institute
When stating the cloud platform adjustment linkage logic, the linkage adjusted that the cloud platform is sent is received by the communication node and is patrolled
Volume, and updating the linkage logic in the building automation strategy is the linkage logic adjusted;And/or
If the training is invalid, linkage logic is reselected in the building automation strategy, and according to the connection reselected
Dynamic logic executes subsequent step.
3. system according to claim 2, which is characterized in that the building automation according to the linkage logical triggering
Subsystem in system links, and completes training, comprising:
The testing result of the subsystem in normally open is obtained, and by testing result storage into log, wherein different
Testing result store into identical or different log;
If the testing result be it is abnormal, according to subsystem itself described in the linkage logical triggering and/or with the subsystem
There are other subsystems of interaction relation to execute predetermined registration operation;
Predetermined registration operation is being executed, and after abnormal releasing, by predetermined registration operation process storage into log, is completing training, wherein
The predetermined registration operation be it is one or more, if multinomial, then the predetermined registration operation process storage of different item to identical or different day
In will.
4. system according to claim 1, which is characterized in that if every group of automatic building control system includes multiple and different types
Subsystem, the system also includes:
Multiple groups private network, the subsystem of the corresponding type of every group of private network;
Same type subsystem in different automatic building control systems accesses corresponding one group of private network.
5. system according to claim 4, which is characterized in that
The cloud platform includes: multiple private servers, the corresponding one group of private network of each private server, by each dedicated
The multiple automatic building control systems of server triggers carry out integrated linkage.
6. described in any item systems according to claim 1~5, which is characterized in that further include:
Monitoring center, and/or, remote user access terminal is communicated to connect with the cloud platform.
7. described in any item systems according to claim 1~5, which is characterized in that
The communication node is relay node;
The communication node is communicated to connect by base station and the cloud platform;And/or
The communication node is communicated to connect by Ethernet and the cloud platform.
8. described in any item systems according to claim 1~5, which is characterized in that the building automatic system includes at least one
A subsystem, each subsystem are communicated to connect with corresponding communication node, and the subsystem includes at least one in following item
:
Fire-fighting detection and alert sub-system, safety monitoring subsystem, environmental monitoring subsystem.
9. a kind of building automation distributed method characterized by comprising
Each automatic building control system receives the control instruction that cloud platform is sent by respective communication node, according to the control
Instruction execution automatic operation;And/or
The result after executing automatic operation is sent to the cloud platform by respective communication node;
Wherein, the automatic building control system is at least one set, and the communication node is at least one, every group of automatic building control system with
Each communication node is arranged in a one-to-one correspondence.
10. according to the method described in claim 9, it is characterized in that,
The automatic operation, including linkage scheme are trained, and the linkage scheme training includes:
The selection linkage logic in the building automation strategy, according in automatic building control system described in the linkage logical triggering
Subsystem links, and completes training;
If the training is effective, the linkage logic is sent to the cloud platform by the communication node, and, in institute
When stating the cloud platform adjustment linkage logic, the linkage adjusted that the cloud platform is sent is received by the communication node and is patrolled
Volume, and updating the linkage logic in the building automation strategy is the linkage logic adjusted;And/or
If the training is invalid, linkage logic is reselected in the building automation strategy, and according to the connection reselected
Dynamic logic executes subsequent step.
11. according to the method described in claim 10, it is characterized in that, the building according to the linkage logical triggering from
Subsystem in control system links, and completes training, comprising:
The testing result of the subsystem in normally open is obtained, and by testing result storage into log, wherein different
Testing result store into identical or different log;
If the testing result be it is abnormal, according to subsystem itself described in the linkage logical triggering and/or with the subsystem
There are other subsystems of interaction relation to execute predetermined registration operation;
Predetermined registration operation is being executed, and after abnormal releasing, by predetermined registration operation process storage into log, is completing training, wherein
The predetermined registration operation be it is one or more, if multinomial, then the predetermined registration operation process storage of different item to identical or different day
In will.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910550844.6A CN110320835B (en) | 2019-06-24 | 2019-06-24 | Building automatic control distributed system and method |
PCT/CN2019/126358 WO2020258769A1 (en) | 2019-06-24 | 2019-12-18 | Building automation distributed system and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910550844.6A CN110320835B (en) | 2019-06-24 | 2019-06-24 | Building automatic control distributed system and method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110320835A true CN110320835A (en) | 2019-10-11 |
CN110320835B CN110320835B (en) | 2021-06-22 |
Family
ID=68121084
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910550844.6A Active CN110320835B (en) | 2019-06-24 | 2019-06-24 | Building automatic control distributed system and method |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN110320835B (en) |
WO (1) | WO2020258769A1 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111885162A (en) * | 2020-07-23 | 2020-11-03 | 珠海格力电器股份有限公司 | Building equipment management system |
WO2020258769A1 (en) * | 2019-06-24 | 2020-12-30 | 珠海格力电器股份有限公司 | Building automation distributed system and method |
CN112967155A (en) * | 2021-03-08 | 2021-06-15 | 青岛科技大学 | Intelligent self-service catering service system architecture and device |
CN116319904A (en) * | 2022-09-08 | 2023-06-23 | 江苏智格高科技有限公司 | Building automatic control distributed method and system |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1407443A (en) * | 2001-08-21 | 2003-04-02 | 深圳市赛格信力德智能系统工程有限公司 | Building intelligent system controlling method |
CN107046578A (en) * | 2017-04-28 | 2017-08-15 | 浙江海邦伟业智能科技股份有限公司 | A kind of comprehensive safeguard management platform |
CN107272535A (en) * | 2017-07-11 | 2017-10-20 | 武汉虹信技术服务有限责任公司 | The linkage and interlock method of a kind of intelligent building management system |
CN107450434A (en) * | 2017-08-16 | 2017-12-08 | 山东建筑大学 | A kind of intelligent node, automatic building control system and method based on two grade network |
CN109194930A (en) * | 2018-10-25 | 2019-01-11 | 广州益牛科技有限公司 | Building environment integral and intelligent management system |
US20190107832A1 (en) * | 2017-10-06 | 2019-04-11 | Johnson Controls Technology Company | Building management system with automatic binding of equipment data |
US20190109725A1 (en) * | 2017-10-06 | 2019-04-11 | Johnson Controls Technology Company | Building management system with adapting iot hub |
CN109714429A (en) * | 2019-01-15 | 2019-05-03 | 南京菲迪尔电子科技有限公司 | The broadband automatic building control system and its automatic control method of the full distributed power line of Internet of Things |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110320835B (en) * | 2019-06-24 | 2021-06-22 | 珠海格力电器股份有限公司 | Building automatic control distributed system and method |
-
2019
- 2019-06-24 CN CN201910550844.6A patent/CN110320835B/en active Active
- 2019-12-18 WO PCT/CN2019/126358 patent/WO2020258769A1/en active Application Filing
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1407443A (en) * | 2001-08-21 | 2003-04-02 | 深圳市赛格信力德智能系统工程有限公司 | Building intelligent system controlling method |
CN107046578A (en) * | 2017-04-28 | 2017-08-15 | 浙江海邦伟业智能科技股份有限公司 | A kind of comprehensive safeguard management platform |
CN107272535A (en) * | 2017-07-11 | 2017-10-20 | 武汉虹信技术服务有限责任公司 | The linkage and interlock method of a kind of intelligent building management system |
CN107450434A (en) * | 2017-08-16 | 2017-12-08 | 山东建筑大学 | A kind of intelligent node, automatic building control system and method based on two grade network |
US20190107832A1 (en) * | 2017-10-06 | 2019-04-11 | Johnson Controls Technology Company | Building management system with automatic binding of equipment data |
US20190109725A1 (en) * | 2017-10-06 | 2019-04-11 | Johnson Controls Technology Company | Building management system with adapting iot hub |
CN109194930A (en) * | 2018-10-25 | 2019-01-11 | 广州益牛科技有限公司 | Building environment integral and intelligent management system |
CN109714429A (en) * | 2019-01-15 | 2019-05-03 | 南京菲迪尔电子科技有限公司 | The broadband automatic building control system and its automatic control method of the full distributed power line of Internet of Things |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2020258769A1 (en) * | 2019-06-24 | 2020-12-30 | 珠海格力电器股份有限公司 | Building automation distributed system and method |
CN111885162A (en) * | 2020-07-23 | 2020-11-03 | 珠海格力电器股份有限公司 | Building equipment management system |
CN112967155A (en) * | 2021-03-08 | 2021-06-15 | 青岛科技大学 | Intelligent self-service catering service system architecture and device |
CN116319904A (en) * | 2022-09-08 | 2023-06-23 | 江苏智格高科技有限公司 | Building automatic control distributed method and system |
Also Published As
Publication number | Publication date |
---|---|
WO2020258769A1 (en) | 2020-12-30 |
CN110320835B (en) | 2021-06-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110320835A (en) | A kind of building automation distributed system and method | |
CN102063116B (en) | Building information total management system and method | |
CN102271767B (en) | Sprinkler with an integrated valve, and fire-extinguishing system using same | |
KR102322427B1 (en) | Bigdata based building fire prevention response system and method | |
US20090322527A1 (en) | Server based distributed security system | |
CN101430815A (en) | Ganged control method and system based on fire disaster alarm integrated monitoring and management system | |
CN111641674A (en) | Underground piping lane control wireless communication system | |
CN108663979A (en) | The high tower comprehensive monitoring system that technology of Internet of things is integrated with 3D | |
CN206311963U (en) | A kind of intelligent building supervising device | |
CN110377066A (en) | A kind of control method of inspection device, device and equipment | |
SA520420073B1 (en) | Distributed Industrial Facility Safety System | |
CN112530132A (en) | Intelligent fire control management and control system based on cloud computing service | |
CN105824281B (en) | A kind of fire-fighting real-time monitoring system | |
JP4816283B2 (en) | Notification system, terminal device of notification system, main control device, backup device, notification method, program, and recording medium | |
CN110061564A (en) | A kind of change distribution place intelligent monitor system and application method based on Internet of Things | |
CN108120475A (en) | The data monitoring method and device of a kind of piping lane | |
CN110185937A (en) | A kind of pipeline inspection monitoring method, server and system | |
CN208074803U (en) | Intelligent emergent lamp and intelligent emergent evacuating system | |
CN113612976B (en) | Security plan optimization method and security plan optimization device | |
KR102473778B1 (en) | Artificial intelligence based smart fire detection device and non-fire alarm analysis system comprising the same | |
KR101832837B1 (en) | Method and system for automatic building control | |
CN102611193B (en) | The interaction control method of power system, Apparatus and system | |
CN202306754U (en) | Intelligent wireless fire control alarming system | |
JP4399750B2 (en) | Damage reduction system at the time of disaster | |
CN112383137A (en) | Transformer area monitoring system and method based on machine vision and thermal imaging technology |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |