CN110318802A - Utilize the technology in gasification slag reparation backfill pit - Google Patents

Utilize the technology in gasification slag reparation backfill pit Download PDF

Info

Publication number
CN110318802A
CN110318802A CN201910412653.3A CN201910412653A CN110318802A CN 110318802 A CN110318802 A CN 110318802A CN 201910412653 A CN201910412653 A CN 201910412653A CN 110318802 A CN110318802 A CN 110318802A
Authority
CN
China
Prior art keywords
pit
gasification slag
side slope
backfill
reparation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910412653.3A
Other languages
Chinese (zh)
Inventor
王永春
王海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changxin Eco-Technology (shaanxi) Co Ltd
Original Assignee
Changxin Eco-Technology (shaanxi) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changxin Eco-Technology (shaanxi) Co Ltd filed Critical Changxin Eco-Technology (shaanxi) Co Ltd
Priority to CN201910412653.3A priority Critical patent/CN110318802A/en
Publication of CN110318802A publication Critical patent/CN110318802A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/005Methods or devices for placing filling-up materials in underground workings characterised by the kind or composition of the backfilling material
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/06Filling-up mechanically

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The embodiment of the invention discloses the technologies using gasification slag reparation backfill pit, mainly comprise the steps that step 1: the smooth compacting in pit bottom, and are laid with certain thickness bed course densification on it, and conduction pipe is laid in bed course;Step 2: permeable hole is arranged in the vertical fixed support tube on bed course, support pipe outer wall, and support bottom of the tube is connected with conduction pipe;Step 3: squeezing into lateral spud pile in the side slope of pit, and spray cement slurry in side slope;Step 4: setting anti-seepage geomembrane in bed course and side slope upper berth;Step 5: gasification slag is imported into pit, is backfilled to pit, and backfills upper surface apart from pit upper limb 0.5-1m;Step 6: planting vegetable layer in pit upper end, vegetable layer is concordant with pit.The pit earth-filling method that the present invention uses, backfilling material is at low cost, and pit stability is strong after backfill, and is provided with vegetable layer on pit surface, backfilling material is combined together with pit, repairing effect is good.

Description

Utilize the technology in gasification slag reparation backfill pit
Technical field
The present embodiments relate to environment remediation technical fields, and in particular to utilizes the skill in gasification slag reparation backfill pit Art.
Background technique
In coal and the recovery process of various mineral resources, big and small pit can be generated, and if these pits It not can be carried out and timely backfill, water storage can be generated after rainfall, since water storage may bring landslide, infiltration, mud-rock flow etc. a variety of Natural calamity has not only broken up original geology style and features, but also may jeopardize the person and property safety.
To solve the problems, such as that above-mentioned pit generates, people, which begin one's study, backfills pit.In the prior art, usually will Solid waste is directly backfilling into pit, has a large amount of gap in backfilling material, can be under into the rainwater in pit Infiltration enters underground water, and the pollutant in solid waste is brought into underground water, polluted water body environment.And in water body In infitration process, collapsing for backfilling material in pit also will cause, affect the effect that pit backfill is repaired.
Therefore, how existing resource is utilized, optimizes pit backfilling process, improved the stability in backfill pit, be ability Field technique personnel technical problem urgently to be resolved.
Summary of the invention
For this purpose, the embodiment of the present invention provide using gasification slag reparation backfill pit technology, with solve in the prior art by Rainwater infiltration polluted underground water and backfilling material is caused to collapse caused by backfilling material has gap.
To achieve the goals above, the embodiment of the present invention provides the following technical solutions:
According to embodiments of the present invention, a kind of technology using gasification slag reparation backfill pit is provided, mainly includes following step It is rapid:
Step 1: the smooth compacting in pit bottom, and it is laid with certain thickness bed course densification on it, it is laid with and leads in bed course Flow tube road;
Step 2: the vertical fixed support tube on bed course, support pipe outer wall are arranged permeable hole, support bottom of the tube and diversion pipe Road is connected;
Step 3: squeezing into lateral spud pile in the side slope of pit, and spray cement slurry in side slope;
Step 4: setting anti-seepage geomembrane in bed course and side slope upper berth;
Step 5: gasification slag is imported into pit, is backfilled to pit, and backfills upper surface apart from pit upper limb 0.5- 1m;
Step 6: planting vegetable layer in pit upper end, vegetable layer is concordant with pit.
It further, further include vertical dregs-blocking dam in step 3, vertical dregs-blocking dam is arranged in side slope, and vertical dregs-blocking dam It is staggered with lateral spud pile.
Further, the cushion thickness is 30-50cm, compacting factor 0.9.
Further, the anti-seepage geomembrane with a thickness of 0.6-0.8mm, puncture intensity >=500N, infiltration coefficient≤0.8 ×10-7cm/s。
Further, in the side slope cement slurry with a thickness of 10-15cm.
Further, the dregs-blocking dam is highly 1-1.5m with a thickness of 0.5-0.8m.
Further, the vegetable layer plantation high density turf and more root system shrubs.
The embodiment of the present invention has the advantages that
The rainwater entered in pit is retained by setting geomembrane, will not be seeped into underground water down, and rainwater It is entered in support tube by the permeable hole on support tube, and enters further into conduction pipe and discharge, it is therefore prevented that rain It is underwater to seep pollution of the pollutant to underground water in entrained gas slugging, protect groundwater environment;Support tube is provided in pit, It is provided with lateral spud pile and vertical dregs-blocking dam in side slope, so as to enhance the interconnection of gasification slag and pit, prevents Collapsing for gasification slag backfilling material, enhances the stability of pit backfilling material;The present invention carries out returning for pit using gasification slag It fills out, not only reduces the influence caused by environment of gasification slag muck product, and also achieve the recycling and reusing of gasification slag.The present invention The pit earth-filling method of use, backfilling material is at low cost, and pit stability is strong after backfill, and is provided with vegetation on pit surface Layer, enables backfilling material to combine together with pit, repairing effect is good.
Specific embodiment
Embodiments of the present invention are illustrated by particular specific embodiment below, those skilled in the art can be by this explanation Content disclosed by book is understood other advantages and efficacy of the present invention easily, it is clear that described embodiment is the present invention one Section Example, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art are not doing Every other embodiment obtained under the premise of creative work out, shall fall within the protection scope of the present invention.
According to embodiments of the present invention, a kind of technology using gasification slag reparation backfill pit is provided, mainly includes following step It is rapid:
Step 1: the basis by mechanical equipment to the smooth compacting in pit bottom, as hole hole bottom.And it is laid on it Certain thickness bed course densification is general using with a thickness of 30-50cm, compacting factor 0.9, due to weight after preventing gasification slag from backfilling Power causes to settle.Conduction pipe is laid in bed course, conduction pipe is mainly used for accepting the rainwater entered in pit, and rainwater is logical Conduction pipe is crossed to discharge.
Step 2: being cleaned out firstly the need of by the rubble of mat surface, spine block etc., facilitate subsequent laying antiseepage geotechnique Film.The vertical fixed support tube on bed course, specifically can be by modes fixed support tubes such as piling, and support pipe outer wall setting is permeable Hole, permeable hole are of moderate size, and can either guarantee permeable effect, and can guarantee that gasification slag cannot enter branch by permeable hole In stay tube.Support bottom of the tube is connected with conduction pipe, therefore the rainwater infiltration entered in gasification slag backfilling material enters In support tube, water body then passes through gravity and enters in conduction pipe and discharge in support tube.To prevent rainwater from seeping Underground water is seeped under pollutant in ventilative slugging, protects the stabilization of groundwater environment.
Step 3: lateral spud pile is squeezed into the side slope of pit, concrete stake, length can be used in specific transverse direction spud pile It can be determined production as needed, general length uses 8-10m, lateral spud pile is squeezed into the length of half by pile driving equipment Degree guarantees the stabilization of lateral spud pile.Further, and in side slope spray cement slurry, in the side slope cement slurry with a thickness of 10-15cm will form a protective layer after cement slurry is dry in side slope, prevent rainwater by seeping under side slope.
Step 4: setting anti-seepage geomembrane in bed course and side slope upper berth, by the way that anti-seepage geomembrane is arranged, the rainwater in pit is only It can be seeped into down on geomembrane and be trapped, and have to enter into support tube and discharged.Anti-seepage geomembrane exists in order to prevent Be destroyed when laying, the anti-seepage geomembrane with a thickness of 0.6-0.8mm, puncture intensity >=500N, infiltration coefficient≤0.8 × 10-7cm/s。
Step 5: gasification slag is imported into pit, is backfilled to pit, and backfills upper surface apart from pit upper limb 0.5- 1m;
Step 6: planting vegetable layer in pit upper end, vegetable layer is concordant with pit, and the vegetable layer plants high density turf With more root system shrubs.
It further, further include vertical dregs-blocking dam in step 3, vertical dregs-blocking dam is arranged in side slope, and vertical dregs-blocking dam It is staggered with lateral spud pile.Further, the dregs-blocking dam is highly 1-1.5m with a thickness of 0.5-0.8m.
The method in gasification slag reparation backfill pit of the invention, the stability after capable of guaranteeing pit backfilling material, and prevent Only there is rainwater infiltration to pollute underground water.
Embodiment 1
According to the technique and scheme of the present invention, a backfill pit is selected in Yulin Prefecture, Shaanxi Province, is named as No. 1 hole.No. 1 100 meters of diameter of hole, 50 meters of height.
A kind of technology using gasification slag reparation backfill pit is provided, is mainly comprised the steps that
Step 1: the basis by mechanical equipment to the smooth compacting in pit bottom, as hole hole bottom.And it is laid on it Certain thickness bed course densification, using with a thickness of 50cm, compacting factor 0.9, since gravity causes after preventing gasification slag from backfilling Sedimentation.Conduction pipe is laid in bed course, conduction pipe is mainly used for accepting the rainwater entered in pit, and rainwater passes through water conservancy diversion Pipeline discharges.
Step 2: being cleaned out firstly the need of by the rubble of mat surface, spine block etc., facilitate subsequent laying antiseepage geotechnique Film.The vertical fixed support tube on bed course, specifically can be by modes fixed support tubes such as piling, and support pipe outer wall setting is permeable Hole, permeable hole are of moderate size, and can either guarantee permeable effect, and can guarantee that gasification slag cannot enter branch by permeable hole In stay tube.Support bottom of the tube is connected with conduction pipe, therefore the rainwater infiltration entered in gasification slag backfilling material enters In support tube, water body then passes through gravity and enters in conduction pipe and discharge in support tube.To prevent rainwater from seeping Underground water is seeped under pollutant in ventilative slugging, protects the stabilization of groundwater environment.
Step 3: lateral spud pile is squeezed into the side slope of pit, concrete stake, length can be used in specific transverse direction spud pile It can be determined production as needed, length uses 10m, lateral spud pile is squeezed into the length of half by pile driving equipment, protects Demonstrate,prove the stabilization of lateral spud pile.Further, and in side slope spray cement slurry, in the side slope cement slurry with a thickness of 10cm, After cement slurry is dry, a protective layer will be formed in side slope, prevent rainwater by seeping under side slope.
Step 4: setting anti-seepage geomembrane in bed course and side slope upper berth, by the way that anti-seepage geomembrane is arranged, the rainwater in pit is only It can be seeped into down on geomembrane and be trapped, and have to enter into support tube and discharged.Anti-seepage geomembrane exists in order to prevent Be destroyed when laying, the anti-seepage geomembrane with a thickness of 0.6-0.8mm, puncture intensity >=500N, infiltration coefficient≤0.8 × 10-7cm/s。
Step 5: gasification slag is imported into pit, is backfilled to pit, and backfills upper surface apart from pit upper limb 0.5- 1m;
Step 6: planting vegetable layer in pit upper end, vegetable layer is concordant with pit, and the vegetable layer plants high density turf With more root system shrubs.
After the slag that gasifies backfills No. 1 hole, after 1 year, to being detected at No. 1 hole.Detect the sedimentation 0.5 downwards of No. 1 hole Rice, detection water quality are simultaneously unchanged.
Embodiment 2
According to the technique and scheme of the present invention, it selects another to backfill pit in Yulin Prefecture, Shaanxi Province, is named as No. 2 holes.2 Number hole 95 meters of diameter, height 52 meters.
A kind of technology using gasification slag reparation backfill pit is provided, is mainly comprised the steps that
Step 1: the basis by mechanical equipment to the smooth compacting in pit bottom, as hole hole bottom.And it is laid on it Certain thickness bed course densification, using with a thickness of 50cm, compacting factor 0.9, since gravity causes after preventing gasification slag from backfilling Sedimentation.Conduction pipe is laid in bed course, conduction pipe is mainly used for accepting the rainwater entered in pit, and rainwater passes through water conservancy diversion Pipeline discharges.
Step 2: being cleaned out firstly the need of by the rubble of mat surface, spine block etc., facilitate subsequent laying antiseepage geotechnique Film.The vertical fixed support tube on bed course, specifically can be by modes fixed support tubes such as piling, and support pipe outer wall setting is permeable Hole, permeable hole are of moderate size, and can either guarantee permeable effect, and can guarantee that gasification slag cannot enter branch by permeable hole In stay tube.Support bottom of the tube is connected with conduction pipe, therefore the rainwater infiltration entered in gasification slag backfilling material enters In support tube, water body then passes through gravity and enters in conduction pipe and discharge in support tube.To prevent rainwater from seeping Underground water is seeped under pollutant in ventilative slugging, protects the stabilization of groundwater environment.
Step 3: lateral spud pile is squeezed into the side slope of pit, concrete stake, length can be used in specific transverse direction spud pile It can be determined production as needed, length uses 10m, lateral spud pile is squeezed into the length of half by pile driving equipment, protects Demonstrate,prove the stabilization of lateral spud pile.Further, and in side slope spray cement slurry, in the side slope cement slurry with a thickness of 15cm, After cement slurry is dry, a protective layer will be formed in side slope, prevent rainwater by seeping under side slope.It further include vertical dregs-blocking dam, Vertical dregs-blocking dam is arranged in side slope, and vertical dregs-blocking dam and lateral spud pile are staggered.Further, the dregs-blocking dam is thick Degree is 0.5m, is highly 1.5m.
Step 4: setting anti-seepage geomembrane in bed course and side slope upper berth, by the way that anti-seepage geomembrane is arranged, the rainwater in pit is only It can be seeped into down on geomembrane and be trapped, and have to enter into support tube and discharged.Anti-seepage geomembrane exists in order to prevent Be destroyed when laying, the anti-seepage geomembrane with a thickness of 0.6-0.8mm, puncture intensity >=500N, infiltration coefficient≤0.8 × 10-7cm/s。
Step 5: gasification slag is imported into pit, is backfilled to pit, and backfills upper surface apart from pit upper limb 0.5- 1m;
Step 6: planting vegetable layer in pit upper end, vegetable layer is concordant with pit, and the vegetable layer plants high density turf With more root system shrubs.
After the slag that gasifies backfills No. 2 holes, after 1 year, to being detected at No. 2 holes.Detect the sedimentation 0.1 downwards of No. 2 holes Rice, detection water quality are simultaneously unchanged.
Therefore, it through the embodiment of the present invention it is found that carry out pit backfill by the technical solution of the invention, can protect substantially Stability after demonstrate,proving pit backfill, and rainwater does not generate lower seep and impacts to underground water.
The embodiment of the present invention has the advantages that
The rainwater entered in pit is retained by setting geomembrane, will not be seeped into underground water down, and rainwater It is entered in support tube by the permeable hole on support tube, and enters further into conduction pipe and discharge, it is therefore prevented that rain It is underwater to seep pollution of the pollutant to underground water in entrained gas slugging, protect groundwater environment;Support tube is provided in pit, It is provided with lateral spud pile and vertical dregs-blocking dam in side slope, so as to enhance the interconnection of gasification slag and pit, prevents Collapsing for gasification slag backfilling material, enhances the stability of pit backfilling material;The present invention carries out returning for pit using gasification slag It fills out, not only reduces the influence caused by environment of gasification slag muck product, and also achieve the recycling and reusing of gasification slag.The present invention The pit earth-filling method of use, backfilling material is at low cost, and pit stability is strong after backfill, and is provided with vegetation on pit surface Layer, enables backfilling material to combine together with pit, repairing effect is good.
Although above having used general explanation and specific embodiment, the present invention is described in detail, at this On the basis of invention, it can be made some modifications or improvements, this will be apparent to those skilled in the art.Therefore, These modifications or improvements without departing from theon the basis of the spirit of the present invention are fallen within the scope of the claimed invention.

Claims (7)

1. utilizing the technology in gasification slag reparation backfill pit, which is characterized in that mainly comprise the steps that
Step 1: the smooth compacting in pit bottom, and it is laid with certain thickness bed course densification on it, diversion pipe is laid in bed course Road;
Step 2: the vertical fixed support tube on bed course, support pipe outer wall are arranged permeable hole, support bottom of the tube and conduction pipe phase Connection;
Step 3: squeezing into lateral spud pile in the side slope of pit, and spray cement slurry in side slope;
Step 4: setting anti-seepage geomembrane in bed course and side slope upper berth;
Step 5: gasification slag is imported into pit, is backfilled to pit, and backfills upper surface apart from pit upper limb 0.5-1m;
Step 6: planting vegetable layer in pit upper end, vegetable layer is concordant with pit.
2. the technology as described in claim 1 using gasification slag reparation backfill pit, which is characterized in that in step 3, further include Vertical dregs-blocking dam, vertical dregs-blocking dam are arranged in side slope, and vertical dregs-blocking dam and lateral spud pile are staggered.
3. the technology using gasification slag reparation backfill pit as described in claim 1, which is characterized in that the cushion thickness is 30-50cm, compacting factor 0.9.
4. the technology as described in claim 1 using gasification slag reparation backfill pit, which is characterized in that the anti-seepage geomembrane With a thickness of 0.6-0.8mm, puncture intensity >=500N, infiltration coefficient≤0.8 × 10-7cm/s。
5. the technology as described in claim 1 using gasification slag reparation backfill pit, which is characterized in that cement in the side slope Slurry is with a thickness of 10-15cm.
6. the technology as claimed in claim 2 using gasification slag reparation backfill pit, which is characterized in that the dregs-blocking dam thickness It is highly 1-1.5m for 0.5-0.8m.
7. the technology as described in claim 1 using gasification slag reparation backfill pit, which is characterized in that the vegetable layer plantation High density turf and more root system shrubs.
CN201910412653.3A 2019-05-17 2019-05-17 Utilize the technology in gasification slag reparation backfill pit Pending CN110318802A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910412653.3A CN110318802A (en) 2019-05-17 2019-05-17 Utilize the technology in gasification slag reparation backfill pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910412653.3A CN110318802A (en) 2019-05-17 2019-05-17 Utilize the technology in gasification slag reparation backfill pit

Publications (1)

Publication Number Publication Date
CN110318802A true CN110318802A (en) 2019-10-11

Family

ID=68113125

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910412653.3A Pending CN110318802A (en) 2019-05-17 2019-05-17 Utilize the technology in gasification slag reparation backfill pit

Country Status (1)

Country Link
CN (1) CN110318802A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2005126999A (en) * 2005-08-26 2007-03-20 Валентин Витаутасович Сенкус (RU) METHOD FOR RECULTIVATION OF OPEN MINING
CN102817366A (en) * 2012-08-13 2012-12-12 大同煤矿集团有限责任公司 Prevention and treatment method for full-mechanized caving mining collapse trap area water disaster for shallow-buried ultra-thick coal seam
CN104088637A (en) * 2014-04-04 2014-10-08 太原理工大学 Method for second mining of upper-group shallow residual coal under coal seam group conditions
CN204530729U (en) * 2015-03-17 2015-08-05 宁波大学 A kind of ecological protection device for greening side slope
CN104818721A (en) * 2015-03-24 2015-08-05 中国地质大学(北京) Geological environment treatment method suitable for steep wall and deep pit type abandoned mine
CN106703050A (en) * 2016-11-30 2017-05-24 中铁二院昆明勘察设计研究院有限责任公司 Expansive soil road cutting side slope reinforced soil back-pressure seepage-preventive supporting structure and construction method thereof
CN107347481A (en) * 2017-07-10 2017-11-17 北京舜土规划顾问有限公司 Casing charge for remittance earthing implant system and the method reclaimed using its outdoor pit body of progress
CN108178536A (en) * 2018-03-09 2018-06-19 湖南科技大学 A kind of method that step calcination coal gas slugging prepares cement with little clinker

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2005126999A (en) * 2005-08-26 2007-03-20 Валентин Витаутасович Сенкус (RU) METHOD FOR RECULTIVATION OF OPEN MINING
CN102817366A (en) * 2012-08-13 2012-12-12 大同煤矿集团有限责任公司 Prevention and treatment method for full-mechanized caving mining collapse trap area water disaster for shallow-buried ultra-thick coal seam
CN104088637A (en) * 2014-04-04 2014-10-08 太原理工大学 Method for second mining of upper-group shallow residual coal under coal seam group conditions
CN204530729U (en) * 2015-03-17 2015-08-05 宁波大学 A kind of ecological protection device for greening side slope
CN104818721A (en) * 2015-03-24 2015-08-05 中国地质大学(北京) Geological environment treatment method suitable for steep wall and deep pit type abandoned mine
CN106703050A (en) * 2016-11-30 2017-05-24 中铁二院昆明勘察设计研究院有限责任公司 Expansive soil road cutting side slope reinforced soil back-pressure seepage-preventive supporting structure and construction method thereof
CN107347481A (en) * 2017-07-10 2017-11-17 北京舜土规划顾问有限公司 Casing charge for remittance earthing implant system and the method reclaimed using its outdoor pit body of progress
CN108178536A (en) * 2018-03-09 2018-06-19 湖南科技大学 A kind of method that step calcination coal gas slugging prepares cement with little clinker

Similar Documents

Publication Publication Date Title
Ingold Geotextiles and geomembranes handbook
US9649673B2 (en) System and method for strengthening a sloped structure such as a berm, basin, levee, embankment, or the like
US8784008B2 (en) Berm and method of construction thereof
CN107366251B (en) Construction method of sludge pond site in-situ ecological restoration system
US9662692B2 (en) Landfill and berm combination
CN112523264B (en) High-steep side slope seepage prevention system and laying method thereof
CN108755589A (en) A kind of antiseep of artificial lake structure and its construction method
CN111424702B (en) Integrated water drainage pipe structure and construction method
CN107321752A (en) A kind of sludge lagoon place Ecosystem restoration system in situ
CN209161804U (en) Gas guide system under a kind of film for sludge curing place
CN105239530A (en) Externally bonded landscape flood prevention wall structure
CN207891929U (en) A kind of ecotype Tailings Dam leakage preventing structure
CN114319455A (en) Full-coverage sealing, environmental treatment and greening process for large-scale refuse landfill
CN110318802A (en) Utilize the technology in gasification slag reparation backfill pit
CN106759174B (en) The method that superfine granule, upper reaches method Tailing dam construction prevent earthquake liquefaction unstable failure
CN205369281U (en) Radial precipitation structure
CN107083729A (en) One kind stores permeable module and preparation method thereof
CN110528538B (en) Refuse landfill and construction method thereof
CN209810895U (en) Horizontal drainage guide system of refuse landfill
US20110135393A1 (en) Berm and method of construction thereof
CN106284615A (en) Building waste is as the sponge urban rainwater seepage well of built-in material and manufacture method
Hötzl Industrial and urban produced impacts
CN112031036A (en) Ecological protection system and ecological protection method for high-salinity tunnel abandoned dreg site
CN110303022A (en) A kind of consumer waste filling and embedding system and method for impermeable pollution
CN109500044B (en) Horizontal drainage system of refuse landfill and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20191011