CN110318661B - Dewatering well construction method - Google Patents

Dewatering well construction method Download PDF

Info

Publication number
CN110318661B
CN110318661B CN201910334877.7A CN201910334877A CN110318661B CN 110318661 B CN110318661 B CN 110318661B CN 201910334877 A CN201910334877 A CN 201910334877A CN 110318661 B CN110318661 B CN 110318661B
Authority
CN
China
Prior art keywords
connecting rod
hammer head
dewatering
pipe
reinforcing ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910334877.7A
Other languages
Chinese (zh)
Other versions
CN110318661A (en
Inventor
李智
廖红玉
钟卫斌
孙仕斌
刘明周
夏颖
金锋
杨济滔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Yiye Construction Engineering Co ltd
Original Assignee
Wuhan Yiye Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Yiye Construction Engineering Co ltd filed Critical Wuhan Yiye Construction Engineering Co ltd
Priority to CN201910334877.7A priority Critical patent/CN110318661B/en
Publication of CN110318661A publication Critical patent/CN110318661A/en
Application granted granted Critical
Publication of CN110318661B publication Critical patent/CN110318661B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B1/00Percussion drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling

Abstract

The invention discloses a construction method of a dewatering well, wherein an air compressor supplies energy to a drilling machine, a pressure beater is installed on the drilling machine, a hammer head is fixedly installed at the bottom end of a connecting rod, a material filtering hole is formed along a dewatering pipe, a reinforcing ring is fixedly installed at the bottom end, the outer diameter of the hammer head is slightly smaller than the inner diameter of the dewatering pipe and slightly larger than the inner diameter of the reinforcing ring, the connecting rod and the hammer head are inserted into the dewatering pipe, then the top end of the connecting rod is fixedly installed with the pressure beater, the drilling machine drives a hammer head seal to press on the reinforcing ring and move downwards through the pressure beater and the connecting rod, the dewatering pipe synchronously sinks along with the reinforcing ring, the connecting rod and the hammer head are moved away after the dewatering pipe sinks in place, underground water flows into the dewatering pipe under the siphon action to complete well washing, a water pump. The method has low construction difficulty, reduces construction procedures, saves construction period and materials, and avoids hole collapse.

Description

Dewatering well construction method
Technical Field
The invention belongs to the field of municipal engineering construction, and particularly relates to a dewatering well construction method.
Technical Field
In municipal works, when the deep foundation pit is constructed, the construction needs to be assisted by a dewatering well. When the existing dewatering well is constructed, the point position is circularly drilled, then a slurry protective wall is adopted, pipe processing is simultaneously carried out, a steel wire mesh and a nylon mesh are wound around the pipe, after the drilling is successful, the pipe is placed into a hole, then the well is washed, then reverse filter materials are backfilled on two sides of the pipe, and finally the dewatering well is operated. At present, the construction of the dewatering well needs to arrange steel wire meshes and nylon meshes around pipes, and the two sides of the pipes need to be backfilled with filter materials, so that the process is complex, the working procedures are complex, the construction efficiency is low, the effect is poor, and if construction waste occurs in the stratum, the circular drilling is difficult to construct, and the hole collapse phenomenon is easily caused.
Disclosure of Invention
The invention aims to provide a dewatering well construction method which is low in construction difficulty, reduces construction procedures, saves construction period and materials and avoids hole collapse.
The technical scheme adopted by the invention is as follows:
a construction method of a dewatering well comprises the following steps:
s1, positioning the dewatering well, and conveying an air compressor, a drilling machine, a pressure applying device, a connecting rod, a hammer head and a dewatering pipe to the position of the dewatering well, wherein the air compressor supplies energy to the drilling machine, the pressure applying device is installed on the drilling machine, the hammer head is fixedly installed at the bottom end of the connecting rod, a filter material hole is formed along the dewatering pipe, a reinforcing ring is fixedly installed at the bottom end, and the outer diameter of the hammer head is slightly smaller than the inner diameter of the dewatering pipe and slightly larger;
s2, inserting the connecting rod and the hammer head into the precipitation pipe, and then fixedly installing the top end of the connecting rod and the pressurizer;
s3, starting the air compressor, driving the hammer head to seal and press the reinforcing ring and move downwards by the drilling machine through the pressuring machine and the connecting rod, and enabling the downcomer to sink synchronously with the reinforcing ring;
s4, after the downcomer sinks to the right position, the connecting rod and the hammer are removed, and underground water flows into the downcomer under the siphon action so as to complete well washing;
s5, placing a water pump in the precipitation pipe, and leading the underground water in the precipitation pipe to the outside of the precipitation well through a drain pipe by the water pump;
and S6, after the foundation pit construction is finished, pulling out the downcomer for recovery.
Furthermore, the reinforcing ring is welded at the bottom end of the downcomer, and two ends of the connecting rod are respectively in threaded connection with the hammer head and the pressure device.
Furthermore, the thickness of the reinforcing ring is 5-10mm, the height of the reinforcing ring is 4-6cm, and the outer diameter of the hammer head is 5-10mm smaller than the inner diameter of the precipitation pipe.
Furthermore, the hole pitch of the filter material holes is 15-25 cm.
Further, the downcomer is pulled out through the pulling machine.
The invention has the beneficial effects that:
in the conventional method, the hole is formed firstly, then the water pipe is descended, the hole forming size is large, the construction difficulty is high, the hole forming and the water pipe descending are synchronously performed, the hole drilling size is close to that of the water pipe descending, the construction difficulty is low, the water pipe descending can conveniently penetrate through a building rubbish layer under the force of a hammer head, and hole collapse is avoided; the dewatering pipe does not need manual well washing and backfilling after being in place, a nylon net, a steel wire mesh and the like do not need to be arranged on the periphery of the pipe, the dewatering pipe can be processed in advance, and recycling and turnover can be achieved.
Drawings
FIG. 1 is a schematic diagram of the operation of an embodiment of the present invention.
Fig. 2 is a schematic view of a connecting rod and a hammer head in an embodiment of the invention.
Figure 3 is a schematic view of a downcomer in an embodiment of the present invention.
FIG. 4 is a schematic illustration of the siphoning action in an embodiment of the present invention.
FIG. 5 is a schematic diagram of the water pump draining in an embodiment of the present invention.
In the figure: 1-an air compressor; 2-a drilling machine; 3-a presser; 4-a connecting rod; 5-a downcomer pipe; 6-hammer head; 7-a reinforcement ring; 8-filtering material holes; 9-a water pump; 10-a drain pipe.
Detailed Description
The invention is further described below with reference to the figures and examples.
A construction method of a dewatering well comprises the following steps:
s1, as shown in figure 1, positioning the dewatering well, and conveying an air compressor 1, a drilling machine 2, a pressure beater 3, a connecting rod 4, a hammer head 6 and a dewatering pipe 5 to the position of the dewatering well, wherein the air compressor 1 supplies energy to the drilling machine 2, the pressure beater 3 is installed on the drilling machine 2, as shown in figure 2, the hammer head 6 is in threaded connection with the bottom end of the connecting rod 4, as shown in figure 3, a filter material hole 8 is formed along the dewatering pipe 5 (the hole distance of the filter material hole 8 is 15-25cm, preferably 20cm, and is used for preventing impurities from entering the dewatering pipe 5 while water is permeated), a reinforcing ring 7 is fixedly welded at the bottom end, the outer diameter of the hammer head 6 is slightly smaller than the inner diameter of the dewatering pipe 5 and slightly larger than the inner diameter of the reinforcing ring 7 (the thickness of the reinforcing ring 7 is 5-10mm, the height is 4-6 cm.
S2, as shown in figure 1, the connecting rod 4 and the hammer head 6 are inserted into the downcomer 5, and then the top end of the connecting rod 4 is connected with the pressure device 3 through screw threads.
S3, as shown in figure 1, starting the air compressor 1, driving the hammer 6 to seal and press the reinforcing ring 7 and move downwards by the drilling machine 2 through the pressure beater 3 and the connecting rod 4 (the pressure of the seal of the hammer 6 is on the reinforcing ring 7, so as to prevent groundwater from rushing in), and the downcomer 5 sinks synchronously along with the reinforcing ring 7.
S4, after the downcomer 5 sinks to the right position, the connecting rod 4 and the hammer head 6 are removed, and as shown in figure 4, underground water flows into the downcomer 5 under the siphon action, so that well washing is completed.
S5, as shown in fig. 5, a water pump 9 is placed in the downcomer 5, and the water pump 9 leads the groundwater in the downcomer 5 to the outside of the precipitation well through the drain pipe 10.
And S6, after the foundation pit construction is finished, pulling out the downcomer 5 through a pulling machine for recycling.
In the conventional method, the hole is formed firstly, then the water pipe 5 is descended, the hole forming size is large, the construction difficulty is high, the hole forming and the water pipe 5 descending are synchronously performed, the hole drilling size is close to the size of the water pipe 5, the construction difficulty is low, the water pipe 5 can conveniently penetrate through a building rubbish layer under the force of the hammer head 6, and the hole collapse is avoided; and need not artifical well-flushing and backfill after downcomer 5 targets in place, avoided needing to carry out well-flushing with equipment such as circulating pump among the conventional art, need not to arrange nylon wire net and wire net etc. at tubular product periphery to downcomer 5 can be processed in advance, also can retrieve the turnover, under the prerequisite of guaranteeing construction quality, has reduced construction process, has saved time limit for a project and material, has reduced engineering cost.
It will be understood that modifications and variations can be made by persons skilled in the art in light of the above teachings and all such modifications and variations are intended to be included within the scope of the invention as defined in the appended claims.

Claims (5)

1. A construction method of a dewatering well is characterized in that: comprises the steps of (a) carrying out,
s1, positioning the dewatering well, and conveying an air compressor, a drilling machine, a pressure applying device, a connecting rod, a hammer head and a dewatering pipe to the position of the dewatering well, wherein the air compressor supplies energy to the drilling machine, the pressure applying device is installed on the drilling machine, the hammer head is fixedly installed at the bottom end of the connecting rod, a filter material hole is formed along the dewatering pipe, a reinforcing ring is fixedly installed at the bottom end, and the outer diameter of the hammer head is slightly smaller than the inner diameter of the dewatering pipe and slightly larger;
s2, inserting the connecting rod and the hammer head into the precipitation pipe, and then fixedly installing the top end of the connecting rod and the pressurizer;
s3, starting the air compressor, driving the hammer head to seal and press the reinforcing ring and move downwards by the drilling machine through the pressuring machine and the connecting rod, and enabling the downcomer to sink synchronously with the reinforcing ring;
s4, after the downcomer sinks to the right position, the connecting rod and the hammer are removed, and underground water flows into the downcomer under the siphon action so as to complete well washing;
s5, placing a water pump in the precipitation pipe, and leading the underground water in the precipitation pipe to the outside of the precipitation well through a drain pipe by the water pump;
and S6, after the foundation pit construction is finished, pulling out the downcomer for recovery.
2. The dewatering well construction method as claimed in claim 1, wherein: the reinforcing ring is welded at the bottom end of the downcomer, and two ends of the connecting rod are respectively in threaded connection with the hammer head and the pressure device.
3. The dewatering well construction method as claimed in claim 1, wherein: the thickness of the reinforcing ring is 5-10mm, the height is 4-6cm, and the outer diameter of the hammer head is 5-10mm smaller than the inner diameter of the precipitation pipe.
4. The dewatering well construction method as claimed in claim 1, wherein: the hole pitch of the filter material holes is 15-25 cm.
5. The dewatering well construction method as claimed in claim 1, wherein: the downcomer is pulled out through a pulling machine.
CN201910334877.7A 2019-04-24 2019-04-24 Dewatering well construction method Active CN110318661B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910334877.7A CN110318661B (en) 2019-04-24 2019-04-24 Dewatering well construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910334877.7A CN110318661B (en) 2019-04-24 2019-04-24 Dewatering well construction method

Publications (2)

Publication Number Publication Date
CN110318661A CN110318661A (en) 2019-10-11
CN110318661B true CN110318661B (en) 2021-03-30

Family

ID=68113192

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910334877.7A Active CN110318661B (en) 2019-04-24 2019-04-24 Dewatering well construction method

Country Status (1)

Country Link
CN (1) CN110318661B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111441722B (en) * 2020-03-24 2021-12-07 中国二十冶集团有限公司 Drilling construction method for pressure-bearing-resistant underwater dewatering well in ultra-deep foundation pit surrounded by ground wall
CN114016902B (en) * 2021-10-26 2023-12-08 博建建工集团有限公司 Soft soil foundation drilling equipment and construction method thereof

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100392599B1 (en) * 2001-03-28 2003-07-23 주식회사 더 디앤에스 Siphon dewatering system of underground gushing water and the pumping out method using of it
CN201158823Y (en) * 2008-02-27 2008-12-03 双流县擦耳罗师机械钻井队 Recoverable impact drill steel pipe downcast well
CN101787702A (en) * 2010-02-08 2010-07-28 上海广联建设发展有限公司 Effective vacuum dewatering method
CN102912806B (en) * 2012-09-27 2016-01-20 中交三航局第二工程有限公司 A kind of construction method of dewatering well
CN204780850U (en) * 2014-12-02 2015-11-18 青岛市勘察测绘研究院 High -efficient intubate of precipitation well point pipe machine
CN104514502A (en) * 2014-12-11 2015-04-15 中铁十九局集团有限公司 Surface precipitation deep well washing device
CN205636765U (en) * 2016-05-04 2016-10-12 上海岩土工程勘察设计研究院有限公司 Inflatable is from inhaling precipitation well
CN106836254B (en) * 2017-04-10 2018-10-26 张继红 A kind of no sand dewatering well construction method
CN207073140U (en) * 2017-08-22 2018-03-06 中国建筑第七工程局有限公司 A kind of well casing dewatering well dewatering device
CN109518706A (en) * 2018-11-19 2019-03-26 五冶集团上海有限公司 A kind of Cheng Jing is not necessarily to the dewatering well construction method of mud in the process

Also Published As

Publication number Publication date
CN110318661A (en) 2019-10-11

Similar Documents

Publication Publication Date Title
CN108149699B (en) Recoverable dewatering well device capable of achieving well fast and construction method thereof
CN110318661B (en) Dewatering well construction method
CN109026097B (en) Anti-floating anchor rod double-drill-bit hole forming construction method
CN104652436A (en) Steel sleeve soil taking and high-pressure water injection soil loosening pile pulling construction method
CN103967028A (en) Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure
CN110939137A (en) Vibration drainage anchor rod supporting structure for sand soil layer and construction method thereof
CN210370479U (en) Dewatering well construction device
CN205502043U (en) Novel light -duty well device
CN110206481A (en) Dewatering well constructing device
CN110055988A (en) For foundation pit drainage-decompression inner curtain type combined shaft and working method and application
CN106939610A (en) A kind of integrated precipitation pumping system
CN201679009U (en) Precipitation device of manual dug pile
CN212104106U (en) A vibration drainage stock supporting construction for sand type soil layer
CN211143179U (en) Fractional pressing-in type recharge well structure
CN210857250U (en) Recyclable downcomer
CN110485510B (en) Fractional press-in type recharging well structure and application method thereof
CN210140839U (en) Device for pulling out dewatering well
CN106958255A (en) A kind of architectural engineering pit precipitation self-punching type pressure reduction well
CN212129141U (en) Municipal works pile prevents excursion device
CN219491050U (en) Simple pipe well dewatering device
CN202610818U (en) Water dropping structure for foundation pit by pipe sinking of prefabricated concrete pipe
CN101343877A (en) Construction method for drilling and pressing precast concrete carrier pile
CN109759225B (en) Construction structure is handled in bored concrete pile mud circulation that punches a hole
CN104452787B (en) Construction method and equipment that a kind of vertical pumping well-point pipe is installed
JP2013036177A (en) Construction method of water collecting pipe, construction device of water collecting pipe, and construction structure of water collecting pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant