CN103967028A - Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure - Google Patents

Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure Download PDF

Info

Publication number
CN103967028A
CN103967028A CN201410227509.XA CN201410227509A CN103967028A CN 103967028 A CN103967028 A CN 103967028A CN 201410227509 A CN201410227509 A CN 201410227509A CN 103967028 A CN103967028 A CN 103967028A
Authority
CN
China
Prior art keywords
water
steel pipe
immersed tube
well
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410227509.XA
Other languages
Chinese (zh)
Inventor
陈辉
瞿学忠
姜雪岐
黄裕平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Nantong No3 Construction Group Co Ltd
Original Assignee
Jiangsu Nantong No3 Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Nantong No3 Construction Group Co Ltd filed Critical Jiangsu Nantong No3 Construction Group Co Ltd
Priority to CN201410227509.XA priority Critical patent/CN103967028A/en
Publication of CN103967028A publication Critical patent/CN103967028A/en
Pending legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses an immersed tube drainage structure, and further discloses a method for handling suddenly-produced foundation pit water bursting and fountains through the immersed tube drainage structure. When the water bursting phenomenon obviously occurs in a foundation pit and mud is sprayed out, landfill is conducted through original soil within the range of a core tube which has been dug, and then well digging and water pumping are conducted. A plurality of wells are formed for the core tube, and shaft bottom elevations are reduced till the shaft bottom elevations are below the natural ground and extend into high-water-content layers; after formation, a submerged pump is placed in each well to conduct water pumping; the upper openings of the wells are connected to form a water pumping network so that underground water can be pumped to a drainage system on the upper edge of the foundation pit; digging is continued after water inside the well is lowered below the foundation bottom elevations of the core tube; in the digging process, water pumping systems of the water pumps keeps working, blinding concrete pouring is conducted instantly after earth excavation conducted on the portions is completed; after pouring, the water pumping systems of the water pumps in the wells stop working after the raft foundation concrete pouring is completed and the strength reaches 75% of the designed strength. The drainage construction method is simple in process, and construction cost of foundation pit drainage construction can be effectively reduced.

Description

A kind of immersed tube Precipitation Structure and adopt this structure to process the method for sudden foundation ditch swelling, fountain
Technical field
The present invention relates to a kind of immersed tube Precipitation Structure.
The present invention relates to a kind of immersed tube precipitation and process the method for sudden foundation ditch swelling, fountain.
Background technology
Foundation pit dewatering mainly comprises sump precipitation method and two kinds of methods of well-points dewatering method, and wherein well-points dewatering method has that displacement is large, precipitation deeply, is not subject to the features such as soil property restriction, is applicable to rich groundwater, and foundation ditch is dark, the engineering lowering level of ground water that foundation ditch floor space is large; Well-points dewatering method is before excavation of foundation pit, at the dewatering well of foundation ditch surrounding construction some, at the bottom of dewatering well welding filter pipe, utilizes pumping equipment that the underground water in well is extracted out, makes dug soil remain the method for dry state;
It is exactly that porosity is low that these filter pipes have a common defect, and porosity is higher, and water inlet effect is just better.In addition, cast iron filament wrapped filter pipe and the intensity of cement filter pipe own are low, easy fracture, in caving ground well water pumping process, very easily rupture, and the negative consequence that causes well to scrap.
A kind of foundation ditch precast concrete pipe immersed tube Precipitation Structure of a disclosed patent name and precipitation method, the patent No. 201210102995.3, be equipped with some layers of macadam at the bottom of concrete pipe, filter with the silt to macadam bottom etc., and the engineering quantity of laying macadam is huge, successively lay according to stone size, but brought another technical barrier simultaneously, does manually how entering water layer lay? waste time and energy, finally consider when constructing structure is removed, should remove mixed earth pipe, remove again the stone laying, engineering quantity is huge.Therefore, need to provide a kind of new technical scheme to solve the problems referred to above.
Summary of the invention
For addressing the above problem, the invention provides a kind of immersed tube Precipitation Structure.
The present invention also provides a kind of immersed tube precipitation to process the method for sudden foundation ditch swelling, fountain.
The technical solution used in the present invention:
A kind of immersed tube Precipitation Structure, it comprises steel pipe, submersible pump, water pipe and gutter, in steel pipe walls, bore full suction hole, it is non-perforated pipe that this steel pipe is positioned at soil layer upper surface, described submersible pump is positioned at steel pipe bottom, described submersible pump top is connected with extraneous gutter by water pipe, and described steel pipe is embedded in raft foundation inside concrete position welding seal ring, described steel pipe welding water shutoff suitable for reading plate.
Described outer wall of steel pipe parcel nylon Dense mesh screen.
Suction hole in described steel pipe walls is the circular hole of aperture 4-6mm, pitch of holes 145-155mm.
A kind of immersed tube precipitation is processed sudden foundation ditch swelling, the method of fountain, comprise the following steps: when obviously occurring swelling ejection phenomenon in foundation ditch, and there is mud when ejection, the Core Walls Structure scope original soil having excavated is carried out to landfill, then dig a well and draw water, Core Walls Structure is arranged multiple wells, shaft bottom absolute altitude is beaten to natural below ground, stretch into high degree of water layer, after moulding, in every well, putting a submersible pump draws water, suitable for readingly be linked to be the network that draws water underground water is evacuated to foundation ditch top drainage system, treat that in well, water is down to the following 1-1.5 rice of Core Walls Structure basis end absolute altitude, continue excavation, in digging process, pumping for water pump system keeps continuous operation, this position soil excavation is complete, immediately carrying out blinding concrete builds, after blinding concrete has been built, Deng raft foundation concreting complete and reach design strength 75% after, in well, pumping system just can quit work.
Well adopts drainage steel tube well, bores full suction hole in steel pipe walls, outer wall parcel nylon Dense mesh screen, and immersed tube Cheng Jing, sinks to aquifer by the steel pipe with suction hole, and soil layer upper surface to be excavated is non-perforated pipe.
Be embedded on the steel pipe of raft foundation inside concrete position and weld three seal rings, and the steel pipe water shutoff plate of burn-oning suitable for reading, shutoff well head is all cast in raft foundation concrete.
Described pumping for water pump system comprises submersible pump and the water pipe being connected with submersible pump.
The invention has the beneficial effects as follows: the present invention adopts immersed tube to carry out precipitation, a drainage steel tube well is set, in well, putting a submersible pump draws water, suitable for readingly be linked to be the network that draws water underground water is evacuated to foundation ditch top drainage system, Deng raft foundation concreting complete and reach design strength 75% after, in well, pumping system just can quit work, and dewatering construction method flow process is simple, can effectively reduce the construction cost of foundation pit dewatering construction.
Brief description of the drawings
Fig. 1 is the schematic diagram of immersed tube Precipitation Structure.
1, steel pipe, 2, nylon Dense mesh screen, 3, submersible pump, 4, water pipe, 5, cable, 6, suction hole, 7, seal ring, 8, water shutoff plate, 9, non-perforated pipe, 10, gutter.
Detailed description of the invention
Following embodiment is only for the present invention is described, but can not limit protection scope of the present invention.
As shown in Figure 1, a kind of immersed tube Precipitation Structure of the present invention, it comprises steel pipe 1, submersible pump 3, water pipe 4 and gutter 10, on steel pipe 1 wall, bore full suction hole 6, this suction hole 6 adopts drilling tool to drill through, terrestrial operation, quite convenient, this suction hole 6 has two effects in addition, can make water in suction hole 6, enter fast on the one hand, instead of only only depend on a steel pipe opening to enter; Suction hole 6 outer wrapping nylon Dense mesh screens 2, can enter water on the other hand, and the silt that is greater than nylon Dense mesh screen aperture can not enter, and silt is just deposited on the end, hole.
It is non-perforated pipe 9 that this steel pipe 1 is positioned at soil layer upper surface, and submersible pump 3 is positioned at steel pipe 1 bottom, and submersible pump 3 tops are connected with extraneous gutter 10 by water pipe 4, the cable 5 outside submersible pump 3 connecting wells, by water pump by outside interior open caisson steel pipe 1 water extraction system.
Steel pipe 1 is embedded in raft foundation inside concrete position welding seal ring 7, and seal ring 7 is the ring flat-plates for preventing seepage, adds exactly the path of the prolongation water maceration of several times, has greatly increased maceration resistance and has reached impervious object, steel pipe 1 welding water shutoff suitable for reading plate 8.For shutoff well head is all cast in raft foundation concrete.
Steel pipe 1 outer wall parcel nylon Dense mesh screen 2.Here said nylon Dense mesh screen is equivalent to water strainer, the silt in can filtering water quality.
Suction hole 6 on steel pipe 1 wall is the circular hole of aperture 4-6mm, pitch of holes 145-155mm.Can filtering be greater than earth, plastics, metal impurities of this size etc.
Adopt above-mentioned immersed tube Precipitation Structure to process the method for sudden foundation ditch swelling, fountain, when obviously occurring swelling ejection phenomenon in foundation ditch, and there is mud when ejection, the Core Walls Structure scope original soil having excavated is carried out to landfill (reason is equilibrium water pressure), dig a well and draw water subsequently, 300 ㎡ Core Walls Structures are arranged 6 wells, and shaft bottom absolute altitude is beaten to natural below ground 38m, stretches into high degree of water layer.
Well adopts drainage steel tube well, well adopts the common steel tube 1 of 400 millimeters of diameters, on steel pipe 1 wall, bore the circular hole (suction hole 6) of full aperture 4-6mm, play into water effect, water enters in steel pipe 1 from circular hole, pitch of holes is 145-155mm, outer wall parcel nylon Dense mesh screen 2, to make water strainer, filtering mud impurity, to sink to aquifer with the steel pipe of suction hole 6,-10.200m is non-perforated pipe 9 to soil layer upper surface to be excavated, and thick to welding three 5mm between-9.500m at steel pipe-10.100m, wide 100mm Plate Welding seal ring 7, after moulding, in every well, putting a submersible pump 3 draws water, suitable for readingly be linked to be the network that draws water underground water is evacuated to foundation ditch top drainage system (gutter 10), form pumping for water pump system from digging a well to, pumping for water pump system comprises submersible pump 3 and the water pipe 4 being connected with submersible pump 3, cable 5 outside submersible pump 3 connecting wells, constantly draw water, water draws up by water pipe 4, discharge from gutter 10 again, after 30 hours, in well, water continually, but it is many to be down to the following 1m of Core Walls Structure basis end absolute altitude, adopt drainage steel tube well, after water level is down to a certain degree, can continue excavation, meanwhile, in digging process, pumping for water pump system keeps continuous operation (because underground water ceaselessly oozes out), reduce the impact on the duration.
This position soil excavation is complete, immediately carrying out blinding concrete builds, after blinding concrete has been built, Deng raft foundation concreting complete and reach design strength 75% after, in 6 wells, pumping system just can quit work, and after treating foundation construction, raft foundation concrete strength has reached 75% of design strength, pumping system quits work (periphery secondary Application of light well point precipitation continue into), has controlled quicksand swelling.
Be embedded on the steel pipe 1 of raft foundation inside concrete position and weld three thick, the wide 100mm Plate Welding of 5mm seal rings 7, and steel pipe 1 is suitable for reading, and (clip-9.350mm is with upper part steel pipe, and at this place's welded steel pipe) the 5mm steel plate welding water shutoff plate 8 of burn-oning, shutoff well head is all cast in raft foundation concrete.
This falls water treatment structure and adopts the method for holing into well, and terrestrial operation is got up convenient, bores full suction hole in steel pipe lower end, suction hole makes into water fast, and current are by outside the suction pump extraction system in shaft bottom, and outer wall of steel pipe wraps up nylon Dense mesh screen, filtering silt, after construction, dismounting is also very convenient.
The present invention adopts immersed tube to carry out precipitation, a drainage steel tube well is set, in well, putting a submersible pump draws water, suitable for readingly be linked to be the network that draws water underground water is evacuated to foundation ditch top drainage system, Deng raft foundation concreting complete and reach design strength 75% after, in well, pumping system just can quit work, and dewatering construction method flow process is simple, can effectively reduce the construction cost of foundation pit dewatering construction.

Claims (7)

1. an immersed tube Precipitation Structure, it is characterized in that: it comprises steel pipe, submersible pump, water pipe and gutter, in steel pipe walls, bore full suction hole, it is non-perforated pipe that this steel pipe is positioned at soil layer upper surface, described submersible pump is positioned at steel pipe bottom, described submersible pump top is connected with extraneous gutter by water pipe, and described steel pipe is embedded in raft foundation inside concrete position welding seal ring, described steel pipe welding water shutoff suitable for reading plate.
2. a kind of immersed tube Precipitation Structure according to claim 1, is characterized in that: described outer wall of steel pipe parcel nylon Dense mesh screen.
3. a kind of immersed tube Precipitation Structure according to claim 1, is characterized in that: the suction hole in described steel pipe walls is the circular hole of aperture 4-6mm, pitch of holes 145-155mm.
4. an immersed tube precipitation is processed sudden foundation ditch swelling, the method of fountain, it is characterized in that, comprise the following steps: when obviously occurring swelling ejection phenomenon in foundation ditch, and there is mud when ejection, the Core Walls Structure scope original soil having excavated is carried out to landfill, then dig a well and draw water, Core Walls Structure is arranged multiple wells, shaft bottom absolute altitude is beaten to natural below ground, stretch into high degree of water layer, after moulding, in every well, putting a submersible pump draws water, suitable for readingly be linked to be the network that draws water underground water is evacuated to foundation ditch top drainage system, treat that in well, water is down to the following 1-1.5 rice of Core Walls Structure basis end absolute altitude, continue excavation, in digging process, pumping for water pump system keeps continuous operation, this position soil excavation is complete, immediately carrying out blinding concrete builds, after blinding concrete has been built, Deng raft foundation concreting complete and reach design strength 75% after, in well, pumping system just can quit work.
5. a kind of immersed tube precipitation according to claim 4 is processed the method for sudden foundation ditch swelling, fountain, it is characterized in that: well adopts drainage steel tube well, in steel pipe walls, bore full suction hole, outer wall parcel nylon Dense mesh screen, immersed tube Cheng Jing, steel pipe with suction hole is sunk to aquifer, and soil layer upper surface to be excavated is non-perforated pipe.
6. a kind of immersed tube precipitation according to claim 5 is processed the method for sudden foundation ditch swelling, fountain, it is characterized in that: be embedded on the steel pipe of raft foundation inside concrete position and weld seal ring, and the steel pipe water shutoff plate of burn-oning suitable for reading, shutoff well head is all cast in raft foundation concrete.
7. a kind of immersed tube precipitation according to claim 4 is processed the method for sudden foundation ditch swelling, fountain, it is characterized in that: described pumping for water pump system comprises submersible pump and the water pipe being connected with submersible pump.
CN201410227509.XA 2014-05-27 2014-05-27 Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure Pending CN103967028A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410227509.XA CN103967028A (en) 2014-05-27 2014-05-27 Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410227509.XA CN103967028A (en) 2014-05-27 2014-05-27 Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure

Publications (1)

Publication Number Publication Date
CN103967028A true CN103967028A (en) 2014-08-06

Family

ID=51236997

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410227509.XA Pending CN103967028A (en) 2014-05-27 2014-05-27 Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure

Country Status (1)

Country Link
CN (1) CN103967028A (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452828A (en) * 2014-10-31 2015-03-25 武汉一冶建筑安装工程有限责任公司 Basement ramp piping point drainage and blocking handling method
CN104452827A (en) * 2014-10-16 2015-03-25 中国电建集团华东勘测设计研究院有限公司 Concrete dam base spring opening processing method
CN105937243A (en) * 2016-06-07 2016-09-14 中国十七冶集团有限公司 Novel concrete pipe precipitation well device for basement
CN106939610A (en) * 2017-05-09 2017-07-11 青岛东捷建设工程有限公司 A kind of integrated precipitation pumping system
CN107326918A (en) * 2017-08-18 2017-11-07 云南省建设投资控股集团有限公司 A kind of concealed type, which passes through raft plate, can block impervious sump and its construction technology
CN108018859A (en) * 2017-12-12 2018-05-11 中国建筑第八工程局有限公司 Foundation Pit Pouring emergency processing method and structure
CN108487276A (en) * 2018-04-27 2018-09-04 陕西建工机械施工集团有限公司 A kind of embed-type shallow-layer combined water drain pipe and construction method
CN108894213A (en) * 2018-06-19 2018-11-27 中铁上海工程局集团有限公司 A kind of artificial digging pile passes through the construction method of rich water drifting sand layer
CN110130375A (en) * 2019-04-30 2019-08-16 江苏楼翔建设有限公司 A foundation pit dewatering device
CN110925018A (en) * 2019-12-02 2020-03-27 河南科技大学 Pump room construction method and pump room construction dewatering system in tunnel connection channel
CN110939143A (en) * 2019-11-29 2020-03-31 中国建筑第四工程局有限公司 Simple and easy core section of thick bamboo stepping water conservancy diversion drainage structures
CN111350191A (en) * 2020-03-04 2020-06-30 中交第三航务工程勘察设计院有限公司 Bucket type foundation structure pumping system and construction process thereof
CN111764396A (en) * 2020-07-07 2020-10-13 中建一局集团建设发展有限公司 Construction method for water-rich stratum pit-in-pit
CN114658018A (en) * 2022-05-23 2022-06-24 德州黄河建业工程有限责任公司维修养护分公司 Water lowering and draining method combining water conservancy project foundation pit and pipe well with light well point

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202577326U (en) * 2012-02-14 2012-12-05 江苏江中集团有限公司 Water lowering device for mine pit
CN103161172A (en) * 2012-05-29 2013-06-19 中国二十二冶集团有限公司 Elevator shaft bottom precipitation construction method
CN203174616U (en) * 2013-04-02 2013-09-04 中建城市建设发展有限公司 Clay foundation rain falling and water saving system
CN103343543A (en) * 2013-07-09 2013-10-09 中国一冶集团有限公司 Foundation pit dewatering well pressure-reduction-type plugging method
CN204000909U (en) * 2014-05-27 2014-12-10 江苏南通三建集团有限公司 A kind of immersed tube Precipitation Structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202577326U (en) * 2012-02-14 2012-12-05 江苏江中集团有限公司 Water lowering device for mine pit
CN103161172A (en) * 2012-05-29 2013-06-19 中国二十二冶集团有限公司 Elevator shaft bottom precipitation construction method
CN203174616U (en) * 2013-04-02 2013-09-04 中建城市建设发展有限公司 Clay foundation rain falling and water saving system
CN103343543A (en) * 2013-07-09 2013-10-09 中国一冶集团有限公司 Foundation pit dewatering well pressure-reduction-type plugging method
CN204000909U (en) * 2014-05-27 2014-12-10 江苏南通三建集团有限公司 A kind of immersed tube Precipitation Structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
沈琦: ""深基坑施工技术"", 《中国市政工程》 *

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104452827A (en) * 2014-10-16 2015-03-25 中国电建集团华东勘测设计研究院有限公司 Concrete dam base spring opening processing method
CN104452827B (en) * 2014-10-16 2016-06-29 中国电建集团华东勘测设计研究院有限公司 A kind of processing method at Concrete Dam spring
CN104452828A (en) * 2014-10-31 2015-03-25 武汉一冶建筑安装工程有限责任公司 Basement ramp piping point drainage and blocking handling method
CN105937243A (en) * 2016-06-07 2016-09-14 中国十七冶集团有限公司 Novel concrete pipe precipitation well device for basement
CN106939610A (en) * 2017-05-09 2017-07-11 青岛东捷建设工程有限公司 A kind of integrated precipitation pumping system
CN107326918A (en) * 2017-08-18 2017-11-07 云南省建设投资控股集团有限公司 A kind of concealed type, which passes through raft plate, can block impervious sump and its construction technology
CN108018859A (en) * 2017-12-12 2018-05-11 中国建筑第八工程局有限公司 Foundation Pit Pouring emergency processing method and structure
CN108487276A (en) * 2018-04-27 2018-09-04 陕西建工机械施工集团有限公司 A kind of embed-type shallow-layer combined water drain pipe and construction method
CN108894213A (en) * 2018-06-19 2018-11-27 中铁上海工程局集团有限公司 A kind of artificial digging pile passes through the construction method of rich water drifting sand layer
CN110130375A (en) * 2019-04-30 2019-08-16 江苏楼翔建设有限公司 A foundation pit dewatering device
CN110939143A (en) * 2019-11-29 2020-03-31 中国建筑第四工程局有限公司 Simple and easy core section of thick bamboo stepping water conservancy diversion drainage structures
CN110925018A (en) * 2019-12-02 2020-03-27 河南科技大学 Pump room construction method and pump room construction dewatering system in tunnel connection channel
CN110925018B (en) * 2019-12-02 2021-06-25 河南科技大学 Construction method and precipitation system of pump house in tunnel communication channel
CN111350191A (en) * 2020-03-04 2020-06-30 中交第三航务工程勘察设计院有限公司 Bucket type foundation structure pumping system and construction process thereof
CN111350191B (en) * 2020-03-04 2021-08-31 中交第三航务工程勘察设计院有限公司 Bucket type foundation structure pumping system and construction process thereof
CN111764396A (en) * 2020-07-07 2020-10-13 中建一局集团建设发展有限公司 Construction method for water-rich stratum pit-in-pit
CN114658018A (en) * 2022-05-23 2022-06-24 德州黄河建业工程有限责任公司维修养护分公司 Water lowering and draining method combining water conservancy project foundation pit and pipe well with light well point

Similar Documents

Publication Publication Date Title
CN103967028A (en) Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure
CN100480475C (en) Controllable one-well lamina precipitation construction method
CN205314118U (en) Drainage system on large -scale basis
CN102226337B (en) Three-dimensional drain and construction method thereof
CN105178289A (en) Prefabricated downcast pipe pile in building foundation pit and use method thereof
CN113279421B (en) Vacuum dewatering process for deep foundation pit
CN204000909U (en) A kind of immersed tube Precipitation Structure
CN206706792U (en) Deep foundation pit precipitation well construction
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN102433886A (en) Construction method for adding dewatering well in water collecting well
CN109083177B (en) Precipitation process of integrated directional vacuum well point pipe
CN106759241A (en) A kind of vacuum method basement process discharge structure
CN203530996U (en) Multi-well-point combined type precipitation facility
CN113585311B (en) Vacuum dewatering method with dewatering well penetrating through deep foundation pit
CN205012325U (en) Prefabricated precipitation tubular pile in building foundation
CN110409420B (en) Underground continuous wall with pit facing surface and precipitation function
CN108708385B (en) Integrated directional vacuum well point pipe
CN205444216U (en) Depth well foundation pit dewatering system on compound stratum of large -scale foundation ditch
CN212336250U (en) Pipe jacking connection guide row structure
CN210797603U (en) Pumping well shaft
CN113356127A (en) Method for reducing saturation line of historical remaining tailing pond
CN103669333B (en) It is easy to the friction pile of vacuum-dewatering
CN205314117U (en) Foundation structure that draw water is carried out with centrifugal pump
CN204551507U (en) A kind of rock foundation ductule local dewatering device
CN104060636B (en) Pressure release anti-float method during high water level regional architecture foundation construction and device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20140806

RJ01 Rejection of invention patent application after publication