CN201679009U - Precipitation device of manual dug pile - Google Patents

Precipitation device of manual dug pile Download PDF

Info

Publication number
CN201679009U
CN201679009U CN2010201356843U CN201020135684U CN201679009U CN 201679009 U CN201679009 U CN 201679009U CN 2010201356843 U CN2010201356843 U CN 2010201356843U CN 201020135684 U CN201020135684 U CN 201020135684U CN 201679009 U CN201679009 U CN 201679009U
Authority
CN
China
Prior art keywords
precipitation device
excavated pile
hand excavated
column skeleton
precipitation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010201356843U
Other languages
Chinese (zh)
Inventor
李永迪
李再春
王太忠
赵志平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan No2 Engineering Co Ltd
Original Assignee
Hunan No2 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan No2 Engineering Co Ltd filed Critical Hunan No2 Engineering Co Ltd
Priority to CN2010201356843U priority Critical patent/CN201679009U/en
Application granted granted Critical
Publication of CN201679009U publication Critical patent/CN201679009U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

A precipitation device of a manual dug pile comprises a columnar framework (5) which consists of a plurality of longitudinal reinforcing steel bars (1) and a plurality of annular reinforcing steel bars (2), wherein a filter screen (3) is arranged at the inside of the columnar framework, and the lower end of the columnar framework (5) is contracted into a pointed cone (6) which is downward; a bearing plate (7) is arranged at the top end of the columnar framework (5). The precipitation device can realize stratification advance precipitation in a manual dug pile hole, effectively improve the construction conditions of digging, and enhance the safety of construction.

Description

A kind of precipitation device of hand excavated pile
Technical field
The utility model belongs to the builing industry construction and uses supporting facility, relates to the precipitation device in a kind of hand excavated pile stake hole.
Background technology
Hand excavated pile is applicable to no underground water or less clay, the silty clay of underground water, and the argillic horizon that contains a spot of sand, sandy gravel, slurry calculus adopts, and is particularly suitable for loess formation and adopts.Because its stress performance is reliable, does not need large-scale plant, construction manipulation process is simple, and cost is lower, also often adopts during rich groundwater.When rich groundwater, infiltration or water yield are bigger, during the stake borehole, according to circumstances generally adopt following measure respectively: 1, seep water on a small quantity and in the stake hole, dig little sump,, muddy water is hung out together with cutting the earth with using well-bucket; 2, a large amount of infiltrations can be dug dark collecting well earlier in the stake hole, establish small-sized submersible pump underground water is discharged outside the stake hole, with cutting the earth with deepening collecting well; When 3, water yield was very big, with a leading excavation, underground water combined in this hole near making, and with submersible pump underground water is extracted out.Adopt said method, execution conditions are all poor, form quicksand under the situations of a large amount of infiltrations easily, and unsafe factor is more, and excavate 30-50 centimetre at every turn and just must carry out retaining wall deeply, and construction speed is slower.
The utility model content
The technical problems to be solved in the utility model is at the deficiencies in the prior art, to provide a kind of precipitation device of hand excavated pile, by the leading precipitation of layering in the stake hole of hand digging, the execution conditions when improving borehole, enhancing safety of construction.
The technical scheme that the utility model adopts for achieving the above object is, the precipitation device of described hand excavated pile comprises the column skeleton of being made up of many longitudinal reinforcements and multiple tracks steel hoop, described column skeleton inboard is provided with filter screen, its design feature is, the lower end of described column skeleton is punctured into a sharp cone distal and pointed cone down, and column skeleton top is provided with force bearing plate.
Below the utility model made further specify.
Referring to Fig. 1, the precipitation device of the utility model hand excavated pile comprises the column skeleton of being made up of many longitudinal reinforcements 1 and multiple tracks steel hoop 25, described column skeleton inboard is provided with filter screen 3, and its design feature is, the lower end of described column skeleton 5 is punctured into a sharp cone distal 6 and pointed cone down; Referring to Fig. 2 or Fig. 3, column skeleton 5 tops are provided with force bearing plate 7.
Referring to Fig. 4, the using method of the utility model device is, when hand excavated pile is excavated to the sand pebble layer of rich groundwater or mud, precipitation device of the present invention is hung in the hole 10, force bearing plate 7 is installed on the top of captation (that is column skeleton 5), adopt the mode of hammering that this precipitation device is squeezed in the sand pebble layer or mud to be excavated, the underground water in the soil layer enters the precipitation device through filter screen 3, adopts submersible pump in the precipitation device water to be extracted out again; Then the soil layer behind the precipitation is excavated, behind excavation one deck, the precipitation device is squeezed into one deck downwards, and then draw water, excavate, so circulation is until passing sand pebble layer or mud.Because of adopting the mode of hammering, this precipitation device squeezes into soil layer to be excavated, realize the leading precipitation of layering, made soil layer substantially dry when excavation of rich groundwater, improved execution conditions greatly, the quicksand phenomenon that has occurred easily when having avoided band water excavation has guaranteed the safety of constructing.
As known from the above, the utility model is a kind of precipitation device of hand excavated pile, and by the leading precipitation of layering in the stake hole of hand digging, the execution conditions when having improved borehole have strengthened safety of construction.
Description of drawings:
Fig. 1 is the overall structure schematic diagram of a kind of embodiment of the utility model;
Fig. 2 is a kind of example structure schematic diagram of force bearing plate;
Fig. 3 is a force bearing plate shown in Figure 2 bottom surface structural representation up;
Fig. 4 is a kind of working state schematic representation of the present utility model.
In the drawings:
The 1-longitudinal reinforcement, the 2-steel hoop, the 3-filter screen,
The stake point that 4-extends downwards, 5-column skeleton, the 6-sharp cone distal,
The 7-force bearing plate, the 8-reinforced cap, 9-soil layer to be excavated,
10-hand digging stake hole.
The specific embodiment
As shown in Figure 1, the precipitation device in the described hand excavated pile comprises the column skeleton of being made up of many (as five) longitudinal reinforcements 1 and multiple tracks (Ru Sidao) steel hoop 25, and described column skeleton inboard is provided with filter screen 3; The lower end of described column skeleton 5 is punctured into a sharp cone distal 6 and pointed cone down; Referring to Fig. 2 or Fig. 3, column skeleton 5 tops are provided with force bearing plate 7.Force bearing plate 7 can be made the structure that is similar to pile cover, correspondence promptly is set in the bottom surface of force bearing plate 7 is nested with reinforced cap 8 on each longitudinal reinforcement 1 top.
Referring to Fig. 1, the bottom of described sharp cone distal 6 can be provided with the stake point 4 of downward extension.
Described longitudinal reinforcement 1 and steel hoop 2 firm welding are formed skeleton.
The top of described longitudinal reinforcement 1 can exceed goes up steel hoop 2 most one so that with the flexible connection of force bearing plate.
Described filter screen adopts the press strip reinforcing bar to be fixed on the column skeleton.

Claims (6)

1. the precipitation device of a hand excavated pile, comprise the column skeleton of forming by many longitudinal reinforcements (1) and multiple tracks steel hoop (2) (5), described column skeleton inboard is provided with filter screen (3), it is characterized in that, the lower end of described column skeleton (5) is punctured into a sharp cone distal (6) and pointed cone down; Column skeleton (5) top is provided with force bearing plate (7).
2. according to the precipitation device of the described hand excavated pile of claim 1, it is characterized in that the bottom surface of force bearing plate (7) is provided with correspondence and is nested with reinforced cap (8) on each longitudinal reinforcement (1) top.
3. according to the precipitation device of the described hand excavated pile of claim 1, it is characterized in that the bottom of described sharp cone distal (6) is provided with the stake point (4) of downward extension.
4. according to the precipitation device of the described hand excavated pile of claim 1, it is characterized in that described longitudinal reinforcement (1) is welded to form skeleton with steel hoop (2).
5. according to the precipitation device of the described hand excavated pile of claim 1, it is characterized in that the top of described longitudinal reinforcement (1) exceeds goes up one steel hoop (2) most.
6. according to the precipitation device of the described hand excavated pile of claim 1, it is characterized in that described filter screen adopts the press strip reinforcing bar to be fixed on the column skeleton.
CN2010201356843U 2010-03-19 2010-03-19 Precipitation device of manual dug pile Expired - Fee Related CN201679009U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201356843U CN201679009U (en) 2010-03-19 2010-03-19 Precipitation device of manual dug pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201356843U CN201679009U (en) 2010-03-19 2010-03-19 Precipitation device of manual dug pile

Publications (1)

Publication Number Publication Date
CN201679009U true CN201679009U (en) 2010-12-22

Family

ID=43344060

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201356843U Expired - Fee Related CN201679009U (en) 2010-03-19 2010-03-19 Precipitation device of manual dug pile

Country Status (1)

Country Link
CN (1) CN201679009U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877477A (en) * 2012-09-20 2013-01-16 中铁隧道勘测设计院有限公司 Temporary column structure with function of dewatering well and construction method thereof
CN106321188A (en) * 2016-11-21 2017-01-11 蚌埠金威滤清器有限公司 Engine oil coarse filter element for motorcycle
CN106801426A (en) * 2017-01-25 2017-06-06 上海二十冶建设有限公司 Hole wall infiltration remover and the application method of artificial digging pile
CN111173013A (en) * 2019-12-24 2020-05-19 福州市第三建筑工程公司 Progressive direct-pressure water intake pipe well

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877477A (en) * 2012-09-20 2013-01-16 中铁隧道勘测设计院有限公司 Temporary column structure with function of dewatering well and construction method thereof
CN106321188A (en) * 2016-11-21 2017-01-11 蚌埠金威滤清器有限公司 Engine oil coarse filter element for motorcycle
CN106801426A (en) * 2017-01-25 2017-06-06 上海二十冶建设有限公司 Hole wall infiltration remover and the application method of artificial digging pile
CN106801426B (en) * 2017-01-25 2019-03-15 上海二十冶建设有限公司 The hole wall infiltration remover and application method of artificial digging pile
CN111173013A (en) * 2019-12-24 2020-05-19 福州市第三建筑工程公司 Progressive direct-pressure water intake pipe well
CN111173013B (en) * 2019-12-24 2021-07-09 福州市第三建筑工程公司 Progressive direct-pressure water intake pipe well

Similar Documents

Publication Publication Date Title
CN103882881B (en) Go deep into rock construction method under water
CN204253056U (en) A kind of shield machine export & import reinforcing structure
CN201679009U (en) Precipitation device of manual dug pile
CN104234062A (en) Landslide control method of ionic type rare earth in-situ mineral leaching stope
CN202881958U (en) Foundation pit supporting structure with water falling function
CN202689009U (en) Steel sheet pile and tubular pile combined foundation pit supporting structure
CN102995643A (en) Underground-space steel truss foundation pit supporting structure and construction method thereof
CN201843135U (en) Composite foundation pile in power transmission line
CN103031838A (en) Bridge site deep-layer displacement method
CN102373706A (en) Pile sinking device and method for middle digging hydraulic method pre-stressed centrifugal pipe pile (square pile)
CN106939610A (en) A kind of integrated precipitation pumping system
CN203878590U (en) Post-reinforcement structure for cast-in-place piles
CN111636821A (en) Pore-forming method for horizontal diversion hole of ionic rare earth ore
CN201078234Y (en) Integral hydraulic pressure steel sheet piling curtain of vertical shaft construction overflowing sand bed
CN106381878A (en) Environment-friendly dismantling construction method for two-layer steel sheet pile and soil core composite cofferdam
CN102953382A (en) Pile sinking device and pile sinking method for steel pipe pile by central stirring and reverse drawing
CN207004431U (en) Soft soil foundation exciting drilling device
CN102251518B (en) Rotary pump perforating piling machine
CN105040705A (en) Ground foundation treatment construction technology under multi-karst-cave geological conditions
CN103195077A (en) Dam foundation reinforcement frame structure and dam foundation reinforcement method
CN201407051Y (en) Karst formation pile hole wall protection structure
CN203129163U (en) Reinforcing framework structure for dam foundation
CN206942768U (en) A kind of superficial stratum piping lane one-shot forming development machine
CN203034462U (en) A steel truss support structure for a ground pit of underground space
CN202359564U (en) Arch steel sheet pile supporting structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101222

Termination date: 20180319

CF01 Termination of patent right due to non-payment of annual fee