CN110310023A - A kind of project scheduling method, equipment, server and computer readable storage medium - Google Patents

A kind of project scheduling method, equipment, server and computer readable storage medium Download PDF

Info

Publication number
CN110310023A
CN110310023A CN201910529345.9A CN201910529345A CN110310023A CN 110310023 A CN110310023 A CN 110310023A CN 201910529345 A CN201910529345 A CN 201910529345A CN 110310023 A CN110310023 A CN 110310023A
Authority
CN
China
Prior art keywords
employee
subset
project
cost
wage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910529345.9A
Other languages
Chinese (zh)
Inventor
侯村林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ping An Puhui Enterprise Management Co Ltd
Original Assignee
Ping An Puhui Enterprise Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ping An Puhui Enterprise Management Co Ltd filed Critical Ping An Puhui Enterprise Management Co Ltd
Priority to CN201910529345.9A priority Critical patent/CN110310023A/en
Publication of CN110310023A publication Critical patent/CN110310023A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06398Performance of employee with respect to a job function
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • Development Economics (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Educational Administration (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Game Theory and Decision Science (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the invention discloses a kind of project scheduling method, equipment, server and computer readable storage mediums, this method comprises: receiving the project scheduling request that terminal is sent;Gather from the employee to match with performance information required by project task is filtered out in employee database;Determine to complete at least one employee's subset of the goal task amount from employee set;According to the original wage of each employee in each employee's subset, determine that the employee of each employee's subset completes the wage cost of the goal task amount;The wage cost of the goal task amount is completed according to the employee of each employee's subset, target employee's subset is determined from least one described employee's subset according to preset rules, to call the employee of the target employee subset to execute the project task, to realize project scheduling task, to improve the efficiency of project scheduling.

Description

A kind of project scheduling method, equipment, server and computer readable storage medium
Technical field
The present invention relates to technical field of data processing more particularly to a kind of project scheduling method, equipment, server and calculating Machine readable storage medium storing program for executing.
Background technique
What project task scheduling system on the market was directed at present mainly guarantees employee skill and skill needed for project task The matching of energy, Consideration is excessively single, thus leads to not correctly provide related to project task other influences factor The scheduling scheme of connection, it is lower so as to cause the accuracy of project scheduling, influence the execution of project task.Therefore how more effectively The efficiency and accuracy that improve project scheduling become the emphasis of research.
Summary of the invention
The embodiment of the invention provides a kind of project scheduling method, equipment, server and computer readable storage mediums, can It is identified project scheduling scheme according to wage cost, improves the efficiency of project scheduling.
In a first aspect, the embodiment of the invention provides a kind of project scheduling methods, this method comprises:
Receive the project scheduling request that terminal is sent, wherein carry project task in the project scheduling request and wanted The performance information and goal task amount asked;
Gather from the employee to match with performance information required by the project task is filtered out in employee database, institute Stating in employee's set includes at least one employee identification;
According to the working efficiency of each employee in employee set, determine to complete the mesh from employee set Mark at least one employee's subset of task amount, wherein include at least one employee in each employee's subset;
The original wage of each employee in each employee's subset is obtained, and according to the original of each employee in each employee's subset Beginning wage determines that the employee of each employee's subset completes the wage cost of the goal task amount;
The wage cost that the goal task amount is completed according to the employee of each employee's subset, according to preset rules from Target employee's subset is determined at least one described employee's subset, to call described in employee's execution of the target employee subset Project task.
Further, the time cost of the project task is carried in the project scheduling request;It is described according to The working efficiency of each employee in employee's set, determines to complete at least the one of the goal task amount from employee set Zooid's brigade collection, comprising:
Obtain the working efficiency of each employee in employee's set;
According to the working efficiency of each employee and the goal task amount in employee set, employee's set is determined Employee complete the time cost of the goal task amount;
Determine that the employee of employee set completes the time cost of the goal task amount and is less than the project scheduling and asks Seek at least one employee's subset of the time cost of the project task of middle carrying.
Further, the working efficiency for obtaining each employee in employee's set, from employee set really Make at least one the employee's subset for completing the goal task amount, comprising:
Obtain the grade of skill of each employee in employee's set;
According to the corresponding relationship of preset grade of skill and working efficiency, determination and each employee in employee set The corresponding working efficiency of grade of skill, and from employee set determine to complete at least one member of the goal task amount Brigade collection.
Further, the original wage according to each employee in each employee's subset, determines every zooid The employee of brigade collection completes the wage cost of the goal task amount, comprising:
According to the working efficiency of each employee and the goal task amount in each employee's subset, each employee's is determined The employee of collection completes the time cost of the goal task amount;
According to the employee of the original wage of each employee and each employee's subset complete the goal task amount when Between cost, the employee for calculating each employee's subset completes the sum of the original wage of the goal task amount, obtains described every The employee of zooid's brigade collection completes the wage cost of the goal task amount.
Further, project cost threshold value is carried in the project scheduling request;It is described sub according to each employee The employee of collection completes the wage cost of the goal task amount, determines from least one described employee's subset according to preset rules Target employee subset out, comprising:
Determine that the wage cost is less than or equal to the project cost threshold value from least one described employee's subset At least one employee's subset;
It is complete less than or equal to the employee of at least one employee's subset of the project cost threshold value to detect the wage cost At the time cost of the goal task amount, and determine the smallest target employee subset of the time cost.
Further, described to determine the wage cost less than or equal to described from least one described employee's subset After at least one employee's subset of project cost threshold value, further includes:
It is complete less than or equal to the employee of at least one employee's subset of the project cost threshold value to obtain the wage cost At the wage cost of the goal task amount;
Complete the wage cost of institute's goal task amount sequence from small to large according to each employee's subset, to it is described at least One zooid's brigade collection is ranked up, and is stored to dispatch list, so that user calls employee's subset to hold according to the dispatch list The row project task.
Further, described to determine target employee from least one described employee's subset according to preset rules
After subset, comprising:
Into the target employee subset, the corresponding user terminal of each employee identification sends a notification message, described in notice The employee of target employee's subset is confirmed whether to execute the project task;
If being not received by the corresponding use of target employee identification in the target employee subset in preset time range The confirmation instruction that family terminal returns, then obtain the target employee identification and correspond to the original work that employee completes the goal task amount Money;
Employee corresponding with the target employee identification is filtered out from other employee's subsets completes the goal task amount Original wage matched employee identification within a preset range, and the matched employee identification is replaced into the target employee subset In target employee identification;
The employee of target employee's subset after replacing the target employee identification is called to execute the project task.
Second aspect, the embodiment of the invention provides a kind of project scheduling equipment, which includes for holding The unit of the project scheduling method of the above-mentioned first aspect of row.
The third aspect, the embodiment of the invention provides a kind of server, including processor, input equipment, output equipment and Memory, the processor, input equipment, output equipment and memory are connected with each other, wherein the memory is for storing branch The computer program that project scheduling equipment executes the above method is held, the computer program includes program instruction, the processor It is configured for calling described program instruction, the method for executing above-mentioned first aspect.
Fourth aspect, the embodiment of the invention provides a kind of computer readable storage medium, the computer storage medium It is stored with computer program, the computer program includes program instruction, and described program instruction makes institute when being executed by a processor State the method that processor executes above-mentioned first aspect.
The embodiment of the present invention, by being filtered out from employee database required by the project scheduling sent with terminal request Employee's set that performance information matches determines at least one employee for completing goal task amount from employee set Collection, and according to the original wage of each employee in each employee's subset, determine that the employee of each employee's subset completes The wage cost of the goal task amount, and according to the wage cost, according to preset rules from least one described employee Target employee's subset is determined in subset, to call the employee of the target employee subset to execute the project task, thus real Existing project scheduling task, to improve the efficiency of project scheduling.
Detailed description of the invention
Technical solution in order to illustrate the embodiments of the present invention more clearly, below will be to needed in embodiment description Attached drawing is briefly described, it should be apparent that, drawings in the following description are some embodiments of the invention, general for this field For logical technical staff, without creative efforts, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is a kind of schematic flow diagram of project scheduling method provided in an embodiment of the present invention;
Fig. 2 is the schematic flow diagram of another project scheduling method provided in an embodiment of the present invention;
Fig. 3 is a kind of schematic block diagram of project scheduling equipment provided in an embodiment of the present invention;
Fig. 4 is a kind of schematic block diagram of server provided in an embodiment of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are some of the embodiments of the present invention, instead of all the embodiments.Based on this hair Embodiment in bright, every other implementation obtained by those of ordinary skill in the art without making creative efforts Example, shall fall within the protection scope of the present invention.
Project scheduling method provided in an embodiment of the present invention can be executed by a kind of project scheduling system, wherein the item It includes project scheduling equipment and terminal that mesh, which dispatches system, and in certain embodiments, the project scheduling equipment can be set in hand On the intelligent terminals such as mechanical, electrical brain, plate, smartwatch.In certain embodiments, the project scheduling equipment and the terminal it Between can establish communication connection, to carry out two-way communication.In certain embodiments, the project scheduling equipment may be mounted at institute It states in terminal, in certain embodiments, the project scheduling equipment can be spatially independently of the terminal, in certain implementations In example, the project scheduling equipment can be the component of the terminal, i.e., the described terminal includes project scheduling equipment.In certain realities It applies in example, the terminal may include: the intelligent terminals such as mobile phone, computer, plate, smartwatch.
It, can be to item when the terminal in the project scheduling system needs to carry out project scheduling in the embodiment of the present invention Mesh controlling equipment sends project scheduling request, so that the project scheduling that the project scheduling equipment can receive terminal transmission is asked It asks.In certain embodiments, performance information required by project task and goal task are carried in the project scheduling request Amount.The project scheduling equipment can screen after receiving the project scheduling request of terminal transmission from employee database The employee to match out with performance information required by the project task gathers, and includes at least one member in employee's set Work mark.The project scheduling equipment can collect according to the working efficiency of each employee in employee set from the employee Determine to complete at least one employee's subset of the goal task amount in conjunction, wherein include at least one in each employee's subset A employee;The original wage of each employee in the available each employee's subset of project scheduling equipment, and according to described each The original wage of each employee in employee's subset determines that the employee of each employee's subset completes the work of the goal task amount Provide cost;The project scheduling equipment can complete the wage of the goal task amount according to the employee of each employee's subset Cost determines target employee's subset from least one described employee's subset according to preset rules, to call the target person The employee of brigade collection executes the project task.
The project scheduling method of the embodiment of the present invention is schematically illustrated with reference to the accompanying drawing.
Referring to Figure 1, Fig. 1 is a kind of schematic flow diagram of project scheduling method provided in an embodiment of the present invention, such as Fig. 1 institute Show, this method can be executed by project scheduling equipment, and the specific explanations of the project scheduling equipment are as previously mentioned, no longer superfluous herein It states.Specifically, described method includes following steps for the embodiment of the present invention.
S101: the project scheduling request that terminal is sent is received, wherein carry project task in the project scheduling request Required performance information and goal task amount.
In the embodiment of the present invention, project scheduling equipment can receive the project scheduling request of terminal transmission, wherein the item Performance information required by project task and goal task amount are carried in mesh scheduling request.
S102: collect from the employee to match with performance information required by the project task is filtered out in employee database It closes, includes at least one employee identification in employee's set.
In the embodiment of the present invention, project scheduling equipment can be filtered out from employee database and be wanted with the project task The employee that the performance information asked matches gathers, and includes at least one employee identification in employee's set.In some embodiments In, the employee database is used to store the employee identification and employee information corresponding with employee identification of multiple employees;At certain In a little embodiments, the corresponding employee of an employee identification, the employee identification may include employee name, employee number, member Work gender, worker demonstrate,prove number, employee's age etc. any one or more.
For example, it is assumed that the project scheduling request that the project scheduling equipment is got is Expert English language training by qualified teachers task, the English Performance information required by the needs of the training programmes is English language skills, then the project scheduling equipment can be filtered out from employee database At least one employee identification that the English language skills of the requirement described in the Expert English language training by qualified teachers task match, if the project scheduling Equipment filtered out from the employee database with English language skills include employee identification 1, employee identification 2 and employee identification 3, It can then determine that forming the employee to match with the English language skills by employee identification 1, employee identification 2 and employee identification 3 gathers.
In one embodiment, the project scheduling equipment is filtering out and the project task institute from employee database It is required that employee's set for matching of performance information before, can detecte the corresponding member of each employee identification in the employee database Whether work has received to execute sundry item task, has received to execute sundry item if detecting in the employee database and existing The employee identification of task then filters out at least one employee identification for not receiving to execute sundry item task, and from described Do not have to filter out at least one employee identification for receiving to execute sundry item task in project task required time information Gather with the employee that performance information required by the project task matches.
In one embodiment, the project scheduling equipment is filtering out and the project task institute from employee database It is required that performance information match employee set before, it is corresponding that each employee identification in the employee database can also be detected Whether employee includes asking false information, if detecting in the employee database that existing includes the employee identification for asking false information, At least one employee identification for not asking false information is filtered out, and from described at least one employee identification for not asking false information The employee to match with performance information required by the project task is filtered out to gather.
In one embodiment, the project scheduling equipment is filtered out from employee database is wanted with the project task After employee's set that the performance information asked matches, the type of the project task can also be obtained, and according to the project The type of task, determines corresponding with the type of project task employee's characteristic information, and from filtering out with the project In employee's set that performance information required by task matches, the characteristic information of each employee is acquired, and determine to meet institute State employee's set of employee's characteristic information.In certain embodiments, employee's characteristic information includes but is not limited to face characteristic The information such as information, eyesight characteristic information.In certain embodiments, the type of the project task includes but is not limited to market pin The types such as sell, plan, investigating, researching and developing, making.
In one embodiment, the project scheduling equipment is from filtering out and technical ability required by the project task When determining the employee's set for meeting employee's characteristic information in employee that information matches set, can to the project Each employee in employee that performance information required by task matches set carries out recognition of face, and analyze identify it is each The face characteristic of employee carries out the face characteristic of each employee employee's characteristic information corresponding with the type of the project task Comparison determines the face characteristic that employee's characteristic information corresponding with the type of the project task matches, and according to the people Face feature determines employee's set corresponding with the face characteristic.
For example, it is assumed that the type of the project task is the type of market sale, if the type with the market sale Corresponding employee's characteristic information includes face characteristic information that is happy, optimistic, having passion, then the project scheduling equipment can be right The each employee in employee's set to match with performance information required by the project task carries out recognition of face, identifies The face characteristic (such as expressive features) of each employee in employee set.During the project scheduling equipment can gather the employee The face characteristic of each employee identified is analyzed, and determines to meet people that is happy, optimistic, having passion in employee set The employee of face characteristic information, so that it is determined that going out by meeting member that is happy, optimistic, being made of the employee of the face characteristic information of passion Work set.
In another example, it is assumed that the type of the project task is the type of research and development, if corresponding with the type of the research and development Employee's characteristic information includes conscientious, rigorous, introvert's face characteristic information, then the project scheduling equipment can to the item Each employee in employee's set that performance information required by mesh task matches carries out recognition of face, identifies that the employee collects The face characteristic (such as expressive features) of each employee in conjunction.What the project scheduling equipment identified in can gathering the employee The face characteristic of each employee is analyzed, and determines that meeting face characteristic that is happy, optimistic, having passion in employee set believes The employee of breath is gathered so that it is determined that going out by meeting the employee that conscientious, rigorous, introvert's face characteristic information employee forms.
In one embodiment, the project scheduling equipment is from filtering out and technical ability required by the project task When determining the employee's set for meeting employee's characteristic information in employee's set that information matches, if it is determined that go out the item The type of mesh task be such as hand embroidering item types relevant to eyesight, then can to required by the project task Each employee in employee's set that performance information matches carries out eyesight testing, and analyzes the eyesight for identifying each employee, The employee for determining that eyesight feature required by eyesight and the type of the project task matches gathers.
For example, it is assumed that the type of the project task be hand embroidering project, then project scheduling equipment can from institute The eye feature that each employee is acquired in employee's set that performance information required by project task matches is stated, and according to eye Signature analysis identifies the eyesight information of each employee.If the visual demand of preset hand embroidering is 4.5, can from Determine that employee of the eyesight more than or equal to 4.5 collects in employee's set that performance information required by the project task matches It closes.
In one embodiment, the project scheduling equipment is in the type according to the project task, the determining and item When the corresponding employee's characteristic information of the type of mesh task, it can detecte that preset project task is corresponding with employee's characteristic information to close It whether there is employee's characteristic information corresponding with the project task type in system, if it does not exist, then appointing according to the project The type of business crawls employee's characteristic information relevant to the type of the project task from network.In other embodiments, institute Employee's characteristic information corresponding with the type of the project task can also be obtained using other modes by stating project scheduling equipment, The embodiment of the present invention is not specifically limited.
S103: it according to the working efficiency of each employee in employee set, determines to complete from employee set At least one employee's subset of the goal task amount, wherein include at least one employee in each employee's subset.
In the embodiment of the present invention, project scheduling equipment can according to the employee gather in each employee working efficiency, Determine to complete at least one employee's subset of the goal task amount from employee set, wherein each employee's subset In include at least one employee.
In one embodiment, the time cost of the project task, the item are carried in the project scheduling request Mesh controlling equipment is determined to complete institute in the working efficiency according to each employee in employee set from employee set When stating at least one employee's subset of goal task amount, the working efficiency of each employee in available employee's set, and According to the working efficiency of each employee and the goal task amount in employee set, determine that the employee of employee's set is complete At the time cost of the goal task amount, and determine that the employee of employee's set completes the time of the goal task amount Cost is less than at least one employee's subset of the time cost of the project task carried in project scheduling request.
For example, it is assumed that the time cost of the project task carried in the project scheduling request is 210 hours, mesh Mark task amount is 200 casees products, if in employee set including 2 employees, the working efficiency of employee 1 is 0.48 case/small When, the working efficiency of employee 2 is 0.5 case/hour, then the project scheduling equipment can determine the employee 1 of employee's set The time cost of described 200 casees products of goal task amount is completed with employee 2 are as follows: 200/ (0.48+0.5)=204 hour, due to 204 are less than the time cost 210 of the project task carried in project scheduling request, then can determine the employee 1 The employee's subset formed with employee 2.
In one embodiment, the project scheduling equipment obtains the working efficiency of each employee in employee's set When, the grade of skill of each employee in available employee set, and according to preset grade of skill and working efficiency Corresponding relationship, it is determining gather with the employee in the corresponding working efficiency of the grade of skill of each employee, so as to from the employee Determine to complete at least one employee's subset of the goal task amount in set.For example, it is assumed that employee 1 in employee's set Grade of skill be 1 grade, the grade of skill of employee 2 is 2 grades, then the project scheduling equipment can be according to preset grade of skill With the corresponding relationship of working efficiency, determining working efficiency 0.48 corresponding with 1 grade of grade of skill of employee 1 in employee set Case/hour determines 0.5 case of working efficiency/hour corresponding with 2 grades of grade of skill of the employee 2.
In one embodiment, the working efficiency of the project scheduling equipment each employee in determining employee's set When, the length of service of each employee in available employee set, and according to the work of each employee in employee set The grade of skill for making each employee in the time limit and employee set determines that the technical ability of each employee in employee's set is skilled Degree, thus according to the corresponding relationship of preset skill proficiency and working efficiency, each employee in determining and employee set The corresponding working efficiency of skill proficiency.In certain embodiments, the working efficiency of the employee with the technical ability it is skilled The increase of degree and improve.
For example, it is assumed that including employee identification 1, employee identification 2 and employee identification 3 in employee's set, if the item Mesh controlling equipment when the working efficiency of each employee, gets employee's mark in employee's set in determining employee's set The length of service for knowing 1 corresponding employee is 1 year, grade of skill is 2 grades, and the length of service of the corresponding employee of employee identification 2 is 2 years, skill Energy grade is 3 grades, and it is 4 grades that the length of service of the corresponding employee of employee identification 3, which is 5 years corresponding grades, then the project scheduling equipment It can be according to the grade of skill of each employee in the length of service of each employee in employee set and employee set, really The skill proficiency for making the corresponding employee of employee identification 1 is 50%, and the skill proficiency of the corresponding employee of employee identification 2 is 60% member The skill proficiency of the corresponding employee of work mark 3 is 80%, to close according to preset skill proficiency is corresponding with working efficiency System determines the working efficiency of the corresponding each employee of employee identification 1, employee identification 2, employee identification 2 in employee set.
S104: the original wage of each employee in each employee's subset is obtained, and according to each member in each employee's subset The original wage of work determines that the employee of each employee's subset completes the wage cost of the goal task amount.
In the embodiment of the present invention, the original wage of each employee in the available each employee's subset of project scheduling equipment, and According to the original wage of each employee in each employee's subset, determine that the employee of each employee's subset completes the mesh Mark the wage cost of task amount.
In one embodiment, project scheduling equipment is in the original wage according to each employee in each employee's subset, It, can be according to every zooid when determining that the employee of each employee's subset completes the wage cost of the goal task amount Brigade concentrate each employee working efficiency and the goal task amount, determine that the employee of each employee's subset completes the target and appoints The time cost of business amount, and the target is completed according to the employee of the original wage of each employee and each employee's subset and is appointed The time cost of business amount, the employee for calculating each employee's subset complete the sum of the original wage of the goal task amount, obtain The wage cost of the goal task amount is completed to the employee of each employee's subset.
Continue to use above-mentioned example, it is assumed that goal task amount is 200 casees products, the working efficiency of employee 1 in employee's set Working efficiency for 0.48 case/hour, employee 2 is 0.5 case/hour, and project scheduling equipment can be determined by employee 1 and employee 2 Employee's subset of composition completes the time cost of described 200 casees products of goal task amount are as follows: 200/ (0.48+0.5)=204 small When, if the original wage of the employee 1 and employee 2 are 10000 yuan, employee 1 and member in employee's subset can be calculated It is 20000 yuan to get complete to the employee 1 of employee's subset and employee 2 that work 2, which completes the sum of original wage of 200 casees products, Wage cost at the goal task amount is 20000 yuan.
In one embodiment, the overtime of the available each employee of the project scheduling equipment, and according to each The overtime of each employee in employee's subset determines that the employee of each employee's subset completes needed for the goal task amount Overtime work cost, and according to the working time of employee in each employee's subset, determine that the employee of each employee's subset completes Wage cost needed for the goal task amount.
In one embodiment, the project scheduling equipment is in the overtime according to each employee in each employee's subset, It, can be according to each employee when determining overtime work cost needed for the employee of each employee's subset completes the goal task amount The overtime of each employee in subset determines that the employee of each employee's subset completes total needed for the goal task amount add Class's time, and according to the corresponding relationship of preset overtime and overtime cost, the determining employee with each employee's subset Complete the corresponding overtime work cost of total overtime needed for the goal task amount.
Continue to use above-mentioned example citing, it is assumed that the corresponding relationship of preset overtime and overtime cost is 100 pieces/hour, If the overtime of employee 1 is 10 hours in employee's subset, the work hours are 190 hours, and employee 2 is overtime For 20 hours, the work hours are 188 hours, then the project scheduling equipment can determine the employee 1 of employee's subset Total overtime needed for completing described 200 casees products of goal task amount with employee 2 are as follows: 10+20=30 hour.The project Controlling equipment can be determining sub with the employee according to 100 piece/hour of corresponding relationship of preset overtime and overtime cost Overtime work cost needed for 30 hours of total overtime needed for the employee of collection completes described 200 casees products of goal task amount are as follows: 100*30=3000 member.Assuming that the original wage of the employee 1 and employee 2 are 10000 yuan, then the employee 1 can be determined The wage cost of 100 casees products is completed with employee 2 are as follows: 10000+10000=20000 member.
In one embodiment, the project scheduling request can carry the temporal information for completing the project task, institute Stating project scheduling equipment can determine each in employee's set according to the working efficiency of each employee in employee set The task amount that employee completes within the unit time, and existed according to each employee in the goal task amount and employee set The task amount completed in unit time determines time cost needed at least one employee completes the goal task amount, thus Determine that the time cost is less than at least one employee's subset of the project task required time information.
S105: completing the wage cost of the goal task amount according to the employee of each employee's subset, according to default Rule determines target employee's subset from least one described employee's subset, to call the employee of the target employee subset to hold The row project task.
In the embodiment of the present invention, project scheduling equipment can complete the target according to the employee of each employee's subset The wage cost of task amount determines target employee's subset from least one described employee's subset according to preset rules, to adjust The project task is executed with the employee of the target employee subset.
In one embodiment, project cost threshold value can be carried in the project scheduling request, the project scheduling is set It is standby in the wage cost for completing the goal task amount according to the employee of each employee's subset, according to preset rules from described When determining target employee's subset at least one employee's subset, it can be determined from least one described employee's subset described Wage cost is less than or equal at least one employee's subset of the project cost threshold value, and the detection wage cost is less than Or the time cost of the goal task amount is completed equal to the employee of at least one employee's subset of the project cost threshold value, and Determine the smallest target employee subset of the time cost.
In one embodiment, the project scheduling equipment is determining the work from least one described employee's subset It provides cost to be less than or equal to after at least one employee's subset of the project cost threshold value, the available wage cost is small The wage cost of the goal task amount is completed in or equal to the employee of at least one employee's subset of the project cost threshold value, And the wage cost of institute's goal task amount sequence from small to large is completed according to each employee's subset, at least one described member Brigade collection is ranked up, and is stored to dispatch list, so that user is according to dispatch list calling employee's subset execution Project task.
In one embodiment, project scheduling equipment is determined from least one described employee's subset according to preset rules After target employee's subset, the corresponding user terminal of each employee identification it can send notice into the target employee subset and disappear Breath, to notify the employee of the target employee subset to be confirmed whether to execute the project task;If in preset time range The confirmation instruction that the corresponding user terminal of each employee identification in the target employee subset returns is received, then can determine calling The employee of the target employee subset executes the project task.
In one embodiment, if the project calls equipment to be not received by target person in the target employee subset Work identifies the confirmation instruction that corresponding user terminal returns, then the available target employee identification corresponds to described in employee's completion The original wage of goal task amount is filtered out from other employee's subsets described in employee's completion corresponding with the target employee identification The original wage of goal task amount matched employee identification within a preset range, and will be described in the matched employee identification replacement Target employee identification in target employee's subset, and call the member of target employee's subset after replacing the target employee identification Work executes the project task.
In one embodiment, whether the employee that project scheduling equipment can detecte in each employee's subset there is overtime work to believe Breath, if there are overtime information in testing result, according to the overtime information, can determine the overtime work of each employee's subset at This, and the overtime work cost and the sum of the wage cost of each employee's subset are calculated separately, obtain each employee's subset Employee completes the project cost of the goal task amount, and is less than the project cost from the project cost according to preset rules Target employee subset is determined at least one employee's subset of threshold value, to call employee's project implementation of the target employee subset Task.
For example, it is assumed that project cost threshold value is 30000 yuan, employee's subset is made of employee 1 and employee 2,1 He of employee The overtime work cost of employee 2 is 3000 yuan, and wage cost is 20000 yuan, then the employee that can calculate employee's subset completes mesh Mark the project cost of 200 casees products of task amount are as follows: 20000+3000=23000, since 23000 less than the project cost threshold value 30000, then it can determine that employee's subset that employee 1 and employee 2 form is target employee subset.
In one embodiment, project scheduling equipment can detecte the project cost less than the project cost threshold value The project cost of each employee's subset, and determine that the project cost is at least one association employee's being preset in this section Collection, and the overtime of each employee in each association employee's subset is obtained, and calculate each in each association employee's subset The sum of overtime of employee, obtain each association employee's subset employee complete the overtime work of the goal task amount at This, to determine target employee's subset of the overtime work cost minimization from least one described association employee's subset.
In one embodiment, project scheduling equipment can complete the target according to the employee of each employee's subset Time cost needed for task amount determines target employee's subset from least one described employee's subset, to call the mesh The employee for marking employee's subset executes the project task.In certain embodiments, project scheduling equipment can detecte described each Time cost needed for the employee of employee's subset completes the goal task amount, when obtaining needed for completing the goal task amount Between at least one the employee's subset of cost in preset time range, and obtain the time cost in preset time range The grade of skill of each employee in each employee's subset, to calculate each employee of the time cost in preset time range The sum of the sum of the grade of skill of each employee is concentrated, and determines the grade of skill maximum target employee subset.
For example, it is assumed that determining that first employee's subset, second employee's subset and third employee's subset, preset time range are 26 days, if the project scheduling equipment detect the first employee subset employee complete goal task amount needed for the time Cost is 24 days, and time cost needed for detecting employee's completion goal task amount of the second employee subset is 25 days, inspection Time cost needed for measuring employee's completion goal task amount of the third employee subset is 28 days, then the project scheduling is set First employee subset of the time cost in preset time range 26 days needed for the standby available completion goal task amount With second employee's subset.Then in the available first employee subset of the project scheduling equipment each employee grade of skill And the grade of skill of each employee in the second employee subset is obtained, if calculating each member in the first employee subset The sum of grade of skill of work is 10, calculates the sum of grade of skill of each employee 9 in the second employee subset, is greater than due to 10 9, then it can determine that the maximum first employee subset of the sum of described grade of skill is target employee subset.
In one embodiment, project scheduling equipment completes the target times according to the employee of each employee's subset Time cost needed for business amount can detecte described when determining target employee's subset from least one described employee's subset Time cost needed for the employee of each employee's subset completes the goal task amount obtains needed for completing the goal task amount Time cost at least one employee's subset in preset time range, obtain the time needed for completing the goal task amount Each employee completes the original wage of the goal task amount at least one the employee's subset of cost in preset time range, meter The employee for calculating each employee's subset completes the sum of the original wage of the goal task amount, obtains described in each employee's subset completion The wage cost of goal task amount, so that it is determined that the smallest target employee of the wage cost for going out to complete the goal task amount Collection.
For example, it is assumed that determining that first employee's subset, second employee's subset and third employee's subset, preset time range are 26 days, if the project scheduling equipment detect the first employee subset employee complete goal task amount needed for the time Cost is 24 days, and time cost needed for detecting employee's completion goal task amount of the second employee subset is 25 days, inspection Time cost needed for measuring employee's completion goal task amount of the third employee subset is 28 days, then the project scheduling is set First employee subset of the time cost in preset time range 26 days needed for the standby available completion goal task amount With second employee's subset.Then in the available first employee subset of the project scheduling equipment each employee original work Money, and the original wage of each employee in the second employee subset is obtained, if calculated in the first employee subset The sum of original wage of each employee is 30000, calculates the sum of the original wage of each employee in the second employee subset 28000, since 30000 are greater than 28000, then it can determine that the minimum second employee subset of the sum of described original wage is target Employee's subset.
In one embodiment, the employee of the available each employee's subset of project scheduling equipment completes the target Time cost needed for task amount and wage cost, and the goal task amount is completed according to the employee of each employee's subset The employee of required time cost and preset time weighting and each employee's subset completes the goal task amount institute The wage cost and preset wage weight needed determines project needed for each employee's subset completes the goal task amount Cost, to determine the minimum target employee's subset of the project cost from each employee's subset.
For example, it is assumed that time cost needed for first employee's subset completes the goal task amount is 22 days, wage cost It is 2.5 ten thousand, time cost needed for second employee's subset completes the goal task amount is 24 days, wage cost is 2.6 ten thousand, the Time cost needed for three employee's subsets complete the goal task amount is 23 days, wage cost is 2.8 ten thousand, if when preset Between weight be 40%, preset wage weight is 60%, then the project scheduling equipment can calculate first employee Collection completes the project cost of the goal task amount are as follows: 22*40%+2.5*60%=10.3 calculates the second employee Collection completes the project cost of the goal task amount are as follows: 24*40%+2.6*60%=11.16 calculates third employee Collection completes the project cost of the goal task amount are as follows: 23*40%+2.8*60%=10.88.Therefore the project scheduling equipment It can determine the project cost minimum 10.3, i.e., the described project scheduling equipment can determine that the first employee subset is Target employee's subset.
In the embodiment of the present invention, project scheduling equipment can filter out the project tune sent with terminal from employee database Employee's set that the required performance information of degree request matches is determined to complete goal task amount from employee set At least one employee's subset, and according to the original wage of each employee in each employee's subset, determine each employee The employee of subset completes the wage cost of the goal task amount, and according to the wage cost, according to preset rules from institute It states and determines target employee's subset at least one employee's subset, to call the employee of the target employee subset to execute the item Mesh task, so that project scheduling task is realized, to improve the efficiency of project scheduling.
Fig. 2 is referred to, Fig. 2 is the schematic flow diagram of another project scheduling method provided in an embodiment of the present invention, such as Fig. 2 Shown, this method can be executed by project scheduling equipment, and the specific explanations of the project scheduling equipment are as previously mentioned, no longer superfluous herein It states.The difference of the embodiment of the present invention and embodiment described in above-mentioned Fig. 1 is that the embodiment of the present invention is to the project scheduling method Specific implementation process schematically illustrated.Specifically, described method includes following steps for the embodiment of the present invention.
S201: the project scheduling request that terminal is sent is received, wherein carry project task in the project scheduling request Required performance information and goal task amount.
In the embodiment of the present invention, project scheduling equipment can receive the project scheduling request of terminal transmission, wherein the item Performance information required by project task and goal task amount are carried in mesh scheduling request, specific embodiment as previously mentioned, this Place repeats no more.
S202: collect from the employee to match with performance information required by the project task is filtered out in employee database It closes, includes at least one employee identification in employee's set.
In the embodiment of the present invention, project scheduling equipment can be filtered out from employee database and be wanted with the project task The employee that the performance information asked matches gathers, and includes at least one employee identification in employee's set, specific implementation is for example Preceding described, details are not described herein again.
S203: the working efficiency of each employee in employee's set is obtained.
In the embodiment of the present invention, the working efficiency of each employee in the available employee's set of project scheduling equipment.
In one embodiment, the project scheduling equipment can complete history according to each employee in employee set Overtime needed for task amount and/or working time determine the working efficiency of each employee in employee's set.
For example, it is assumed that the goal task amount is 200 casees products, preset time cost is 210 hours, if the member It include 2 employees in work set, historic task amount is 100 casees products, when overtime work needed for the employee 1 completes 100 casees products Between be 10 hours, the working time is 200 hours, then the project scheduling equipment can determine member in employee set The working efficiency of work 1 are as follows: 100/210=0.48 case/hour;If overtime needed for employee 2 completes 100 casees products is 20 A hour, working time are 180 hours, then the project scheduling equipment can determine employee 2 in employee's set Working efficiency are as follows: 100/200=0.5 case/hour.
S204: according to the working efficiency of each employee and the goal task amount in employee set, the member is determined The employee of work set completes the time cost of the goal task amount.
In the embodiment of the present invention, project scheduling equipment can according to the employee gather in each employee working efficiency and The goal task amount determines that the employee of employee's set completes the time cost of the goal task amount.
For example, it is assumed that the working efficiency of employee 1 are as follows: 100/210=0.48 case/hour, the working efficiency of employee 2 are as follows: 100/200=0.5 case/hour, if goal task amount is 200 casees, the project scheduling equipment can be according to the employee 1 With the working efficiency of employee 2, time cost needed for the employee 1 and employee 2 complete described goal task amount 200 casees is determined Are as follows: 200/ (0.48+0.5)=204 hour.
S205: determine that the employee of employee's set completes the time cost of the goal task amount less than the project tune At least one employee's subset of the time cost of the project task carried in degree request.
In the embodiment of the present invention, project scheduling equipment can determine that the employee of employee's set completes the goal task The time cost of amount is less than at least one employee of the time cost of the project task carried in project scheduling request Subset.
Above-mentioned example is continued to use to illustrate, it is assumed that the time of the project task carried in project scheduling request at This is 210 hours, time cost needed for the employee 1 and employee 2 complete described goal task amount 200 casees are as follows: 200/ (0.48+0.5)=204 hour, then the time cost 204 is less than the time cost 210 of the project task, it can really Make the employee's subset being made of employee 1 and employee 2.
S206: the original wage of each employee in each employee's subset is obtained, and according to each member in each employee's subset The original wage of work determines that the employee of each employee's subset completes the wage cost of the goal task amount.
In the embodiment of the present invention, the original wage of each employee in the available each employee's subset of project scheduling equipment, and According to the original wage of each employee in each employee's subset, determine that the employee of each employee's subset completes the mesh The wage cost of task amount is marked, specific embodiment is as previously mentioned, details are not described herein again.
S207: completing the wage cost of the goal task amount according to the employee of each employee's subset, according to default Rule determines target employee's subset from least one described employee's subset, to call the employee of the target employee subset to hold The row project task.
In the embodiment of the present invention, project scheduling equipment can complete the target according to the employee of each employee's subset The wage cost of task amount determines target employee's subset from least one described employee's subset according to preset rules, to adjust The project task is executed with the employee of the target employee subset, specific embodiment is as previously mentioned, details are not described herein again.
In one embodiment, project scheduling equipment determines target employee's subset from least one described employee's subset Later, it the corresponding user terminal of each employee identification can send a notification message into the target employee subset, to notify The employee for stating target employee's subset is confirmed whether to execute the project task, if receiving each member in the target employee subset Work identifies the confirmation instruction that corresponding user terminal returns, then confirms that the employee for transferring the target employee subset executes the item Mesh task.
In one embodiment, if project scheduling equipment is not received by the target employee in preset time range The confirmation instruction that the corresponding user terminal of target employee identification returns in subset, then can be again into the target employee subset The corresponding user terminal of the target employee identification sends a notification message, if be not received by preset time range described Target employee identification corresponds to the confirmation instruction of user terminal return, then filters out from other employee's subsets and the target employee The immediate employee identification of any one or more employee information such as corresponding original wage, grade of skill, length of service is identified, Replace the target employee identification in the target employee subset.
In the embodiment of the present invention, project scheduling equipment can filter out the project tune sent with terminal from employee database Employee's set that the required performance information of degree request matches is determined to complete goal task amount from employee set At least one employee's subset, and according to the original wage of each employee in each employee's subset, determine each employee The employee of subset completes the wage cost of the goal task amount, and according to the wage cost, according to preset rules from institute It states and determines target employee's subset at least one employee's subset, to call the employee of the target employee subset to execute the item Mesh task, so that project scheduling task is realized, to improve the efficiency of project scheduling.
The embodiment of the invention also provides a kind of project scheduling equipment, the project scheduling equipment is any one of aforementioned for executing The unit of the method.It specifically, is a kind of signal of project scheduling equipment provided in an embodiment of the present invention referring to Fig. 3, Fig. 3 Block diagram.The project scheduling equipment of the present embodiment includes: receiving unit 301, screening unit 302, the first determination unit 303, second Determination unit 304 and call unit 305.
Receiving unit 301, for receiving the project scheduling request of terminal transmission, wherein taken in the project scheduling request With performance information and goal task amount required by project task;
Screening unit 302, for from being filtered out in employee database and performance information phase required by the project task Matched employee gathers, and includes at least one employee identification in employee's set;
First determination unit 303 collects for the working efficiency according to each employee in employee set from the employee Determine to complete at least one employee's subset of the goal task amount in conjunction, wherein include at least one in each employee's subset A employee;
Second determination unit 304, for obtaining the original wage of each employee in each employee's subset, and according to described each The original wage of each employee in employee's subset determines that the employee of each employee's subset completes the work of the goal task amount Provide cost;
Call unit 305, for completed according to the employee of each employee's subset the wage of the goal task amount at This, determines target employee's subset from least one described employee's subset according to preset rules, to call the target employee The employee of subset executes the project task.
Further, the time cost of the project task is carried in the project scheduling request;Described first determines Unit 303 is determined to complete the mesh according to the working efficiency of each employee in employee set from employee set When marking at least one employee's subset of task amount, it is specifically used for:
Obtain the working efficiency of each employee in employee's set;
According to the working efficiency of each employee and the goal task amount in employee set, employee's set is determined Employee complete the time cost of the goal task amount;
Determine that the employee of employee set completes the time cost of the goal task amount and is less than the project scheduling and asks Seek at least one employee's subset of the time cost of the project task of middle carrying.
Further, when first determination unit 303 obtains the working efficiency of each employee in employee's set, tool Body is used for:
Obtain the grade of skill of each employee in employee's set;
According to the corresponding relationship of preset grade of skill and working efficiency, determination and each employee in employee set The corresponding working efficiency of grade of skill, so as to determine to complete from the employee set goal task amount at least one Employee's subset.
Further, second determination unit 304 is according to the original wage of each employee in each employee's subset, really When the employee for making each employee's subset completes the wage cost of the goal task amount, it is specifically used for:
According to the working efficiency of each employee and the goal task amount in each employee's subset, each employee's is determined The employee of collection completes the time cost of the goal task amount;
According to the employee of the original wage of each employee and each employee's subset complete the goal task amount when Between cost, the employee for calculating each employee's subset completes the sum of the original wage of the goal task amount, obtains described every The employee of zooid's brigade collection completes the wage cost of the goal task amount.
Further, project cost threshold value is carried in the project scheduling request;The call unit 305 is according to described The employee of each employee's subset completes the wage cost of the goal task amount, according to preset rules from least one described employee When determining target employee's subset in subset, it is specifically used for:
Determine that the wage cost is less than or equal to the project cost threshold value from least one described employee's subset At least one employee's subset;
It is complete less than or equal to the employee of at least one employee's subset of the project cost threshold value to detect the wage cost At the time cost of the goal task amount, and determine the smallest target employee subset of the time cost.
Further, first determination unit 303 determined from least one described employee's subset the wage at This is less than or equal to after at least one employee's subset of the project cost threshold value, is also used to:
It is complete less than or equal to the employee of at least one employee's subset of the project cost threshold value to obtain the wage cost At the wage cost of the goal task amount;
Complete the wage cost of institute's goal task amount sequence from small to large according to each employee's subset, to it is described at least One zooid's brigade collection is ranked up, and is stored to dispatch list, so that user calls employee's subset to hold according to the dispatch list The row project task.
Further, the call unit 305 determines mesh from least one described employee's subset according to preset rules After marking employee's subset, it is also used to:
Into the target employee subset, the corresponding user terminal of each employee identification sends a notification message, described in notice The employee of target employee's subset is confirmed whether to execute the project task;
If being not received by the corresponding use of target employee identification in the target employee subset in preset time range The confirmation instruction that family terminal returns, then obtain the target employee identification and correspond to the original work that employee completes the goal task amount Money;
Employee corresponding with the target employee identification is filtered out from other employee's subsets completes the goal task amount Original wage matched employee identification within a preset range, and the matched employee identification is replaced into the target employee subset In target employee identification;
The employee of target employee's subset after replacing the target employee identification is called to execute the project task.
In the embodiment of the present invention, project scheduling equipment can filter out the project tune sent with terminal from employee database Employee's set that the required performance information of degree request matches is determined to complete goal task amount from employee set At least one employee's subset, and according to the original wage of each employee in each employee's subset, determine each employee The employee of subset completes the wage cost of the goal task amount, and according to the wage cost, according to preset rules from institute It states and determines target employee's subset at least one employee's subset, to call the employee of the target employee subset to execute the item Mesh task, so that project scheduling task is realized, to improve the efficiency of project scheduling.
Referring to fig. 4, Fig. 4 is a kind of schematic block diagram of server provided in an embodiment of the present invention.This implementation as shown in the figure Server in example may include: one or more processors 401;One or more input equipments 402, one or more output Equipment 403 and memory 404.Above-mentioned processor 401, input equipment 402, output equipment 403 and memory 404 pass through bus 405 connections.Memory 404 is for storing computer program, and the computer program includes program instruction, and processor 401 is used for Execute the program instruction that memory 404 stores.Wherein, processor 401 is configured for calling described program instruction execution:
Receive the project scheduling request that terminal is sent, wherein carry project task in the project scheduling request and wanted The performance information and goal task amount asked;
Gather from the employee to match with performance information required by the project task is filtered out in employee database, institute Stating in employee's set includes at least one employee identification;
According to the working efficiency of each employee in employee set, determine to complete the mesh from employee set Mark at least one employee's subset of task amount, wherein include at least one employee in each employee's subset;
The original wage of each employee in each employee's subset is obtained, and according to the original of each employee in each employee's subset Beginning wage determines that the employee of each employee's subset completes the wage cost of the goal task amount;
The wage cost that the goal task amount is completed according to the employee of each employee's subset, according to preset rules from Target employee's subset is determined at least one described employee's subset, to call described in employee's execution of the target employee subset Project task.
Further, the time cost of the project task is carried in the project scheduling request;The processor 401 According to the working efficiency of each employee in employee set, determine to complete the goal task amount from employee set At least one employee's subset when, be specifically used for:
Obtain the working efficiency of each employee in employee's set;
According to the working efficiency of each employee and the goal task amount in employee set, employee's set is determined Employee complete the time cost of the goal task amount;
Determine that the employee of employee set completes the time cost of the goal task amount and is less than the project scheduling and asks Seek at least one employee's subset of the time cost of the project task of middle carrying.
Further, it is specific to use when the processor 401 obtains the working efficiency of each employee in employee's set In:
Obtain the grade of skill of each employee in employee's set;
According to the corresponding relationship of preset grade of skill and working efficiency, determination and each employee in employee set The corresponding working efficiency of grade of skill, so as to determine to complete from the employee set goal task amount at least one Employee's subset.
Further, the processor 401 determines institute according to the original wage of each employee in each employee's subset When stating the employee of each employee's subset and completing the wage cost of the goal task amount, it is specifically used for:
According to the working efficiency of each employee and the goal task amount in each employee's subset, each employee's is determined The employee of collection completes the time cost of the goal task amount;
According to the employee of the original wage of each employee and each employee's subset complete the goal task amount when Between cost, the employee for calculating each employee's subset completes the sum of the original wage of the goal task amount, obtains described every The employee of zooid's brigade collection completes the wage cost of the goal task amount.
Further, project cost threshold value is carried in the project scheduling request;The processor 401 is according to described every The employee of zooid's brigade collection completes the wage cost of the goal task amount, sub from least one described employee according to preset rules When concentration determines target employee's subset, it is specifically used for:
Determine that the wage cost is less than or equal to the project cost threshold value from least one described employee's subset At least one employee's subset;
It is complete less than or equal to the employee of at least one employee's subset of the project cost threshold value to detect the wage cost At the time cost of the goal task amount, and determine the smallest target employee subset of the time cost.
Further, the processor 401 determines that the wage cost is less than from least one described employee's subset Or equal at least one employee's subset of the project cost threshold value after, be also used to:
It is complete less than or equal to the employee of at least one employee's subset of the project cost threshold value to obtain the wage cost At the wage cost of the goal task amount;
Complete the wage cost of institute's goal task amount sequence from small to large according to each employee's subset, to it is described at least One zooid's brigade collection is ranked up, and is stored to dispatch list, so that user calls employee's subset to hold according to the dispatch list The row project task.
Further, the processor 401 determines target from least one described employee's subset according to preset rules After employee's subset, it is also used to:
Into the target employee subset, the corresponding user terminal of each employee identification sends a notification message, described in notice The employee of target employee's subset is confirmed whether to execute the project task;
If being not received by the corresponding use of target employee identification in the target employee subset in preset time range The confirmation instruction that family terminal returns, then obtain the target employee identification and correspond to the original work that employee completes the goal task amount Money;
Employee corresponding with the target employee identification is filtered out from other employee's subsets completes the goal task amount Original wage matched employee identification within a preset range, and the matched employee identification is replaced into the target employee subset In target employee identification;
The employee of target employee's subset after replacing the target employee identification is called to execute the project task.
In the embodiment of the present invention, server can filter out the project scheduling sent with terminal from employee database and request Employee's set that required performance information matches is determined to complete at least the one of goal task amount from employee set Zooid's brigade collection, and according to the original wage of each employee in each employee's subset, determine each employee's subset Employee completes the wage cost of the goal task amount, and according to the wage cost, according to preset rules from it is described at least One zooid's brigade concentration determines target employee's subset, is appointed with calling the employee of the target employee subset to execute the project Business, so that project scheduling task is realized, to improve the efficiency of project scheduling.
It should be appreciated that in embodiments of the present invention, alleged processor 401 can be central processing unit (CenSral Processing UniS, CPU), which can also be other general processors, digital signal processor (DigiSal Signal Processor, DSP), specific integrated circuit (ApplicaSion Specific InSegraSed CircuiS, ASIC), ready-made programmable gate array (Field-Programmable GaSe Array, FPGA) or other programmable logic Device, discrete gate or transistor logic, discrete hardware components etc..General processor can be microprocessor or this at Reason device is also possible to any conventional processor etc..
Input equipment 402 may include Trackpad, microphone etc., output equipment 403 may include display (LCD etc.), Loudspeaker etc..
The memory 404 may include read-only memory and random access memory, and to processor 401 provide instruction and Data.The a part of of memory 404 can also include nonvolatile RAM.For example, memory 404 can also be deposited Store up the information of device type.
In the specific implementation, processor 401 described in the embodiment of the present invention, input equipment 402, output equipment 403 can Execute realization side described in embodiment of the method described in Fig. 1 or Fig. 2 of project scheduling method provided in an embodiment of the present invention The implementation of project scheduling equipment described in Fig. 3 of the embodiment of the present invention also can be performed in formula, and details are not described herein.
A kind of computer readable storage medium is additionally provided in the embodiment of the present invention, the computer readable storage medium is deposited Computer program is contained, the computer program realizes item described in embodiment corresponding to Fig. 1 or Fig. 2 when being executed by processor Mesh dispatching method can also realize the project scheduling equipment of embodiment corresponding to Fig. 3 of the present invention, and details are not described herein.
It deposits the inside that the computer readable storage medium can be project scheduling equipment described in aforementioned any embodiment Storage unit, such as the hard disk or memory of project scheduling equipment.The computer readable storage medium is also possible to the project tune Spend the External memory equipment of equipment, such as the plug-in type hard disk being equipped in the project scheduling equipment, intelligent memory card (SmarS Media Card, SMC), secure digital (Secure DigiSal, SD) card, flash card (Flash Card) etc..Further, The computer readable storage medium can also both include the internal storage unit of the project scheduling equipment or deposit including outside Store up equipment.The computer readable storage medium is for storing needed for the computer program and the project scheduling equipment Other programs and data.The computer readable storage medium, which can be also used for temporarily storing, have been exported or will export Data.
Those of ordinary skill in the art may be aware that list described in conjunction with the examples disclosed in the embodiments of the present disclosure Member and algorithm steps, can be realized with electronic hardware, computer software, or a combination of the two, in order to clearly demonstrate hardware With the interchangeability of software, each exemplary composition and step are generally described according to function in the above description.This A little functions are implemented in hardware or software actually, the specific application and design constraint depending on technical solution.Specially Industry technical staff can use different methods to achieve the described function each specific application, but this realization is not It is considered as beyond the scope of this invention.
If the integrated unit is realized in the form of SFU software functional unit and sells or use as independent product When, it can store in a computer readable storage medium.Based on this understanding, technical solution of the present invention is substantially The all or part of the part that contributes to existing technology or the technical solution can be in the form of software products in other words It embodies, which is stored in a storage medium, including some instructions are used so that a computer Equipment (can be personal computer, server or the network equipment etc.) executes the complete of each embodiment the method for the present invention Portion or part steps.And storage medium above-mentioned includes: USB flash disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), magnetic or disk etc. are various can store journey The medium of sequence code.
The above, some embodiments only of the invention, but scope of protection of the present invention is not limited thereto, and it is any Those familiar with the art in the technical scope disclosed by the present invention, can readily occur in various equivalent modifications or replace It changes, these modifications or substitutions should be covered by the protection scope of the present invention.

Claims (10)

1. a kind of project scheduling method characterized by comprising
Receive the project scheduling request that terminal is sent, wherein carry required by project task in the project scheduling request Performance information and goal task amount;
Gather from the employee to match with performance information required by the project task is filtered out in employee database, the member It include at least one employee identification in work set;
According to the working efficiency of each employee in employee set, determine that completing the target appoints from employee set At least one employee's subset of business amount, wherein include at least one employee in each employee's subset;
The original wage of each employee in each employee's subset is obtained, and according to the original work of each employee in each employee's subset Money, determines that the employee of each employee's subset completes the wage cost of the goal task amount;
The wage cost that the goal task amount is completed according to the employee of each employee's subset, according to preset rules from described Target employee's subset is determined at least one employee's subset, to call the employee of the target employee subset to execute the project Task.
2. the method according to claim 1, wherein carrying the project task in project scheduling request Time cost;The working efficiency according to each employee in employee set, has been determined from employee set At at least one employee's subset of the goal task amount, comprising:
Obtain the working efficiency of each employee in employee's set;
According to the working efficiency of each employee and the goal task amount in employee set, the member of employee's set is determined Work completes the time cost of the goal task amount;
Determine that the employee of employee's set completes the time cost of the goal task amount less than in project scheduling request At least one employee's subset of the time cost of the project task carried.
3. according to the method described in claim 2, it is characterized in that, the work for obtaining each employee in employee's set Efficiency, comprising:
Obtain the grade of skill of each employee in employee's set;
According to the corresponding relationship of preset grade of skill and working efficiency, the determining technical ability with each employee in employee set The corresponding working efficiency of grade, to determine to complete at least one employee of the goal task amount from employee set Subset.
4. according to the method described in claim 3, it is characterized in that, the original according to each employee in each employee's subset Beginning wage determines that the employee of each employee's subset completes the wage cost of the goal task amount, comprising:
According to the working efficiency of each employee and the goal task amount in each employee's subset, each employee's subset is determined Employee completes the time cost of the goal task amount;
According to the employee of the original wage of each employee and each employee's subset complete time of the goal task amount at This, the employee for calculating each employee's subset completes the sum of the original wage of the goal task amount, obtains every zooid The employee of brigade collection completes the wage cost of the goal task amount.
5. according to the method described in claim 4, it is characterized in that, carrying project cost threshold in project scheduling request Value;The employee according to each employee's subset completes the wage cost of the goal task amount, according to preset rules from Target employee's subset is determined at least one described employee's subset, comprising:
Determined from least one described employee's subset the wage cost be less than or equal to the project cost threshold value to Few zooid's brigade collection;
The employee that the wage cost is detected less than or equal at least one employee's subset of the project cost threshold value completes institute The time cost of goal task amount is stated, and determines the smallest target employee subset of the time cost.
6. according to the method described in claim 5, it is characterized in that, described determine institute from least one described employee's subset After wage cost is stated less than or equal at least one employee's subset of the project cost threshold value, further includes:
The employee that the wage cost is obtained less than or equal at least one employee's subset of the project cost threshold value completes institute State the wage cost of goal task amount;
Complete the wage cost of institute's goal task amount sequence from small to large according to each employee's subset, to it is described at least one Employee's subset is ranked up, and is stored to dispatch list, so that user calls employee's subset to execute institute according to the dispatch list State project task.
7. the method according to claim 1, wherein described sub from least one described employee according to preset rules Concentration is determined after target employee's subset, further includes:
Into the target employee subset, the corresponding user terminal of each employee identification sends a notification message, to notify the target The employee of employee's subset is confirmed whether to execute the project task;
If it is whole to be not received by the corresponding user of target employee identification in the target employee subset in preset time range The confirmation instruction that end returns, then obtain the target employee identification and correspond to the original wage that employee completes the goal task amount;
Employee corresponding with the target employee identification is filtered out from other employee's subsets completes the original of the goal task amount Wage matched employee identification within a preset range, and the matched employee identification is replaced in the target employee subset Target employee identification;
The employee of target employee's subset after replacing the target employee identification is called to execute the project task.
8. a kind of project scheduling equipment, which is characterized in that including for executing as described in any one of claim 1-7 claim Method unit.
9. a kind of server, which is characterized in that including processor, input equipment, output equipment and memory, the processor, Input equipment, output equipment and memory are connected with each other, wherein the memory is for storing computer program, the calculating Machine program includes program instruction, and the processor is configured for calling described program instruction, is executed as claim 1-7 is any Method described in.
10. a kind of computer readable storage medium, which is characterized in that the computer storage medium is stored with computer program, The computer program includes program instruction, and described program instruction makes the processor execute such as right when being executed by a processor It is required that the described in any item methods of 1-7.
CN201910529345.9A 2019-06-18 2019-06-18 A kind of project scheduling method, equipment, server and computer readable storage medium Pending CN110310023A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910529345.9A CN110310023A (en) 2019-06-18 2019-06-18 A kind of project scheduling method, equipment, server and computer readable storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910529345.9A CN110310023A (en) 2019-06-18 2019-06-18 A kind of project scheduling method, equipment, server and computer readable storage medium

Publications (1)

Publication Number Publication Date
CN110310023A true CN110310023A (en) 2019-10-08

Family

ID=68076918

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910529345.9A Pending CN110310023A (en) 2019-06-18 2019-06-18 A kind of project scheduling method, equipment, server and computer readable storage medium

Country Status (1)

Country Link
CN (1) CN110310023A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111652997A (en) * 2020-05-28 2020-09-11 浙江舜江建设集团有限公司 Real-name management method for constructors in large-scale construction site
CN111754121A (en) * 2020-06-28 2020-10-09 北京百度网讯科技有限公司 Task allocation method, device, equipment and storage medium
CN114240188A (en) * 2021-12-21 2022-03-25 中国建设银行股份有限公司 Task allocation method and device

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103930911A (en) * 2011-03-01 2014-07-16 郭忠信 Project management system
CN107545377A (en) * 2017-09-30 2018-01-05 新奥(中国)燃气投资有限公司 A kind of project management method and device
US20180039928A1 (en) * 2016-08-03 2018-02-08 Xerox Corporation Method and system for auto-selection of employees for trainings in an organization
CN107818407A (en) * 2017-10-20 2018-03-20 平安科技(深圳)有限公司 Method for allocating tasks, device, storage medium and computer equipment
CN107909334A (en) * 2017-10-24 2018-04-13 中国平安人寿保险股份有限公司 A kind of project management method, device, server and computer-readable recording medium
CN109636205A (en) * 2018-12-18 2019-04-16 合肥师范学院 More skill's dispatching methods in a kind of research & development portfolio
CN109711742A (en) * 2018-12-29 2019-05-03 华润电力(菏泽)有限公司 A kind of distribution method of task, device, equipment and storage medium
CN109816259A (en) * 2019-01-30 2019-05-28 翟红鹰 Task distribution method, terminal device and storage medium based on block chain

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103930911A (en) * 2011-03-01 2014-07-16 郭忠信 Project management system
US20180039928A1 (en) * 2016-08-03 2018-02-08 Xerox Corporation Method and system for auto-selection of employees for trainings in an organization
CN107545377A (en) * 2017-09-30 2018-01-05 新奥(中国)燃气投资有限公司 A kind of project management method and device
CN107818407A (en) * 2017-10-20 2018-03-20 平安科技(深圳)有限公司 Method for allocating tasks, device, storage medium and computer equipment
CN107909334A (en) * 2017-10-24 2018-04-13 中国平安人寿保险股份有限公司 A kind of project management method, device, server and computer-readable recording medium
CN109636205A (en) * 2018-12-18 2019-04-16 合肥师范学院 More skill's dispatching methods in a kind of research & development portfolio
CN109711742A (en) * 2018-12-29 2019-05-03 华润电力(菏泽)有限公司 A kind of distribution method of task, device, equipment and storage medium
CN109816259A (en) * 2019-01-30 2019-05-28 翟红鹰 Task distribution method, terminal device and storage medium based on block chain

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴吉义等: "《软件项目管理理论与案例分析》", 31 August 2007, 中国电力出版社, pages: 116 - 121 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111652997A (en) * 2020-05-28 2020-09-11 浙江舜江建设集团有限公司 Real-name management method for constructors in large-scale construction site
CN111754121A (en) * 2020-06-28 2020-10-09 北京百度网讯科技有限公司 Task allocation method, device, equipment and storage medium
CN111754121B (en) * 2020-06-28 2024-02-06 北京百度网讯科技有限公司 Method, device, equipment and storage medium for task allocation
CN114240188A (en) * 2021-12-21 2022-03-25 中国建设银行股份有限公司 Task allocation method and device

Similar Documents

Publication Publication Date Title
CN110322127A (en) A kind of project scheduling method, equipment, server and computer readable storage medium
KR101781705B1 (en) Method and apparatus for remote site monitoring
CN110310023A (en) A kind of project scheduling method, equipment, server and computer readable storage medium
US7933934B2 (en) Operator-specific quality management and quality improvement
US8805717B2 (en) Method and system for improving performance of customer service representatives
CN110334921A (en) A kind of project scheduling method, equipment, server and computer readable storage medium
US20130179314A1 (en) Risk Based Data Assessment
CN110322126A (en) A kind of project scheduling method, equipment, server and computer readable storage medium
Ma et al. Evaluating service identification with design metrics on business process decomposition
CN109272219A (en) Performance appraisal method, apparatus, computer equipment and storage medium
CN110060087A (en) Detection method, device and the server of abnormal data
KR100842231B1 (en) System for integrated performance management
CN113342939B (en) Data quality monitoring method and device and related equipment
Barisic et al. How to reach a usable DSL? Moving toward a Systematic Evaluation
CN109409900A (en) A kind of trade company's checking method and server
CN111095424A (en) Clinical trial support system, clinical trial support program, and clinical trial support method
US20190172069A1 (en) Computer-based Understanding of Customer Behavior Patterns for Better Customer Outcomes
CN108764825A (en) Job information matching process, device, computer equipment and storage medium
WO2011149608A1 (en) Identifying and using critical fields in quality management
CN107818390A (en) A kind of check requirements generation method and device
CN110334920A (en) A kind of project scheduling method, equipment, server and computer readable storage medium
CN110263068A (en) A kind of method and system handling monitoring data
CN115617670A (en) Software test management method, storage medium and system
CN115423305A (en) IT service management method and device and server
CN109214548A (en) A kind of prediction technique and device of order time

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination