CN110258895A - Silk ball moulding furred ceiling and its construction method - Google Patents

Silk ball moulding furred ceiling and its construction method Download PDF

Info

Publication number
CN110258895A
CN110258895A CN201910497489.0A CN201910497489A CN110258895A CN 110258895 A CN110258895 A CN 110258895A CN 201910497489 A CN201910497489 A CN 201910497489A CN 110258895 A CN110258895 A CN 110258895A
Authority
CN
China
Prior art keywords
skeleton
frame
silk ball
furred ceiling
backboard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910497489.0A
Other languages
Chinese (zh)
Other versions
CN110258895B (en
Inventor
罗杨诏
韦年达
谢金城
梁东景
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201910497489.0A priority Critical patent/CN110258895B/en
Publication of CN110258895A publication Critical patent/CN110258895A/en
Application granted granted Critical
Publication of CN110258895B publication Critical patent/CN110258895B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/06Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
    • E04B9/061Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members supporting construction for curved ceilings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/18Means for suspending the supporting construction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/22Connection of slabs, panels, sheets or the like to the supporting construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Non-Portable Lighting Devices Or Systems Thereof (AREA)
  • Mirrors, Picture Frames, Photograph Stands, And Related Fastening Devices (AREA)

Abstract

The present invention relates to a kind of silk ball moulding furred ceiling and its construction methods, the skeleton including being installed on building top;And height is adjustably located in multiple petal-shaped structures of the skeleton, the petal-shaped structure includes a frame, and the frame hang on the skeleton by suspender member.The present invention forms the installation foundation of silk ball moulding in such a way that skeleton connecting building structure is arranged in top, provides construction basis and location base for the ceiling construction that height is big, span is big.And adjustably hang down in skeleton lower height and set petal-shaped structure in silk ball moulding, the height by adjusting petal-shaped structure is the radian of adjustable silk ball moulding, convenient for reaching positioning requirements.

Description

Silk ball moulding furred ceiling and its construction method
Technical field
The present invention relates to technical field of building construction, a kind of silk ball moulding furred ceiling and its construction method are refered in particular to.
Background technique
In recent years, with the development of national architecture, majority building will be national generally according to national cultural feature in design Distinctive culture article is incorporated into building decoration and fitment, to derive diversified decorations moulding.And furred ceiling It is the important component of indoor decorating, there is the moulding of national characters ceiling decoration can not only be internalized by indoor environment, moreover it is possible to Build colourful interior space art.The silk ball mascot common as folks of china, especially in ethnic group region, Silk ball moulding is usually incorporated into building decoration furred ceiling, and production likeness in form silk ball, lines are terse, moulding atmosphere silk ball moulding furred ceiling Zhuang national architecture characteristic can greatly be embodied.
However since silk ball moulding ceiling height is big, span is big, difficulty of construction is big, and structure is arc-shaped, wants to positioning Ask higher, in addition, lamps and lanterns built in furred ceiling, in design it is also necessary to take into account that the subsequent maintenance to lamps and lanterns.
Summary of the invention
It is an object of the invention to overcome the deficiencies of existing technologies, a kind of silk ball moulding furred ceiling and its construction method are provided, It can solve since silk ball moulding ceiling structure is arc-shaped, the problem of difficulty of construction is big to the more demanding of positioning.
Realizing the technical solution of above-mentioned purpose is:
The present invention provides a kind of silk ball moulding furred ceilings, comprising:
It is installed on the skeleton of building top;And
Height is adjustably located in multiple petal-shaped structures of the skeleton.
The invention has the advantages that forming the peace of silk ball moulding in such a way that skeleton connecting building structure is arranged in top Dress basis provides construction basis and location base for the ceiling construction that height is big, span is big.And it is adjustable in skeleton lower height Hang down the petal-shaped structure set in silk ball moulding on ground, and the height by adjusting petal-shaped structure is the radian of adjustable silk ball moulding, Convenient for reaching positioning requirements.
Silk ball moulding furred ceiling of the present invention further improvement lies in that, the petal-shaped structure include a frame, the frame The skeleton is hung on by suspender member.
Silk ball moulding furred ceiling of the present invention further improvement lies in that, the suspender member include top be fixed on the skeleton Screw rod and the connector for being sheathed on the screw rod are screwed with the stop nut for limiting the connector on the screw rod, described Connector is fixed with the frame, by adjusting position of the stop nut on the screw rod to adjust the connector Height.
Silk ball moulding furred ceiling of the present invention further improvement lies in that, support frame is formed at the top of the frame, and described Backboard is removably installed on support frame, the bottom of the outline border is covered with decorative layer, between the backboard and the decorative layer It is laid with lamps and lanterns.
Silk ball moulding furred ceiling of the present invention further improvement lies in that, the backboard is installed on support frame as described above, and the back It is installed with fixed strip on plate, and is installed with the installation part that can hang on support frame as described above on the fixed strip.
The present invention also provides a kind of construction methods of silk ball moulding furred ceiling, comprising:
One skeleton is provided, the skeleton is installed on building top;And
Multiple petal-shaped structures are provided, the petal-shaped structure height is adjustably located in the skeleton.
The construction method of silk ball moulding furred ceiling of the present invention further improvement lies in that, the petal-shaped structure include a frame Frame, the described the step of petal-shaped structure height is adjustably located in the skeleton include:
Suspender member is provided, the frame is hung on the skeleton by the suspender member.
The construction method of silk ball moulding furred ceiling of the present invention further improvement lies in that, the suspender member include screw rod, limit The step of frame is hung on the skeleton by the suspender member described in nut and connector further include:
It will be fixed on the skeleton at the top of the screw rod, the connector is sheathed on the screw rod, and by the limit Position nut is screwed together in the screw rod and for limiting the connector, the connector and the frame is fixed, by adjusting institute Position of the stop nut on the screw rod is stated to adjust the height of the connector.
The construction method of silk ball moulding furred ceiling of the present invention further improvement lies in that, support is formed at the top of the frame Frame, the construction method further include:
Backboard is provided, the backboard is removably installed on support frame as described above;
Decorative layer is provided, the decorative layer is overlying on to the bottom of the outline border;
Lamps and lanterns are provided, the lamps and lanterns are laid between the backboard and the decorative layer.
The construction method of silk ball moulding furred ceiling of the present invention further improvement lies in that, be installed with fixation on the backboard Item is installed with installation part on the fixed strip, described that the backboard is removably installed in step packet on support frame as described above It includes:
Installation part on the backboard is hung on support frame as described above.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of silk ball moulding furred ceiling of the present invention.
Fig. 2 is the structural schematic diagram of silk ball moulding furred ceiling middle skeleton of the present invention.
Fig. 3 is the side view of silk ball moulding furred ceiling of the present invention.
Fig. 4 is the top view of petal-shaped structure in silk ball moulding furred ceiling of the present invention.
Fig. 5 is the bottom view of petal-shaped structure in silk ball moulding furred ceiling of the present invention.
Fig. 6 is the structural schematic diagram of suspender member in silk ball moulding furred ceiling of the present invention.
Description of symbols:
10- skeleton;11- main joist;12- secondary joist;13- mounting portion;131- reinforcing bar;14- repairs riding track;
20- triangle decoration panel;21- arc decoration panel;
30- petal-shaped structure;31- frame;311- vertical supporting bar;312- transverse support bar;32- backboard;33- hanging Part;331- screw rod;332- connector;333- stop nut;334- stop screw;34- lamps and lanterns;35- decorative layer.
Specific embodiment
The present invention will be further explained below with reference to the attached drawings and specific examples.
Refering to fig. 1, it the present invention provides a kind of silk ball moulding furred ceiling, solves since silk ball moulding ceiling structure is in arc The problem of shape, difficulty of construction is big to the more demanding of positioning.Silk ball moulding furred ceiling of the present invention is said with reference to the accompanying drawing It is bright.
As shown in figures 1 and 3, silk ball moulding furred ceiling of the present invention includes being connected to the skeleton 10 of building top and hanging down to set In multiple triangle decoration panels 20, multiple arcs decoration panel 21 and the multiple petal-shaped structures 30 of skeleton.By triangle decoration panel 20, Arc decoration panel 21 and petal-shaped structure 30 form silk ball moulding.And 30 height of petal-shaped structure is adjustably located in skeleton 10.
As shown in Figures 2 and 3, skeleton 10 is located in building top, and skeleton 10 includes the main joist 11 being radially arranged And using being fixedly welded on secondary joist 12 between adjacent two main joists so that adjacent two main joists 11 with connect two masters The secondary joist 12 of keel connects into stable triangular structure.Further, multiple connections of secondary joist 12 form multiple be adapted to The ring structure of silk ball moulding, and multiple ring structures are distributed in concentric circles.Ensure large span furred ceiling through this structure Stability, the installation for triangle decoration panel, arc decoration panel and petal-shaped structure provide basis.
Preferably, by the way that support angle steel connection, the top of support angle steel is welded and fixed between main joist 11 and building top It is fixedly welded on building top, bottom is fixedly welded on the junction for being located at main joist and secondary joist on main joist 11.
Preferably, skeleton 10 is formed with the mounting portion 13 of diamond shape close to the position at furred ceiling center, each mounting portion 13 is by four Root installation keel are welded and fixed to be formed, and shape, size and the position of setting of mounting portion 13 are adapted with petal-shaped structure 30, It is not only the installation offer basis of petal-shaped structure 30, and plays the role of positioning 30 installation site of petal-shaped structure.Into one Step, two installation keel on each mounting portion 13 extend to adjacent mounting portion and are formed reinforcing bar 131, reinforcing bar 131 End be fixedly welded on the installation keel on adjacent mounting portion, to be formed between two neighboring mounting portion 13 multiple Stable triangular structure.And the end of the mounting portion 13 of multiple diamond shapes converges at the center of furred ceiling, mounting portion 13 is located at furred ceiling The end at center is fixed by the connecting rod in building top, the both ends of connecting rod respectively with building top and corresponding installation keel It is welded and fixed.And the other end of mounting portion 13 is fixed on building top also by connecting rod, in addition, connecting rod is also by reinforcing bar 131 connect with building top, so that skeleton 10 is respectively formed on multiple stable triangular structures in horizontal plane and vertical face. Preferably, connecting rod is logical for hot galvanizing angle side.
In the present embodiment, the quantity of mounting portion 13 is five, and the end of five mounting portions 13 is converged and is fixed on and hangs The position at top center, is arranged radially.Preferably, main joist 11 selects channel-section steel keel, and secondary joist 12 and installation keel are selected Hot galvanizing angle steel keel.
As shown in Figure 1, Figure 4 and Figure 5, petal-shaped structure 30 includes a frame 31, which passes through multiple suspender members 33 It is hung on skeleton 10, multiple suspender members 33 are uniformly distributed in the edge of 31 upper surface of frame.As shown in connection with fig. 6, suspender member 33 wraps It includes top and is fixedly welded on the screw rod 331 of skeleton 10 and the connector that is sheathed on screw rod 331 and can move up and down along screw rod 331 332, which is a hook part with opening, and the top of connector 332 is formed with a horizontal connection sheet, the company Contact pin is sheathed on screw rod 331, and the lower part of connector 332 is formed with the space for accommodating 31 edge of frame, and under connector 332 Portion is equipped with a stop screw 334 to which 31 edge of frame to be limited in the space, prevents 31 edge of frame de- from opening It falls.Be screwed with the stop nut 333 for limit connector 332 on screw rod 331, the quantity of stop nut 333 there are two and against In the upper and lower surface of connection sheet, by the setting of stop nut 333 so that 332 height of connector is adjustably fixed on screw rod 331 Lower part, and then realize the height of frame 31 and be adjustably located in skeleton.Preferably, each frame 31 is equipped with three pairs of suspender members 33, each pair of suspender member 33 is set to the opposite two sides of frame 31, and one pair of them suspender member 33 is set to two ends of frame 31.
The formation at 31 top of frame has support frame, and the surface of the support frame is an even curface, and support frame includes multiple Vertical supporting bar 311 and transverse support bar 312, the end of vertical supporting bar 311 are fixedly welded on 31 edge of frame, cross-brace Bar 312 is connected between adjacent vertical supporting bar 311, will by the setting of vertical supporting bar 311 and transverse support bar 312 The top of petal-shaped structure 30 is divided into multiple regions.Petal-shaped structure 30 further includes being removably installed in 31 top of frame Backboard 32, and each backboard 32 is set in corresponding region.The edge of backboard 32 is connected to corresponding vertical supporting bar 311 and cross To support rod 312, specifically, it is installed with fixed strip on backboard 32, vertical supporting bar 311 and transverse support bar are corresponded on fixed strip 312 are installed with installation part, and installation part is downward opening claw, hang on corresponding vertical supporting bar 311 by installation part It is installed in transverse support bar 312 to realize that backboard 32 is dismountable.Preferably, the two sides of backboard 32 are equipped with handle 321, with Just staff is lifted up backboard 32 and dismantles to it.Preferably, backboard 32 is the fire-retardant clip back plate of aluminium sheet backing.
The bottom of frame 31 is covered with decorative layer 35, and lamps and lanterns 34 are laid between decorative layer 35 and backboard 32, is needing When replacing lamps and lanterns, backboard 32 can be dismantled by lifting backboard 32 using handle 321, convenient for the lamps and lanterns 34 to the lower section of backboard 32 into Row replacement.Preferably, lamps and lanterns 34 are LED lamp bar, it is laid with a LED light bar in each region, and further, LED light bar It is laid in bow font, the position that LED light bar both ends are corresponded on backboard 32 offers the threading hole that supply lines passes through.Preferably one In embodiment, the maintenance riding track 14 that petal-shaped structure 30 is equipped with upper people, maintenance 14 one end of riding track position are corresponded on skeleton 10 It is located at corresponding petal-shaped structure in the edge of furred ceiling, the other end, after construction finishes, scaffold is removed, staff The maintenance and replacement that portable lighter of going forward side by side from petal-shaped structure 30 being moved to from maintenance riding track 14 has.
The decorative layer 35 is the light transmission mantle of arc-shaped setting.Preferably, the bottom of frame corresponds to the decorative layer 35 of arc It is formed with rigid curved support net, the upper surface of decorative layer 35 is posted and fixed in the lower surface of supporting network, so that dress The radian for adoring layer 35 is consistent with the radian of supporting network, and decorative layer 35 flexible is avoided to generate biggish amount of deflection because span is larger. Preferably, the supporting network is corresponding with the shape of support frame, supporting network includes the cross-brace item of arc and longitudinal branch of arc Stay, the corresponding lower section for being located at transverse support bar 312 of cross-brace item, longitudinal bracing item, which corresponds to, is located at vertical supporting bar 311 Lower section.
In conjunction with shown in Fig. 1 and Fig. 3, triangle decoration panel 20 is set between two neighboring petal-shaped structure 30, to cover phase Space between adjacent two petal-shaped structures 30, arc decoration panel 21 are then adjacent to triangle decoration panel 20, and multiple arcs facing The outer rim of plate 21 surrounds circle, meets the moulding of silk ball furred ceiling.The surface of triangle decoration panel 20 and arc decoration panel 21 is arc Face, the material of the two are preferably aluminium-plastic panel.The back side of triangle decoration panel 20 and arc decoration panel 21 is installed with mounting bar, and should Mounting bar is adjustably located in skeleton 10 by suspender member height, to realize to triangle decoration panel 20 and arc decoration panel 21 The control of radian.Structure and above-mentioned suspender member 33 due to the suspender member to install triangle decoration panel 20 and arc decoration panel 21 Structure it is identical, therefore herein without repeating.
The construction method of silk ball moulding furred ceiling of the present invention is illustrated with reference to the accompanying drawing.
As shown in Figure 1, the construction method of silk ball moulding furred ceiling of the present invention includes:
BIM model is established, determines the radian and bone of petal-shaped structure 30, triangle decoration panel 20 and arc decoration panel 21 The length and setting angle of each keel, guarantee the accuracy of material in frame 10.
Scaffold is set up below ceiling construction position, and the circle of furred ceiling is determined according to design drawing combination measuring instrument The installation site of each keel on the heart and skeleton.
One skeleton 10 is provided, skeleton 10 is installed on building top, specifically includes the following steps:
Support angle steel is provided, support angle steel and building top are fixed, and main joist 11 and secondary joist 12 are provided, by main dragon Bone 11 is radially arranged and is welded and fixed with support angle steel, and secondary joist 12 is fixedly welded between adjacent two main joists, And multiple connections of secondary joist 12 are made to form multiple ring structures for being adapted to silk ball moulding, and multiple ring structures are in concentric circles point Cloth, to form skeleton 10.
Preferably, also providing installation keel and reinforcing bar, installation keel is corresponded into petal-shaped structure 30, diamondwise is set simultaneously It is welded and fixed, to form the mounting portion 13 of diamond shape in skeleton 10, the shape of mounting portion 13, size and the position of setting are equal It is adapted with petal-shaped structure 30.Then reinforcing bar is fixedly welded between two mounting portions 13 to form stable triangle Structure.
Multiple petal-shaped structures 30 are provided, the height of petal-shaped structure 30 is adjustably located in skeleton 10, specifically include with Lower step:
Frame 31 and suspender member 33 are provided, the top of multiple suspender members 33 is fixedly welded on skeleton 10, and by suspender member 33 lower part is connected to the edge of corresponding frame 31, so that frame 31 is hung on skeleton 10 by suspender member 33.
Further, suspender member 33 includes screw rod 331, connector 332 and stop nut 333, and frame is passed through suspender member The step of hanging on skeleton include:
The top of screw rod 331 is fixedly welded on skeleton 10, the top of connector 332 is sheathed on screw rod 331, and will limit Position nut 333 is screwed together in screw rod 331 and limit connector 332,31 edge of frame is put into connector 332 and by a limit Screw 334 keeps 31 edge of frame and connector 332 fixed, by adjust position of the stop nut 332 on screw rod 331 to The height of adjusting connector 332.
The top of frame 31 is formed with support frame, and the surface of the support frame is an even curface, and support frame includes multiple Vertical supporting bar 311 and transverse support bar 312, construction method of the invention are further comprising the steps of:
The end of vertical supporting bar 311 is fixedly welded on 31 edge of frame, and transverse support bar 312 is connected to phase Between adjacent vertical supporting bar 311, by the setting of vertical supporting bar 311 and transverse support bar 312 by petal-shaped structure 30 Top is divided into multiple regions;
Backboard 32 is provided, backboard 32 is removably installed on support frame, and each backboard 32 is set to corresponding region It is interior, the edge of backboard 32 is connected to corresponding vertical supporting bar 311 and transverse support bar 312.Specifically, in the upper of backboard 32 Item is welded and fixed in surface, and the position welding installation part of vertical supporting bar 311 and transverse support bar 312, peace are corresponded on fixed strip Piece installing is downward opening claw, is hung on corresponding vertical supporting bar 311 and transverse support bar 312 by installation part To realize that backboard 32 is removably installed.Preferably, in the fixed handle 321 in the two sides of backboard 32, so that staff is upward Lift backboard 32 and it is dismantled.
Decorative layer 35 and lamps and lanterns 34 are provided, decorative layer 35 are overlying on to the bottom of outline border, and lamps and lanterns 34 are laid in decorative layer Between 35 and backboard 32.When needing replacing lamps and lanterns, backboard 32 can be dismantled by lifting backboard 32 using handle 321, convenient for pair The lamps and lanterns 34 of 32 lower section of backboard are replaced.Preferably, lamps and lanterns 34 are LED light bar, it is laid with a LED in each region Lamp bar, and further, LED light bar is laid in bow font, and open threading in the position for corresponding to LED light bar both ends on backboard 32 Hole passes through for the electric wire of lamps and lanterns 34.Petal-shaped structure 30 is also corresponded in a preferable embodiment, on skeleton 10 to build The maintenance riding track 14 of upper people, making maintenance, 14 one end of riding track is located at the edge of furred ceiling, the other end is located at corresponding petal knot At structure, so that staff can be moved to from petal-shaped structure 30 simultaneously from maintenance riding track 14 after construction finishes, scaffold is removed Carry out the maintenance and replacement of lamps and lanterns.
Decorative layer 35 is the light transmission mantle of arc-shaped setting.Preferably, corresponding to the decorative layer 35 of arc in the bottom of frame It is formed with rigid curved support net, the upper surface of the decorative layer 35 is posted and fixed in the lower surface of supporting network, so that dress The radian for adoring layer 35 is consistent with the radian of supporting network.
In conjunction with shown in Fig. 1 and Fig. 3,
Multiple triangle decoration panels 20 and multiple arcs decoration panel 21 are provided, triangle decoration panel 20 is set to two neighboring petal Between shape structure 30, it is adjacent to pair to cover the space between two neighboring petal-shaped structure 30, and by arc decoration panel 21 The triangle decoration panel 20 answered, and the outer rim of multiple arcs decoration panel 21 is made to surround circle, meet the moulding of silk ball furred ceiling.Three angle ribs The surface of panel 20 and arc decoration panel 21 is cambered surface, and the material of the two is preferably aluminium-plastic panel.In triangle decoration panel 20 and arc Item is fixedly mounted in the back side of shape decoration panel 21, and the mounting bar is adjustably located in skeleton 10 by suspender member height, from And realize the control to the radian of triangle decoration panel 20 and arc decoration panel 21.Due to install triangle decoration panel 20 and arc The structure of the suspender member of decoration panel 21 is identical as the structure of above-mentioned suspender member 33, therefore herein without repeating.
Silk ball moulding furred ceiling of the present invention and its construction method have the beneficial effect that
The present invention is made by the silk ball of three petal-shaped structure, triangle decoration panel and arc decoration panel part group cambers Type reduces the amount of deflection that decoration panel is generated by self weight, if being constructed with monolith decoration panel, can generate because decoration panel self weight is bigger Excessive amount of deflection, is unable to satisfy decorative effect.
The present invention forms the installation foundation of silk ball moulding in such a way that skeleton connecting building structure is arranged in top, for height Greatly, the big ceiling construction of span provides construction basis and location base.And it adjustably hangs down in skeleton lower height and sets silk ball and make Petal-shaped structure, triangle decoration panel and arc decoration panel in type, the height by adjusting three are adjustable silk ball moulding Radian, consequently facilitating reaching positioning requirements.
Petal-shaped structure installs backboard using dismountable mode in the present invention, and maintenance riding track is provided on skeleton, Convenient for the lamps and lanterns in furred ceiling are safeguarded and are replaced.
The present invention has been described in detail with reference to the accompanying drawings, those skilled in the art can be according to upper It states and bright many variations example is made to the present invention.Thus, certain details in embodiment should not constitute limitation of the invention, this Invention will be using the range that the appended claims define as protection scope of the present invention.

Claims (10)

1. a kind of silk ball moulding furred ceiling characterized by comprising
It is installed on the skeleton of building top;And
Height is adjustably located in multiple petal-shaped structures of the skeleton.
2. silk ball moulding furred ceiling as described in claim 1, which is characterized in that the petal-shaped structure includes a frame, described Frame hang on the skeleton by suspender member.
3. silk ball moulding furred ceiling as claimed in claim 2, which is characterized in that the suspender member includes that the bone is fixed at top The screw rod of frame and the connector for being sheathed on the screw rod are screwed with the stop nut for limiting the connector on the screw rod, The connector is fixed with the frame, by adjusting position of the stop nut on the screw rod to adjust the company The height of fitting.
4. silk ball moulding furred ceiling as claimed in claim 2, which is characterized in that support frame is formed at the top of the frame, and Backboard is removably installed on support frame as described above, the bottom of the outline border is covered with decorative layer, the backboard and the decorative layer Between be laid with lamps and lanterns.
5. silk ball moulding furred ceiling as claimed in claim 4, which is characterized in that the backboard is installed on support frame as described above, and institute It states and is installed with fixed strip on backboard, and be installed with the installation part that can hang on support frame as described above on the fixed strip.
6. a kind of construction method of silk ball moulding furred ceiling characterized by comprising
One skeleton is provided, the skeleton is installed on building top;And
Multiple petal-shaped structures are provided, the petal-shaped structure height is adjustably located in the skeleton.
7. the construction method of silk ball moulding furred ceiling as claimed in claim 6, which is characterized in that the petal-shaped structure includes one Frame, the described the step of petal-shaped structure height is adjustably located in the skeleton include:
Suspender member is provided, the frame is hung on the skeleton by the suspender member.
8. the construction method of silk ball moulding furred ceiling as claimed in claim 7, which is characterized in that the suspender member include screw rod, The step of frame is hung on the skeleton by the suspender member described in stop nut and connector further include:
It will be fixed on the skeleton at the top of the screw rod, the connector is sheathed on the screw rod, and by the limit spiral shell Mother is screwed together in the screw rod and for limiting the connector, the connector and the frame is fixed, by adjusting the limit Position of the position nut on the screw rod is to adjust the height of the connector.
9. the construction method of silk ball moulding furred ceiling as claimed in claim 7, which is characterized in that be formed at the top of the frame Support frame, the construction method further include:
Backboard is provided, the backboard is removably installed on support frame as described above;
Decorative layer is provided, the decorative layer is overlying on to the bottom of the outline border;
Lamps and lanterns are provided, the lamps and lanterns are laid between the backboard and the decorative layer.
10. the construction method of silk ball moulding furred ceiling as claimed in claim 9, which is characterized in that be installed on the backboard Determine item, installation part is installed on the fixed strip, it is described that the backboard is removably installed in step on support frame as described above Include:
Installation part on the backboard is hung on support frame as described above.
CN201910497489.0A 2019-06-10 2019-06-10 Silk ball modeling suspended ceiling and construction method thereof Active CN110258895B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910497489.0A CN110258895B (en) 2019-06-10 2019-06-10 Silk ball modeling suspended ceiling and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910497489.0A CN110258895B (en) 2019-06-10 2019-06-10 Silk ball modeling suspended ceiling and construction method thereof

Publications (2)

Publication Number Publication Date
CN110258895A true CN110258895A (en) 2019-09-20
CN110258895B CN110258895B (en) 2024-06-14

Family

ID=67917365

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910497489.0A Active CN110258895B (en) 2019-06-10 2019-06-10 Silk ball modeling suspended ceiling and construction method thereof

Country Status (1)

Country Link
CN (1) CN110258895B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112031251A (en) * 2020-08-24 2020-12-04 苏州金螳螂建筑装饰股份有限公司 Adjustable arc aluminum square tube design ceiling structure and installation method
CN117248670A (en) * 2023-09-20 2023-12-19 北京城建集团有限责任公司 Large-span undulating suspended ceiling structure with elliptical skylight

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU16605U1 (en) * 2000-08-22 2001-01-20 Закрытое акционерное общество "Аркада" False Ceiling Design, BASIC, CROSS, CORNER, OUTDOOR CORNER, INTERNAL CORNER, ANGLE F-SHAPED AND STEADED CEILING PROFILES AND SUSPENSIONS (NOT OPTIONS FOR
CN202324292U (en) * 2011-11-25 2012-07-11 中建七局建筑装饰工程有限公司 Full-rigid connection structure for suspended ceiling
CN106948538A (en) * 2017-05-11 2017-07-14 中国建筑第二工程局有限公司 Suspended ceiling structure and building structure
CN109235739A (en) * 2018-11-01 2019-01-18 苏州金螳螂建筑装饰股份有限公司 A kind of hanging moulding large span furred ceiling of petal
CN109736504A (en) * 2019-01-25 2019-05-10 中建一局集团装饰工程有限公司 Detachable ceiling edge keel system and construction method thereof
CN210713466U (en) * 2019-06-10 2020-06-09 中国建筑第八工程局有限公司 Embroidered ball modeling ceiling

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU16605U1 (en) * 2000-08-22 2001-01-20 Закрытое акционерное общество "Аркада" False Ceiling Design, BASIC, CROSS, CORNER, OUTDOOR CORNER, INTERNAL CORNER, ANGLE F-SHAPED AND STEADED CEILING PROFILES AND SUSPENSIONS (NOT OPTIONS FOR
CN202324292U (en) * 2011-11-25 2012-07-11 中建七局建筑装饰工程有限公司 Full-rigid connection structure for suspended ceiling
CN106948538A (en) * 2017-05-11 2017-07-14 中国建筑第二工程局有限公司 Suspended ceiling structure and building structure
CN109235739A (en) * 2018-11-01 2019-01-18 苏州金螳螂建筑装饰股份有限公司 A kind of hanging moulding large span furred ceiling of petal
CN109736504A (en) * 2019-01-25 2019-05-10 中建一局集团装饰工程有限公司 Detachable ceiling edge keel system and construction method thereof
CN210713466U (en) * 2019-06-10 2020-06-09 中国建筑第八工程局有限公司 Embroidered ball modeling ceiling

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112031251A (en) * 2020-08-24 2020-12-04 苏州金螳螂建筑装饰股份有限公司 Adjustable arc aluminum square tube design ceiling structure and installation method
CN117248670A (en) * 2023-09-20 2023-12-19 北京城建集团有限责任公司 Large-span undulating suspended ceiling structure with elliptical skylight

Also Published As

Publication number Publication date
CN110258895B (en) 2024-06-14

Similar Documents

Publication Publication Date Title
CN200992763Y (en) Ceiling unit structure hanging aluminium slat under hyperboloid grid third quavter
CN110258895A (en) Silk ball moulding furred ceiling and its construction method
CN210713466U (en) Embroidered ball modeling ceiling
CN109811951A (en) Modularization weaves plate furred ceiling component and its furred ceiling and installation method
CN205875666U (en) A platform suspends in midair that is used for building eaves oral area position to be under construction
CN209457232U (en) A kind of U-shaped aluminium Fang Tongyu downlight combination furred ceiling
CN109132843B (en) The installation method of super-section metal bellows in a kind of vertical shaft
CN201292595Y (en) Support framework for architectural decoration
CN207110193U (en) Keel component and ceiling structure
CN107227829B (en) A kind of quick levelling hanging structure of metope
CN205035957U (en) Staggered floor roof beam
CN207394578U (en) The double integrated lights of hanging edge of a dripping tile tile
CN205935359U (en) Printing opacity arch suspended ceiling's mounting structure
CN206308881U (en) A kind of triangular keel accessory
CN217232553U (en) Cylindrical-shaped light well
CN219794367U (en) Suspended ceiling structure convenient for dismounting aluminum veneer
CN221193915U (en) Suspended ceiling mounting structure
CN213453249U (en) Improved hollow pendant lamp
CN220337656U (en) A gallows for truss lower chord fixed shower
CN220341980U (en) Fixing structure for electromechanical pipeline of high-low difference floor roof
CN213983459U (en) Ceiling lamp suspension arm capable of fixing ceiling lamp conveniently
CN214220206U (en) Ceiling structure with adjustable height
CN113187226B (en) Be used for crossbeam to pour fashioned template structure
CN206989015U (en) A kind of Integral ceiling light fixture of the detachable lamp panel of band
CN218708581U (en) Free hook structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant