CN110258656A - A kind of underground waterproof engineering pre-installed and inverted adhered construction method - Google Patents

A kind of underground waterproof engineering pre-installed and inverted adhered construction method Download PDF

Info

Publication number
CN110258656A
CN110258656A CN201910454805.6A CN201910454805A CN110258656A CN 110258656 A CN110258656 A CN 110258656A CN 201910454805 A CN201910454805 A CN 201910454805A CN 110258656 A CN110258656 A CN 110258656A
Authority
CN
China
Prior art keywords
waterproof roll
waterproof
laid
construction
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910454805.6A
Other languages
Chinese (zh)
Inventor
丛峰
李阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Third Metallurgical Group Co Ltd
Original Assignee
China Third Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Third Metallurgical Group Co Ltd filed Critical China Third Metallurgical Group Co Ltd
Priority to CN201910454805.6A priority Critical patent/CN110258656A/en
Publication of CN110258656A publication Critical patent/CN110258656A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/025Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples

Abstract

The present invention relates to a kind of underground waterproof engineering pre-installed and inverted adhered construction methods, comprising: 1) base cleaning;2) unwrapping wire positions;3) node processing;4) waterproof roll is laid with;5) waterproof roll receives waterproof sealing at head node;6) it finished product protection and inspects for acceptance.Construction method of the present invention is low to basic level requirement without setting screed-coat, not by weather and base's moisture effect;Waterproof roll top directly carries out reinforced concrete construction, substantially increases construction speed without doing protective layer;Work progress is cold-working industry, the flames of anger, non-toxic and tasteless, non-environmental-pollution and hidden fire-fighting danger, safety and environmental protection.

Description

A kind of underground waterproof engineering pre-installed and inverted adhered construction method
Technical field
The present invention relates to technical field of building construction more particularly to a kind of underground waterproof engineering pre-installed and inverted adhered construction methods.
Background technique
Currently, China overwhelming majority underground waterproofing work is all made of conventional waterproof material as waterproof layer, waterproof material paving It is affixed on bed course basal plane, then does protective layer, then casting concrete structure, waterproof layer is not bonded with structural concrete.This way Defect when being that waterproof layer is destroyed, channelling can occur between waterproof layer and structure sheaf for underground water.Due to structure coagulation Soil is porosity Inhomogeneous wave fields, is existed such as: because the vibrate honeycomb hole of not firm generation, objective factor cause in casting process Concrete reserving gaps (construction joint, deformation joint etc.) and uneven settlement of foundation caused by structural cracks the defects of, channelling Moisture between waterproof layer and structure sheaf will enter inside configuration along the defects of gap, hole of structural concrete, make At leakage.
A kind of pre-installed and inverted adhered technology is described in " 10 new technologies of construction industry (2017 editions) ", using be covered with macromolecule from Adhesive surface sky is layered on blinding layer by the waterproof roll of viscose glue film layer, and bonding is combined into cast-in-place concrete face upwardly One, centre is without channeling water hidden danger;Even if waterproof roll is locally destroyed, water can be also limited to very a small range.Used in it Waterproof roll not only reached international most advanced level in product technology compared with conventional waterproof coiled material, but also price also compares Conventional waterproof coiled material is cheap.Waterproof effect is even more to lead over the latter, substantially increases reliability, the durability of buildings waterproof.
Summary of the invention
The present invention provides a kind of underground waterproof engineering pre-installed and inverted adhered construction methods, without setting screed-coat, to basic level requirement It is low, not by weather and base's moisture effect;Waterproof roll top directly carries out reinforced concrete construction, greatly without doing protective layer Construction speed is improved greatly;Work progress is cold-working industry, the flames of anger, non-toxic and tasteless, non-environmental-pollution and hidden fire-fighting danger, safety collar It protects.
In order to achieve the above object, the present invention is implemented with the following technical solutions:
A kind of underground waterproof engineering pre-installed and inverted adhered construction method, includes the following steps:
1) base cleaning;Flattening foot layer removes surface irregularities and greasy dirt;
2) unwrapping wire positions;Reference line when base upper surface releases waterproof roll paving, when guaranteeing waterproof roll paving It is not in dislocation, crooked phenomenon;
3) node processing;It is arranged at the node including plane and facade junction, deformation joint, construction joint, pipe root The additional enhancement layer of waterproof roll, additional enhancement layer are cut according to actual measurement size at the scene, and additional enhancement layer is using two-sided Adhesive waterproof coil;Unstressed concentration position base and additional enhancement layer are glued using full, and stress concentration portion position is using empty paving;It is full viscous Position before laying first brush oiliness base treatment agent, re-lay additional enhancement layer after dry;
4) waterproof roll is laid with;Waterproof roll selects reaction bonded type macromolecule wet-laying waterproof roll, using pre-installed and inverted adhered The directly empty paving of method, after reserving overlap joint size according to the width of selected waterproof roll, carries out waterproof roll laying by reference line;It is laid with When, the overlapping the slot of adjacent 2 width waterproof roll is staggered, and the length that is staggered is not less than 1500mm;Overlapping the slot is close using overlap joint Self-adhesive It is real;Waterproof roll when being laid with downward, up, first drawn at the edge of surface isolation film by lap width cross-laminated film surface by bonding It opens, then the isolation film of adjacent 2 width waterproof roll overlap edge is torn, overlap edge uses cold bonding knot;
5) waterproof roll receives waterproof sealing at head node;Waterproof roll after being laid with to brick fetal membrane upper pressing it is fixed, after pour Band position waterproof roll reserves enough laps of splice, and upper cover plank sheathing is protected;
6) it finished product protection and inspects for acceptance;Waterproof roll carries out finished product protection after the completion of being laid with, and prevents sharp objects from hitting Waterproof layer is stabbed, then weld waterproof roll surface sets interim safeguard measure if you need to weld job;Coiled material is prevented to be laid on inspection After qualification, the isolation film on waterproof roll surface is torn before binding baseplate reinforcing bar, and spread plain water waterproof roll surface is thin Mud powder;
The positioning of placing of reinforcement unwrapping wire, which uses, when reinforced concrete construction, under bottom plate spreads lime or logical line is drawn to carry out as control line Construction, after the completion of lower placing of reinforcement construction, brush paint or the logical line of drawing are as control line on reinforcing bar;Reinforcing bar, which is hung, a little sets interim protection Measure;When assembling reinforcement, concrete pad is first arranged, concrete pad bottom adds one layer of waterproof roll enhancing;Weld Bottom Board Steel When muscle, interim protection baffle is set in welding operating surface.
Compared with prior art, the beneficial effects of the present invention are:
1) it is constructed using pre-laid method, waterproof roll forms waterproof layer new together in conjunction with basic plate face, the waterproof Layer effectively prevents underground water channelling into it, even if waterproof roll part by water being limited to a small range destruction, side Just it is quickly found out breakthrough and adopts an effective measure and carry out leak stopping, the hidden danger leaked again will not be generated;
2) waterproof roll combines together with major structure of construction, and waterproof performance is not influenced by main body structure sediment, can be effective Groundwater infiltration is prevented, waterproof quality is substantially increased;
3) protective layer on waterproof roll can not be done, directly progress armored concrete pouring construction, while to basic level requirement It is low, not by weather and base's moisture effect, speed of application is substantially increased, the construction period is shortened;
4) cold-working industry, the flames of anger, non-toxic and tasteless, non-environmental-pollution and hidden fire-fighting danger, safety and environmental protection are used;
5) waterproof layer have stronger chemical corrosion resistance, have good repellence to the buck from concrete, not by House refuse and biological infestation, it is mould proof, it is corrosion-resistant.
Specific embodiment
A kind of underground waterproof engineering pre-installed and inverted adhered construction method, includes the following steps:
1) base cleaning;Flattening foot layer removes surface irregularities and greasy dirt;
2) unwrapping wire positions;Reference line when base upper surface releases waterproof roll paving, when guaranteeing waterproof roll paving It is not in dislocation, crooked phenomenon;
3) node processing;It is arranged at the node including plane and facade junction, deformation joint, construction joint, pipe root The additional enhancement layer of waterproof roll, additional enhancement layer are cut according to actual measurement size at the scene, and additional enhancement layer is using two-sided Adhesive waterproof coil;Unstressed concentration position base and additional enhancement layer are glued using full, and stress concentration portion position is using empty paving;It is full viscous Position before laying first brush oiliness base treatment agent, re-lay additional enhancement layer after dry;
4) waterproof roll is laid with;Waterproof roll selects reaction bonded type macromolecule wet-laying waterproof roll, using pre-installed and inverted adhered The directly empty paving of method, after reserving overlap joint size according to the width of selected waterproof roll, carries out waterproof roll laying by reference line;It is laid with When, the overlapping the slot of adjacent 2 width waterproof roll is staggered, and the length that is staggered is not less than 1500mm;Overlapping the slot is close using overlap joint Self-adhesive It is real;Waterproof roll when being laid with downward, up, first drawn at the edge of surface isolation film by lap width cross-laminated film surface by bonding It opens, then the isolation film of adjacent 2 width waterproof roll overlap edge is torn, overlap edge uses cold bonding knot;
5) waterproof roll receives waterproof sealing at head node;Waterproof roll after being laid with to brick fetal membrane upper pressing it is fixed, after pour Band position waterproof roll reserves enough laps of splice, and upper cover plank sheathing is protected;
6) it finished product protection and inspects for acceptance;Waterproof roll carries out finished product protection after the completion of being laid with, and prevents sharp objects from hitting Waterproof layer is stabbed, then weld waterproof roll surface sets interim safeguard measure if you need to weld job;Coiled material is prevented to be laid on inspection After qualification, the isolation film on waterproof roll surface is torn before binding baseplate reinforcing bar, and spread plain water waterproof roll surface is thin Mud powder;
The positioning of placing of reinforcement unwrapping wire, which uses, when reinforced concrete construction, under bottom plate spreads lime or logical line is drawn to carry out as control line Construction, after the completion of lower placing of reinforcement construction, brush paint or the logical line of drawing are as control line on reinforcing bar;Reinforcing bar, which is hung, a little sets interim protection Measure;When assembling reinforcement, concrete pad is first arranged, concrete pad bottom adds one layer of waterproof roll enhancing;Weld Bottom Board Steel When muscle, interim protection baffle is set in welding operating surface.
Following embodiment is implemented under the premise of the technical scheme of the present invention, gives detailed embodiment and tool The operating process of body, but protection scope of the present invention is not limited to following embodiments.Method therefor is such as without spy in following embodiments Not mentionleting alone bright is conventional method.
[embodiment]
In the present embodiment, construction main body is that monomer villa adds underground garage, overall floorage about 59106.81m2, wherein Lower room area 11413.72m2, basic plate face expansion about 15000m2, basement elevation of floor level -5.80m, top elevation - 1.80m, totally one layer, the high 4m of layer.
The waterproof layer structure of former design mistake is: 100mm thickness C15 concrete cushion+1.5mm thickness waterproof roll+ 50mm thickness C20 protective layer+cast-in-situ steel reinforced concrete bottom plate, wherein waterproof roll uses the advanced compound D type self-adhesion waterproof roll of KDS Material, price are 32 yuan/m2, 10.5 yuan/m of labour cost2
After pre-installed and inverted adhered construction method of the present invention, CPL-XE reaction bonded type macromolecule wet-laying waterproof roll is selected Material, 20 yuan/m of price2, 9.5 yuan/m of labour cost2.195000 yuan of mass-type foundation waterproof construction escapable cost.
The direct sky of waterproof roll is layered in mat surface, is not required to brush cement slurry, and waterproof roll reserves overlap joint size, long short side It is 80mm, the length that is staggered when adjacent 2 width waterproof roll overlaps is not less than 1500mm, lap of splice 80mm.
Since reaction bonded type macromolecule wet-laying waterproof roll can construct immediately after bed course reaches upper people's intensity, without etc. It is dry to mat surface, waterproof protective layer is not in addition done, therefore the time is greatly saved, engineering total construction period shortens 7 days.
The present embodiment, according to " underground waterproof engineering waterproof technique specification " (GB50108-2008), " underground waterproof engineering matter Measure acceptance specification " (GB50208-2011) and " overlaying/wet-laying waterproof roll " related request carry out quality control, test on inspection It receives, complies fully with standard requirements.
This engineering formally went into operation on April 1st, 2017, was completed on March 30th, 2019.Basement does not occur any at present Leakage phenomenon, waterproof effect are good.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (1)

1. a kind of underground waterproof engineering pre-installed and inverted adhered construction method, which comprises the steps of:
1) base cleaning;Flattening foot layer removes surface irregularities and greasy dirt;
2) unwrapping wire positions;Base upper surface release waterproof roll paving when reference line, guarantee waterproof roll paving when will not There is dislocation, crooked phenomenon;
3) node processing;Waterproof is set at the node including plane and facade junction, deformation joint, construction joint, pipe root The additional enhancement layer of coiled material, additional enhancement layer are cut according to actual measurement size at the scene, and additional enhancement layer uses double-sided self-adhesive Waterproof roll;Unstressed concentration position base and additional enhancement layer are glued using full, and stress concentration portion position is using empty paving;Completely viscous portion Position first brush oiliness base treatment agent before laying, re-lays additional enhancement layer after dry;
4) waterproof roll is laid with;Waterproof roll selects reaction bonded type macromolecule wet-laying waterproof roll, straight using pre-laid method Empty paving is connect, after reserving overlap joint size according to the width of selected waterproof roll, carries out waterproof roll laying by reference line;When laying, The overlapping the slot of adjacent 2 width waterproof roll is staggered, and the length that is staggered is not less than 1500mm;Overlapping the slot is closely knit using overlap joint Self-adhesive; Waterproof roll when being laid with downward, up, first scratched at the edge of surface isolation film by lap width cross-laminated film surface by bonding, The isolation film of adjacent 2 width waterproof roll overlap edge is torn again, overlap edge uses cold bonding knot;
5) waterproof roll receives waterproof sealing at head node;Upper pressing is fixed after waterproof roll is laid with to brick fetal membrane top, post-cast strip position It sets waterproof roll and reserves enough laps of splice, upper cover plank sheathing is protected;
6) it finished product protection and inspects for acceptance;Waterproof roll carries out finished product protection after the completion of being laid with, and prevents sharp objects shock from stabbing Waterproof layer, if you need to weld job, then weld waterproof roll surface sets interim safeguard measure;Coiled material is prevented to be laid with qualified on inspection Afterwards, the isolation film on waterproof roll surface is torn before binding baseplate reinforcing bar, and spread plain cement powder waterproof roll surface is thin;
The positioning of placing of reinforcement unwrapping wire, which uses, when reinforced concrete construction, under bottom plate spreads lime or logical line is drawn to be applied as control line Work, after the completion of lower placing of reinforcement construction, brush paint or the logical line of drawing are as control line on reinforcing bar;Reinforcing bar hangs a little to set temporarily to protect and arrange It applies;When assembling reinforcement, concrete pad is first arranged, concrete pad bottom adds one layer of waterproof roll enhancing;Weld baseplate reinforcing bar When, interim protection baffle is set in welding operating surface.
CN201910454805.6A 2019-05-29 2019-05-29 A kind of underground waterproof engineering pre-installed and inverted adhered construction method Pending CN110258656A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910454805.6A CN110258656A (en) 2019-05-29 2019-05-29 A kind of underground waterproof engineering pre-installed and inverted adhered construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910454805.6A CN110258656A (en) 2019-05-29 2019-05-29 A kind of underground waterproof engineering pre-installed and inverted adhered construction method

Publications (1)

Publication Number Publication Date
CN110258656A true CN110258656A (en) 2019-09-20

Family

ID=67915751

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910454805.6A Pending CN110258656A (en) 2019-05-29 2019-05-29 A kind of underground waterproof engineering pre-installed and inverted adhered construction method

Country Status (1)

Country Link
CN (1) CN110258656A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111173045A (en) * 2019-12-31 2020-05-19 上海东方雨虹防水技术有限责任公司 Construction method for pre-paving and reversely adhering TPO (thermoplastic polyolefin) waterproof coiled material of basement bottom plate
CN112922030A (en) * 2021-03-24 2021-06-08 江苏凯伦建材股份有限公司 Construction method for pre-laying waterproof coiled material overlap edge on bottom plate and bottom plate side mold supporting structure
CN113653103A (en) * 2021-07-30 2021-11-16 北京市第五建筑工程集团有限公司 Construction method for polymer pre-laid anti-sticking waterproof coiled material

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111173045A (en) * 2019-12-31 2020-05-19 上海东方雨虹防水技术有限责任公司 Construction method for pre-paving and reversely adhering TPO (thermoplastic polyolefin) waterproof coiled material of basement bottom plate
CN112922030A (en) * 2021-03-24 2021-06-08 江苏凯伦建材股份有限公司 Construction method for pre-laying waterproof coiled material overlap edge on bottom plate and bottom plate side mold supporting structure
CN113653103A (en) * 2021-07-30 2021-11-16 北京市第五建筑工程集团有限公司 Construction method for polymer pre-laid anti-sticking waterproof coiled material
CN113653103B (en) * 2021-07-30 2023-01-20 北京市第五建筑工程集团有限公司 Construction method for polymer pre-laid anti-sticking waterproof coiled material

Similar Documents

Publication Publication Date Title
CN101914927B (en) Waterproof system for basement bottom board and wall surface and construction method thereof
CN106120873B (en) A kind of construction method of pile-raft foundation pre-installed and inverted adhered composite high-molecular waterproof roll
CN110258656A (en) A kind of underground waterproof engineering pre-installed and inverted adhered construction method
CN107190844B (en) The waterproof and water drainage system and construction method of a kind of basement bottom board and exterior wall
CN106988440B (en) Waterproof structure for main body and auxiliary interface of subway station and construction method of waterproof structure
CN108708453A (en) Basementwaterproofing construction method
CN107190783A (en) A kind of construction method of basement waterproofing structure and its outer wall of basement waterproof construction
CN211037072U (en) Piping lane bottom plate waterproof construction
CN106801517A (en) A kind of schoolhouse surface consolidation of Prefabricated porous plate brick mixed structure strengthens method
CN107059946A (en) A kind of basement drain plate and its construction
CN102852290A (en) Roof parapet flashing place structure and construction method thereof
CN213952303U (en) Basement outer wall post-cast strip assembled protection wall construction structures
CN201695411U (en) Waterproof system of bottom board and wall surface of basement
CN107165290A (en) Basement bottom board prespreading Macromolecular self-adhesive membrane waterproof roll non-bituminous base construction
CN105862928A (en) Post-cast strip outer wall in-advance water stopping treatment structure and construction process thereof
CN105887923A (en) Construction method for pre-paving and invertedly adhering waterproof coiled material in large underground waterproof project
CN105239729B (en) It has constructed the construction method of poling reparation of punching after roofing
CN109629845A (en) Concrete structure seam areas leakage treatment device and its construction method
CN102912945B (en) Roof compound seepage-proofing steam exhausting hole detail treatment technology
CN105401962B (en) The hermetically sealed waterproof construction method of side wall, engineering top surface
CN106759955A (en) The construction method of waterproof system is laid in a kind of toilet and toilet with waterproof system
CN110067311A (en) The connection structure and method of new-old concrete component junction
CN107587887A (en) A kind of construction joint structure and its waterproof construction method
CN209722876U (en) A kind of structure of interior canal storing facilities of water waterproof layer
CN207998873U (en) Basement bottom plate rear pouring tape structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190920

WD01 Invention patent application deemed withdrawn after publication