CN110258656A - A kind of underground waterproof engineering pre-installed and inverted adhered construction method - Google Patents
A kind of underground waterproof engineering pre-installed and inverted adhered construction method Download PDFInfo
- Publication number
- CN110258656A CN110258656A CN201910454805.6A CN201910454805A CN110258656A CN 110258656 A CN110258656 A CN 110258656A CN 201910454805 A CN201910454805 A CN 201910454805A CN 110258656 A CN110258656 A CN 110258656A
- Authority
- CN
- China
- Prior art keywords
- waterproof roll
- waterproof
- laid
- construction
- layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
- E02D31/025—Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples
Abstract
The present invention relates to a kind of underground waterproof engineering pre-installed and inverted adhered construction methods, comprising: 1) base cleaning;2) unwrapping wire positions;3) node processing;4) waterproof roll is laid with;5) waterproof roll receives waterproof sealing at head node;6) it finished product protection and inspects for acceptance.Construction method of the present invention is low to basic level requirement without setting screed-coat, not by weather and base's moisture effect;Waterproof roll top directly carries out reinforced concrete construction, substantially increases construction speed without doing protective layer;Work progress is cold-working industry, the flames of anger, non-toxic and tasteless, non-environmental-pollution and hidden fire-fighting danger, safety and environmental protection.
Description
Technical field
The present invention relates to technical field of building construction more particularly to a kind of underground waterproof engineering pre-installed and inverted adhered construction methods.
Background technique
Currently, China overwhelming majority underground waterproofing work is all made of conventional waterproof material as waterproof layer, waterproof material paving
It is affixed on bed course basal plane, then does protective layer, then casting concrete structure, waterproof layer is not bonded with structural concrete.This way
Defect when being that waterproof layer is destroyed, channelling can occur between waterproof layer and structure sheaf for underground water.Due to structure coagulation
Soil is porosity Inhomogeneous wave fields, is existed such as: because the vibrate honeycomb hole of not firm generation, objective factor cause in casting process
Concrete reserving gaps (construction joint, deformation joint etc.) and uneven settlement of foundation caused by structural cracks the defects of, channelling
Moisture between waterproof layer and structure sheaf will enter inside configuration along the defects of gap, hole of structural concrete, make
At leakage.
A kind of pre-installed and inverted adhered technology is described in " 10 new technologies of construction industry (2017 editions) ", using be covered with macromolecule from
Adhesive surface sky is layered on blinding layer by the waterproof roll of viscose glue film layer, and bonding is combined into cast-in-place concrete face upwardly
One, centre is without channeling water hidden danger;Even if waterproof roll is locally destroyed, water can be also limited to very a small range.Used in it
Waterproof roll not only reached international most advanced level in product technology compared with conventional waterproof coiled material, but also price also compares
Conventional waterproof coiled material is cheap.Waterproof effect is even more to lead over the latter, substantially increases reliability, the durability of buildings waterproof.
Summary of the invention
The present invention provides a kind of underground waterproof engineering pre-installed and inverted adhered construction methods, without setting screed-coat, to basic level requirement
It is low, not by weather and base's moisture effect;Waterproof roll top directly carries out reinforced concrete construction, greatly without doing protective layer
Construction speed is improved greatly;Work progress is cold-working industry, the flames of anger, non-toxic and tasteless, non-environmental-pollution and hidden fire-fighting danger, safety collar
It protects.
In order to achieve the above object, the present invention is implemented with the following technical solutions:
A kind of underground waterproof engineering pre-installed and inverted adhered construction method, includes the following steps:
1) base cleaning;Flattening foot layer removes surface irregularities and greasy dirt;
2) unwrapping wire positions;Reference line when base upper surface releases waterproof roll paving, when guaranteeing waterproof roll paving
It is not in dislocation, crooked phenomenon;
3) node processing;It is arranged at the node including plane and facade junction, deformation joint, construction joint, pipe root
The additional enhancement layer of waterproof roll, additional enhancement layer are cut according to actual measurement size at the scene, and additional enhancement layer is using two-sided
Adhesive waterproof coil;Unstressed concentration position base and additional enhancement layer are glued using full, and stress concentration portion position is using empty paving;It is full viscous
Position before laying first brush oiliness base treatment agent, re-lay additional enhancement layer after dry;
4) waterproof roll is laid with;Waterproof roll selects reaction bonded type macromolecule wet-laying waterproof roll, using pre-installed and inverted adhered
The directly empty paving of method, after reserving overlap joint size according to the width of selected waterproof roll, carries out waterproof roll laying by reference line;It is laid with
When, the overlapping the slot of adjacent 2 width waterproof roll is staggered, and the length that is staggered is not less than 1500mm;Overlapping the slot is close using overlap joint Self-adhesive
It is real;Waterproof roll when being laid with downward, up, first drawn at the edge of surface isolation film by lap width cross-laminated film surface by bonding
It opens, then the isolation film of adjacent 2 width waterproof roll overlap edge is torn, overlap edge uses cold bonding knot;
5) waterproof roll receives waterproof sealing at head node;Waterproof roll after being laid with to brick fetal membrane upper pressing it is fixed, after pour
Band position waterproof roll reserves enough laps of splice, and upper cover plank sheathing is protected;
6) it finished product protection and inspects for acceptance;Waterproof roll carries out finished product protection after the completion of being laid with, and prevents sharp objects from hitting
Waterproof layer is stabbed, then weld waterproof roll surface sets interim safeguard measure if you need to weld job;Coiled material is prevented to be laid on inspection
After qualification, the isolation film on waterproof roll surface is torn before binding baseplate reinforcing bar, and spread plain water waterproof roll surface is thin
Mud powder;
The positioning of placing of reinforcement unwrapping wire, which uses, when reinforced concrete construction, under bottom plate spreads lime or logical line is drawn to carry out as control line
Construction, after the completion of lower placing of reinforcement construction, brush paint or the logical line of drawing are as control line on reinforcing bar;Reinforcing bar, which is hung, a little sets interim protection
Measure;When assembling reinforcement, concrete pad is first arranged, concrete pad bottom adds one layer of waterproof roll enhancing;Weld Bottom Board Steel
When muscle, interim protection baffle is set in welding operating surface.
Compared with prior art, the beneficial effects of the present invention are:
1) it is constructed using pre-laid method, waterproof roll forms waterproof layer new together in conjunction with basic plate face, the waterproof
Layer effectively prevents underground water channelling into it, even if waterproof roll part by water being limited to a small range destruction, side
Just it is quickly found out breakthrough and adopts an effective measure and carry out leak stopping, the hidden danger leaked again will not be generated;
2) waterproof roll combines together with major structure of construction, and waterproof performance is not influenced by main body structure sediment, can be effective
Groundwater infiltration is prevented, waterproof quality is substantially increased;
3) protective layer on waterproof roll can not be done, directly progress armored concrete pouring construction, while to basic level requirement
It is low, not by weather and base's moisture effect, speed of application is substantially increased, the construction period is shortened;
4) cold-working industry, the flames of anger, non-toxic and tasteless, non-environmental-pollution and hidden fire-fighting danger, safety and environmental protection are used;
5) waterproof layer have stronger chemical corrosion resistance, have good repellence to the buck from concrete, not by
House refuse and biological infestation, it is mould proof, it is corrosion-resistant.
Specific embodiment
A kind of underground waterproof engineering pre-installed and inverted adhered construction method, includes the following steps:
1) base cleaning;Flattening foot layer removes surface irregularities and greasy dirt;
2) unwrapping wire positions;Reference line when base upper surface releases waterproof roll paving, when guaranteeing waterproof roll paving
It is not in dislocation, crooked phenomenon;
3) node processing;It is arranged at the node including plane and facade junction, deformation joint, construction joint, pipe root
The additional enhancement layer of waterproof roll, additional enhancement layer are cut according to actual measurement size at the scene, and additional enhancement layer is using two-sided
Adhesive waterproof coil;Unstressed concentration position base and additional enhancement layer are glued using full, and stress concentration portion position is using empty paving;It is full viscous
Position before laying first brush oiliness base treatment agent, re-lay additional enhancement layer after dry;
4) waterproof roll is laid with;Waterproof roll selects reaction bonded type macromolecule wet-laying waterproof roll, using pre-installed and inverted adhered
The directly empty paving of method, after reserving overlap joint size according to the width of selected waterproof roll, carries out waterproof roll laying by reference line;It is laid with
When, the overlapping the slot of adjacent 2 width waterproof roll is staggered, and the length that is staggered is not less than 1500mm;Overlapping the slot is close using overlap joint Self-adhesive
It is real;Waterproof roll when being laid with downward, up, first drawn at the edge of surface isolation film by lap width cross-laminated film surface by bonding
It opens, then the isolation film of adjacent 2 width waterproof roll overlap edge is torn, overlap edge uses cold bonding knot;
5) waterproof roll receives waterproof sealing at head node;Waterproof roll after being laid with to brick fetal membrane upper pressing it is fixed, after pour
Band position waterproof roll reserves enough laps of splice, and upper cover plank sheathing is protected;
6) it finished product protection and inspects for acceptance;Waterproof roll carries out finished product protection after the completion of being laid with, and prevents sharp objects from hitting
Waterproof layer is stabbed, then weld waterproof roll surface sets interim safeguard measure if you need to weld job;Coiled material is prevented to be laid on inspection
After qualification, the isolation film on waterproof roll surface is torn before binding baseplate reinforcing bar, and spread plain water waterproof roll surface is thin
Mud powder;
The positioning of placing of reinforcement unwrapping wire, which uses, when reinforced concrete construction, under bottom plate spreads lime or logical line is drawn to carry out as control line
Construction, after the completion of lower placing of reinforcement construction, brush paint or the logical line of drawing are as control line on reinforcing bar;Reinforcing bar, which is hung, a little sets interim protection
Measure;When assembling reinforcement, concrete pad is first arranged, concrete pad bottom adds one layer of waterproof roll enhancing;Weld Bottom Board Steel
When muscle, interim protection baffle is set in welding operating surface.
Following embodiment is implemented under the premise of the technical scheme of the present invention, gives detailed embodiment and tool
The operating process of body, but protection scope of the present invention is not limited to following embodiments.Method therefor is such as without spy in following embodiments
Not mentionleting alone bright is conventional method.
[embodiment]
In the present embodiment, construction main body is that monomer villa adds underground garage, overall floorage about 59106.81m2, wherein
Lower room area 11413.72m2, basic plate face expansion about 15000m2, basement elevation of floor level -5.80m, top elevation -
1.80m, totally one layer, the high 4m of layer.
The waterproof layer structure of former design mistake is: 100mm thickness C15 concrete cushion+1.5mm thickness waterproof roll+
50mm thickness C20 protective layer+cast-in-situ steel reinforced concrete bottom plate, wherein waterproof roll uses the advanced compound D type self-adhesion waterproof roll of KDS
Material, price are 32 yuan/m2, 10.5 yuan/m of labour cost2。
After pre-installed and inverted adhered construction method of the present invention, CPL-XE reaction bonded type macromolecule wet-laying waterproof roll is selected
Material, 20 yuan/m of price2, 9.5 yuan/m of labour cost2.195000 yuan of mass-type foundation waterproof construction escapable cost.
The direct sky of waterproof roll is layered in mat surface, is not required to brush cement slurry, and waterproof roll reserves overlap joint size, long short side
It is 80mm, the length that is staggered when adjacent 2 width waterproof roll overlaps is not less than 1500mm, lap of splice 80mm.
Since reaction bonded type macromolecule wet-laying waterproof roll can construct immediately after bed course reaches upper people's intensity, without etc.
It is dry to mat surface, waterproof protective layer is not in addition done, therefore the time is greatly saved, engineering total construction period shortens 7 days.
The present embodiment, according to " underground waterproof engineering waterproof technique specification " (GB50108-2008), " underground waterproof engineering matter
Measure acceptance specification " (GB50208-2011) and " overlaying/wet-laying waterproof roll " related request carry out quality control, test on inspection
It receives, complies fully with standard requirements.
This engineering formally went into operation on April 1st, 2017, was completed on March 30th, 2019.Basement does not occur any at present
Leakage phenomenon, waterproof effect are good.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto,
Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its
Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.
Claims (1)
1. a kind of underground waterproof engineering pre-installed and inverted adhered construction method, which comprises the steps of:
1) base cleaning;Flattening foot layer removes surface irregularities and greasy dirt;
2) unwrapping wire positions;Base upper surface release waterproof roll paving when reference line, guarantee waterproof roll paving when will not
There is dislocation, crooked phenomenon;
3) node processing;Waterproof is set at the node including plane and facade junction, deformation joint, construction joint, pipe root
The additional enhancement layer of coiled material, additional enhancement layer are cut according to actual measurement size at the scene, and additional enhancement layer uses double-sided self-adhesive
Waterproof roll;Unstressed concentration position base and additional enhancement layer are glued using full, and stress concentration portion position is using empty paving;Completely viscous portion
Position first brush oiliness base treatment agent before laying, re-lays additional enhancement layer after dry;
4) waterproof roll is laid with;Waterproof roll selects reaction bonded type macromolecule wet-laying waterproof roll, straight using pre-laid method
Empty paving is connect, after reserving overlap joint size according to the width of selected waterproof roll, carries out waterproof roll laying by reference line;When laying,
The overlapping the slot of adjacent 2 width waterproof roll is staggered, and the length that is staggered is not less than 1500mm;Overlapping the slot is closely knit using overlap joint Self-adhesive;
Waterproof roll when being laid with downward, up, first scratched at the edge of surface isolation film by lap width cross-laminated film surface by bonding,
The isolation film of adjacent 2 width waterproof roll overlap edge is torn again, overlap edge uses cold bonding knot;
5) waterproof roll receives waterproof sealing at head node;Upper pressing is fixed after waterproof roll is laid with to brick fetal membrane top, post-cast strip position
It sets waterproof roll and reserves enough laps of splice, upper cover plank sheathing is protected;
6) it finished product protection and inspects for acceptance;Waterproof roll carries out finished product protection after the completion of being laid with, and prevents sharp objects shock from stabbing
Waterproof layer, if you need to weld job, then weld waterproof roll surface sets interim safeguard measure;Coiled material is prevented to be laid with qualified on inspection
Afterwards, the isolation film on waterproof roll surface is torn before binding baseplate reinforcing bar, and spread plain cement powder waterproof roll surface is thin;
The positioning of placing of reinforcement unwrapping wire, which uses, when reinforced concrete construction, under bottom plate spreads lime or logical line is drawn to be applied as control line
Work, after the completion of lower placing of reinforcement construction, brush paint or the logical line of drawing are as control line on reinforcing bar;Reinforcing bar hangs a little to set temporarily to protect and arrange
It applies;When assembling reinforcement, concrete pad is first arranged, concrete pad bottom adds one layer of waterproof roll enhancing;Weld baseplate reinforcing bar
When, interim protection baffle is set in welding operating surface.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910454805.6A CN110258656A (en) | 2019-05-29 | 2019-05-29 | A kind of underground waterproof engineering pre-installed and inverted adhered construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910454805.6A CN110258656A (en) | 2019-05-29 | 2019-05-29 | A kind of underground waterproof engineering pre-installed and inverted adhered construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110258656A true CN110258656A (en) | 2019-09-20 |
Family
ID=67915751
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910454805.6A Pending CN110258656A (en) | 2019-05-29 | 2019-05-29 | A kind of underground waterproof engineering pre-installed and inverted adhered construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110258656A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111173045A (en) * | 2019-12-31 | 2020-05-19 | 上海东方雨虹防水技术有限责任公司 | Construction method for pre-paving and reversely adhering TPO (thermoplastic polyolefin) waterproof coiled material of basement bottom plate |
CN112922030A (en) * | 2021-03-24 | 2021-06-08 | 江苏凯伦建材股份有限公司 | Construction method for pre-laying waterproof coiled material overlap edge on bottom plate and bottom plate side mold supporting structure |
CN113653103A (en) * | 2021-07-30 | 2021-11-16 | 北京市第五建筑工程集团有限公司 | Construction method for polymer pre-laid anti-sticking waterproof coiled material |
-
2019
- 2019-05-29 CN CN201910454805.6A patent/CN110258656A/en active Pending
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111173045A (en) * | 2019-12-31 | 2020-05-19 | 上海东方雨虹防水技术有限责任公司 | Construction method for pre-paving and reversely adhering TPO (thermoplastic polyolefin) waterproof coiled material of basement bottom plate |
CN112922030A (en) * | 2021-03-24 | 2021-06-08 | 江苏凯伦建材股份有限公司 | Construction method for pre-laying waterproof coiled material overlap edge on bottom plate and bottom plate side mold supporting structure |
CN113653103A (en) * | 2021-07-30 | 2021-11-16 | 北京市第五建筑工程集团有限公司 | Construction method for polymer pre-laid anti-sticking waterproof coiled material |
CN113653103B (en) * | 2021-07-30 | 2023-01-20 | 北京市第五建筑工程集团有限公司 | Construction method for polymer pre-laid anti-sticking waterproof coiled material |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101914927B (en) | Waterproof system for basement bottom board and wall surface and construction method thereof | |
CN106120873B (en) | A kind of construction method of pile-raft foundation pre-installed and inverted adhered composite high-molecular waterproof roll | |
CN110258656A (en) | A kind of underground waterproof engineering pre-installed and inverted adhered construction method | |
CN107190844B (en) | The waterproof and water drainage system and construction method of a kind of basement bottom board and exterior wall | |
CN106988440B (en) | Waterproof structure for main body and auxiliary interface of subway station and construction method of waterproof structure | |
CN108708453A (en) | Basementwaterproofing construction method | |
CN107190783A (en) | A kind of construction method of basement waterproofing structure and its outer wall of basement waterproof construction | |
CN211037072U (en) | Piping lane bottom plate waterproof construction | |
CN106801517A (en) | A kind of schoolhouse surface consolidation of Prefabricated porous plate brick mixed structure strengthens method | |
CN107059946A (en) | A kind of basement drain plate and its construction | |
CN102852290A (en) | Roof parapet flashing place structure and construction method thereof | |
CN213952303U (en) | Basement outer wall post-cast strip assembled protection wall construction structures | |
CN201695411U (en) | Waterproof system of bottom board and wall surface of basement | |
CN107165290A (en) | Basement bottom board prespreading Macromolecular self-adhesive membrane waterproof roll non-bituminous base construction | |
CN105862928A (en) | Post-cast strip outer wall in-advance water stopping treatment structure and construction process thereof | |
CN105887923A (en) | Construction method for pre-paving and invertedly adhering waterproof coiled material in large underground waterproof project | |
CN105239729B (en) | It has constructed the construction method of poling reparation of punching after roofing | |
CN109629845A (en) | Concrete structure seam areas leakage treatment device and its construction method | |
CN102912945B (en) | Roof compound seepage-proofing steam exhausting hole detail treatment technology | |
CN105401962B (en) | The hermetically sealed waterproof construction method of side wall, engineering top surface | |
CN106759955A (en) | The construction method of waterproof system is laid in a kind of toilet and toilet with waterproof system | |
CN110067311A (en) | The connection structure and method of new-old concrete component junction | |
CN107587887A (en) | A kind of construction joint structure and its waterproof construction method | |
CN209722876U (en) | A kind of structure of interior canal storing facilities of water waterproof layer | |
CN207998873U (en) | Basement bottom plate rear pouring tape structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20190920 |
|
WD01 | Invention patent application deemed withdrawn after publication |