CN110255376A - A method of replacement metallurgical bridge crane wirerope - Google Patents

A method of replacement metallurgical bridge crane wirerope Download PDF

Info

Publication number
CN110255376A
CN110255376A CN201910457338.2A CN201910457338A CN110255376A CN 110255376 A CN110255376 A CN 110255376A CN 201910457338 A CN201910457338 A CN 201910457338A CN 110255376 A CN110255376 A CN 110255376A
Authority
CN
China
Prior art keywords
wirerope
rope
new
wire rope
old wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910457338.2A
Other languages
Chinese (zh)
Other versions
CN110255376B (en
Inventor
孙荣学
安世敏
刘福东
王永斌
郭全真
岳勇臣
司贵卯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Handan Iron and Steel Group Co Ltd
HBIS Co Ltd Handan Branch
Original Assignee
Handan Iron and Steel Group Co Ltd
HBIS Co Ltd Handan Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Handan Iron and Steel Group Co Ltd, HBIS Co Ltd Handan Branch filed Critical Handan Iron and Steel Group Co Ltd
Priority to CN201910457338.2A priority Critical patent/CN110255376B/en
Publication of CN110255376A publication Critical patent/CN110255376A/en
Application granted granted Critical
Publication of CN110255376B publication Critical patent/CN110255376B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A method of replacement metallurgical bridge crane wirerope belongs to lifting equipment maintaining method technical field, is used for quick-replaceable metallurgical bridge crane wirerope.Its technical solution is: new wirerope cheese being transported to overhead traveling crane in the following, the old wire rope of four wedge joints is successively cut off, while rope clamp being dismantled, the drift of wedge joint is removed;The rope end of new old wire rope is connected;Lifting mechanism is started, new rope is driven with old wire rope, old wire rope is rolled on reel, it is temporarily fixed on new wire rope roll to reel;Then it drives the rope end of old wire rope to drop down onto ground, old wire rope rope end is connect with the new wirerope other end, new rope hoisting to equalizer bar is installed to wedge joint;Old rope wirerope is all put to ground, and four new wirerope are fixed on reel.The present invention can reduce the place occupied in replacement process, be effectively prevented from discounting, the buckling phenomenon of wirerope, shorten replacing construction, mitigate the labor intensity of worker.

Description

A method of replacement metallurgical bridge crane wirerope
Technical field
The present invention relates to a kind of methods for replacing metallurgical bridge crane wirerope, belong to lifting equipment maintaining method Technical field.
Background technique
In iron and steel enterprise, metallurgical bridge crane carries the transport of molten iron and molten steel, and work frequent and environment Temperature is high.Metallurgy uses two-fold cylinder, double flat balance beam and four wirerope, process of the wirerope in handling molten steel with bridge crane In play an important role.Since wirerope is three big important components (brake, wirerope and suspension hook) of overhead traveling crane safety in production One of, using frequent, wear more, it is therefore desirable to often be replaced, to guarantee to keep the safety in production, avoid the generation of accident.
Currently, there is the following aspects in metallurgical bridge crane more change steel rope:
First, metallurgical bridge crane shares four, wirerope, and the length of every wirerope is about 300 meters.Changing rope every time Before new rope is put well need in advance, four 300 meters of steel wire rope releasing is the very big work of workload, need a large amount of manpower, It is also required to occupy very big place.
Second, the connection of new old wire rope is problematic, in the past by new and old rope end directly with welding together, in raising Connecting portion is harder in the process, the bending of wirerope easily occurs, turns round strength phenomenon.
One end of third, the installation of wedge joint, the rope end of four wirerope is fixed with wedge joint, in the past connects wedge shape Head, which unloads, places ground, is successively pulled with 5 tons of guide chains and accomplishes fluently connector, time-consuming and laborious.
Problem existing for metallurgical bridge crane more change steel rope is efficiently solved at present, to production Detrimental effect is gone on smoothly, it would be highly desirable to be improved.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of methods for replacing metallurgical bridge crane wirerope.It is this Method can reduce the place that wirerope occupies in replacement process, and the discounting, bending after being effectively prevented from wirerope connection are existing As shortening replacing construction, mitigating the labor intensity of worker.
The technical solution for solving above-mentioned technical problem is:
A method of replacement metallurgical bridge crane wirerope, it is carried out using following steps:
A. new wirerope is placed on rope support, four rope supports for placing new wirerope are placed individually into below overhead traveling crane;
B. suspension hook is fallen, it is it is steady, be securely placed on ground, make pulley vertically upward;
C. the old wire rope lower end respectively by two wedge joints connection on two equalizer bars is successively cut off, and reserves rope end, together When overhead traveling crane main carriage on staff connector rope clamp is dismantled, the drift of the wedge joint on aerial equalizer bar is removed;
D. with the rope end of the new old wire rope of nut-welding, the nut of new old wire rope is connected by rope clamp;
E. lifting mechanism is started, new wirerope is driven with old wire rope, old wire rope is rolled on reel, when new wire rope roll arrives Reel 3 stops when enclosing, and unclamps rope clamp, new wirerope is temporarily tied up on the suitable position of trolley, is then driven old wire rope Rope end is dropped down into ground by the hole under equalizer bar;
F. it by rope end that four old wire ropes are fallen and after being fixed respectively with the other end of four new wirerope with rope clamp, then opens Four new wirerope are mounted respectively to wedge when the other end of four new wirerope rises to equalizer bar position by dynamic lifting mechanism In shape connector, each connector rope clamp is successively accomplished fluently, after the rope end of four new wirerope is installed to four wedge joints, then Slow raising is accomplished fluently four wedge joints of equalizer bar using the gravity of wirerope;
G. two reels are rotated further by, four old wire ropes are dropped down into ground respectively, have all been fallen to old wire rope, by old wire rope Pressing plate dismantle, old wire rope all unloads, then successively uses be fixed temporarily four new wirerope on two reels respectively Pressing plate presses, and the both ends of four new wirerope all fix;
H. lifting mechanism is started, reel winds new wirerope, and raising suspension hook, all more change jobs end.
The method of above-mentioned replacement metallurgical bridge crane wirerope, the rope support of the new wirerope of placement in the step a by Bracket and wirerope cheese composition, bracket are welded by channel steel and I-steel, and bracket is fixed on two opposite bearings Seat, rotation axis are mounted between two bearing blocks, and wirerope cheese covers on the rotating shaft, the length of the wirerope of wirerope cheese For the length needed to change.
The method of above-mentioned replacement metallurgical bridge crane wirerope, in the step d, the spiral shell of new old wire rope both ends welding Parent phase pair is each passed through new old wire rope both ends nut using wirerope lantern ring, and the both ends of wirerope lantern ring are connected solid by rope clamp It is fixed.
The beneficial effects of the present invention are:
The present invention places new wirerope using rotatable wirerope cheese, and occupied ground when avoiding new steel wire rope releasing is adopted The time is saved with scale rope, and alleviates the labor intensity of worker;Steel wire is used after the rope end welded nut of new old wire rope Rope sling is connected with rope clamp, is realized new old wire rope and is directly flexible coupling, and the torsion strength in old wire rope will not pass to new wirerope On, it ensure that the use of new wirerope, and avoid and be obstructed when passing through pulley;Wedge joint on equalizer bar penetrates new steel After cord, wedge joint is accomplished fluently using the gravity of wirerope, the time is greatly saved in this way, alleviates labor intensity.
The present invention is to replace initiating for metallurgical bridge crane wirerope method, operatively solves wirerope and is replacing In the process the problem of the discounting after occupied ground, wirerope connection, bending, replacing construction is significantly shortened, rope technique is put and saves 10 people 6 hours, the installation of wedge joint saved 8 people 4 hours, and alleviate the labor intensity of worker.The present invention realizes Metallurgical bridge crane wirerope changes the optimization of rope technique, optimizes the connection type of new and old steel wire rope, extends wirerope Service life.
Detailed description of the invention
Fig. 1 is working state schematic representation of the invention;
Fig. 2 is the structural schematic diagram of rope support;
Fig. 3 is the attachment structure schematic diagram of new old wire rope;
Fig. 4 is the mounting structure schematic diagram of wedge joint.
Mark in figure as follows: reel 1, fixed pulley group 2, equalizer bar 3, old wire rope 4, running block 5, be flexible coupling 6, new steel Cord 7, rope support 8, bracket 9, bearing block 10, rotation axis 11, wirerope cheese 12, nut 13, wirerope lantern ring 14, rope clamp 15, Wedge joint 16, drift 17, steel wire rope bending 18, connector rope clamp 19.
Specific embodiment
The present invention is a kind of method of new replacement metallurgical bridge crane wirerope, in this new more change steel rope Needed in method using place the rope support 8 of new wirerope 7, the new old wire rope of connection is flexible coupling 6, and by new wirerope 7 It is needed when being connect with wedge joint 16 using new method.
Fig. 2 shows that the rope support 8 for placing new wirerope 7 is made of bracket 9 and wirerope cheese 12, and bracket 9 is by channel steel and work Word steel is welded, and bracket 9 is fixed on two opposite bearing blocks 10, rotation axis 11 be mounted on two bearing blocks 10 it Between, 12 sets of wirerope cheese in rotation axis 11.New wirerope 7 is placed using rotatable wirerope cheese 12, is avoided new Occupied ground when wirerope 7 puts rope saves the time using scale rope, and alleviates the labor intensity of worker.
Fig. 3 shows, connecting being flexible coupling for new old wire rope 6 includes nut 13, wirerope lantern ring 14, rope clamp 15.Two spiral shells Mother 13 is respectively welded at new old wire rope both ends, when connection, nut 13 that two are welded on new old wire rope both ends is opposite, makes It is each passed through new old wire rope both ends nut 13 with wirerope lantern ring 14, the both ends of wirerope lantern ring 14 are connected solid by rope clamp 15 It is fixed.This connection structure realizes new old wire rope and is directly flexible coupling, and the torsion strength in old wire rope 4 will not pass to new wirerope On 7, the use of new wirerope 7 ensure that, and avoid and be obstructed when passing through pulley.
Fig. 4 shows that new method when new wirerope 7 is connect with wedge joint 16 is that the wedge joint 16 on equalizer bar 3 is worn Enter new wirerope 7 and accomplished fluently with connector rope clamp 19, drift 17 is filled in the head of steel wire rope bending 18, four new wirerope 7 according to It is secondary after the installation is completed, then slow raising, is accomplished fluently four wedge joints 16 of equalizer bar 3 using the gravity of wirerope.
Fig. 1 shows that the method for replacement metallurgical bridge crane wirerope of the invention, it is carried out using following steps:
I. new wirerope 7 is placed on rope support 8, four rope supports 8 for placing new wirerope 7 are placed individually into below overhead traveling crane;
J. suspension hook is fallen, it is it is steady, be securely placed on ground, make pulley vertically upward;
K. 4 lower end of old wire rope that two wedge joints 16 on two equalizer bars 3 connect successively is cut off respectively, reserves rope Head, while the staff on overhead traveling crane main carriage dismantles connector rope clamp 19, the wedge joint 16 on aerial equalizer bar 3 Drift 17 removes;
The nut 13 of new old wire rope is connected by the rope end that new old wire rope is l. welded with nut 13 by rope clamp 15;
M. lifting mechanism is started, drives new wirerope 7 with old wire rope 4, new wirerope 7 passes through running block 5 and fixed pulley group 2, old wire rope 4 is rolled on reel 1, when new wirerope 7 is rolled onto parking when reel 1 three encloses, release rope clamp 15, new wirerope 7 temporarily tie up on the suitable position of trolley, then drive old wire rope 4 that rope end is dropped down onto ground by the hole under equalizer bar 3;
N. the rope end that four old wire ropes 4 are fallen is fixed with the other end rope clamp 15 respectively with four new wirerope 7 Afterwards, restart lifting mechanism, when the other end of four new wirerope 7 rises to 3 position of equalizer bar, four new wirerope 7 are divided Each connector rope clamp 19 An Zhuan not be successively accomplished fluently, the rope end of four new wirerope 7 is installed to four wedge shapes in wedge joint 16 After connector 16, then slow raising, is accomplished fluently four wedge joints 16 of equalizer bar 3 using the gravity of wirerope;
O. two reels 1 are rotated further by, four old wire ropes 4 are dropped down into ground respectively, have all been fallen to old wire rope 4, by old steel The pressing plate of cord 4 is dismantled, and old wire rope 4 all unloads, then successively rolls up be fixed temporarily four new wirerope 7 at two respectively It is pressed on cylinder 1 with pressing plate, the both ends of four new wirerope 7 all fix;
P. lifting mechanism is started, reel 1 winds new wirerope 7, and raising suspension hook, all more change jobs end.
One embodiment of the present of invention is as follows:
The diameter of new wirerope 7 is 30mm, length 310m;
The height of bracket 9 is 12000mm, width 15000mm;
The model 1510 of bearing block 10;
The diameter of rotation axis 11 is 50mm, length 16000mm;
The diameter of wirerope cheese 12 is 10500mm;
The specification of nut 13 is M24 nut;
Wirerope lantern ring 14 is 8 wirerope of φ;
Rope clamp 15 is 30mm wire cable clamp.

Claims (3)

1. a kind of method for replacing metallurgical bridge crane wirerope, it is characterised in that: it is carried out using following steps:
A. new wirerope (7) is placed on rope support (8), four rope supports (8) for placing new wirerope (7) are placed individually into overhead traveling crane Below;
B. suspension hook is fallen, it is it is steady, be securely placed on ground, make pulley vertically upward;
C. old wire rope (4) lower end respectively by two wedge joints (16) connection on two equalizer bars (3) is successively cut off, and is stayed Rope end out, while the staff on overhead traveling crane main carriage dismantles connector rope clamp (19), the wedge shape on aerial equalizer bar (3) The drift (17) of connector (16) removes;
The nut (13) of new old wire rope is connected by the rope end that new old wire rope is d. welded with nut (13) by rope clamp (15) It connects;
E. lifting mechanism is started, new wirerope (7) is driven with old wire rope (4), old wire rope (4) is rolled on reel (1), when New wirerope (7) is rolled onto when reel (1) 3 encloses and stops, and unclamps rope clamp (15), it is suitable in trolley that new wirerope (7) is temporarily tied up On position, then drive old wire rope (4) that rope end is dropped down onto ground by the hole under equalizer bar (3);
F. the rope end that four old wire ropes (4) is fallen with consolidated respectively with the other end of four new wirerope (7) with rope clamp (15) After setting, restart lifting mechanism, when the other end of four new wirerope (7) rises to equalizer bar (3) position, by four new steel Cord (7) is mounted respectively in wedge joint (16), successively accomplishes fluently each connector rope clamp (19), the rope of four new wirerope (7) Head installation is to after four wedge joints (16), then slow raising, using the gravity of wirerope by four of equalizer bar (3) Wedge joint (16) is accomplished fluently;
G. two reels (1) are rotated further by, four old wire ropes (4) are dropped down into ground respectively, have all been fallen to old wire rope (4), The pressing plate of old wire rope (4) is dismantled, old wire rope (4) all unloads, then successively by be fixed temporarily four new wirerope (7) It is pressed on two reels (1) with pressing plate respectively, the both ends of four new wirerope (7) all fix;
H. lifting mechanism is started, reel (1) winds new wirerope (7), and raising suspension hook, all more change jobs end.
2. the method for replacement metallurgical bridge crane wirerope according to claim 1, it is characterised in that: the step a In the rope support (8) of the new wirerope of placement (7) be made of bracket (9) and wirerope cheese (12), bracket (9) is by channel steel and I-shaped Steel is welded, and bracket (9) is fixed on two opposite bearing blocks (10), and rotation axis (11) is mounted on two bearing blocks (10) between, wirerope cheese (12) covers on rotation axis (11), the length of the wirerope of wirerope cheese (12) be it is required more The length changed.
3. the method for replacement metallurgical bridge crane wirerope according to claim 1, it is characterised in that: the step d In, the nut (13) of new old wire rope both ends welding relatively, is each passed through new old wire rope both ends using wirerope lantern ring (14) The both ends of nut (13), wirerope lantern ring (14) are connected and fixed by rope clamp (15).
CN201910457338.2A 2019-05-29 2019-05-29 Method for replacing steel wire rope of metallurgical bridge crane Active CN110255376B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910457338.2A CN110255376B (en) 2019-05-29 2019-05-29 Method for replacing steel wire rope of metallurgical bridge crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910457338.2A CN110255376B (en) 2019-05-29 2019-05-29 Method for replacing steel wire rope of metallurgical bridge crane

Publications (2)

Publication Number Publication Date
CN110255376A true CN110255376A (en) 2019-09-20
CN110255376B CN110255376B (en) 2021-05-28

Family

ID=67915882

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910457338.2A Active CN110255376B (en) 2019-05-29 2019-05-29 Method for replacing steel wire rope of metallurgical bridge crane

Country Status (1)

Country Link
CN (1) CN110255376B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111960184A (en) * 2020-08-18 2020-11-20 马鞍山钢铁股份有限公司 Replacement structure and replacement method for single steel wire rope of metallurgical crane
CN112010216A (en) * 2020-10-10 2020-12-01 山东莱钢永锋钢铁有限公司 Method for replacing steel wire rope of large-tonnage metallurgical casting crane
CN112357777A (en) * 2020-11-10 2021-02-12 鞍钢股份有限公司 Method for quickly replacing steel rope of hook beam of gantry crane
CN112794168A (en) * 2019-11-14 2021-05-14 上海梅山钢铁股份有限公司 Grab bucket steel wire rope replacing device for bridge type grab bucket ship unloader

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102009917A (en) * 2010-10-26 2011-04-13 北京首钢建设集团有限公司 Method for replacing steel wire rope and gantry hook of large-scale bridge crane simultaneously
CN103274323A (en) * 2013-06-13 2013-09-04 济钢集团有限公司 Quick replacement method for movable pulley blocks and wire ropes in cranes
CN105800490A (en) * 2016-06-06 2016-07-27 山东钢铁股份有限公司 Method for replacing crane main hook steel wire rope
CN105905806A (en) * 2016-06-20 2016-08-31 甘肃酒钢集团宏兴钢铁股份有限公司 Changing device for steel wire rope of metallurgy overhead crane, manufacturing method and utilization method
CN108190742A (en) * 2017-12-31 2018-06-22 新疆八钢铁股份有限公司 A kind of operating method for replacing lifting equipment steel wire rope
CN109553012A (en) * 2017-09-27 2019-04-02 宝山钢铁股份有限公司 A kind of replacing options of crane rope

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102009917A (en) * 2010-10-26 2011-04-13 北京首钢建设集团有限公司 Method for replacing steel wire rope and gantry hook of large-scale bridge crane simultaneously
CN103274323A (en) * 2013-06-13 2013-09-04 济钢集团有限公司 Quick replacement method for movable pulley blocks and wire ropes in cranes
CN105800490A (en) * 2016-06-06 2016-07-27 山东钢铁股份有限公司 Method for replacing crane main hook steel wire rope
CN105905806A (en) * 2016-06-20 2016-08-31 甘肃酒钢集团宏兴钢铁股份有限公司 Changing device for steel wire rope of metallurgy overhead crane, manufacturing method and utilization method
CN109553012A (en) * 2017-09-27 2019-04-02 宝山钢铁股份有限公司 A kind of replacing options of crane rope
CN108190742A (en) * 2017-12-31 2018-06-22 新疆八钢铁股份有限公司 A kind of operating method for replacing lifting equipment steel wire rope

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112794168A (en) * 2019-11-14 2021-05-14 上海梅山钢铁股份有限公司 Grab bucket steel wire rope replacing device for bridge type grab bucket ship unloader
CN111960184A (en) * 2020-08-18 2020-11-20 马鞍山钢铁股份有限公司 Replacement structure and replacement method for single steel wire rope of metallurgical crane
CN111960184B (en) * 2020-08-18 2022-04-05 马鞍山钢铁股份有限公司 Replacement structure and replacement method for single steel wire rope of metallurgical crane
CN112010216A (en) * 2020-10-10 2020-12-01 山东莱钢永锋钢铁有限公司 Method for replacing steel wire rope of large-tonnage metallurgical casting crane
CN112357777A (en) * 2020-11-10 2021-02-12 鞍钢股份有限公司 Method for quickly replacing steel rope of hook beam of gantry crane

Also Published As

Publication number Publication date
CN110255376B (en) 2021-05-28

Similar Documents

Publication Publication Date Title
CN110255376A (en) A method of replacement metallurgical bridge crane wirerope
CN101122114A (en) Back-cable-free cable-stayed bridge steel tower vertical turn construction method
CN100519396C (en) Gin pole integrated dismounting method for tower crane
CN102071644A (en) Lifting installation method of integral bridge arch rib
CN111042540A (en) Construction method for aerial butt joint of ground suspension cables of super-large-span prestressed pipe truss
CN105905806B (en) Metallurgical crown block steel rope replacing device and production method and application method
CN106044574B (en) The synchronous method for changing ladle carne gantry beam and steel wire rope
CN201999622U (en) Hoisting device for working roller or intermediate roller
CN105460817A (en) Steel wire rope winding device
CN210714046U (en) Device for lifting inverted chimney steel inner cylinder by using steel twisted rope hydraulic pressure
CN110409803B (en) Hoisting method for disassembling central drum ring of hydraulic mold lifting device
CN109622932B (en) Method for quickly replacing rotary bearing of large continuous casting ladle turret
CN106698223A (en) Replacing method of travelling crane main hook steel wire rope
CN102060231A (en) Hoisting method and device for work roller or middle roller
CN205802798U (en) Metallurgical crown block steel rope replacing device
CN203319620U (en) Portable jack
CN208869140U (en) A kind of wheel hub structure for mine hoist head sheave
CN205056647U (en) A roll -changing device for cold rolling production line
CN205129795U (en) Change frock of mixed iron blast base and roll table
CN108792908B (en) Device for mechanically recycling flat and round tail ropes
CN102030271B (en) Lifting device with fixed pulley set dismantling and landing automatically and self-dismantling method
CN203922604U (en) Subway lay a railway track gantry crane dismounting and transportation rotary lifter
CN214989771U (en) Device is changed to overhead traveling crane steel cable
CN110255361B (en) Double-sliding lifting device for water-cooled wall of boiler and application method of double-sliding lifting device
CN112027944B (en) Lifting steel wire rope reel assembly of four-connecting-rod portal crane and replacement process

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant