CN110242372A - A kind of steam turbine building arragement construction suitable for garbage burning factory - Google Patents

A kind of steam turbine building arragement construction suitable for garbage burning factory Download PDF

Info

Publication number
CN110242372A
CN110242372A CN201811650974.9A CN201811650974A CN110242372A CN 110242372 A CN110242372 A CN 110242372A CN 201811650974 A CN201811650974 A CN 201811650974A CN 110242372 A CN110242372 A CN 110242372A
Authority
CN
China
Prior art keywords
steam turbine
meters
building
turbine building
arragement construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811650974.9A
Other languages
Chinese (zh)
Inventor
龙吉生
岳兴月
何秋德
洪勇
钱达蔚
陈圆
李英
王玮
钱锦纶
刘道杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai SUS Environment Co Ltd
Original Assignee
Shanghai SUS Environment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai SUS Environment Co Ltd filed Critical Shanghai SUS Environment Co Ltd
Priority to CN201811650974.9A priority Critical patent/CN110242372A/en
Publication of CN110242372A publication Critical patent/CN110242372A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01KSTEAM ENGINE PLANTS; STEAM ACCUMULATORS; ENGINE PLANTS NOT OTHERWISE PROVIDED FOR; ENGINES USING SPECIAL WORKING FLUIDS OR CYCLES
    • F01K13/00General layout or general methods of operation of complete plants

Abstract

The present invention discloses a kind of steam turbine building arragement construction suitable for burning power plant, present invention innovation uses reactionary style axial exhaust turbine, make longitudinal correct, the single layer arrangement of the steam turbine in workshop, Steam Turbine center absolute altitude is installed on 2.8 meters of layers, and 0.6 meter of foundation elevation, no 4.5 meters of layers operate layer, no steam turbine is hung, generator amature maintenance can be evacuated to outdoor, and economical material can be used in steam turbine building alien invasion, and steam turbine building top layer top may be designed to visit leisure place.

Description

A kind of steam turbine building arragement construction suitable for garbage burning factory
Technical field
The present invention relates to municipal solid wastes incineration power generation fields, are the unconventional arragement construction of steamer computer room, Ci Zhongbu Main building cost and its up-front investment can be reduced by setting, while greatly improve the plant thermal efficiency of garbage burning factory.
Background technique
Turbo-generator Set is the important equipment in garbage burning factory, and conventional steam turbine is lower steam discharge arrangement, and equipment is put It is placed on 8 meters of operating layers, condenser is placed on the downside of turbine discharge mouth, since steam discharge will be by can just drain into after a corner Condenser, this considerably increases the losses of the steam discharge of steam turbine, reduce the efficiency of steam turbine;Since operating layer is higher, lubricating oil The arrangement stood is also relatively high, and centre, which must be provided with 4.5 meters of layer platforms just, can rise to 8 meters of layers, so conventional power plant steam turbine building is equal Using rebuilding, which substantially increases the investment costs of civil engineering structure, can solve using reactionary style axial exhaust turbine This problem, while reactionary style axial exhaust turbine can also be improved the efficiency of steam turbine.
The height of turbine efficiency directly affects generated energy, so the efficiency for improving steam turbine is to improve plant thermal efficiency Important way, while the more raising steam turbine energy-saving and environment-friendly, garbage burning factory uses at present can also be played the role of The mode of efficiency has following several: (1) slow-speed of revolution reaction turbine;(2) high revolving speed impulse turbine.(3) high revolving speed is anti- Dynamic formula steam turbine;(4) high and low rotating speed impulsion, reaction combination turbine.The above several ways are the forms using lower steam discharge, It also there is no the Engineering Projects of axial exhaust.
Summary of the invention
Mesh of the invention it is: (1) reduces the height of main building, saves infrastructure cost;(2) steam turbine is improved Efficiency improves economy of power plant benefit;(3) it saves equipment investment cost, save equipment operation maintenance cost.
The specific technical solution of the present invention is: a kind of steam turbine building arragement construction suitable for garbage burning factory, and steam turbine is vertical To correct, single layer arrangement, 38 meters of single steam turbine longitudinal size, 2 steam turbine total lengths are 72.2 meters;14 meters of lateral dimension, vapour Wheel unit centre absolute altitude is installed on 2.8 meters of layers, and directly from 0 meter of basis installation, steam turbine building top layer absolute altitude is by 8.5 meters of designs.
Further, the maintenance door that setting truck crane in steam turbine building two sides passes in and out, centre setting access path, facilitates truck crane Enter in steam turbine building at any time, the maintenance and maintenance of turbine generator machine equipment rotor and components are directly carried out in 0 meter of layer, are no longer needed to In addition a set of steam turbine is individually arranged to hang.
Further, the rotor of steam turbine generator is directly drawn to vapour by the reserved gate of power generation drive end unit out of workshop It is overhauled on the outside of computer room, without additional reserved pumping rotor space, which reduces the span of steam turbine building and entire areas.
Further, lube plant is directly arranged at zero meter of layer, cancels the 4.5 meters of layer platforms routinely arranged.
Color steel plate or other economic and reliables may be selected without bearing equipment, building and alien invasion in steam turbine building single layer arrangement, roof Material.
The income effect that the present invention innovates includes: the height that (1) reduces main building, with saving the mesh of construction cost.It is conventional Workshop and innovation workshop size comparison are as follows:
Serial number Title The double-deck main building (M) Single layer main building (M)
1 Operate layer height 8.5 0.6
2 Roof absolute altitude 21 8.5
3 2 machine steam turbine building overall lengths 65.6 72.2
4 Overall width 24.8 22.3
(2) Steam Turbine whole efficiency about 7% (30MW unit) is improved, increases economy of power plant benefit.(3) it is not provided with steam turbine It hangs, saves equipment investment early period and the operation maintenance cost in later period, save overhaul life cost.(4) it is easily installed, improves construction Speed reduces the construction period.
Detailed description of the invention
Fig. 1 is floor plan of the present invention.
Fig. 2 is section layout drawing of the invention.
In figure: 1, steam turbine 2, condenser 3, generator 4, condensate pump 5, vacuum pump 6, feed pump 7, low-pressure heater; 8, gear-box;9, water tank.
Specific embodiment
In conjunction with shown in attached drawing 1 and Fig. 2: steam turbine 1 is longitudinally arranged, and condensate pump 4 is arranged in the solidifying pump hole of 2 front side of condenser In, absolute altitude is at -2 meters, and pump hole top can use checker plate or flase floor be covered, that is, the problem of cavitation for solving solidifying pump is again beautiful It sees.
Solidifying pump left side is condenser 2, and condenser 2 is directly connected to steam turbine 1, generator 3, gear-box 8, and equipment can be whole Body fortune causes in-site installation, is used uniformly common backplane, entire bottom block is in an independent concrete foundation, and foundation elevation is only It is 0.6 meter.
Since the foundation elevation and center absolute altitude of steam turbine 1 are all preferably minimized place, so to the lubrication of 1 bearing of steam turbine Petrol station, can be in steam turbine side arrangement without high level is put into.
Vacuum pump 5, feed pump 6 and drain tank 9 are placed on zero meter of deaerator bay A-B axis, mutual with Turbo-generator Set 3 It answers.4.5 meters of layers of A-B axis are designed to cable and pipe sandwich as conventional model burning power plant, use for pipe arrangement.A- 8.5 meters of layers of B axle are designed to that visit corridor, left side can be designed to that windowpane visits waste incineration line, and right side is designed to glass door And windowpane, 8.5 meters of layer roofs of steam turbine building can be led to.The roof layouts of steam turbine building can place several sets at leisure place Sunshade and the sports centers such as tables and chairs or shuttlecock, table tennis, can also be designed to green belt kind plant and gourd, fruit and vegetable Deng.14 meters of layers of A-B axis are deaerator bays, place oxygen-eliminating device and associated conduit attachment.

Claims (6)

1. a kind of steam turbine building arragement construction suitable for garbage burning factory, which is characterized in that the longitudinal correct, single layer cloth of steam turbine It sets, 38 meters of single steam turbine longitudinal size, 2 steam turbine total lengths are 72.2 meters;14 meters of lateral dimension, Steam Turbine center absolute altitude 2.8 meters of layers are installed on, directly from 0 meter of basis installation, steam turbine building top layer absolute altitude is by 8.5 meters of designs.
2. a kind of steam turbine building arragement construction suitable for garbage burning factory according to claim 1, which is characterized in that steam turbine The maintenance door that truck crane passes in and out, the access path that centre setting facilitates truck crane to enter in steam turbine building at any time, vapour is arranged in room two sides The maintenance and maintenance of turbine generator equipment rotor and components are directly carried out in 0 meter of layer.
3. a kind of steam turbine building arragement construction suitable for garbage burning factory according to claim 1, which is characterized in that steamer The rotor of generator is directly drawn on the outside of steam turbine building out of workshop by the reserved gate of power generation drive end unit and is overhauled.
4. a kind of steam turbine building arragement construction suitable for garbage burning factory according to claim 1, which is characterized in that lubrication Oily device is directly arranged at zero meter of layer, cancels the 4.5 meters of layer platforms routinely arranged.
5. a kind of steam turbine building arragement construction suitable for garbage burning factory according to claim 1, which is characterized in that steam turbine Room single layer arrangement, roof is without bearing equipment.
6. a kind of steam turbine building arragement construction suitable for garbage burning factory according to claim 1, which is characterized in that steamer Machine uses axial exhaust turbine.
CN201811650974.9A 2018-12-31 2018-12-31 A kind of steam turbine building arragement construction suitable for garbage burning factory Pending CN110242372A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811650974.9A CN110242372A (en) 2018-12-31 2018-12-31 A kind of steam turbine building arragement construction suitable for garbage burning factory

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811650974.9A CN110242372A (en) 2018-12-31 2018-12-31 A kind of steam turbine building arragement construction suitable for garbage burning factory

Publications (1)

Publication Number Publication Date
CN110242372A true CN110242372A (en) 2019-09-17

Family

ID=67882443

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811650974.9A Pending CN110242372A (en) 2018-12-31 2018-12-31 A kind of steam turbine building arragement construction suitable for garbage burning factory

Country Status (1)

Country Link
CN (1) CN110242372A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2943961A1 (en) * 1979-10-31 1981-05-07 Aka Aufbereitung Konstruktion Large scale coal dressing plant - is laid out on single level in building with regular symmetrical floor area
CN200993111Y (en) * 2006-12-27 2007-12-19 沈阳鼓风机(集团)有限公司 Integral assembling unit for single-shaft multi-stage centrifugal compressor
CN202970804U (en) * 2012-11-08 2013-06-05 中信重工机械股份有限公司 Single layer layout turbine system
CN203613834U (en) * 2013-12-19 2014-05-28 国电建投内蒙古能源有限公司 Compact four-column type arrangement structure of ultra supercritical air cooling unit main power house
CN105155880A (en) * 2014-12-29 2015-12-16 浙江省电力设计院 One-supporting-one multi-axis combined cycle thermal generator set combined workshop low-position arrangement structure
WO2016181029A1 (en) * 2015-05-13 2016-11-17 Outotec (Finland) Oy A flotation plant and its uses and methods of maintenance of a flotation plant
CN207892670U (en) * 2018-01-03 2018-09-21 杭州汽轮机股份有限公司 50MW grade axial exhaust condensing-type industrial steam turbines

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2943961A1 (en) * 1979-10-31 1981-05-07 Aka Aufbereitung Konstruktion Large scale coal dressing plant - is laid out on single level in building with regular symmetrical floor area
CN200993111Y (en) * 2006-12-27 2007-12-19 沈阳鼓风机(集团)有限公司 Integral assembling unit for single-shaft multi-stage centrifugal compressor
CN202970804U (en) * 2012-11-08 2013-06-05 中信重工机械股份有限公司 Single layer layout turbine system
CN203613834U (en) * 2013-12-19 2014-05-28 国电建投内蒙古能源有限公司 Compact four-column type arrangement structure of ultra supercritical air cooling unit main power house
CN105155880A (en) * 2014-12-29 2015-12-16 浙江省电力设计院 One-supporting-one multi-axis combined cycle thermal generator set combined workshop low-position arrangement structure
WO2016181029A1 (en) * 2015-05-13 2016-11-17 Outotec (Finland) Oy A flotation plant and its uses and methods of maintenance of a flotation plant
CN207892670U (en) * 2018-01-03 2018-09-21 杭州汽轮机股份有限公司 50MW grade axial exhaust condensing-type industrial steam turbines

Similar Documents

Publication Publication Date Title
CN102352696B (en) Lateral structure and arranging method of steam turbine generator unit of 1000MW-grade set in thermal power plant
CN212029822U (en) Underground garage exhaust fume exhaust system
CN204435946U (en) A kind of coal-fired 1,000,000 unit turbine house structures
CN105155880A (en) One-supporting-one multi-axis combined cycle thermal generator set combined workshop low-position arrangement structure
CN105019695A (en) High-position arrangement method and structure of combined main power house of split-shaft gas-steam combined-cycle power plant
CN110242372A (en) A kind of steam turbine building arragement construction suitable for garbage burning factory
JP3898847B2 (en) Thermal power plant
CN203613834U (en) Compact four-column type arrangement structure of ultra supercritical air cooling unit main power house
CN202100032U (en) Direct air-cooling steam turbine generator set system
CN202139876U (en) Transverse structure of 1000MW stage set turbo generator set of thermal power plant
CN205077914U (en) Split axle gas - steam combined -cycle power plant unites high -order arrangement structure of main building
CN207485050U (en) A kind of large-size thermal power plant main building arrangement structure
CN206319988U (en) A kind of various dimensions float-type Wave power generation device
CN203684747U (en) Arrangement structure of circulating water pump house of gas turbine power plant
CN207620450U (en) A kind of double-deck covering semi-underground type sewage plant arrangement
CN201025222Y (en) Push force bearing cooling structure for vertical water wheel generation unit
CN104763178A (en) Main power building of thermal power plant
CN206600027U (en) Split axle Combined cycle gas-steam turbine unit low level combines main building arrangement structure
CN209483444U (en) A kind of steam turbine building based on coal base distributing-supplying-energy system
CN106523048A (en) Main building arrangement structure of gas-steam combined cycle power generation plant
CN105890434A (en) Power plant circulating water cooling system and cooling method and application
CN218843232U (en) Land-saving sludge incineration plant water supply system arrangement structure
CN206376906U (en) Gas combustion-gas vapor combined cycle factory owner's plant layout structure
CN219509317U (en) Factory building high-order arrangement structure of single-shaft gas steam combined cycle generator set
CN110630056A (en) Compact three-row steam turbine room structure of 660MW coal-fired generator set

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190917

WD01 Invention patent application deemed withdrawn after publication