CN110206561A - Disease in Tunnel Base point processing method - Google Patents

Disease in Tunnel Base point processing method Download PDF

Info

Publication number
CN110206561A
CN110206561A CN201910461156.2A CN201910461156A CN110206561A CN 110206561 A CN110206561 A CN 110206561A CN 201910461156 A CN201910461156 A CN 201910461156A CN 110206561 A CN110206561 A CN 110206561A
Authority
CN
China
Prior art keywords
disease
injected hole
point
stratum
tunnel base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910461156.2A
Other languages
Chinese (zh)
Inventor
李军
田劲松
高永强
徐剑宇
高贝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenshuo Railway Branch of China Shenhua Energy Co Ltd
Original Assignee
Shenshuo Railway Branch of China Shenhua Energy Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenshuo Railway Branch of China Shenhua Energy Co Ltd filed Critical Shenshuo Railway Branch of China Shenhua Energy Co Ltd
Priority to CN201910461156.2A priority Critical patent/CN110206561A/en
Publication of CN110206561A publication Critical patent/CN110206561A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The present invention relates to a kind of Disease in Tunnel Base point processing methods comprising following steps: determining the disease point position of Tunnel Base;Injected hole is drilled to the stratum of the disease point, is connected to the injected hole with the area of coming to nothing below the stratum of the disease point;Slurries are filled into the area of coming to nothing below the stratum of the disease point by the injected hole using grouting equipment;When slurries are overflowed out of described injected hole, the grouting equipment is withdrawn, and closure processing is carried out to the aperture of the injected hole.Present treatment scheme can effectively fill the area of coming to nothing of disease point, while block to injected hole, realize and thoroughly eliminate problem of rising soil inside and outside, and its treatment process is simple, the construction equipment used is few, thus construction cost is low, good economy performance.

Description

Disease in Tunnel Base point processing method
Technical field
The present invention relates to Tunnel Base Strengthening Technology fields, more particularly to a kind of Disease in Tunnel Base point processing method.
Background technique
With being widely applied for railway construction in China, the various risks and disease met during construction are also cured Add protrusion.Such as be filled in operation to Tunnel Base, can exist between the concrete and inverted arch of tunnel bottom and be engaged not There is crack enough, this underground water for directly resulting in tunnel bottom is mingled with solidifying soil and constantly gushes out from crack, this, which is risen soil, asks Topic can seriously delay tunnel normal construction progress, while endanger the personal safety of construction personnel.
There are some processing methods and preventing mean for administering problem of rising soil on the market in problem in view of this.But Preventing mean can only play palliative effect, can not fundamentally solve the problems, such as to rise soil;And the place generallyd use Reason method, then mostly treatment process is complicated, needs it is high to cause processing cost, and be difficult to protect using a large amount of all kinds of ancillary equipments Good treatment effect is demonstrate,proved, the problem of rising soil secondary recurrence is caused.
Summary of the invention
Based on this, it is necessary to provide a kind of Disease in Tunnel Base point processing method, can be carried out to the area of coming to nothing of disease point Effectively filling, while injected hole is blocked, it realizes and thoroughly eliminates problem of rising soil inside and outside, and the letter of its treatment process It is single, it is at low cost.
Its technical solution is as follows:
A kind of Disease in Tunnel Base point processing method comprising following steps:
Determine the disease point position of Tunnel Base;
Injected hole is drilled to the stratum of the disease point, makes the injected hole and coming to nothing below the stratum of the disease point Area's connection;
Slurries are filled into the area of coming to nothing below the stratum of the disease point by the injected hole using grouting equipment;
When slurries are overflowed out of described injected hole, the grouting equipment is withdrawn, and carry out to the aperture of the injected hole Closure processing.
Using the above method reply Tunnel Base existing for rise soil problem when, it is necessary first to determine the disease of Tunnel Base Evil point position, i.e. locking construction target area;Injected hole is drilled on the stratum of disease point later, makes the injected hole and disease point Stratum below come to nothing area connection, with formed slip casting filling necessary condition;And then, using grouting equipment into injected hole Slurries are injected, slurries is enable gradually to fill area of coming to nothing, the area that can so make to come to nothing tamps to form good Tunnel Base again Structure, and can prevent internal underground water from continuing punching area of coming to nothing after grout cures and gush out;Later, to slurries from the injected hole After inside starting spilling, grouting equipment is withdrawn, and closure processing is carried out to the aperture of injected hole, to prevent the water in external environment Body invades in Tunnel Base.In conclusion present treatment scheme can effectively fill the area of coming to nothing of disease point, while to note It starches hole to block, realizes and thoroughly eliminate problem of rising soil inside and outside, and its treatment process is simple, the construction equipment used It is few, thus construction cost is low, good economy performance.
The technical solution of the application is further described below:
It further include step in one of the embodiments, before the step of stratum to the disease point drills injected hole It is rapid: to remove the confining bed of the surface of stratum of the disease point.
Injected hole is drilled on the stratum to the disease point in one of the embodiments, and removes the disease point After the confining bed of surface of stratum, further comprises the steps of: and excavate at least one sewage ditch in the surrounding formation of the disease point, and It is connected to the sewage ditch with the injected hole.
At least one sewage ditch is excavated in the surrounding formation of the disease point in one of the embodiments, and makes institute It states after sewage ditch is connected to the injected hole, further comprises the steps of: the obstacle removed in the sewage ditch.
In one of the embodiments, in the step of stratum to the disease point drills injected hole, further comprise the steps of: Drainage hole is drilled on the stratum of the disease point simultaneously, makes the company, area of coming to nothing below the stratum of the drainage hole and the disease point It is logical.
In one of the embodiments, using grouting equipment by the injected hole to below the stratum of the disease point Area of coming to nothing in fill slurries after, further comprise the steps of: using smash vibration equipment will be in de- below the stratum of the disease point Slurries in dead zone are compacted.
Vibration equipment is smash by coming to nothing in area below the stratum in the disease point in use in one of the embodiments, Slurries it is compacted after, further comprise the steps of: to be inserted into stiffener into slurries before grout cures, make the stiffener It is integrated with slurries condensation.
In one of the embodiments, when slurries are overflowed out of described injected hole, the grouting equipment is withdrawn, and right The aperture of the injected hole carried out in the step of blocking processing, was specially coated using waterproof material in the aperture of the injected hole At least one layer of waterproof membrane.
At least one layer of waterproof membrane is being coated in the aperture of the injected hole using waterproof material in one of the embodiments, Later, it further comprises the steps of: and the waterproof membrane after molding is cut, the area of the waterproof membrane is made to be greater than the injected hole Orifice area.
The aperture of the injected hole is 50mm~75mm in one of the embodiments,;The centerline hole of the injected hole Angle with horizontal plane where the Tunnel Base is 15 °~30 °;Edge of the sewage ditch based on the Tunnel Base is inside The oblique 30 ° of moldings of lateral deviation.
Detailed description of the invention
Fig. 1 is the process flow chart of Disease in Tunnel Base point processing method described in one embodiment of the invention.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention more comprehensible, below in conjunction with attached drawing and specific embodiment party Formula, the present invention is further described in detail.It should be understood that the specific embodiments described herein are only to solve The present invention is released, and the scope of protection of the present invention is not limited.
It should be noted that when element is referred to as " being fixedly arranged on ", " being set to " or " install in " another element, it can be with Directly on the other element or there may also be elements placed in the middle.When an element is considered as " connection " another yuan Part, it can be directly to another element or may be simultaneously present centering elements;One element and another element The concrete mode being fixedly connected can be achieved by the prior art, and details are not described herein, it is preferred to use the fixation side of threaded connection Formula.
Unless otherwise defined, all technical and scientific terms used herein and belong to technical field of the invention The normally understood meaning of technical staff is identical.Term as used herein in the specification of the present invention is intended merely to description tool The purpose of the embodiment of body, it is not intended that in the limitation present invention.Term " and or " used herein includes one or more Any and all combinations of relevant listed item.
Currently, for the traffic tunnel that supply train, the mobile devices such as automobile use, usually to excavate in underground deep layer or Structures inside massif.Tunnel Base is commonly used in construction molding road or is laid with track, to basement strata when due to construction Inside the pressure or basement strata of application underground water wash away or basement strata inside soil layer or rock movement, be likely to Soil layer or the discontinuous exclusion region of rock below stratum are caused, that is, forms area of coming to nothing.Underground water is acted on by stratum internal pressure, meeting It is washed away by coming to nothing area to stratum, final entrainment silt breaks through Tunnel Base stratum and phenomenon of rising soil occurs, to constructing tunnel Huge security risk is caused with normal use.Therefore, the application is precisely in order to the one kind for solving the problems, such as this and proposing is new turns over Slurry emits the processing method of mud.
As shown in Figure 1, the process flow chart of the Disease in Tunnel Base point processing method shown for one embodiment of the application, Include the following steps:
S100: the disease point position of Tunnel Base is determined.
Because in real work, for tunnel longer for length, disease point is usually only present in certain of Tunnel Base At one or a few place positions, thus how the specific location of quick lock in disease point, will become quick, effective hidden perils head Want condition.The method for determining disease point position can be construction personnel and hold health check tool walks in tunnel internal, when walking pair Suspicious region is tapped or is observed detection, when there is the sign risen soil, then can determine that the region is disease point.Or Person, shoots Tunnel Base stratum using Image-forming instrument, determines the point of the disease in image by analysis chart image quality looks, finally The disease point position in actual tunnel substrate is obtained by measuring and calculating.
S200: drilling injected hole to the stratum of the disease point, below the stratum for making the injected hole and the disease point Come to nothing area connection.
Specifically, air drill machine or rotary drilling rig can be used and drill operation to what the stratum of disease point carried out injected hole.Work as brill Head, which protrudes into, comes to nothing area when by lesser axial force, then shows that injected hole has been penetrated through with area of coming to nothing, fill to form slip casting It comes to nothing the necessary condition in area.
In an alternative embodiment, the aperture of the injected hole is 50mm~75mm;It can guarantee slurries injection effect at this time Rate, while making the aperture of the injected hole caliber bigger than normal in Grouting Pipe enables and comes to nothing underground water in area and silt from slurries Under stuffing pressure effect, quickly it is discharged from the fit clearance of Guan Yukong.Particularly, the centerline hole of the injected hole with it is described The angle of horizontal plane is 15 °~30 ° where Tunnel Base.At this point, drill bit can carry out bore operation with lateral attitude, it can not be by The excessive limitation of tunnel height;Underground water and the more easily discharge of silt mixture come to nothing in area simultaneously.
And in order to further increase treatment efficiency, the injected hole of two or more quantity can be drilled simultaneously, it specifically can basis The execution conditions of there and then are set, and details are not described herein.
In addition, further comprising the steps of: before the step of stratum to the disease point drills injected hole and removing the disease The confining bed of the surface of stratum of point.Therefore drilling difficulty can be reduced, mitigates the load and loss of drilling device, improve drilling effect Rate.It should be understood that confining bed can be the concrete foundation of Tunnel Base, which usually has certain thickness, should It is purged by demolition equipment, to reduce the formation thickness of disease point.Alternatively, confining bed is also possible to be deposited in surface of stratum Sundries, such as miscellaneous stone, tool.
Further, in an embodiment, injected hole is drilled on the stratum to the disease point, and remove the disease point After the confining bed of surface of stratum, further comprises the steps of: and excavate at least one sewage ditch in the surrounding formation of the disease point, and It is connected to the sewage ditch with the injected hole.Therefore, the underground water and silt mixture being discharged from injected hole can be accumulated Into sewage ditch, discharge tunnel is concentrated by sewage ditch, environment in tunnel is avoided pollution, reduces difficulty of removing contamination.Particularly, work as disease When point appears in the central region or close central region of Tunnel Base, two or more blowdowns can be opened up around injected hole The problem of ditch, the underground water being discharged out of injected hole with reply and silt mixture may flee toward any direction.
Further, at least one sewage ditch is excavated in the surrounding formation of the disease point, and makes the sewage ditch After being connected to the injected hole, the obstacle removed in the sewage ditch is further comprised the steps of:.The obstacle is, for example, tiny Stone, soil grumeleuse etc. are removed obstacle clean, it is ensured that the underground water and silt mixture of discharge flow in sewage ditch It is smooth.
It should be noted that 30 ° of the deflection moldings inwardly of edge of the sewage ditch based on the Tunnel Base.So that row Dirty ditch has bigger mobile potential energy after there is certain gradient, underground water and silt mixture to enter sewage ditch, thus more It is easy to drain along the extending direction flowing of sewage ditch, avoids being blocked in sewage ditch.It of courses, in other embodiments, blowdown The angle excursion of ditch can also be other numerical value, such as 25 ° or 35 °.
In addition, the depth in gutter is 5~10cm, to guarantee enough drainabilities.
In another embodiment, it in the step of stratum to the disease point drills injected hole, further comprises the steps of: simultaneously Drainage hole is drilled on the stratum of the disease point, is connected to the drainage hole with the area of coming to nothing below the stratum of the disease point. Only it is responsible in this way, being just capable of forming injected hole to area's injection slurries that come to nothing, not only injected hole is excessive without opening, but also underground water It will not cause to impact with slurries opposite direction flowing with silt mixture, cause slurries injection unsmooth, cause noise and vibration.Draining Hole then can sole duty in the discharge of underground water and silt mixture, the velocity of discharge is fast, forms marginal not slurry, side blowdown with injected hole Coordinated can effectively promote the regulation efficiency of disease point.Particularly, for make to come to nothing underground water and silt mixing in area Object is more quickly discharged, and can drill the drainage hole of two or more quantity simultaneously.
S300: slurry is filled into the area of coming to nothing below the stratum of the disease point by the injected hole using grouting equipment Liquid.
All kinds of grouting equipments in the prior art can be selected in grouting equipment, as long as slurries can reliably be injected to disease point Coming to nothing in area below stratum.According to area of coming to nothing deeply and volume size, the injection pressure of slurries is chosen as 3~ 8MPa, injection speed are 18L/min~30L/min.The slurries of injection can be concrete slurry, silt slurries or composite material Slurries.In the present embodiment, slurries are concrete slurry.
Slurries are being filled into the area of coming to nothing below the stratum of the disease point by the injected hole using grouting equipment Later, it further comprises the steps of: using vibration equipment is smash that the slurries to come to nothing in area below the stratum in the disease point are compacted.It adopts It is vibrated, can further be floated the agitation of air, underground water and silt to the slurries in area that come to nothing are injected with vibration equipment is smash, from And be more completely discharged out of come to nothing area, guarantee the purity and quality of concrete slurry, the concrete block after making condensation has Higher structural strength, and then promote the support stability to Tunnel Base.Optionally, smash vibration equipment can be agitating auger, Vibrator etc., for making in the concrete slurry flowing come to nothing in area and seething.
Vibration equipment is smash by coming to nothing in area below the stratum in the disease point in use in one of the embodiments, Slurries it is compacted after, further comprise the steps of: to be inserted into stiffener into slurries before grout cures, make the stiffener It is integrated with slurries condensation.By being inserted into stiffener into concrete slurry, after concrete setting, can further improve The structural strength of concrete block, and then promote the support performance to Tunnel Base.
It should be noted that the type and structural style of stiffener are not construed as limiting, such as it can be single steel bar or more The connected body of root reinforcing bar.The diameter of stiffener is 32~40mm, is preferably 36mm.To guarantee that stiffener can be complete It is immersed in concrete slurry, length need to be 5~10mm shorter than the hole depth of injected hole.
S400: when slurries are overflowed out of described injected hole, the grouting equipment is withdrawn, and to the aperture of the injected hole Carry out closure processing.
Closure processing is carried out to the aperture of injected hole, can prevent the water body ecto-entad outside the stratum of disease point from invading Inside stratum.Specifically, in an embodiment, when slurries are overflowed out of described injected hole, the grouting equipment is withdrawn, and right The aperture of the injected hole carried out in the step of blocking processing, was specially coated using waterproof material in the aperture of the injected hole At least one layer of waterproof membrane.The operation mode is easy to operate, easy to implement, and the waterproof membrane formed is tightly combined with surface of stratum, Thus there is excellent sealing performance.
Optionally, used waterproof material is polyurethane water-proof paint.It of courses, it in other embodiments, can also be with Using other types of waterproof material, such as water-proof acrylic acid paint in the prior art.
Further, it after coating at least one layer of waterproof membrane in the aperture of the injected hole using waterproof material, also wraps It includes step: the waterproof membrane after molding is cut, the area of the waterproof membrane is made to be greater than the aperture face of the injected hole Product.It can so be further ensured that sealing performance, outside body of water is avoided to penetrate into inside stratum from gap.
To sum up, when problem of rising soil existing for the processing method reply Tunnel Base using the application, it is necessary first to really Determine the disease point position of Tunnel Base, i.e. locking construction target area;Injected hole is drilled on the stratum of disease point later, makes this Injected hole is connected to the area of coming to nothing below the stratum of disease point, to form the necessary condition of slip casting filling;And then, using slip casting Equipment injects slurries into injected hole, and slurries is enable gradually to fill area of coming to nothing, and the area that can so make to come to nothing tamps to be formed again Good Tunnel Base structure, and can prevent internal underground water from continuing punching area of coming to nothing after grout cures and gush out;Later, wait starch Liquid after spilling, withdraws grouting equipment, and carry out closure processing to the aperture of injected hole, to prevent since in the injected hole In water body intrusion Tunnel Base in external environment.In conclusion present treatment scheme can have the area of coming to nothing of disease point Effect filling, while injected hole is blocked, it realizes and thoroughly eliminates problem of rising soil inside and outside, and its treatment process is simple, The construction equipment used is few, thus construction cost is low, good economy performance.
Each technical characteristic of embodiment described above can be combined arbitrarily, for simplicity of description, not to above-mentioned reality It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, all should be considered as described in this specification.
The embodiments described above only express several embodiments of the present invention, and the description thereof is more specific and detailed, but simultaneously It cannot therefore be construed as limiting the scope of the patent.It should be pointed out that coming for those of ordinary skill in the art It says, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to protection of the invention Range.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.

Claims (10)

1. a kind of Disease in Tunnel Base point processing method, which comprises the steps of:
Determine the disease point position of Tunnel Base;
Injected hole is drilled to the stratum of the disease point, makes the company, area of coming to nothing below the stratum of the injected hole and the disease point It is logical;
Slurries are filled into the area of coming to nothing below the stratum of the disease point by the injected hole using grouting equipment;
When slurries are overflowed out of described injected hole, the grouting equipment is withdrawn, and block to the aperture of the injected hole Processing.
2. Disease in Tunnel Base point processing method according to claim 1, which is characterized in that on the ground to the disease point Before the step of layer drills injected hole, the confining bed for removing the surface of stratum of the disease point is further comprised the steps of:.
3. Disease in Tunnel Base point processing method according to claim 2, which is characterized in that on the ground to the disease point Layer drills injected hole, and after removing the confining bed of surface of stratum of the disease point, further comprises the steps of: in the disease point At least one sewage ditch is excavated in surrounding formation, and is connected to the sewage ditch with the injected hole.
4. Disease in Tunnel Base point processing method according to claim 3, which is characterized in that around the disease point At least one sewage ditch is excavated on stratum, and after being connected to the sewage ditch with the injected hole, further comprise the steps of: and remove institute State the obstacle in sewage ditch.
5. Disease in Tunnel Base point processing method according to claim 1, which is characterized in that on the ground to the disease point In the step of layer drills injected hole, further comprises the steps of: while drilling drainage hole on the stratum of the disease point, make the drainage hole It is connected to the area of coming to nothing below the stratum of the disease point.
6. Disease in Tunnel Base point processing method according to claim 1, which is characterized in that pass through using grouting equipment After the injected hole fills slurries into the area of coming to nothing below the stratum of the disease point, further comprises the steps of: and set using smashing vibration It is standby that the slurries to come to nothing in area below the stratum in the disease point are compacted.
7. Disease in Tunnel Base point processing method according to claim 6, which is characterized in that smash vibration equipment for place using After slurries to come to nothing in area below the stratum of the disease point are compacted, further comprise the steps of: to before grout cures, to slurry It is inserted into stiffener in liquid, condenses the stiffener with slurries and is integrated.
8. Disease in Tunnel Base point processing method according to claim 1, which is characterized in that slurries from the slip casting When overflowing in hole, the grouting equipment is withdrawn, and specially make in the step of blocking processing to the aperture of the injected hole At least one layer of waterproof membrane is coated in the aperture of the injected hole with waterproof material.
9. Disease in Tunnel Base point processing method according to claim 8, which is characterized in that in use waterproof material in institute After at least one layer of waterproof membrane of aperture coating for stating injected hole, further comprises the steps of: and the waterproof membrane after molding is cut, The area of the waterproof membrane is set to be greater than the orifice area of the injected hole.
10. Disease in Tunnel Base point processing method according to claim 3, which is characterized in that the aperture of the injected hole For 50mm~75mm;The angle of horizontal plane is 15 °~30 ° where the centerline hole of the injected hole and the Tunnel Base;Institute State 30 ° of the deflection moldings inwardly of edge of the sewage ditch based on the Tunnel Base.
CN201910461156.2A 2019-05-30 2019-05-30 Disease in Tunnel Base point processing method Pending CN110206561A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910461156.2A CN110206561A (en) 2019-05-30 2019-05-30 Disease in Tunnel Base point processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910461156.2A CN110206561A (en) 2019-05-30 2019-05-30 Disease in Tunnel Base point processing method

Publications (1)

Publication Number Publication Date
CN110206561A true CN110206561A (en) 2019-09-06

Family

ID=67789554

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910461156.2A Pending CN110206561A (en) 2019-05-30 2019-05-30 Disease in Tunnel Base point processing method

Country Status (1)

Country Link
CN (1) CN110206561A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111878119A (en) * 2020-07-08 2020-11-03 上海地铁维护保障有限公司工务分公司 Subway tunnel ballast bed pipe piece wall post-grouting method
CN113090289A (en) * 2021-03-22 2021-07-09 中国神华能源股份有限公司神朔铁路分公司 Method and system for treating water leakage of tunnel construction joint

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1267035A1 (en) * 2001-06-15 2002-12-18 Valplast AG Method for constructing underground waterproof tunnels with a concrete inner shell
CN103410529A (en) * 2013-08-29 2013-11-27 中南大学 Tunnel supporting arch foot reinforced structure for soft surrounding rocks and construction method
CN104033165A (en) * 2014-05-26 2014-09-10 江苏鼎泰工程材料有限公司 Repairing method and grout for tunnel defects
CN104500108A (en) * 2014-12-11 2015-04-08 中铁十九局集团有限公司 Tunnel foundation water return point processing method
CN105443141A (en) * 2015-11-30 2016-03-30 中国神华能源股份有限公司 Tunnel base reinforcement method
CN108252726A (en) * 2018-03-09 2018-07-06 中交第二航务工程局有限公司 The device and its construction method that prevention Tunnel Second Lining vault comes to nothing
CN109457571A (en) * 2018-11-16 2019-03-12 中铁二十三局集团第四工程有限公司 The construction method of ground deformation slot repairing

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1267035A1 (en) * 2001-06-15 2002-12-18 Valplast AG Method for constructing underground waterproof tunnels with a concrete inner shell
CN103410529A (en) * 2013-08-29 2013-11-27 中南大学 Tunnel supporting arch foot reinforced structure for soft surrounding rocks and construction method
CN104033165A (en) * 2014-05-26 2014-09-10 江苏鼎泰工程材料有限公司 Repairing method and grout for tunnel defects
CN104500108A (en) * 2014-12-11 2015-04-08 中铁十九局集团有限公司 Tunnel foundation water return point processing method
CN105443141A (en) * 2015-11-30 2016-03-30 中国神华能源股份有限公司 Tunnel base reinforcement method
CN108252726A (en) * 2018-03-09 2018-07-06 中交第二航务工程局有限公司 The device and its construction method that prevention Tunnel Second Lining vault comes to nothing
CN109457571A (en) * 2018-11-16 2019-03-12 中铁二十三局集团第四工程有限公司 The construction method of ground deformation slot repairing

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111878119A (en) * 2020-07-08 2020-11-03 上海地铁维护保障有限公司工务分公司 Subway tunnel ballast bed pipe piece wall post-grouting method
CN111878119B (en) * 2020-07-08 2022-03-18 上海地铁维护保障有限公司工务分公司 Subway tunnel ballast bed pipe piece wall post-grouting method
CN113090289A (en) * 2021-03-22 2021-07-09 中国神华能源股份有限公司神朔铁路分公司 Method and system for treating water leakage of tunnel construction joint
CN113090289B (en) * 2021-03-22 2024-03-01 中国神华能源股份有限公司神朔铁路分公司 Method and system for treating leakage water of tunnel construction joint

Similar Documents

Publication Publication Date Title
CN104453913B (en) A kind of Shaft Stopes front pre-grouting method
CN102518135B (en) Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
CN104846810B (en) Self-circulating posterior grouting bored pile construction method
CN100510274C (en) Construction method of enclosing level rotary-jet pile hole-mouth using double-liquid slip jection method
CN104499479B (en) It is a kind of to pass through the dug pile construction method that sand gravel backfills layer
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN104631438B (en) Long auger guncreting uplift pile construction method
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN109538216A (en) Pass through mined out and subsidence area constructing tunnel technique
CN108166483A (en) Bored pile construction method
CN111119128B (en) Danger-removing, reinforcing and seepage-proofing method for natural rock-fill dam of barrier lake
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN101614020A (en) Flexible bladder type anti-corrosive apparatus and use the anticorrosion stake and the job practices of this device
CN107489158A (en) A kind of spiral-digging pore stirs the construction method of water spray soil occlusion curtain pile
CN105862721A (en) Grouting composite ground suitable for consolidation and deviation rectification of high-rise building structure and provided with adjustable pre-buried steel pipe and construction method thereof
CN108999195A (en) It is a kind of block the larger water burst of deep-foundation side wall stratum in the safe grouting construction process of step heap weir formula
CN110130936A (en) It dashes forward in a kind of shield tunneling process and meets the construction method of untreated solution cavity or crack
CN105937241A (en) Post-grouting device for drilled grouting piles and pile frame structure for drilled grouting piles
CN105484266B (en) The grouting equipment and its construction method of a kind of multifunctional information
CN110778328A (en) Loess tunnel entrance section construction method for passing through landslide body
CN109440757A (en) A kind of foundation reinforcement method for karst region
CN110206561A (en) Disease in Tunnel Base point processing method
CN105937221A (en) Manufacturing method for drilled grouting piles
CN107587502A (en) A kind of spiral-digging pore pressure pour water soil occlusion curtain pile construction method
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination