CN110206374A - Communication antenna mounting bracket and power communication with the bracket share steel tower - Google Patents
Communication antenna mounting bracket and power communication with the bracket share steel tower Download PDFInfo
- Publication number
- CN110206374A CN110206374A CN201910507718.2A CN201910507718A CN110206374A CN 110206374 A CN110206374 A CN 110206374A CN 201910507718 A CN201910507718 A CN 201910507718A CN 110206374 A CN110206374 A CN 110206374A
- Authority
- CN
- China
- Prior art keywords
- diagonal brace
- bracket
- antenna
- communication
- arm
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/02—Structures made of specified materials
- E04H12/08—Structures made of specified materials of metal
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/24—Cross arms
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01Q—ANTENNAS, i.e. RADIO AERIALS
- H01Q1/00—Details of, or arrangements associated with, antennas
- H01Q1/12—Supports; Mounting means
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Chemical & Material Sciences (AREA)
- Materials Engineering (AREA)
- Wood Science & Technology (AREA)
- Support Of Aerials (AREA)
Abstract
The present invention provides communication antenna mounting bracket and the power communication with the bracket shares steel tower, belongs to electric power and communication engineering technical field.A kind of communication antenna mounting bracket, including horizontally-supported, bracket diagonal brace and reversed diagonal brace, the horizontally-supported first end is connect with cross arm end, and the lower part of second end and antenna connects, the first end of the bracket diagonal brace is connect with cross-arm lower end surface, and the top of second end and antenna connects, the reversed diagonal brace is arranged between the described horizontally-supported and described bracket diagonal brace.The present invention is cooperated by the connection of horizontally-supported, bracket diagonal brace and reversed diagonal brace, had not only been realized communication antenna and has been shared unobstructed installation on steel tower in power communication, but also can fold and pack up, and had avoided antenna and overhaul the generation for causing transmission line of electricity to be forced power failure phenomenon.
Description
Technical field
The invention belongs to electric power and communication engineering technical field, and in particular to a kind of communication antenna mounting bracket and have
The power communication of the bracket shares steel tower.
Background technique
It is to install communication equipment on electric power tower to realize the shared of steel tower resource that power communication, which shares steel tower, in order to guarantee
The safe and reliable operation of power circuit, while avoiding signal of communication by iron tower construction member, leading the screening effect of (ground) line, previous
Communication antenna is mounted on the steel tower tower body position of the lower section (i.e. the lower section of conducting wire cross-arm) of power line more, is keeping foot with power line
While enough safe spacings, realize that the antenna direction of the launch is not blocked;Previous antenna mounting locations, although meeting shared
The installation and operation of steel tower needs, but due to the lower section of the installation site of communication antenna cross-arm under conducting wire, so that steel tower has
Effect height cannot be fully utilized, and when being higher than electric power tower design height to communication antenna mounting height, need in order to full
The installation of sufficient antenna needs, and specially increases the whole design height of electric power tower, to cause the increase of construction investment.
The patent document of Publication No. CN108590313 A discloses a kind of novel Joint construction and sharing power communication poles, including
Tower body (1), the tower body (1) include multiple tower body units (11) connected each other, and the tower body (1) is equipped with plugboard
Component (13), the Joint construction and sharing power communication poles (100) further include: cross-arm unit (2), the cross-arm unit (2) with it is described
It is fixedly connected between tower body (1) by plugboard component (13), high-voltage line is connected on the cross-arm unit (2);With pole list
First (3), the pole unit (3) are set to the lower end of the cross-arm unit (2), and communication antenna is movably disposed in the pole list
On first (3).The novel Joint construction and sharing power communication poles can hang communication and power equipment simultaneously, substantially reduce cost, save
Occupied area is built in resource, saving.Communication antenna is arranged in below the cross-arm of high-voltage line in the shared steel tower, so that steel tower has
Effect height cannot be fully utilized, and when being higher than electric power tower design height to communication antenna mounting height, need in order to full
The installation of sufficient antenna needs, and specially increases the whole design height of electric power tower, to cause the increase of construction investment, antenna
Not foldable, installation is inconvenient.
The patent document of Publication No. CN106836936A discloses a kind of electric power tower of mountable 4G antenna, including bottom
Seat, tower body and tower head are additionally provided with elevating mechanism above the tower body, and the side of the tower body is additionally provided with ladder stand, described to climb
The side for climbing body is additionally provided with position-limiting unit, and the side of the position-limiting unit is additionally provided with supporting mechanism, and the elevating mechanism includes branch
Column, lifting unit, the first drawstring, shaft and elevator chamber, the supporting mechanism include L-type curved bar, the second idler wheel, third idler wheel,
The electric power tower of sliding block, screw rod, spill spin block, fixed block, link block and baffle, the mountable 4G antenna is ingenious in design, feasibility
Height is placed on 4G antenna in elevator chamber, and elevator chamber is drawn to tower body top by elevating mechanism and is installed, due to 4G antenna
It is relatively valuable, be easy to break when shaking back and forth during rising or fall, by supporting mechanism can make elevator chamber it is steady on
It rises, has ensured equipment and the safety of operator.The top of steel tower is arranged in antenna by the shared steel tower, installs need to meet it
It wants, increases cumbersome lifting device, increase construction investment, antenna is not foldable, and installation is inconvenient.
Summary of the invention
In view of this, technical problem to be solved by the invention is to provide one kind to make up the shortcomings of the prior art
Communication antenna mounting bracket and power communication with the bracket share steel tower, are led to solving electric power tower for shared installation
When believing facility, under the premise of not increasing steel tower original design height, meet communication antenna to mounting height, the difference of installation environment
It is required that giving full play to the effective height of electric power tower.
In order to solve the above technical problems, the technical scheme adopted by the invention is that:
A kind of communication antenna mounting bracket, including horizontally-supported, bracket diagonal brace and reversed diagonal brace, the horizontally-supported first end
It being connect with cross arm end, and the lower part of second end and antenna connects, the first end of the bracket diagonal brace is connect with cross-arm lower end surface,
And the top of second end and antenna connects, the reversed diagonal brace is arranged between the described horizontally-supported and described bracket diagonal brace.
Preferably, hinged joint is set on the bracket diagonal brace, it is described reversed during the bracket diagonal brace folds
The first end of diagonal brace moves in the lower end surface of the bracket diagonal brace, the relatively described horizontal bracing of the second end of the reversed diagonal brace
Second end rotation.
Preferably, limiting slot is arranged in the lower end surface of the bracket diagonal brace.
Preferably, the communication antenna mounting bracket, which is adopted, is made from an insulative material.
A kind of shared steel tower of power communication, including iron tower body, the cross-arm being arranged in the iron tower body and is suspended on
Transmission pressure on the cross-arm further includes communication antenna mounting bracket, and the communication antenna mounting bracket is arranged in the cross
On the outside of the end of load.
Preferably, the cross-arm is from top to bottom successively symmetricly set on the two sides of the iron tower body.
Preferably, the communication antenna mounting bracket mounted antennas, it is net between the antenna and the transmission pressure
Ullage is from the safe distance for being not less than 1 times.
Preferably, the communication antenna mounting bracket, including horizontally-supported, bracket diagonal brace and reversed diagonal brace, the level
The first end of support is connect with the cross arm end, and the lower part of second end and antenna connects, the first end of the bracket diagonal brace
It is connect with the cross-arm lower end surface, and the top of second end and antenna connects, the reversed diagonal brace is arranged described horizontally-supported
Between the bracket diagonal brace.
Preferably, hinged joint is set on the bracket diagonal brace, it is described reversed during the bracket diagonal brace folds
The first end of diagonal brace moves in the lower end surface of the bracket diagonal brace, the relatively described horizontal bracing of the second end of the reversed diagonal brace
Second end rotation.
Preferably, limiting slot is arranged in the lower end surface of the bracket diagonal brace.
Compared with prior art, the beneficial effects of the present invention are:
The present invention provides a kind of communication antenna mounting brackets, are matched by horizontally-supported, bracket diagonal brace and reversed diagonal brace connection
It closes, had not only realized communication antenna and shared unobstructed installation on steel tower in power communication, but also can fold and pack up, and avoided antenna
Overhaul the generation for causing transmission line of electricity to be forced power failure phenomenon.
The present invention also provides the power communications with above-mentioned communication antenna mounting bracket to share steel tower, which exists
The fixed device of cross-arm outboard end setting communication antenna for setting up transmission pressure, on the one hand realizes and is applied to lead to by electric power tower
Letter, improves the utilization rate of electric power tower, on the other hand realizes unobstructed installation of the communication antenna on electric power tower, and
Antenna overhauls zero influence on transmission line of electricity normal power supply.The shared iron tower structure of the present invention is simple, both ensure that power circuit
Safe and reliable operation in turn ensures the unobstructed transmitting of signal of communication, and caused transmission line of electricity has a power failure when avoiding antenna maintenance,
It efficiently solves the problems, such as that power communication is shared to influence each other between transmission pressure and communication antenna in steel tower.
Communication antenna mounting bracket of the present invention can realize that folding is packed up, and when communication antenna is overhauled, will communicate
Antenna installation stent, which is folded inward, to be packed up, and by antenna by being retracted to the inside of transmission pressure on the outside of transmission pressure, and is placed on
Above the cross-arm of iron tower body, withdrawal and maintenance of the transmission line of electricity not under power-off condition to communication antenna are realized.Communication antenna peace
Dress bracket is packed up by folding stage by stage with rotation, is guaranteed during entirely packing up, net between antenna and transmission pressure
Ullage is from not less than 1 times of safe distance.The present invention can be realized for the communication antenna mounting bracket of shared electric power tower thereon
Folding is packed up, and personnel convenient to overhaul install or remove antenna, so as to avoid the power failure of transmission line of electricity when antenna maintenance.
The present invention, without specially increasing steel tower height because communication antenna is installed additional, is saved for shared electric power tower
Construction cost;Communication antenna is mounted on the outside of the end of the conducting wire cross-arm of electric power tower, and the signal transmitting aspect of antenna is without appointing
What is shielded;Communication antenna mounting bracket uses insulating materials, preferably glass reinforced plastic and packs up, it can be achieved that folding, and avoids antenna maintenance
When transmission line of electricity power failure.
Detailed description of the invention
The present invention is done with reference to the accompanying drawing and is further described in detail.
A kind of Fig. 1: structural schematic diagram of communication antenna mounting bracket of the present invention;
Fig. 2: the usage state diagram of present invention another kind communication antenna mounting bracket;
Fig. 3: the structural schematic diagram of bracket diagonal brace in Fig. 2 of the present invention;
Fig. 4: a kind of power communication of the present invention shares the structural schematic diagram of steel tower;
Fig. 5: mounting bracket folds the structural schematic diagram packed up at B phase transmission pressure in Fig. 4 of the present invention;
Fig. 6: the folding principle schematic diagram of mounting bracket in Fig. 4 of the present invention;
Wherein, 1- is horizontally-supported, 2- bracket diagonal brace, the reversed diagonal brace of 3-, 4- cross-arm, 5- antenna, 6- hinged joint, 7- limiting slot,
8- iron tower body, 9- transmission pressure, 901-A phase transmission pressure, 902-B phase transmission pressure, 903-C phase transmission pressure, 10- installation
Bracket.
Specific embodiment
For a better understanding of the present invention, the contents of the present invention, but this hair are further fairly set out below with reference to embodiment
Bright protection content is not limited solely to the following examples.In the following description, give a large amount of concrete details so as to
More thorough understanding of the invention is provided.It will be apparent, however, to one skilled in the art that the present invention can be with
It is carried out without one or more of these details.
Embodiment 1
Refering to fig. 1, a kind of communication antenna mounting bracket 10, including horizontally-supported 1, bracket diagonal brace 2 and reversed diagonal brace 3, level branch
The first end 101 of support 1 is connect with 4 end of cross-arm, and second end 102 is connect with the lower part of antenna 5, the first end of bracket diagonal brace 2
201 connect with 4 lower end surface of cross-arm, and second end 202 is connect with the top of antenna 5, and reversed diagonal brace 3 is arranged in horizontally-supported 1 He
Between bracket diagonal brace 2.
Referring to Fig.2, hinged joint 6 is set on bracket diagonal brace 2, during bracket diagonal brace 2 folds, reversed diagonal brace 3
First end 301 moves in the lower end surface of bracket diagonal brace 2, and the second end of the 302 relative level diagonal brace of second end of reversed diagonal brace 3 turns
It is dynamic.The design of hinged joint 6 enables bracket diagonal brace 2 to carry out rotary folding by axis of the point, for this purpose, reversed diagonal brace 3 also needs
It is moved in the lower end surface of bracket diagonal brace 2, to cooperate bracket diagonal brace 2 to complete rotary folding.
The second end 302 of reversed diagonal brace is overlapped with horizontally-supported second end 102.
The length of reversed diagonal brace 3 with horizontally-supported 1 equal length;The first end 201 of hinged joint 6 and bracket diagonal brace 2
Between length and bracket diagonal brace 2 first end 201 and horizontally-supported 1 first end 101 between equal length, to guarantee to pacify
Fill the folding effect of bracket.
Refering to Fig. 3, limiting slot 7 is arranged in the lower end surface of bracket diagonal brace 2, oblique in bracket with the first end for limiting reversed diagonal brace 3
Support the supporting point and moving direction in 2 lower end surfaces.
Communication antenna mounting bracket 10, which is adopted, to be made from an insulative material, it is preferred to use alkali-free glass fibre reinforced resin base is compound
Material is commonly called as glass reinforced plastic.
Embodiment 2
Refering to Fig. 4-5, a kind of shared steel tower of power communication including iron tower body 8, the cross-arm being arranged in iron tower body 84 and hangs
The transmission pressure 9 on cross-arm 4 is hung over, further includes communication antenna mounting bracket 10, communication antenna mounting bracket 10 is arranged in cross-arm 4
End on the outside of.
Cross-arm 4 is from top to bottom successively symmetricly set on the two sides of iron tower body 8, in specific embodiment shown in Fig. 4-5,
Cross-arm is three layers, and the two sides of every layer of cross-arm hang transmission pressure, from top to bottom successively hangs A phase transmission pressure 901, B phase is defeated
Electric lead 902 and C phase transmission pressure 903.
10 mounted antennas 5 of communication antenna mounting bracket, the clearance between antenna 5 and adjacent power conductors 9 be not small
In 1 times of safe distance.
Refering to fig. 1-3, communication antenna mounting bracket 10, including horizontally-supported 1, bracket diagonal brace 2 and reversed diagonal brace 3, it is horizontal
The first end of support 1 is connect with 4 end of cross-arm, and second end is connect with the lower part of antenna 5, the first end and cross of bracket diagonal brace 2
Carry on a shoulder pole the connection of 4 lower end surfaces, and second end is connect with the top of antenna 5, reversed diagonal brace 3 be arranged horizontally-supported 1 and bracket diagonal brace 2 it
Between.
Hinged joint 6 is set on bracket diagonal brace 2, and during bracket diagonal brace 2 folds, the first end of reversed diagonal brace 3 exists
It is moved in the lower end surface of bracket diagonal brace 2, the second end rotation of the second end relative level diagonal brace of reversed diagonal brace 3.
Limiting slot 7 is arranged in the lower end surface of bracket diagonal brace 2, to limit the first end of reversed diagonal brace 3 in 2 lower end surface of bracket diagonal brace
Interior supporting point and moving direction.
Refering to Fig. 4-5, communication antenna 5 of the present invention is mounted on the outside of cross-arm 4 in iron tower body 8 by mounting bracket 10,
Signal is not blocked by transmission pressure 9 and tower material;Simultaneously by antenna 5(metal material) extend centainly to the outside of cross-arm 4
Distance ensure that the clearance between antenna 5 and adjacent power conductors 9 is not less than 1 times of safe distance requirement, while antenna
Clearance of 5 upper ends apart from top transmission pressure 9 reaches maximum value.
Refering to fig. 1, the installation method of communication antenna mounting bracket 10 of the present invention, specific steps are as follows: 1) by horizontally-supported 1
First end 101 is hinged on the end of cross-arm 4, and 2) first end 201 of bracket diagonal brace 2 is hinged on the lower end surface of cross-arm 4, i.e., it is complete
At installation.
After antenna installation stent 10 to be communicated is installed, the top of antenna 5 is connected to the second end of bracket diagonal brace 2
202, the lower part of antenna 5 is connected to horizontally-supported 1 second end 102, that is, completes the installation of antenna 5.
Referring to Fig.2, the installation method of communication antenna mounting bracket 10 of the present invention, the specific steps are, further includes: 3) with bracket
Hinged joint 6 on diagonal brace 2 is fulcrum, pull-up bracket diagonal brace 2, while the first end 301 of reversed diagonal brace 3 to bracket diagonal brace 2
202 direction of second end is mobile until stablizing, completion installation.
Communication antenna mounting bracket 10 of the present invention can realize that folding is packed up, and when communication antenna 5 is overhauled, will lead to
Letter antenna installation stent 10, which is folded inward, to be packed up, and antenna 5 is retracted to the inside of transmission pressure 9 by the outside of transmission pressure 9, and
It is placed on above the cross-arm 4 of iron tower body 8, realizes withdrawal and maintenance of the transmission line of electricity not under power-off condition to communication antenna 5.
Refering to Fig. 4-6, communication antenna mounting bracket 10 is packed up by folding stage by stage with rotation, guarantees entirely packing up
In the process, the clearance between antenna 5 and transmission pressure 9 is not less than 1 times of safe distance.Below to communication antenna mounting bracket
10 folding process is described in detail.For the antenna 5 in 902 outside of B phase transmission pressure is set.
Refering to Fig. 4-6, the folding process of communication antenna mounting bracket 10 includes the following steps:
S1: being moved down by the hinged joint 6 being arranged on bracket diagonal brace 2, and the first end 301 of reversed diagonal brace 3 is oblique along bracket
Limiting slot 7 in support 2 moves down simultaneously, at this time the water of the upper end of antenna 5 and top transmission pressure (i.e. A phase transmission pressure 901)
Flat projector distance reduces, but upright projection distance increases, 5 upper end of antenna and top transmission pressure (i.e. A phase transmission pressure 901)
Between clearance still not less than 1 times safe distance requirement;Meanwhile the lower end of antenna 5 apart from lower section transmission pressure (i.e.
C phase transmission pressure 903) clearance be in increase trend;
S2: bracket diagonal brace 2 and reversed diagonal brace 3 continue to move down along hinged joint 6, when the first end 301 and hinged segments of reversed diagonal brace 3
When point 6 is overlapped, reversed diagonal brace 3 is in a horizontal position, and hinged joint 6 is overlapped with the tie point of horizontally-supported 1 and cross-arm 4 at this time;
S3: after reversed diagonal brace 3 is in a horizontal position, by mounting bracket 10 and antenna 5 with hinged joint 6(with horizontally-supported 1 and
The tie point of cross-arm 4 is overlapped) it is that axial rotary is overturn close to the direction of iron tower body 8, when the connection of bracket diagonal brace 2 and antenna 5
Point and the line of hinged joint 6 it is vertical with the lower end surface of cross-arm 4 when, at this time the upper end of antenna 5 apart from top transmission pressure (i.e.
A phase transmission pressure 901) clearance be minimum value, since bracket diagonal brace 2 is partially packed up, the clearance is still not less than 1
Safe distance requirement again;
S4: mounting bracket 10 and antenna 5 are continued to overturn, until bracket diagonal brace 2 is overlapped with the oblique material in the top of cross-arm 4, day at this time
Line 5 and mounting bracket 10 are support with the cross-arm of electric power tower 4, reach the stable state packed up, that is, complete to fold.
Bracket 10 to be installed is completed after folding, and service personnel can realize in the environment for guaranteeing safety to 5 He of antenna
Maintenance or dismounting.
The present invention compared with example to disclose as above, and however, it is not to limit the invention.In the technical field of the invention
Has usually intellectual, without departing from the spirit and scope of the present invention, when can be used for a variety of modifications and variations.Therefore, this hair
Bright to be not limited to examples detailed above, those skilled in the art's announcement according to the present invention, do not depart from that scope of the invention made changes
Into and modification all should be within protection scope of the present invention.
Claims (10)
1. a kind of communication antenna mounting bracket, it is characterised in that: including horizontally-supported, bracket diagonal brace and reversed diagonal brace, the water
The first end of flat support connect with cross arm end, and the connection of the lower part of second end and antenna, the first end of the bracket diagonal brace and
The connection of cross-arm lower end surface, and the top of second end and antenna connects, the reversed diagonal brace is arranged described horizontally-supported and described
Between bracket diagonal brace.
2. communication antenna mounting bracket according to claim 1, it is characterised in that: hinged segments are arranged on the bracket diagonal brace
Point, during the bracket diagonal brace folds, the first end of the reversed diagonal brace is moved in the lower end surface of the bracket diagonal brace
Dynamic, the second end of the reversed diagonal brace is rotated relative to the second end of the horizontal bracing.
3. communication antenna mounting bracket according to claim 2, it is characterised in that: the lower end surface of the bracket diagonal brace is arranged
Limiting slot.
4. communication antenna mounting bracket according to claim 3, it is characterised in that: the communication antenna mounting bracket uses
Insulating materials is made.
5. a kind of power communication shares steel tower, including iron tower body, the cross-arm being arranged in the iron tower body and it is suspended on institute
State the transmission pressure on cross-arm, it is characterised in that: it further include communication antenna mounting bracket, the communication antenna mounting bracket setting
On the outside of the end of the cross-arm.
6. power communication according to claim 5 shares steel tower, it is characterised in that: the cross-arm is successively symmetrical from top to bottom
The two sides of the iron tower body are set.
7. power communication according to claim 6 shares steel tower, it is characterised in that: pacify in the communication antenna mounting bracket
Antenna is filled, the clearance between the antenna and the transmission pressure is not less than 1 times of safe distance.
8. sharing steel tower according to the described in any item power communications of claim 5-7, it is characterised in that: the communication antenna installation
Bracket, including horizontally-supported, bracket diagonal brace and reversed diagonal brace, the horizontally-supported first end are connect with the cross arm end,
And the lower part of second end and antenna connects, the first end of the bracket diagonal brace connect with the cross-arm lower end surface, and second end and
The top of antenna connects, and the reversed diagonal brace is arranged between the described horizontally-supported and described bracket diagonal brace.
9. power communication according to claim 8 shares steel tower, it is characterised in that: hinged segments are arranged on the bracket diagonal brace
Point, during the bracket diagonal brace folds, the first end of the reversed diagonal brace is moved in the lower end surface of the bracket diagonal brace
Dynamic, the second end of the reversed diagonal brace is rotated relative to the second end of the horizontal bracing.
10. power communication according to claim 9 shares steel tower, it is characterised in that: the lower end surface of the bracket diagonal brace is set
Set limiting slot.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910507718.2A CN110206374B (en) | 2019-06-12 | 2019-06-12 | Communication antenna installing support and have electric power communication sharing iron tower of this support |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910507718.2A CN110206374B (en) | 2019-06-12 | 2019-06-12 | Communication antenna installing support and have electric power communication sharing iron tower of this support |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110206374A true CN110206374A (en) | 2019-09-06 |
CN110206374B CN110206374B (en) | 2021-01-29 |
Family
ID=67792201
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910507718.2A Active CN110206374B (en) | 2019-06-12 | 2019-06-12 | Communication antenna installing support and have electric power communication sharing iron tower of this support |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110206374B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112096164A (en) * | 2020-09-09 | 2020-12-18 | 国网福建省电力有限公司经济技术研究院 | Special support for sharing tower and mounting method thereof |
CN112423307A (en) * | 2020-10-27 | 2021-02-26 | 北方工业大学 | Arrangement method of communication antenna carrying platform of shared power iron tower |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20060087476A1 (en) * | 2005-06-09 | 2006-04-27 | Andrew Corporation | Antenna sector frame |
CN201340900Y (en) * | 2008-10-10 | 2009-11-04 | 中国人民解放军军械工程学院 | Foldable magnesium alloy satellite antenna stand |
JP2013128357A (en) * | 2011-12-19 | 2013-06-27 | Tokyo Electric Power Co Inc:The | Reconstructing method of steel tower for overhead transmission line |
CN203760619U (en) * | 2014-04-11 | 2014-08-06 | 中国电子科技集团公司第五十四研究所 | Vehicle-mounted antenna pedestal |
CN204024186U (en) * | 2014-07-09 | 2014-12-17 | 国家电网公司 | A kind of electric power tower installing 4G antenna |
CN206189980U (en) * | 2016-09-26 | 2017-05-24 | 安徽华电工程咨询设计有限公司 | Communication and sending end integral type shaft tower |
CN107013075A (en) * | 2017-06-06 | 2017-08-04 | 牛文东 | Power communication multi-function emergency line bar |
CN207116670U (en) * | 2017-08-16 | 2018-03-16 | 云南电网有限责任公司 | A kind of antenna for base station support |
WO2018097357A1 (en) * | 2016-11-24 | 2018-05-31 | 주식회사 성진 | Movable auxiliary arm apparatus for use in uninterruptible power distribution works and method using same |
-
2019
- 2019-06-12 CN CN201910507718.2A patent/CN110206374B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20060087476A1 (en) * | 2005-06-09 | 2006-04-27 | Andrew Corporation | Antenna sector frame |
CN201340900Y (en) * | 2008-10-10 | 2009-11-04 | 中国人民解放军军械工程学院 | Foldable magnesium alloy satellite antenna stand |
JP2013128357A (en) * | 2011-12-19 | 2013-06-27 | Tokyo Electric Power Co Inc:The | Reconstructing method of steel tower for overhead transmission line |
CN203760619U (en) * | 2014-04-11 | 2014-08-06 | 中国电子科技集团公司第五十四研究所 | Vehicle-mounted antenna pedestal |
CN204024186U (en) * | 2014-07-09 | 2014-12-17 | 国家电网公司 | A kind of electric power tower installing 4G antenna |
CN206189980U (en) * | 2016-09-26 | 2017-05-24 | 安徽华电工程咨询设计有限公司 | Communication and sending end integral type shaft tower |
WO2018097357A1 (en) * | 2016-11-24 | 2018-05-31 | 주식회사 성진 | Movable auxiliary arm apparatus for use in uninterruptible power distribution works and method using same |
CN107013075A (en) * | 2017-06-06 | 2017-08-04 | 牛文东 | Power communication multi-function emergency line bar |
CN207116670U (en) * | 2017-08-16 | 2018-03-16 | 云南电网有限责任公司 | A kind of antenna for base station support |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112096164A (en) * | 2020-09-09 | 2020-12-18 | 国网福建省电力有限公司经济技术研究院 | Special support for sharing tower and mounting method thereof |
CN112423307A (en) * | 2020-10-27 | 2021-02-26 | 北方工业大学 | Arrangement method of communication antenna carrying platform of shared power iron tower |
Also Published As
Publication number | Publication date |
---|---|
CN110206374B (en) | 2021-01-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206634981U (en) | A kind of liftable mobile trolley and equipment transfer device | |
CN106121339B (en) | A kind of electric force pole tower | |
CN110206374A (en) | Communication antenna mounting bracket and power communication with the bracket share steel tower | |
CN107473102B (en) | A kind of miniature crawler belt derrick car of substation equipment maintenance and repair | |
CN102530736A (en) | On-site crane car for power transformation engineering | |
CN108899631A (en) | A kind of portable communications mobile base station | |
CN108439095A (en) | A kind of efficient power cable conveying device | |
CN107086488A (en) | A kind of charged for replacement overhead transmission line straight line pole cross-arm, insulator arrangement | |
CN210656028U (en) | Lifting type operation platform and crank arm type overhead working truck | |
CN206878371U (en) | A kind of charged for replacement overhead transmission line straight line pole cross-arm, insulator arrangement | |
CN103474905B (en) | The device of auxiliary grounding wire installing | |
CN203456708U (en) | An auxiliary support for installing a ground wire | |
CN207225433U (en) | A kind of pipe fitting handling device | |
CN107181198B (en) | Lift single pole crossing frame | |
CN209308543U (en) | The interim shielding device of substation's combined type | |
CN103332608A (en) | Special suspender for replacing GW6 disconnector knob insulator | |
CN207096534U (en) | Adjustable storage rack for redundant optical cable | |
CN204884907U (en) | Conveying rack | |
CN209493181U (en) | A kind of power cable frame lifting device | |
CN107184018A (en) | A kind of communication equipment sale frame being easily installed | |
CN107487723B (en) | A kind of substation equipment maintenance and repair hoisting apparatus | |
CN215479301U (en) | A hoist and mount fixing device for subway construction | |
CN204884906U (en) | Transport vehicle | |
CN206685796U (en) | Lift single pole crossing frame | |
CN209042872U (en) | Seed freezer Lifting basket structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |