CN110145314A - A kind of method that the tall and big Core Soil of extra-large cross-section bored tunnel is removed - Google Patents

A kind of method that the tall and big Core Soil of extra-large cross-section bored tunnel is removed Download PDF

Info

Publication number
CN110145314A
CN110145314A CN201910390833.6A CN201910390833A CN110145314A CN 110145314 A CN110145314 A CN 110145314A CN 201910390833 A CN201910390833 A CN 201910390833A CN 110145314 A CN110145314 A CN 110145314A
Authority
CN
China
Prior art keywords
tunnel
core soil
base tunnel
base
big
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910390833.6A
Other languages
Chinese (zh)
Other versions
CN110145314B9 (en
CN110145314B (en
Inventor
黄成�
张彪
胡朝伟
付孟
陈晨
罗安全
梁军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Tunnel Construction Co Ltd
Original Assignee
China Construction Tunnel Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Tunnel Construction Co Ltd filed Critical China Construction Tunnel Construction Co Ltd
Priority to CN201910390833.6A priority Critical patent/CN110145314B9/en
Publication of CN110145314A publication Critical patent/CN110145314A/en
Application granted granted Critical
Publication of CN110145314B publication Critical patent/CN110145314B/en
Publication of CN110145314B9 publication Critical patent/CN110145314B9/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Abstract

The present invention provides the methods that a kind of tall and big Core Soil of extra-large cross-section bored tunnel is removed, and include the following steps: step 1: one upper lateral part of Core Soil on top is longitudinally excavated along tunnel to form the first base tunnel;First base tunnel is in a horizontal state;Step 2: another upper lateral part of Core Soil on top is longitudinally excavated along tunnel to form the second base tunnel being in a horizontal state;The Core Soil on top is excavated after promoting the first base tunnel and the second base tunnel to excavation direction to form the interconnection perpendicular to the first base tunnel and the second base tunnel;Step 3: excavating the first base tunnel to form the first step group including several steps, each length of bench of composition first step group is 3-5m;Step 4: laterally the Core Soil on dismounting top is the step tunneling boring of 6m with formation length;Step 5: excavated downwards below the second base tunnel to form the second step group for including several steps;Step 6: carrying out Core Soil inverted arch excavation and inverted arch two of constructing serves as a contrast;Step 7: carrying out the lining construction of tunnel big cross section two.

Description

A kind of method that the tall and big Core Soil of extra-large cross-section bored tunnel is removed
Technical field
The present invention relates to constructing tunnel fields, and in particular to a kind of side that the tall and big Core Soil of extra-large cross-section bored tunnel is removed Method.
Background technique
It is especially big involved in urban track traffic in civilian infrastructure construction as the paces that China develops increasingly are accelerated Section shallow bored tunnel increases increasingly, becomes the big characteristic in urban construction, how in the prosperity urban district of city quickly, peace Urban underground Tunnel is built entirely as urgent problem.
Following two method is primarily present in the prior art to hole: extra-large cross-section bored tunnel commonly excavate CD method be by Big cross section divides left and right sidewall, and branch carries out, and completes left side wall and excavates, forms left side supporting and mid-board temporary support.It is unilateral There are still larger security risk when wall is constructed, top is there are being easy to cause bias when building, and unilateral wall earthwork is big, after Interim partition wall temporary support removes that difficulty is big, and operation height is high, and risk is big, while a side wall is as construction channel, vehicle into It is inconvenient out.It is one-way construction that common two side-wall pilot tunnel, which excavates, and work surface interference is big, in Station with when give it is attached The construction time limit of entrance is too short, and the Core Soil formed after the landing of two sides base tunnel is excessively tall and big, and dismounting difficulty is very big, security risk It is high.
Summary of the invention
The present invention is to solve removing in the prior art, the tall and big Core Soil risk in tunnel is high, difficulty is big, temporary support is torn open Except difficult problem, in view of this, the object of the present invention is to provide the sides that a kind of tall and big Core Soil of extra-large cross-section bored tunnel is removed Method, this method, which can effectively improve construction speed while avoid, removes difficult problem because Core Soil is excessively tall and big, ensure that Construction transportation tissue, traffic convenience, Core Soil longest time limit play supporting role, greatly improve working security, ensure top Building safety.
To achieve the above object, present invention employs the following technical solutions:
A kind of a kind of tall and big core of extra-large cross-section bored tunnel of method that the tall and big Core Soil of extra-large cross-section bored tunnel is removed The method that soil is removed, includes the following steps:
Step 1: one upper lateral part of Core Soil on top is longitudinally excavated along tunnel to form the first base tunnel, and to the core on top Cubsoil carries out supporting;
First base tunnel is in a horizontal state, and the Core Soil on the top is located at tunnel upper middle position;
Step 2: another upper lateral part of Core Soil on top is longitudinally excavated along tunnel is led with forming be in a horizontal state second Hole, the face of the second base tunnel are 15m along tunneling direction distance away from the first base tunnel face;
The Core Soil that top is excavated after promoting the first base tunnel and the second base tunnel to excavation direction is led with being formed perpendicular to first The interconnection in hole and the second base tunnel;
Step 3: excavating the first base tunnel to form the first step group including several steps, form each of first step group Length of bench is 3-5m;
Step 4: laterally the Core Soil on dismounting top is the step tunneling boring of 6m with formation length;
Step 5: excavated downwards below the second base tunnel to form the second step group for including several steps;
Step 6: carrying out Core Soil inverted arch excavation and inverted arch two of constructing serves as a contrast;
Step 7: carrying out the lining construction of tunnel big cross section two.
Further, second base tunnel horizontal width is 8m in the step 1, and vertical height is 8m.
One step, in the step 2 after second excavation with guide pit, the Core Soil indwelling width on top is 5.6m.
One step, second lower base tunnel and the Core Soil on top divide step is synchronous to excavate in the step 5, to form wide 14m The rectangular-shaped step of height 3m.
Compared with the prior art, the invention has the following beneficial effects:
(1) working efficiency of construction is improved, the dismounting efficiency of especially big cross section Core Soil greatly improves, and reduces chief engineer Phase;
(2) reduce big cross section Core Soil gib, save cost and activity time.
(3) Core Soil on top laterally excavates the interconnection formed, and construction transportation tissue is convenient;
(4) supporting is carried out to Core Soil, and excavating is step-like progress, the soil for not having top in this way falls security performance It is high.
When the essence of this method is that extra-large cross-section excavates, constructed in advance by the first base tunnel on the left of the Core Soil of top, core Second base tunnel on native right side follows and opens up interconnection by remaining core soil in advance interval after propulsion, further according to step sequence subdividing by Step promotes the first base tunnel of left side, and middle and lower part Core Soil and the second base tunnel of right side synchronous bench cut downwards form more work surfaces, Greatly improve construction speed;Central nucleus cubsoil follows the second base tunnel of right side is synchronous to remove, and efficiently solves tall and big Core Soil and removes The problems such as difficulty, risk is high;Through the base tunnel on interconnection connection double side wall, construction transportation tissue is effectively solved;With conventional tunnel Road excavation method is compared, and extra-large cross-section bored tunnel of the present invention reserves median septum step and removes tall and big Core Soil excavation Method can effectively control tall and big Core Soil and remove risk, reduce rock mass disturbance, the first base tunnel and the second base tunnel face it is longitudinal away from It can construct simultaneously from 15m, improve the efficiency of construction, save a variety of materials dosage and mechanical equipment used time, reduce The mechanical equipment proportion of goods damageds;
More former CD, double side wall excavation method, this engineering method operate and are easier to realize, section excavation effect is good, excavate progress Fast and security performance is high.
Further advantage, target and feature of the invention will be partially reflected by the following instructions, and part will also be by this The research and practice of invention and be understood by the person skilled in the art.
Detailed description of the invention
Fig. 1 is constructing tunnel schematic three dimensional views of the present invention;
Fig. 2 is tunnel lateral direction section construction way schematic diagram of the present invention;
Fig. 3 is that tunnel excavation of the present invention walks sequence elevational schematic view;
Fig. 4 is that tunnel top of the present invention Core Soil reserves the horizontal longitudinal schematic diagram of rock pillar;
Fig. 5 is that tunnel top of the present invention Core Soil reserves rock pillar schematic longitudinal section.
Appended drawing reference in figure: the first base tunnel 1, the second base tunnel 2, first step group 3, Core Soil 6, interconnection 61, second Step group 7, the lining of inverted arch 10, two 11, reserved rock pillar 12.
Specific embodiment
In order to make the present invention realize technological means, creation characteristic, reach purpose and effect more clearly and be apparent to, The present invention is further elaborated with reference to the accompanying drawings and detailed description:
A kind of method that the tall and big Core Soil of extra-large cross-section bored tunnel is removed, includes the following steps:
Fig. 1 is constructing tunnel schematic three dimensional views of the present invention;Fig. 2 is tunnel lateral direction section construction way schematic diagram of the present invention; Fig. 3 is that tunnel excavation of the present invention walks sequence elevational schematic view;Fig. 4 reserves 12 level of rock pillar for tunnel top of the present invention Core Soil 6 and indulges To schematic diagram;Fig. 5 is that tunnel top of the present invention Core Soil 6 reserves 12 schematic longitudinal section of rock pillar.
A kind of method that the tall and big Core Soil of extra-large cross-section bored tunnel is removed, comprising the following steps:
Step 1: 6 first base tunnel 1 of left side of Core Soil on top excavates, and 6 one upper lateral part of Core Soil on top is vertical along tunnel To excavating to form the first base tunnel 1, while supporting is carried out to the Core Soil on top 6.
Step 2: Core Soil 6 the second base tunnel 2 of right side in top excavates, and another upper lateral part of Core Soil 6 on top is vertical along tunnel To excavating to form the second base tunnel 2 being in a horizontal state, the face of the second base tunnel is away from the first base tunnel face along tunneling direction Distance be 15m, face is a common technical term in tunnel construction, namely excavate tunnel Tunnel Engineering in constantly to Be pushed forward into working face, be the equal of the first base tunnel and the second base tunnel be it is interleaved come, be guarantee one safety meet On the other hand code requirement can thus enable the first base tunnel and the second base tunnel to construct simultaneously, improve construction Efficiency.
First base tunnel 1 of 6 left and right sides of Core Soil and the second base tunnel 2 are promoted centainly towards front (i.e. tunnelling direction) After distance, depending on actual conditions, to top Core Soil 6, laterally (i.e. perpendicular to the mode of the first base tunnel 1 and the second base tunnel 2) segmentation is opened It digs (every section of excavation 10m), formation length is not less than the reserved rock pillar 12 of 20m, on the one hand prevents from collapsing in this way, is on the other hand formed Interconnection 61 forms cargo, the road that construction personnel passes through, is convenient for contacted tissue.
Step 3: 6 left side staged multi-step of top Core Soil driving, that is, excavating the first base tunnel 1 to be formed includes several The first step group 3 of rank, it is progressive using multi-step mode, under being unfolded in the left side of top Core Soil 6 from top to bottom in upper, left side into The multiple operation surface constructions of row, each length of bench of composition first step group 3 are 3-5m.
Step 4: top Core Soil 6 excavates, and is laterally removed using 6 second base tunnel of right side 2 of Core Soil on established top The Core Soil 6 on top is the step tunneling boring of 6m with formation length.
Step 5: excavated downwards below the second base tunnel 2 to form the second step group 7 for including several steps, staged is more Step is progressive, and carries out supporting in time.
Step 6: inverted arch 10 excavates, and inverted arch 10 is to improve top supporting construction stress condition and the anti-of tunnel bottom is arranged in It is one of chief component of tunnel structure to domes, it is popular to be construed to the arch faced upward.Carry out 6 inverted arch of Core Soil 10 excavations and the lining of inverted arch 10 2 11 of constructing.
Step 7: carrying out 11 construction of the lining of tunnel big cross section two, determine that secondary lining is applied by country rock convergent deformation monitoring data It does opportunity, big cross section secondary lining utilizes telescoping steel form, the long 6m of trolley completes big cross section two and serve as a contrast 11 length to be 6m every time.Match It closes reinforcement trolley and first completes waterproof, reinforcing bar binding, two lining 11 telescoping steel forms follow-ups, a mould 6m bis- lining 11 is completed in trolley formwork positioning Concreting, then next 11 construction of the lining of mould big cross section two of incremental progress.
Technological principle of the present invention is will be big in conjunction with corresponding feature based on two side-wall pilot tunnel, CD method and benching tunnelling method Section, extra-large cross-section are divided into 6 left and right sides of Core Soil, 6 region each section of center upper portion Core Soil, while by the first base tunnel of left and right sides 1,2 subdividing polyisocyanate shape step of the second base tunnel expands 6 force area of middle and lower part Core Soil, and right side step and 6 entirety of Core Soil are opened It digs, is that platform completes the dismounting of 6 region of top Core Soil using molded the second base tunnel of right side 2, it is quick to be gradually completing big cross section It excavates, a kind of integrated approach of safe excavation.It is to be protected by reasonable 6 trough of Core Soil of determination and subdividing step height Card construction fast and stable forms big cross section closure, reduces the disturbance to rock mass.Its core is that left side subdividing step promotes, and is established Transport channel in hole, and interconnection 61 and laterally dismounting top Core Soil 6 are opened up for platform indwelling rock pillar using leading on right side, Right side middle and lower part Core Soil 6 is integrated with right side middle and lower part base tunnel, increases core stress unit, and divides during middle bench is It is upper, in get out of a predicament or an embarrassing situation, after scene reaches implementation condition, gradually it is whole excavate in it is upper, in lower Core Soil region and base tunnel;Meet drilling depth After step pitch, left and right sides can excavate simultaneously, and more work surfaces are unfolded, and greatly improve construction speed, ensure large cross section excavation to greatest extent Safety connects double side wall through interconnection 61, and forming many places interconnection 61 in hole can effectively solve the problem that construction transportation tissue not Convenient problem.
Compared with conventional tunnel excavation method, extra-large cross-section bored tunnel of the present invention is reserved median septum step and is torn open Except tall and big Core Soil excavating load, it can effectively control tall and big Core Soil 6 and remove risk, reduce rock mass disturbance, save various materials Expect dosage and save the mechanical equipment used time, reduces the mechanical equipment proportion of goods damageds;More former CD, double side wall excavation method, this engineering method It operates and is easier to realize, section excavation effect is good, and excavation progress is fast and security performance is high.
Finally, it is stated that the above examples are only used to illustrate the technical scheme of the present invention and are not limiting, although referring to compared with Good embodiment describes the invention in detail, those skilled in the art should understand that, it can be to skill of the invention Art scheme is modified or replaced equivalently, and without departing from the objective and range of technical solution of the present invention, should all be covered at this In the scope of the claims of invention.

Claims (4)

1. a kind of method that the tall and big Core Soil of extra-large cross-section bored tunnel is removed, which comprises the steps of:
Step 1: one upper lateral part of Core Soil on top is longitudinally excavated along tunnel to form the first base tunnel, and to the Core Soil on top Carry out supporting;
First base tunnel is in a horizontal state, and the Core Soil on the top is located at tunnel upper middle position;
Step 2: another upper lateral part of Core Soil on top is longitudinally excavated along tunnel to form the second base tunnel being in a horizontal state, the The face of two base tunnels is 15m along tunneling direction distance away from the first base tunnel face;
The Core Soil on top is excavated after promoting the first base tunnel and the second base tunnel to excavation direction to be formed perpendicular to the first base tunnel and The interconnection of second base tunnel;
Step 3: excavating the first base tunnel to form the first step group including several steps, form each step of first step group Length is 3-5m;
Step 4: laterally the Core Soil on dismounting top is the step tunneling boring of 6m with formation length;
Step 5: excavated downwards below the second base tunnel to form the second step group for including several steps;
Step 6: carrying out Core Soil inverted arch excavation and inverted arch two of constructing serves as a contrast;
Step 7: carrying out the lining construction of tunnel big cross section two.
2. the method that the tall and big core of extra-large cross-section bored tunnel according to claim 1 is removed, which is characterized in that the step Second base tunnel horizontal width is 8m in 1, and vertical height is 8m.
3. the method that the tall and big core of extra-large cross-section bored tunnel according to claim 1 is removed, which is characterized in that the step In 2 after second excavation with guide pit, the Core Soil indwelling width on top is 5.6m.
4. the method that the tall and big core of extra-large cross-section bored tunnel according to claim 1 is removed, which is characterized in that the step Second lower base tunnel and the Core Soil on top divide step is synchronous to excavate in 5, to form the rectangular-shaped step of width 14m height 3m.
CN201910390833.6A 2019-05-10 2019-05-10 Method for removing high and large core soil of extra-large section underground tunnel Active CN110145314B9 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910390833.6A CN110145314B9 (en) 2019-05-10 2019-05-10 Method for removing high and large core soil of extra-large section underground tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910390833.6A CN110145314B9 (en) 2019-05-10 2019-05-10 Method for removing high and large core soil of extra-large section underground tunnel

Publications (3)

Publication Number Publication Date
CN110145314A true CN110145314A (en) 2019-08-20
CN110145314B CN110145314B (en) 2020-07-24
CN110145314B9 CN110145314B9 (en) 2020-11-20

Family

ID=67594112

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910390833.6A Active CN110145314B9 (en) 2019-05-10 2019-05-10 Method for removing high and large core soil of extra-large section underground tunnel

Country Status (1)

Country Link
CN (1) CN110145314B9 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112282782A (en) * 2020-10-28 2021-01-29 中铁大桥局集团有限公司 Method for rapidly discharging slag from anchor hole of large-inclination-angle tunnel of suspension bridge
CN113339012A (en) * 2021-07-07 2021-09-03 中建八局第二建设有限公司 Construction method of ultra-wide section tunnel

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU977792A1 (en) * 1981-06-29 1982-11-30 Специальное конструкторско-технологическое бюро Института геотехнической механики АН УССР Rotary implement for tunneling machine
JPH01285472A (en) * 1988-05-10 1989-11-16 Topy Ind Ltd Manufacture of elastic crawler
JP2001280061A (en) * 2000-03-28 2001-10-10 Toda Constr Co Ltd Tunnel blasting method
CN102562075A (en) * 2012-03-09 2012-07-11 中交第二公路工程局有限公司 Large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method
CN202560245U (en) * 2012-05-11 2012-11-28 中国建筑第五工程局有限公司 Multifunctional trolley with freely retractable arms
CN106979013A (en) * 2017-04-07 2017-07-25 中交第二航务工程局有限公司 A kind of excavation construction method for the large section tunnel for biasing Shallow-Buried Soft Rock
CN107288653A (en) * 2017-06-27 2017-10-24 中铁十局集团第四工程有限公司 A kind of the benching tunnelling method excavation supporting structure of weak surrounding rock large cross-section tunnel double -side approach three and construction method
CN108131145A (en) * 2017-12-20 2018-06-08 中铁五局集团有限公司 A kind of construction method of super-span tunnel excavation support
CN108442943A (en) * 2018-03-05 2018-08-24 北京市政建设集团有限责任公司 A kind of branch-cut bridge section tunnel and Double side heading method construction method
CN108643940A (en) * 2018-04-17 2018-10-12 中铁二院工程集团有限责任公司 Large section Shallow-Buried Soft Rock tunnel groined type double side wall support system and method for tunnel construction
CN108756894A (en) * 2018-04-23 2018-11-06 中铁二十五局集团第工程有限公司 Tunnel micro- three step top Core Soil construction
CN109113749A (en) * 2018-08-20 2019-01-01 中铁建大桥工程局集团第五工程有限公司 Four line large section railway tunnel construction method of weak surrounding rock
CN208734343U (en) * 2018-05-25 2019-04-12 中国建筑股份有限公司 A kind of station tunnel excavation structure with interim middle spacer post support
CN109681212A (en) * 2018-12-17 2019-04-26 中交第二航务工程局有限公司 The excavation construction method of light section loess tunnel

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU977792A1 (en) * 1981-06-29 1982-11-30 Специальное конструкторско-технологическое бюро Института геотехнической механики АН УССР Rotary implement for tunneling machine
JPH01285472A (en) * 1988-05-10 1989-11-16 Topy Ind Ltd Manufacture of elastic crawler
JP2001280061A (en) * 2000-03-28 2001-10-10 Toda Constr Co Ltd Tunnel blasting method
CN102562075A (en) * 2012-03-09 2012-07-11 中交第二公路工程局有限公司 Large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method
CN202560245U (en) * 2012-05-11 2012-11-28 中国建筑第五工程局有限公司 Multifunctional trolley with freely retractable arms
CN106979013A (en) * 2017-04-07 2017-07-25 中交第二航务工程局有限公司 A kind of excavation construction method for the large section tunnel for biasing Shallow-Buried Soft Rock
CN107288653A (en) * 2017-06-27 2017-10-24 中铁十局集团第四工程有限公司 A kind of the benching tunnelling method excavation supporting structure of weak surrounding rock large cross-section tunnel double -side approach three and construction method
CN108131145A (en) * 2017-12-20 2018-06-08 中铁五局集团有限公司 A kind of construction method of super-span tunnel excavation support
CN108442943A (en) * 2018-03-05 2018-08-24 北京市政建设集团有限责任公司 A kind of branch-cut bridge section tunnel and Double side heading method construction method
CN108643940A (en) * 2018-04-17 2018-10-12 中铁二院工程集团有限责任公司 Large section Shallow-Buried Soft Rock tunnel groined type double side wall support system and method for tunnel construction
CN108756894A (en) * 2018-04-23 2018-11-06 中铁二十五局集团第工程有限公司 Tunnel micro- three step top Core Soil construction
CN208734343U (en) * 2018-05-25 2019-04-12 中国建筑股份有限公司 A kind of station tunnel excavation structure with interim middle spacer post support
CN109113749A (en) * 2018-08-20 2019-01-01 中铁建大桥工程局集团第五工程有限公司 Four line large section railway tunnel construction method of weak surrounding rock
CN109681212A (en) * 2018-12-17 2019-04-26 中交第二航务工程局有限公司 The excavation construction method of light section loess tunnel

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张旭: "《自由伸缩手臂多功能型钢台车拆除高大核心土施工技术》", 《施工技术》 *
邹翀等: "《超大断面隧道双侧壁导坑法开挖步序优化》", 《河南科技大学学报》 *
郝小苏: "《龙头山八车道公路隧道双侧壁导坑法施工》", 《铁道标准设计 》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112282782A (en) * 2020-10-28 2021-01-29 中铁大桥局集团有限公司 Method for rapidly discharging slag from anchor hole of large-inclination-angle tunnel of suspension bridge
CN113339012A (en) * 2021-07-07 2021-09-03 中建八局第二建设有限公司 Construction method of ultra-wide section tunnel

Also Published As

Publication number Publication date
CN110145314B9 (en) 2020-11-20
CN110145314B (en) 2020-07-24

Similar Documents

Publication Publication Date Title
CN101864963B (en) Large-section loess tunnel construction method
CN105041349A (en) Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel
CN106223967B (en) A kind of great burying rectangle or class rectangle tunneling shield constructing device and method
CN109057807A (en) A kind of gradual change Large span tunnel reversely digs method
CN103089270B (en) Excavating method suitable for large section loess tunnels
CN104653187B (en) Water-rich sand layer geology large cross-section tunnel excavation method
CN104632235A (en) Method for expanding excavation of large-diameter shield tunnel for subway station construction through pile arch wall support
CN101566064B (en) Large-section tunnel construction method
CN102400689B (en) Convoluted excavation method for undermined tunnel with extra-large cross section
CN104481546B (en) A kind of soft rock tunnel inclined shaft enters the construction method of the double curvature arch in positive hole
CN105064397A (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN110735656A (en) Method for reversely building underground excavation station tunnel with ultra-large section in soft rock area based on arch cover method
CN105201516A (en) Subway station body structure and four-joint-arch PBA underground excavation construction method thereof
CN106968691A (en) Improve CD method construction methods in a kind of extremely frigid zones silty clay tunnel
KR100991630B1 (en) A container sleeve push ahead type tunnel manufacture method
CN110924952B (en) Construction method for three-step seven-step normal medium rock pillar method conversion of super-large section tunnel
CN104632227A (en) Subway station excavation technology of single-layer beam arch structure
CN104929649A (en) Tunnel transverse cave-to-master cave top brushing construction method and top brushing structure
CN110486021B (en) Construction method for converting large-section tunnel into two small-section tunnels
CN110145314A (en) A kind of method that the tall and big Core Soil of extra-large cross-section bored tunnel is removed
CN111997616A (en) Method for continuously recycling residual top-bottom column by adopting large section
CN204457789U (en) A kind of stake arch wall supports the subway station digging large diameter shield tunnel and build
CN108915714B (en) One-hole double-TBM (tunnel boring machine) installing method
CN113027495B (en) Underground excavation large-span station construction method implemented by interval tunnel organization
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CI03 Correction of invention patent
CI03 Correction of invention patent

Correction item: Denomination of Invention|Abstract

Correct: A method of removing large core soil in large cross section tunnel|Correct

False: A method of demolishing large and large nuclear core in large cross section tunnel|error

Number: 30-02

Volume: 36

Correction item: Denomination of Invention|Abstract|Claims|Description

Correct: A method of removing large core soil in large cross section tunnel|Correct

False: A method of demolishing large and large nuclear core in large cross section tunnel|error

Number: 30-02

Page: ??

Volume: 36