CN110145018A - A kind of building main body and its construction method - Google Patents

A kind of building main body and its construction method Download PDF

Info

Publication number
CN110145018A
CN110145018A CN201910454712.3A CN201910454712A CN110145018A CN 110145018 A CN110145018 A CN 110145018A CN 201910454712 A CN201910454712 A CN 201910454712A CN 110145018 A CN110145018 A CN 110145018A
Authority
CN
China
Prior art keywords
frame
main body
cylinder
building main
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910454712.3A
Other languages
Chinese (zh)
Inventor
肖岩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910454712.3A priority Critical patent/CN110145018A/en
Publication of CN110145018A publication Critical patent/CN110145018A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/34Extraordinary structures, e.g. with suspended or cantilever parts supported by masts or tower-like structures enclosing elevators or stairs; Features relating to the elastic stability
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/34Extraordinary structures, e.g. with suspended or cantilever parts supported by masts or tower-like structures enclosing elevators or stairs; Features relating to the elastic stability
    • E04B1/3404Extraordinary structures, e.g. with suspended or cantilever parts supported by masts or tower-like structures enclosing elevators or stairs; Features relating to the elastic stability supported by masts or tower-like structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3583Extraordinary methods of construction, e.g. lift-slab, jack-block using permanent tensioning means, e.g. cables or rods, to assemble or rigidify structures (not pre- or poststressing concrete), e.g. by tying them around the structure

Abstract

The present invention relates to a kind of building main body and its construction methods, belong to technical field of buildings, and building main body includes column, suspension cable is fixedly installed on the column, the suspension cable bottom is fixedly installed with frame, and the frame lower end is equipped with floor, and the floor is connected by hoist cable with frame;The present invention passes through production column, frame and floor, and frame is fixed on column by suspension cable, then floor is sequentially fixed at frame lower end by hoist cable, it can be built simultaneously in different height, improve the construction speed of building main body, stable structure, work efficiency is high, overcomes the drawbacks of existing building can only be built in layer from bottom.

Description

A kind of building main body and its construction method
Technical field
The present invention relates to technical field of buildings, specifically a kind of building main body and its construction method.
Background technique
Building refers to two layers or two layers or more of house.Current building is multilayer, and especially in city, cost of land is high, Building is generally ten several layers of or tens layers.It is all since ground, gradually from bottom to skyscraper, entirely when building building The wall of building is accumulated piece by piece with brick, and the finishing for carrying out inner-outer wall after entire building main body completion again is built at complete Whole building.
Current building can only be built in construction from the lower layer of one layer of construction in construction due to being successively to build If after complete one layer next layer could be built after the concrete dry, it certainly will will lead to that the construction period is long, and construction efficiency is low in this way, And some builders may carry out next layer of construction to work to tight deadlines in the case where concrete does not have completely dry, this is increased by The risk of construction, affects the service life of building.
Summary of the invention
The purpose of the present invention is to provide a kind of building main body and its construction methods, to solve to propose in above-mentioned background technique The problem of.
To achieve the above object, the invention provides the following technical scheme:
A kind of building main body, including column are fixedly installed with suspension cable on the column, and the suspension cable bottom is fixedly installed with Frame, the frame lower end are equipped with floor, and the floor is connected by hoist cable with frame.
As further technical solution of the present invention: the column includes the first cylinder and the second cylinder, second column Body is fixedly connected by stablizing beam with the first cylinder, and first cylinder and the second cylinder bottom are fixedly installed with pedestal, the One cylinder and the second cylinder upper end are fixedly installed with column cap, and first for installing suspension cable is fixedly installed on the column cap HiAm anchorage, the frame upper end are fixedly installed with the second HiAm anchorage for installing suspension cable, and the base of frame is fixedly mounted There is the third HiAm anchorage for installing hoist cable.
As further technical solution of the invention: being equipped in first cylinder and walk terraced channel and access to elevators.
As further technical solution of the invention: being equipped with blast tube, cold/hot water passage, strong in second cylinder Electric channel and light current channel.
As further technical solution of the invention: being equipped with the fixed mechanism for installing hoist cable in the floor.
As further technical solution of the invention: the fixed mechanism includes mutually matched first clamp and second Clamp, first clamp and the second clamp offer the first mounting hole and mounting groove, first clamp and the second clamp It is also provided with the second mounting hole of coaxial arrangement.
A kind of construction method of building main body, comprising the following steps:
Step 1: making column 1, frame 3 and floor 5 respectively according to design size;
Step 2: hoist cable 4 is fixed on 3 bottom of frame, then frame 3 is connect by suspension cable 2 with column 1;
Step 3: floor 5 is fixedly mounted on the suitable position on hoist cable 4 to get building main body.
Compared with prior art, the beneficial effects of the present invention are: by production column, frame and floor, and frame is led to Cross suspension cable to be fixed on column, floor be then sequentially fixed at frame lower end by hoist cable, can different height simultaneously Construction, improves the construction speed of building main body, stable structure, work efficiency is high, and overcoming existing building can only be from bottom one The drawbacks of one layer of construction of layer.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of building main body;
Fig. 2 is the main view of building main body;
Fig. 3 is the main view of building main body central post;
Fig. 4 is the top cross-sectional view of building main body central post;
Fig. 5 is the main view of frame in building main body;
Fig. 6 is the top view of frame in building main body;
Fig. 7 is the left view of frame in building main body;
Fig. 8 is the main view of fixed mechanism in building main body;
Fig. 9 is the bottom view of fixed mechanism in building main body;
Figure 10 is the left view of the second clamp in building main body.
In figure: 1- column, 2- suspension cable, 3- frame, 4- hoist cable, 5- floor, the first cylinder of 6-, the second cylinder of 7-, 8- are steady Determining beam, 9- pedestal, 10- column cap, the first HiAm anchorage of 11-, 12-, to walk terraced channel, 13- access to elevators, 14- blast tube, 15- cold and hot Aquaporin, 16- forceful electric power channel, 17- light current channel, the second HiAm anchorage of 18-, 19- third HiAm anchorage, the first clamp of 20-, 21- Two clamps, the first mounting hole of 22-, 23- mounting groove, the second mounting hole of 24-.
Specific embodiment
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside", " up time The orientation or positional relationship of the instructions such as needle ", " counterclockwise ", " axial direction ", " radial direction ", " circumferential direction " be orientation based on the figure or Positional relationship is merely for convenience of description of the present invention and simplification of the description, rather than the device or element of indication or suggestion meaning must There must be specific orientation, be constructed and operated in a specific orientation, therefore be not considered as limiting the invention.
In addition, term " first ", " second " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance Or implicitly indicate the quantity of indicated technical characteristic.Define " first " as a result, the feature of " second " can be expressed or Implicitly include one or more of the features.In the description of the present invention, the meaning of " plurality " is two or more, Unless otherwise specifically defined.
In the present invention unless specifically defined or limited otherwise, term " installation ", " connected ", " connection ", " fixation " etc. Term shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral;It can be mechanical connect It connects, is also possible to be electrically connected;It can be directly connected, can also can be in two elements indirectly connected through an intermediary The interaction relationship of the connection in portion or two elements.It for the ordinary skill in the art, can be according to specific feelings Condition understands the concrete meaning of above-mentioned term in the present invention.
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description.
Embodiment 1
Building main body as shown in figs. 1-7, including column 1 are fixedly installed with suspension cable 2, the suspension cable 2 on the column 1 Bottom is fixedly installed with frame 3, and 3 lower end of frame is equipped with floor 5, and the floor 5 is connected by hoist cable 4 with frame 3, by It is stereochemical structure in building main body, 1 quantity of column to setting four, when construction is fixed on ground, makes it by making frame 3 It is connected and fixed by suspension cable 2 and column 1, cooperates corresponding suspension cable 2 can be from column 1 not by the way that multiple frames 3 are arranged Built with position, then connect with hoist cable 4 by floor 5 and be fabricated to unacceptable floor, when building can and meanwhile from Different floors open up construction, improve the construction speed of building main body.
Specifically, the column 1 includes the first cylinder 6 and the second cylinder 7, second cylinder 7 is by stablizing beam 8 and the One cylinder 6 is fixedly connected, and first cylinder 6 and 7 bottom of the second cylinder are fixedly installed with pedestal 9, is made by the way that pedestal 9 is arranged It is more stable in ground, ensure that the eager to do well in everything degree of the stability of building main structure;7 upper end of first cylinder 6 and the second cylinder It is fixedly installed with column cap 10, the first HiAm anchorage 11 for installing suspension cable 2, HiAm anchorage are fixedly installed on the column cap 10 Technology is the prior art, and when production can install HiAm anchorage fixed plate additional on column cap 10 and casing completion is connected and fixed;The frame 3 upper end of frame is fixedly installed with the second HiAm anchorage 18 for installing suspension cable 2, and 3 bottom of frame is fixedly installed with for pacifying The third HiAm anchorage 19 for filling hoist cable 4, it is convenient to suspension cable by the way that the second HiAm anchorage 18 and third HiAm anchorage 19 are arranged on the frame 3 2 and hoist cable 4 be attached fixation.
Further, current for convenience of construction personnel when building, it is equipped in first cylinder 6 and walks terraced channel 12 and electricity Terraced channel 13 is respectively used to construction step ladder and elevator;Further, for convenience of practical water, electricity and gas, in second cylinder 7 Equipped with blast tube 14, cold/hot water passage 15, forceful electric power channel 16 and light current channel 17, for carrying out the installation of water, electricity and gas.
A kind of construction method of building main body, comprising the following steps:
Step 1: making column 1, frame 3 and floor 5 respectively according to design size;
Step 2: hoist cable 4 is fixed on 3 bottom of frame, then frame 3 is connect by suspension cable 2 with column 1;
Step 3: floor 5 is fixedly mounted on the suitable position on hoist cable 4 to get building main body.
Embodiment 2
Further progress optimizes the present embodiment on the basis of embodiment 1, and as seen in figs. 8-10, installation is useful in the floor 5 In the fixed mechanism of installation hoist cable 4, installation hoist cable 4 is carried out for convenience, the fixed mechanism includes mutually matched first clamp 20 and second clamp 21, first clamp 20 and the second clamp 21 offer the first mounting hole 22 and mounting groove 23, pass through Two mounting grooves 23 cooperation on first clamp 20 and the second clamp 21 is fixed by hoist cable 4, is specially slidably arranged in floor 5 It is interior, it is fixed by 22 fitted bolt of the first mounting hole, further, to guarantee that the first clamp 20 and the second clamp 21 can incite somebody to action 4 fixing-stable of hoist cable is also provided with the second mounting hole 24 of coaxial arrangement in first clamp 20 and the second clamp 21, passes through Second mounting hole 24 is set, when installation after hoist cable 4 is by mounting groove 23, cooperates the second mounting hole 24 by the first folder by bolt Body 20 and the locking of the second clamp 21, so that floor 5 is fixed on hoist cable 4.
A kind of construction method of building main body, comprising the following steps:
Step 1: making column 1, frame 3 and floor 5 respectively according to design size;
Step 2: hoist cable 4 is fixed on 3 bottom of frame, then frame 3 is connect by suspension cable 2 with column 1;
Step 3: hoist cable 4 is passed through the fixed mechanism in floor 5, and floor 5 is fixedly mounted on by hoist cable 4 by fixed mechanism On suitable position to get building main body.
Column 1, frame 3 and floor 5 in above-described embodiment can be poured or be used lightweight material by armored concrete Prefabricated, suspension cable 2 and the use of hoist cable 4 existing commercial product are carried out in the case that intensity needs guaranteeing to meet.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (7)

1. a kind of building main body, including column (1), it is characterised in that: be fixedly installed with suspension cable (2), institute on the column (1) It states suspension cable (2) bottom to be fixedly installed with frame (3), frame (3) lower end is equipped with floor (5), and the floor (5) passes through Hoist cable (4) is connected with frame (3).
2. building main body according to claim 1, it is characterised in that: the column (1) includes the first cylinder (6) and second Cylinder (7), second cylinder (7) are fixedly connected by stablizing beam (8) with the first cylinder (6), first cylinder (6) and Two cylinders (7) bottom is fixedly installed with pedestal (9), and the first cylinder (6) and the second cylinder (7) upper end are fixedly installed with column cap (10), the first HiAm anchorage (11) for installing suspension cable (2) is fixedly installed on the column cap (10), on the frame (3) End is fixedly installed with the second HiAm anchorage (18) for installing suspension cable (2), and frame (3) bottom is fixedly installed with for pacifying Fill the third HiAm anchorage (19) of hoist cable (4).
3. building main body according to claim 2, it is characterised in that: be equipped in first cylinder (6) and walk terraced channel (12) and access to elevators (13).
4. building main body according to claim 2, it is characterised in that: be equipped with blast tube in second cylinder (7) (14), cold/hot water passage (15), forceful electric power channel (16) and light current channel (17).
5. building main body according to claim 1, it is characterised in that: be equipped in the floor (5) for installing hoist cable (4) fixed mechanism.
6. building main body according to claim 5, it is characterised in that: the fixed mechanism includes mutually matched first folder Body (20) and the second clamp (21), first clamp (20) and the second clamp (21) offer the first mounting hole (22) and peace Tankage (23), first clamp (20) and the second clamp (21) are also provided with the second mounting hole (24) of coaxial arrangement.
7. it is a kind of according to claim 1-6 it is any as described in building main body construction method, which is characterized in that including following step It is rapid:
Step 1: making column (1), frame (3) and floor (5) respectively according to design size;
Step 2: hoist cable (4) is fixed on frame (3) bottom, then frame (3) are connected by suspension cable (2) and column (1) It connects;
Step 3: floor (5) is fixedly mounted on the suitable position on hoist cable (4) to get building main body.
CN201910454712.3A 2019-05-29 2019-05-29 A kind of building main body and its construction method Pending CN110145018A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910454712.3A CN110145018A (en) 2019-05-29 2019-05-29 A kind of building main body and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910454712.3A CN110145018A (en) 2019-05-29 2019-05-29 A kind of building main body and its construction method

Publications (1)

Publication Number Publication Date
CN110145018A true CN110145018A (en) 2019-08-20

Family

ID=67593654

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910454712.3A Pending CN110145018A (en) 2019-05-29 2019-05-29 A kind of building main body and its construction method

Country Status (1)

Country Link
CN (1) CN110145018A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112982669A (en) * 2021-02-09 2021-06-18 清华大学建筑设计研究院有限公司 Eccentric annular large-cantilever prestressed steel structural system and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112982669A (en) * 2021-02-09 2021-06-18 清华大学建筑设计研究院有限公司 Eccentric annular large-cantilever prestressed steel structural system and construction method thereof
CN112982669B (en) * 2021-02-09 2022-09-16 清华大学建筑设计研究院有限公司 Eccentric annular large-cantilever prestressed steel structural system and construction method thereof

Similar Documents

Publication Publication Date Title
RU2459058C2 (en) Rail system of self-rising formwork equipped with elements of lifting rails extension
CN107090932B (en) Construction method of large-span thin-wall plane arch truss based on stiff ring beam
CN205777723U (en) Bicycle access and connection robot
CN103362317B (en) Story adding and stair adding structure of existing masonry building, and construction method thereof
CN107366356A (en) Assembled architecture agent structure
CN101914947A (en) Novel frame-core tube combination structure system for high-rise
CN110145018A (en) A kind of building main body and its construction method
CN108868161B (en) Staggered construction method for external attachment landing type tower crane of super high-rise building structure
CN103075016B (en) Installing method of extendable latticed shell structure
CN102454218A (en) Tube-in-tube structure for reinforced concrete core tubes and integrally-assembled space steel grids
CN109235773B (en) Lattice type anti-seismic steel pipe column applied to large-span truss and construction method thereof
CN108104260B (en) Construction method of cantilever component of fabricated building
CN113089950A (en) High-strength prefabricated staircase and hoisting installation method thereof
CN109113306A (en) A kind of modularization elevator shaft and its construction method
CN210562580U (en) Building main body
CN201778389U (en) Super-tall novel framework-core drum mixed structural system
CN113738122B (en) Mounting method of circular silo steel structure
CN206529892U (en) A kind of architectural structure system applied to high-level structure
CN205369905U (en) Improved generation chimney template structure
CN214785468U (en) High-strength prefabricated staircase
CN211850018U (en) Middle and high-rise concrete building structure system
CN112431305B (en) Assembly type building frame and quick connection method thereof
CN211597546U (en) Area is waited terraced room integration steel construction well
CN208763390U (en) A kind of suspended operating platform
CN108457376B (en) Cylinder modular building embedded construction structure and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190820