CN110144974B - 一种固定埋入式止水带的施工方法及其结构 - Google Patents
一种固定埋入式止水带的施工方法及其结构 Download PDFInfo
- Publication number
- CN110144974B CN110144974B CN201910537054.4A CN201910537054A CN110144974B CN 110144974 B CN110144974 B CN 110144974B CN 201910537054 A CN201910537054 A CN 201910537054A CN 110144974 B CN110144974 B CN 110144974B
- Authority
- CN
- China
- Prior art keywords
- positioning
- water stop
- steel bars
- installing
- right trapezoid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 57
- 238000010276 construction Methods 0.000 title claims abstract description 16
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 36
- 239000010959 steel Substances 0.000 claims abstract description 36
- 238000009434 installation Methods 0.000 claims abstract description 12
- 238000005452 bending Methods 0.000 claims abstract description 7
- 238000004519 manufacturing process Methods 0.000 claims abstract description 5
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims description 3
- 238000000034 method Methods 0.000 claims description 2
- 230000002349 favourable effect Effects 0.000 abstract description 6
- 230000003014 reinforcing effect Effects 0.000 abstract description 5
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- 125000006850 spacer group Chemical group 0.000 description 3
- 238000006073 displacement reaction Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 238000004140 cleaning Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Lining And Supports For Tunnels (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
本发明公开了一种固定埋入式止水带的施工方法及其结构,包括制作定位结构,定位结构包括两个对称设置且采用钢筋弯制形成的定位钢筋,定位钢筋包括两个等高的直角梯形,两个直角梯形的斜边平行,两个直角梯形的斜边之间形成用于安装止水带的限位孔;在伸缩缝两侧做出定位线,确定定位钢筋与止水带的安装位置;将多个定位结构沿着伸缩缝的长度方向并按照定位线安装,并使定位钢筋与伸缩缝两侧的主体钢筋连接;将止水带安装在限位孔内。本发明的有益效果是:本方案利用定位钢筋能够提高止水带的定位精度以及位置精度,有利于提高结构的防水性能,定位钢筋的结构简单,容易制造,有利于提高施工效率,止水带的安装十分简单,有利于提高施工效率。
Description
技术领域
本发明涉及止水带技术领域,具体是一种固定埋入式止水带的施工方法及其结构。
背景技术
由于橡胶止水带安装时存在定位不准确或者混凝土浇筑过程中发生位移或者变形等问题,使得橡胶止水带的安装难以达到设计及规范要求,从而导致变形缝容易出现漏水的现象,变形缝处漏水将引起综合管廊泡水等现象,甚至加速舱内设备的损害,致使综合管廊不能正常运行。
发明内容
为克服现有技术的不足,本发明提供了一种固定埋入式止水带的施工方法及其结构,用于提高止水带的定位安装精度,避免漏水。
本发明解决上述问题所采用的技术方案是:一种固定埋入式止水带的施工方法及其结构,包括以下几个步骤:
步骤S1:制作定位结构,定位结构包括两个对称设置且采用钢筋弯制形成的定位钢筋,定位钢筋包括两个等高的直角梯形,两个直角梯形的斜边平行,两个直角梯形的斜边之间形成用于安装止水带的限位孔;
步骤S2:在伸缩缝两侧做出定位线,确定定位钢筋与止水带的安装位置;
步骤S3:将多个定位结构沿着伸缩缝的长度方向并按照定位线安装,并使定位钢筋与伸缩缝两侧的主体钢筋连接;
步骤S4:将止水带安装在限位孔内。
进一步地,为了更好的实现本发明,所述的斜边与直角梯形下底的夹角在60°~75°之间。
进一步地,为了更好的实现本发明,还包括:
步骤S5:在止水带顶部安装顶层钢筋,在止水带端部使用端部模板与止水带贴紧并固定牢固;
步骤S6:浇筑混凝土。
一种固定埋入式止水带的结构,包括若干个沿着止水带长度方向设置的定位结构和安装在定位结构内的止水带,所述的定位结构包括两个对称设置且采用钢筋弯制形成的定位钢筋,所述的定位钢筋包括两个等高且斜边平行的直角梯形。
进一步地,为了更好的实现本发明,所述的斜边与直角梯形下底的夹角在60°~75°之间。
本方案所取得的有益效果是:
本方案利用定位钢筋能够提高止水带的定位精度以及位置精度,有利于提高结构的防水性能,定位钢筋的结构简单,容易制造,有利于提高施工效率,止水带的安装十分简单,有利于提高施工效率。
附图说明
图1为止水带的安装示意图;
图2为定位钢筋的结构示意图。
其中:1-定位钢筋,2-止水带,3-端部模板。
具体实施方式
下面结合实施例及附图,对本发明作进一步的详细说明,但本发明的实施方式不限于此。
实施例1:
本实施例中,一种固定埋入式止水带的结构,包括若干个沿着止水带2长度方向设置的定位结构和安装在定位结构内的止水带2,其通过以下步骤完成施工:
步骤S1:如图2所示,定位结构包括两个对称设置的定位钢筋1,定位钢筋1采用钢筋弯制形成,定位钢筋1包括两个等高的直角梯形,两个直角梯形的斜边平行,两个直角梯形的斜边之间形成用于安装止水带2的限位孔,弯制工作采用弯曲机即可完成,本实施例中,所述的定位钢筋1采用φ8的钢筋制作,使弯制后的定位钢筋1整体呈矩形,有利于定位钢筋1本身的定位、安装,由于φ8的钢筋制作,定位钢筋1的制作也很简单、方便,有利于提高施工效率。
步骤S2:在伸缩缝两侧做出定位线,确定定位钢筋1与止水带2的安装位置;
步骤S3:将多个定位结构沿着伸缩缝的长度方向并按照定位线安装,并使定位钢筋1与伸缩缝两侧的主体钢筋连接,本实施例中,采用绑扎的方式将定位钢筋1与伸缩缝两侧的主体钢筋连接,需要绑扎牢固,避免松动;
步骤S4:如图1所示,将止水带2安装在限位孔内,使止水带2从伸缩缝端部依次穿过每一个定位钢筋1的限位孔,使止水带2的中间空心圆孔位于定位钢筋1的对称面所在位置。定位钢筋1上两个直角梯形的连接处能够对止水带2起到限位的作用,避免止水带2超出定位钢筋1的范围,以此提高止水带2的定位精度。
使两个斜边的间距小于止水带2的厚度,还能够利用两个斜边对止水带2起到夹紧的作用。也能够在安装之前使两个斜边的间距大于止水带2的厚度,而方便止水带2移动、安装,在止水带2定位之后,通过调整两个斜边的间距来夹紧止水带2。以此能够省去其他结构对止水带2进行装夹,能够避免止水带2倍穿破而存在漏水风险,通过对止水带2进行夹持,能够提高其稳定性,避免浇注混凝土时,止水带2受到混凝土的冲击发生位移而存在漏水的风险。本实施例中,使斜边与直角梯形下底的夹角在60°~75°之间。以此能够满足止水带2在安装时需要向上倾斜15°~30°的施工要求,具体的夹角根据设计要求进行选择。
步骤S5:在止水带2顶部安装顶层钢筋,验收完成后,在止水带2端部使用端部模板3与止水带2贴紧并固定牢固,以此在混凝土浇筑时,起到防止止水带2漏浆、胀模、移位的效果;
步骤S6:浇筑混凝土,在止水带2一端的混凝土浇筑完成后,拆除该端的端部模板3,将未浇筑的部分橡胶止水带清理干净,按照设计要求安装嵌缝材料,再进行另一端的施工。
本实施例中,其它未描述的内容与上述实施例相同,故不赘述。
以上所述的,仅是本发明的较佳实施例而已,并非对本发明作任何形式上的限制,依据本发明的技术实质,在本发明的精神和原则之内,对以上实施例所作的任何简单的修改、等同替换与改进等,均仍属于本发明技术方案的保护范围之内。
Claims (1)
1.一种固定埋入式止水带的施工方法,其特征在于:基于一种固定埋入式止水带的结构,包括以下几个步骤:
步骤S1:制作定位结构,定位结构包括两个对称设置且采用钢筋弯制形成的定位钢筋,定位钢筋包括两个等高的直角梯形,两个直角梯形的斜边平行,两个直角梯形的斜边之间形成用于安装止水带的限位孔;
步骤S2:在伸缩缝两侧做出定位线,确定定位钢筋与止水带的安装位置;
步骤S3:将多个定位结构沿着伸缩缝的长度方向并按照定位线安装,并使定位钢筋与伸缩缝两侧的主体钢筋连接;
步骤S4:将止水带安装在限位孔内;
所述的斜边与直角梯形下底的夹角在60°~75°之间;
还包括:
步骤S5:在止水带顶部安装顶层钢筋,在止水带端部使用端部模板与止水带贴紧并固定牢固;
步骤S6:浇筑混凝土;
所述固定埋入式止水带的结构包括若干个沿着止水带长度方向设置的定位结构和安装在定位结构内的止水带。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910537054.4A CN110144974B (zh) | 2019-06-20 | 2019-06-20 | 一种固定埋入式止水带的施工方法及其结构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910537054.4A CN110144974B (zh) | 2019-06-20 | 2019-06-20 | 一种固定埋入式止水带的施工方法及其结构 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110144974A CN110144974A (zh) | 2019-08-20 |
CN110144974B true CN110144974B (zh) | 2023-12-26 |
Family
ID=67596011
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910537054.4A Active CN110144974B (zh) | 2019-06-20 | 2019-06-20 | 一种固定埋入式止水带的施工方法及其结构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110144974B (zh) |
Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DD237343A1 (de) * | 1985-05-16 | 1986-07-09 | Zbo Dreilaendereck Olbersdorf | Wasserdichte dehnungsfuge fuer bauwerke aus betonfertigteilen |
GB8929299D0 (en) * | 1988-12-29 | 1990-02-28 | Asahi Denka Kogyo Kk | Expansion joint for concrete structures |
DE4242471A1 (de) * | 1992-07-24 | 1994-06-23 | Herbert Reichart | Elementschalung zur Herstellung von wasserdichten Arbeits- und Dehnfugen im Beton- und Stahlbetonbau |
JP2004098628A (ja) * | 2002-09-12 | 2004-04-02 | Abe Concrete Kk | コンクリートブロックの製造方法 |
KR20040095980A (ko) * | 2003-04-29 | 2004-11-16 | 일 김 | 맨홀의 보강 구조물 |
DE102006053186A1 (de) * | 2006-11-09 | 2008-05-15 | Hochtief Construction Ag | Verfahren zur Abdichtung eines Tunnels und Tunnelabdichtung |
KR20090116342A (ko) * | 2008-05-07 | 2009-11-11 | 이정락 | 콘크리트토류벽용 트러스패널 과 이를 이용한 콘크리트흙막이벽 시공방법 |
AU2010201761A1 (en) * | 2009-05-07 | 2010-11-25 | Smyth, Clayton Mr | Wall panel and installation thereof |
KR101312873B1 (ko) * | 2012-05-17 | 2013-09-30 | 김창환 | 벽체 시공을 위한 수도관 지지 장치 |
CN103469973A (zh) * | 2013-09-24 | 2013-12-25 | 扬州大学 | 一种平缝型、可卸式屋面变形缝及其构造方法 |
CN104099942A (zh) * | 2013-04-09 | 2014-10-15 | 上海市政工程设计研究总院(集团)有限公司 | 一种地下钢筋混凝土箱涵结构临时封堵墙施工方法 |
CN104314104A (zh) * | 2014-09-30 | 2015-01-28 | 上海市政工程设计研究总院(集团)有限公司 | 一种与地下箱涵斜交的变形缝设置方法 |
CN205557856U (zh) * | 2016-04-28 | 2016-09-07 | 中国化学工程第三建设有限公司 | 建筑物伸缩缝防渗漏结构 |
CN107059938A (zh) * | 2017-07-04 | 2017-08-18 | 中铁上海设计院集团有限公司 | 一种用于地道变形缝处止水的补强结构及其施工方法 |
CN107326940A (zh) * | 2017-09-01 | 2017-11-07 | 广州番禺职业技术学院 | 一种地下室超前止水后浇带结构及其施工方法 |
CN108360574A (zh) * | 2018-01-23 | 2018-08-03 | 济南城建集团有限公司 | 整体浇筑式管廊施工止水部件加固方法 |
CN108360550A (zh) * | 2018-02-28 | 2018-08-03 | 五冶集团上海有限公司 | 一种钢结构直埋地脚螺栓施工方法 |
CN211498965U (zh) * | 2019-06-20 | 2020-09-15 | 中国五冶集团有限公司 | 一种固定埋入式止水带的结构 |
-
2019
- 2019-06-20 CN CN201910537054.4A patent/CN110144974B/zh active Active
Patent Citations (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DD237343A1 (de) * | 1985-05-16 | 1986-07-09 | Zbo Dreilaendereck Olbersdorf | Wasserdichte dehnungsfuge fuer bauwerke aus betonfertigteilen |
GB8929299D0 (en) * | 1988-12-29 | 1990-02-28 | Asahi Denka Kogyo Kk | Expansion joint for concrete structures |
DE4242471A1 (de) * | 1992-07-24 | 1994-06-23 | Herbert Reichart | Elementschalung zur Herstellung von wasserdichten Arbeits- und Dehnfugen im Beton- und Stahlbetonbau |
JP2004098628A (ja) * | 2002-09-12 | 2004-04-02 | Abe Concrete Kk | コンクリートブロックの製造方法 |
KR20040095980A (ko) * | 2003-04-29 | 2004-11-16 | 일 김 | 맨홀의 보강 구조물 |
DE102006053186A1 (de) * | 2006-11-09 | 2008-05-15 | Hochtief Construction Ag | Verfahren zur Abdichtung eines Tunnels und Tunnelabdichtung |
KR20090116342A (ko) * | 2008-05-07 | 2009-11-11 | 이정락 | 콘크리트토류벽용 트러스패널 과 이를 이용한 콘크리트흙막이벽 시공방법 |
AU2010201761A1 (en) * | 2009-05-07 | 2010-11-25 | Smyth, Clayton Mr | Wall panel and installation thereof |
KR101312873B1 (ko) * | 2012-05-17 | 2013-09-30 | 김창환 | 벽체 시공을 위한 수도관 지지 장치 |
CN104099942A (zh) * | 2013-04-09 | 2014-10-15 | 上海市政工程设计研究总院(集团)有限公司 | 一种地下钢筋混凝土箱涵结构临时封堵墙施工方法 |
CN103469973A (zh) * | 2013-09-24 | 2013-12-25 | 扬州大学 | 一种平缝型、可卸式屋面变形缝及其构造方法 |
CN104314104A (zh) * | 2014-09-30 | 2015-01-28 | 上海市政工程设计研究总院(集团)有限公司 | 一种与地下箱涵斜交的变形缝设置方法 |
CN205557856U (zh) * | 2016-04-28 | 2016-09-07 | 中国化学工程第三建设有限公司 | 建筑物伸缩缝防渗漏结构 |
CN107059938A (zh) * | 2017-07-04 | 2017-08-18 | 中铁上海设计院集团有限公司 | 一种用于地道变形缝处止水的补强结构及其施工方法 |
CN107326940A (zh) * | 2017-09-01 | 2017-11-07 | 广州番禺职业技术学院 | 一种地下室超前止水后浇带结构及其施工方法 |
CN108360574A (zh) * | 2018-01-23 | 2018-08-03 | 济南城建集团有限公司 | 整体浇筑式管廊施工止水部件加固方法 |
CN108360550A (zh) * | 2018-02-28 | 2018-08-03 | 五冶集团上海有限公司 | 一种钢结构直埋地脚螺栓施工方法 |
CN211498965U (zh) * | 2019-06-20 | 2020-09-15 | 中国五冶集团有限公司 | 一种固定埋入式止水带的结构 |
Non-Patent Citations (1)
Title |
---|
伸缩缝止水带断裂原因及处理;李爱军;;科技致富向导(第15期);全文 * |
Also Published As
Publication number | Publication date |
---|---|
CN110144974A (zh) | 2019-08-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101649609B (zh) | 一种埋设固定水平止浆带的方法 | |
CN112942812A (zh) | 剪力墙模板的定位装置及利用该装置安装模板的方法 | |
CN110144974B (zh) | 一种固定埋入式止水带的施工方法及其结构 | |
CN211498965U (zh) | 一种固定埋入式止水带的结构 | |
CN115749250A (zh) | 一种直墙圆拱现浇结构模板及其安装方法 | |
CN208105909U (zh) | 预埋槽道的安装定位装置 | |
CN109779241B (zh) | 一种多功能墙体模板根部定位系统及其施工方法 | |
CN104929295A (zh) | 一种用于双曲率弧形屋面的无缝钢管施工方法 | |
CN108858740B (zh) | 预制梁负弯矩张拉槽的施工方法 | |
CN206554288U (zh) | 一种止水带定位装置 | |
CN106284683B (zh) | 一种预埋在框架结构与填充墙之间的连体焊件 | |
CN103422515A (zh) | 一种止水带及其定位方法 | |
CN109723141B (zh) | 一种装配式结构转换层处支撑结构及其施工方法 | |
CN204645616U (zh) | 侧墙钢边橡胶止水带固定模具 | |
CN108691419B (zh) | 一种混凝土楼板平整度控制工具 | |
CN109025277B (zh) | 副框及其预埋结构和方法 | |
CN216379866U (zh) | 一种砼排水沟伸缩缝泡沫板固定装置 | |
CN108004986B (zh) | 隧道防撞墙模板加固体系及施工方法 | |
CN219864170U (zh) | 一种独立基础预埋地脚螺栓定位装置 | |
CN215926441U (zh) | 一种套管定位装置 | |
CN204552084U (zh) | 一种混凝土施工缝的模板结构 | |
CN216042638U (zh) | 一种免支架楼层放线洞支模装置 | |
CN212295641U (zh) | 一种可调式柱模板装置 | |
CN221345895U (zh) | 一种建筑用隔震支座预埋螺栓定位装置 | |
CN209907976U (zh) | 墙体预埋件固定施工模具 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |