CN110080345A - A kind of head-tank structure - Google Patents

A kind of head-tank structure Download PDF

Info

Publication number
CN110080345A
CN110080345A CN201910452028.1A CN201910452028A CN110080345A CN 110080345 A CN110080345 A CN 110080345A CN 201910452028 A CN201910452028 A CN 201910452028A CN 110080345 A CN110080345 A CN 110080345A
Authority
CN
China
Prior art keywords
pond
head
water
setting pot
blow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910452028.1A
Other languages
Chinese (zh)
Inventor
鲍伟
郑雪玉
杜帅群
黄叶飘
吴银刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201910452028.1A priority Critical patent/CN110080345A/en
Publication of CN110080345A publication Critical patent/CN110080345A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • E02B9/02Water-ways
    • E02B9/04Free-flow canals or flumes; Intakes
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B11/00Arrangements or adaptations of tanks for water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a kind of head-tank structure, including pond, the pond is single overall structure, alternatively, being at least 2 by quantity and the sink unit to work independently is constituted;It is equipped with cover board at the top in pond, is equipped with water inlet pipe in the side of pond side, the opposite other side is equipped with outlet pipe;It is equipped with setting pot and training wall in the inside in pond, the training wall is equipped with pillar, and the setting pot is equipped with blow-down pipe.Using technical solution of the present invention, it can effectively ensure that water body is clean in head-tank, while water flow is smooth in pond, fluidised form is preferable, and easy for construction, structure safety.Suitable for the wide popularization and application in hydraulic engineering field.Moreover, each sink unit can work independently when pond is made of multiple sink units, emptying, can in time individually be overhauled structure in some pond respectively, not influence water supply when maintenance, easy for construction, structure safety.Suitable for the wide popularization and application in hydraulic engineering field.

Description

A kind of head-tank structure
Technical field
The present invention relates to a kind of head-tank structure, belong to diversion hydrotechny field in hydraulic engineering.
Background technique
It is reasonable utilized head as head-tank set in hydraulic engineering, guarantees head-tank to each water supply Point Some routes are water delivery by gravity flow, reduce pipeline investment and water lift expense, and need to make rational planning for head-tank structure, keep pond Interior fluid stable, clean water quality, while head-tank should be made to have maintenance function, to be overhauled when something goes wrong.Mesh Preceding head-tank structure, is generally only arranged single pond, needs to overhaul if structure goes wrong, and interrupts intake-outlet water flow, stops It only supplies water, is vented pond, influences downstream water supply.
Summary of the invention
To overcome the shortcomings of the prior art, goes out the object of the present invention is to provide a kind of non-pressure tunnel and flow or have inspection Repair more gate head-tank structures of function.
To achieve the above object, the invention provides the following technical scheme:
A kind of head-tank structure, including pond, the pond is single overall structure, alternatively, being at least 2 by quantity And the sink unit to work independently is constituted;It is equipped with cover board at the top in pond, is equipped with water inlet pipe in the side of pond side, relatively The other side be equipped with outlet pipe;It is equipped with setting pot and training wall in the inside in pond, the training wall is equipped with pillar, described heavy Sand pond is equipped with blow-down pipe.
Further, the water inlet pipe number is corresponding with the number of pond or sink unit.
Further, manhole and ventilation hole are also set up on the cover board, the manhole is entered in pond by ladder Portion.
Further, the base plate vicinity of setting pot is arranged in the blow-down pipe, and setting pot and blow-down pipe number are at least each Pond or each sink unit are arranged one.
Beneficial effects of the present invention:
Using technical solution of the present invention, it can effectively ensure that water body is clean in head-tank, while water flow is smooth in pond, Fluidised form is preferable, and easy for construction, structure safety.Suitable for the wide popularization and application in hydraulic engineering field.Moreover, when pond is by more A sink unit constitute when, each sink unit can work independently, respectively emptying, can in time individually to structure in some pond into Row maintenance does not influence water supply when maintenance, easy for construction, structure safety.Suitable for the wide popularization and application in hydraulic engineering field.
Detailed description of the invention
Fig. 1 is the structural plan figure of embodiment 1;
Fig. 2 is the A-A cross-sectional view of the structure in Fig. 1;
Fig. 3 is the B-B cross-sectional view of the structure in Fig. 1;
Fig. 4 is the C-C cross-sectional view of the structure in Fig. 1.
Fig. 5 is the structural plan figure of embodiment 2;
Fig. 6 is the A-A cross-sectional view of the structure in Fig. 5;
Fig. 7 is the B-B cross-sectional view of the structure in Fig. 5;
Fig. 8 is the C-C cross-sectional view of the structure in Fig. 5.
1 description of symbols of embodiment: the pond 1-, 2- cover board, 3- water inlet pipe, 4- setting pot, 5- training wall, 6- pillar, 7- water outlet, 8- blow-down pipe, 11- manhole, 12- ventilation hole, 13- ladder, 71- check gate, 72- gate pier, 73- tunnel.
2 description of symbols of embodiment: the pond 1-, 2- cover board, 3- water inlet pipe, 4- setting pot, 5- training wall, 6- pillar, 7- water outlet, 8- blow-down pipe, 11- manhole, 12- ventilation hole, 13- ladder, 71- check gate, 72- non-pressure tunnel.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation " " is set Be equipped with ", " be arranged/connect ", " connection " etc., shall be understood in a broad sense, such as " connection ", may be a fixed connection, be also possible to removable Connection is unloaded, or is integrally connected;It can be mechanical connection, be also possible to be electrically connected;It can be directly connected, it can also be in Between medium be indirectly connected, can be the connection inside two elements.It for the ordinary skill in the art, can be specific Situation understands the concrete meaning of above-mentioned term in the present invention.
Embodiment 1:
As Figure 1-Figure 4, a kind of more gate head-tank structures with maintenance function, including two sink unit structures At pond 1, cover board 2, water inlet pipe 3, setting pot 4, training wall 5, pillar 6, water outlet 7, blow-down pipe 3.Water inlet pipe 3 is used as water flow Water flow is introduced pond 1 by entrance, and cover board 2 can guarantee 1 water body of head-tank not by outside contamination, and training wall 5 is mainly used to return Water flow in pond 1 downstream, keeps outlet flow pattern preferable, and setting pot 4 is used to precipitate water flow and is mingled with silt, and it is miscellaneous to reduce 7 water flow of water outlet Matter, blow-down pipe 8 are used to the impurity for being vented pond 1 and being discharged in settling pit 4.
Sink unit is at least 2, and each sink unit can work independently and distinguish emptying.3 number of water inlet pipe and pond Unit is corresponding.Cover board 2 can effectively ensure that water body is not by outside contamination in pond 1, also set up manhole 11 thereon, manhole 11 can Realize the maintenance of structure in pond 1, ventilation hole 12, the manhole 11 is entered inside pond by ladder 13.Blow-down pipe 8 is arranged In the base plate vicinity of setting pot 4, meet the emptying of pond 1 and sediment outflow needs.Setting pot 4 is typically located at the small ground of flow rate of water flow Side, convenient for sediment deposition in water;Pond 1 first passes through setting pot 4 blow-down pipe 8 when overhauling is vented pond, is then overhauled, clearly Except desilting.Setting pot 4 and at least each sink unit of 8 number of blow-down pipe are arranged one.
Pillar 6 is arranged in 5 certain distance interval of training wall, fully ensures that the stable structure of training wall.In each sink unit It is respectively provided with training wall 5.Check gate 71 is set at water outlet 7, is controllable to downstream water supply amount.It is followed by tunnel 73, tunnel 73 can be with To there is pressure hole, or without pressure hole, 71 number of check gate is corresponding with sink unit, and gate pier is arranged between every two check gate 71 72。
Embodiment 2:
As viewed in figures 5-8, a kind of non-pressure tunnel goes out the head-tank structure flowed, including pond 1, cover board 2, water inlet pipe 3, heavy Sand pond 4, training wall 5, pillar 6, water outlet 7, blow-down pipe 3.Wherein, water flow is introduced pond 1 as flow inlet by water inlet pipe 3, Cover board 2 can guarantee head-tank water body not by outside contamination, and training wall 5 is mainly used to come over and pledge allegiance to the water flow in pond, makes to export Fluidised form is preferable, and setting pot 4, which is used to precipitate water flow, is mingled with silt, reduces water outlet water flow impurity, blow-down pipe 8 be used to be vented pond and The impurity in settling pit is discharged.
The settable one or more of water inlet pipe 3 can increase pond flow of inlet water when being arranged multiple, avoid structure from bearing high Internal water pressure, structure is simple, easy for construction.Cover board 2 can effectively ensure that water body is also set up thereon not by outside contamination in pond 1 Manhole 11, manhole 11 can realize the maintenance of structure in pond 1, ventilation hole 12, and the manhole 11 is entered by ladder 13 Inside pond.
The base plate vicinity of setting pot 4 is arranged in blow-down pipe 8, meets the emptying of pond 1 and sediment outflow needs.The general cloth of setting pot 4 The place small in flow rate of water flow is set, convenient for sediment deposition in water;Pond 1 first passes through setting pot discharge tube when overhauling, be vented pond, Then maintenance pond is carried out, desilting is removed.
Pillar 6 is arranged in 5 certain distance interval of training wall, fully ensures that the stable structure of training wall.Section is set at water outlet 7 Check 71 is controllable to downstream water supply amount, and check gate 71 is followed by non-pressure tunnel 72, makes to have pressure high flow rate water flow stationary to be transitioned into low Flow velocity pressure free current.
Although the present invention is described in detail referring to the foregoing embodiments, for those skilled in the art, It is still possible to modify the technical solutions described in the foregoing embodiments, or part of technical characteristic is carried out etc. With replacement, all within the spirits and principles of the present invention, any modification, equivalent replacement, improvement and so on should be included in this Within the protection scope of invention.

Claims (4)

1. a kind of head-tank structure, it is characterised in that: including pond (1), the pond (1) is single overall structure, alternatively, It is at least 2 by quantity and the sink unit to work independently is constituted;Cover board (2) are equipped at the top of pond (1), in pond (1) The side of side is equipped with water inlet pipe (3), and the opposite other side is equipped with outlet pipe (7);Setting pot is equipped in the inside of pond (1) (4) and training wall (5), the training wall (5) are equipped with pillar (6), and the setting pot (4) is equipped with blow-down pipe (8).
2. head-tank structure according to claim 1, it is characterised in that: water inlet pipe (3) number and pond (1) or The number of person's sink unit is corresponding.
3. head-tank structure according to claim 1, it is characterised in that: also set up manhole on the cover board (2) (11) and ventilation hole (12), the manhole (11) enter pond (1) inside by ladder (13).
4. head-tank structure according to claim 1, it is characterised in that: the blow-down pipe (8) is arranged in setting pot (4) Base plate vicinity, setting pot (4) and at least each pond (1) of blow-down pipe (8) number or each sink unit are arranged one.
CN201910452028.1A 2019-05-28 2019-05-28 A kind of head-tank structure Pending CN110080345A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910452028.1A CN110080345A (en) 2019-05-28 2019-05-28 A kind of head-tank structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910452028.1A CN110080345A (en) 2019-05-28 2019-05-28 A kind of head-tank structure

Publications (1)

Publication Number Publication Date
CN110080345A true CN110080345A (en) 2019-08-02

Family

ID=67422189

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910452028.1A Pending CN110080345A (en) 2019-05-28 2019-05-28 A kind of head-tank structure

Country Status (1)

Country Link
CN (1) CN110080345A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201943116U (en) * 2011-01-11 2011-08-24 蒋星学 Stainless steel water tank capable of overhauling without stopping water
CN202298761U (en) * 2011-08-10 2012-07-04 贵阳铝镁设计研究院有限公司 Pond grid allocation structure
US20140026965A1 (en) * 2012-07-30 2014-01-30 Pinnacle Companies, Inc. Fluid storage container and method
CN206052863U (en) * 2016-09-21 2017-03-29 三峡大学 A kind of mountain area cistern
CN207538118U (en) * 2017-11-29 2018-06-26 扬州大学 A kind of column training wall for improving lateral intake pumping plant fluidised form
CN210151827U (en) * 2019-05-28 2020-03-17 中国电建集团贵阳勘测设计研究院有限公司 High-level water pool structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201943116U (en) * 2011-01-11 2011-08-24 蒋星学 Stainless steel water tank capable of overhauling without stopping water
CN202298761U (en) * 2011-08-10 2012-07-04 贵阳铝镁设计研究院有限公司 Pond grid allocation structure
US20140026965A1 (en) * 2012-07-30 2014-01-30 Pinnacle Companies, Inc. Fluid storage container and method
CN206052863U (en) * 2016-09-21 2017-03-29 三峡大学 A kind of mountain area cistern
CN207538118U (en) * 2017-11-29 2018-06-26 扬州大学 A kind of column training wall for improving lateral intake pumping plant fluidised form
CN210151827U (en) * 2019-05-28 2020-03-17 中国电建集团贵阳勘测设计研究院有限公司 High-level water pool structure

Similar Documents

Publication Publication Date Title
CN108425341B (en) Stepped landscape retaining wall for ecological river channel and construction method thereof
CN205444399U (en) Cascaded drop well
CN106869245B (en) Suitable for Mountain Area high water level variation fully-loaded stream can submerged lift pumping station
CN203227334U (en) Secondary inclined-tube sedimentation tank
CN110080345A (en) A kind of head-tank structure
CN210151827U (en) High-level water pool structure
CN204571433U (en) Fluid erosion prevention sulfuric acid tank
CN107956249B (en) A method of improving municipal sewage Boosting pumping station Inlet flow pattern
CN207646698U (en) Training for sediment structure with suspended sediment collecting function
CN206418579U (en) A kind of integrated form coal sewage lifting pump station
CN105019414B (en) Composite lock chamber structure for narrow water intake of mountain hydropower project
CN214763502U (en) Multistage sedimentation device for blast furnace granulated slag system
CN212129072U (en) Submerged energy dissipation pool for water conservancy system tail end
CN205399343U (en) Reinforcement type waterproof and anti -seepage bank protection
CN210621642U (en) Drainage structure for high-speed flow area of stilling pool
CN100460602C (en) Sand discharging construction for diversion tunnel forebay
CN110747829B (en) Snail blocking wall and oncomelania settling pond for hydraulic and hydroelectric engineering
CN208517904U (en) A kind of hydraulic engineering drainage gate
CN206667363U (en) A kind of submergence type culvert water inlet structure
CN220633144U (en) Combined sand sedimentation tank structure
CN208726946U (en) Coal slime water purification installation
CN214436734U (en) Energy-saving sedimentation tank
CN215691890U (en) Silt-preventing and mud-discharging structure at bottom of distribution well
CN204996223U (en) Filter equipment suitable for hydraulic engineering
CN205995091U (en) A kind of uniform sedimentation basin

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190802