CN206052863U - A kind of mountain area cistern - Google Patents

A kind of mountain area cistern Download PDF

Info

Publication number
CN206052863U
CN206052863U CN201621068275.XU CN201621068275U CN206052863U CN 206052863 U CN206052863 U CN 206052863U CN 201621068275 U CN201621068275 U CN 201621068275U CN 206052863 U CN206052863 U CN 206052863U
Authority
CN
China
Prior art keywords
water
pool
domestic
water pool
production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621068275.XU
Other languages
Chinese (zh)
Inventor
高婷
张发
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Three Gorges University CTGU
Original Assignee
China Three Gorges University CTGU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges University CTGU filed Critical China Three Gorges University CTGU
Priority to CN201621068275.XU priority Critical patent/CN206052863U/en
Application granted granted Critical
Publication of CN206052863U publication Critical patent/CN206052863U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treatment Of Biological Wastes In General (AREA)

Abstract

一种山区蓄水池,包括沉淀池、生活用水池及生产用水池;所述沉淀池通过穿孔整流墙分成配水区和沉淀缓冲区,其中,配水区和沉淀缓冲区底部设有多个集泥斗和穿孔排泥管;所述生活用水池与沉淀池通过穿孔墙上的通孔连通,生活用水池上安装有生活用水池出水管和生活用水池放空管;所述生产用水池设置在生活用水池一侧,生产用水池上设有生产用水池出水管、溢流管及生产用水池放空管。本实用新型提供的一种山区蓄水池,通过设置沉淀池、生活用水池及生产用水池,可以贮存生活、生产用水,解决用水困难,提高用水水质,保证用水安全。

A kind of water storage pond in mountain area, including sedimentation pond, domestic water pond and production water pond; Said sedimentation pond is divided into water distribution area and sedimentation buffer zone through perforated rectification wall, wherein, the bottom of water distribution area and sedimentation buffer zone is provided with a plurality of mud Bucket and perforated mud discharge pipe; the domestic water pool is connected with the sedimentation tank through the through hole on the perforated wall, and the domestic water pool is equipped with a domestic water pool outlet pipe and a domestic water pool vent pipe; the production water pool is set in the living water pool On one side of the water pool, the production water pool is provided with a production water pool outlet pipe, an overflow pipe and a production water pool vent pipe. The utility model provides a water storage pool in mountainous areas, which can store domestic and production water by setting sedimentation tanks, domestic water pools and production water pools, solve water problems, improve water quality, and ensure water safety.

Description

一种山区蓄水池a mountain reservoir

技术领域technical field

本实用新型涉及蓄水池,尤其是一种用于山区的蓄水池。The utility model relates to a water storage pool, in particular to a water storage pool used in mountainous areas.

背景技术Background technique

由于山区缺乏供水设施,水源远等问题,山区居民生活生产用水十分困难,为了满足人畜饮水和生产用水,往往需要到很远的地方挑水。不仅用水难,用水的安全也难以保障。为解决山区用水难、用水安全的问题,国家推行小型水利设施建设,蓄水池就是其中之一。但是,一般蓄水池只是一个水池,十分简单,不能保障用水的水质,也无法分别用于生活和生产使用。Due to the lack of water supply facilities and remote water sources in mountainous areas, it is very difficult for mountainous residents to obtain water for living and production. In order to meet the drinking water and production water needs of humans and animals, they often need to carry water from far away places. Not only is it difficult to use water, but the safety of water is also difficult to guarantee. In order to solve the problems of water difficulty and water safety in mountainous areas, the country promotes the construction of small water conservancy facilities, and the reservoir is one of them. However, the general reservoir is just a pond, which is very simple, cannot guarantee the water quality of water, and cannot be used for living and production respectively.

发明内容Contents of the invention

本实用新型所要解决的技术问题是提供一种用于山区的蓄水池,能够解决当前山区用水难、以及蓄水池不分区的问题,提高水质、保证用水安全。The technical problem to be solved by the utility model is to provide a water storage tank used in mountainous areas, which can solve the problems of difficult water use in mountainous areas and non-divided storage tanks, improve water quality and ensure water safety.

为解决上述技术问题,本实用新型所采用的技术方案是:In order to solve the problems of the technologies described above, the technical solution adopted in the utility model is:

一种山区蓄水池,包括沉淀池、生活用水池及生产用水池;A mountain water storage pond, including a sedimentation pond, a domestic water pond and a production water pond;

所述沉淀池通过穿孔整流墙分成配水区和沉淀缓冲区,其中,配水区和沉淀缓冲区底部设有多个集泥斗和穿孔排泥管;The sedimentation tank is divided into a water distribution area and a sedimentation buffer zone through a perforated rectifying wall, wherein a plurality of mud collecting buckets and perforated mud discharge pipes are arranged at the bottom of the water distribution area and the sedimentation buffer area;

所述生活用水池与沉淀池通过穿孔墙上的通孔连通,生活用水池上安装有生活用水池出水管和生活用水池放空管;The domestic water pool is connected with the sedimentation tank through the through hole on the perforated wall, and the domestic water pool is equipped with a domestic water pool outlet pipe and a domestic water pool vent pipe;

所述生产用水池设置在生活用水池一侧,生产用水池上设有生产用水池出水管、溢流管及生产用水池放空管。The production water pool is arranged on one side of the domestic water pool, and the production water pool is provided with a water outlet pipe, an overflow pipe and an emptying pipe of the production water pool.

所述该蓄水池为封闭结构,封闭结构顶端设有带盖的井口和排气管。The reservoir is a closed structure, and the top of the closed structure is provided with a wellhead with a cover and an exhaust pipe.

所述沉淀区设有阻流板和斜板。The settling area is provided with baffles and inclined plates.

所述配水区一侧设有进水管,进水管上安装有分支管,分支管另一端与生活用水池连通。A water inlet pipe is arranged on one side of the water distribution area, and a branch pipe is installed on the water inlet pipe, and the other end of the branch pipe communicates with the domestic water pool.

所述穿孔整流墙下部设有多个配水孔。The lower part of the perforated rectifying wall is provided with a plurality of water distribution holes.

所述沉淀池、生活用水池及生产用水池的池底由下往上均由素土层、灰土层、碎石层、C10混凝土及C20混凝土建造;沉淀池、生活用水池及生产用水池的侧壁均采用C25混凝土建造;沉淀池、生活用水池及生产用水池的顶部采用C20混凝土建造。The bottom of the sedimentation tank, the domestic water pool and the production water pool are all constructed from plain soil layer, lime soil layer, crushed stone layer, C10 concrete and C20 concrete from bottom to top; The side walls are all made of C25 concrete; the tops of the sedimentation tank, domestic water pool and production water pool are made of C20 concrete.

所述生活用水池出水管上装有管式滤片消毒器。A tubular filter disc sterilizer is installed on the water outlet pipe of the domestic water pool.

本实用新型一种山区蓄水池,具有以下技术效果:通过设置沉淀池、生活用水池及生产用水池,在沉淀池外设置分别流经沉淀池和生活用水池的进水管,这样,在一般正常情况下,山上的泉水可通过引流的方式储存在生产用水池中,或溢流到生产用水池中,方便直接使用;当下雨天,接收到的雨水含污泥较多时,进水管经过 沉淀池进行沉淀,然后储存在生产用水池中,或溢流到生产用水池中。这样,相对于原来单个水池而言,可进行多次过滤,最终经消毒后供引用,这样提高用水水质,保证用水安全,且充分了利用水资源。The utility model is a water storage pond in a mountain area, which has the following technical effects: by setting a sedimentation pond, a domestic water pond and a production water pond, the water inlet pipes respectively flowing through the sedimentation pond and the domestic water pond are arranged outside the sedimentation pond. Under normal circumstances, the spring water on the mountain can be stored in the production water pool by drainage, or overflowed into the production water pool for direct use; on rainy days, when the received rainwater contains a lot of sludge, the water inlet pipe passes through the sedimentation tank Sedimentation is carried out and then stored in, or overflowed into, process water ponds. In this way, compared with the original single pool, it can be filtered multiple times, and finally sterilized for use, thus improving the water quality, ensuring water safety, and making full use of water resources.

附图说明Description of drawings

下面结合附图和实施例对本实用新型作进一步说明:Below in conjunction with accompanying drawing and embodiment the utility model is further described:

图1是实用新型的示意图。Fig. 1 is the schematic diagram of utility model.

图2为图1的A-A剖面图。FIG. 2 is a cross-sectional view along line A-A of FIG. 1 .

图3为图1的B-B剖面图。Fig. 3 is a B-B sectional view of Fig. 1 .

图4为图1的C-C剖面图。Fig. 4 is a C-C sectional view of Fig. 1 .

图中:进水管1,沉淀池2,穿孔墙3,配水区2-1,穿孔整流墙2-2,配水孔2-3,阻流板2-4,斜板2-5,通孔2-6,集泥斗2-7,穿孔排泥管2-8,沉淀缓冲区2-9,穿孔墙3,生活用水池4,生活用水池出水管5,生活用水池放空管6,生产用水池7,溢流管8,生产用水池放空管9,井口10,爬梯11,地基12,排气管13,生产用水池出水管14,管式滤片消毒器15,分支管16。In the figure: water inlet pipe 1, sedimentation tank 2, perforated wall 3, water distribution area 2-1, perforated rectification wall 2-2, water distribution hole 2-3, baffle plate 2-4, inclined plate 2-5, through hole 2 -6, mud collecting bucket 2-7, perforated mud discharge pipe 2-8, sedimentation buffer zone 2-9, perforated wall 3, domestic water pool 4, domestic water pool outlet pipe 5, domestic water pool vent pipe 6, production Water tank 7, overflow pipe 8, production tank emptying pipe 9, wellhead 10, ladder 11, foundation 12, exhaust pipe 13, production tank outlet pipe 14, tubular filter disc sterilizer 15, branch pipe 16.

具体实施方式detailed description

如图1所示:一种山区蓄水池包括沉淀池2、生活用水池4和生产用水池7As shown in Figure 1: a mountain reservoir includes a sedimentation tank 2, a domestic water tank 4 and a production water tank 7

如图3所示,山区水源的水通过进水管进入沉淀池2的配水区2-1,然后通过穿孔整流墙2-2下部的配水孔2-3进入沉淀缓冲区2-9,水流向上运动通过斜板2-5,水中的悬浮物沉淀下来,清水向上流动通过通孔2-6进入生活用水池4。沉淀池中的泥沙进入集泥斗2-7在重力的作用下通过穿孔排泥管2-8排出。配水区中的泥沙同样通过穿孔排泥管2-8排出。在穿孔墙22与斜板25底部装有阻流板24,防止水流短流,影响出水水质。斜板2-5上缘向沉淀池2进水端后倾安装。As shown in Figure 3, the water from the mountain water source enters the water distribution area 2-1 of the sedimentation tank 2 through the water inlet pipe, and then enters the sedimentation buffer zone 2-9 through the water distribution hole 2-3 at the bottom of the perforated rectifying wall 2-2, and the water flow moves upward Through the inclined plate 2-5, the suspended matter in the water settles down, and the clear water flows upwards and enters the domestic water pool 4 through the through hole 2-6. The silt in the settling tank enters the mud collecting bucket 2-7 and is discharged through the perforated mud discharge pipe 2-8 under the action of gravity. The silt in the water distribution area is discharged through the perforated mud discharge pipe 2-8 equally. A spoiler 24 is installed at the bottom of the perforated wall 22 and the slant plate 25 to prevent the short flow of the water flow and affect the water quality of the effluent. The upper edge of the sloping plate 2-5 is installed backwardly towards the water inlet of the sedimentation tank 2.

经沉淀池2处理后的清水通过穿孔墙3上的通孔2-6进入生活用水池4,蓄满至设计水位,生活用水通过生活用水池出水管5流入用水户。在生活用水池出水管5上装有管式滤片消毒器14,对生活用水进行消毒,保证用水安全。当生活用水池4需要清洗时,打开生活用水池放空管6,将水排尽,进行清洗。The clear water treated by the sedimentation tank 2 enters the domestic water pool 4 through the through holes 2-6 on the perforated wall 3, and is filled to the design water level, and the domestic water flows into the water users through the domestic water pool outlet pipe 5. Tubular filter disc sterilizer 14 is housed on the outlet pipe 5 of the domestic water pool, and domestic water is sterilized to ensure water safety. When the domestic water pool 4 needs to be cleaned, the domestic water pool vent pipe 6 is opened, and the water is exhausted for cleaning.

当生活用水池4中水蓄满后,如还有多余水,则溢流至生产用水池7。生产用水通过生产用水池出水管14输送至农田等。当生产用水池蓄满后多余的水通过溢流管8排出。需要清洗时,打开生产用水池放空管9,将水排尽,进行清洗。When the water in the domestic water pool 4 is full, if there is excess water, it will overflow to the production water pool 7. The production water is transported to the farmland etc. through the outlet pipe 14 of the production water pool. When the production water pool is full, the excess water is discharged through the overflow pipe 8. When needing to clean, open the venting pipe 9 of the production water pool, drain the water and clean.

根据水源地的水量,通过设计计算,确定生活用水池4的池体积,确保生活用水停留时间不超过2天,确保用水安全。若水源来水量为0.2升每秒,则生活用水池长宽高分别3米、2米、3米。According to the amount of water in the water source, the pool volume of the domestic water pool 4 is determined through design calculations to ensure that the residence time of domestic water does not exceed 2 days and ensure water safety. If the water flow from the water source is 0.2 liters per second, the length, width and height of the domestic water pool are 3 meters, 2 meters and 3 meters respectively.

蓄水池池顶设有排气管13,排气管13用于排出浑浊空气。The top of the reservoir is provided with an exhaust pipe 13, and the exhaust pipe 13 is used to discharge turbid air.

进水管1连有一分支管16,由于山区水质一般为泉水,一般可直接饮用,而当下雨天时水中泥沙比较大,需要沉淀。通过设置分支管16,当水质满足生活用水要求时(平时正常情况),水可以通过分支管16直接进入生活用水池4,当水质污泥较多时(下雨天),水可以通过进水管1流到沉淀池2中先经过事先沉淀。Water inlet pipe 1 is connected with a branch pipe 16, because the water quality in mountain area is generally spring water, generally can directly drink, and silt in the water is bigger when rainy day, needs precipitation. By setting the branch pipe 16, when the water quality meets the domestic water requirements (normal situation), the water can directly enter the domestic water pool 4 through the branch pipe 16, and when there is a lot of sludge in the water quality (rainy day), the water can flow through the water inlet pipe 1 Go through the previous precipitation in the sedimentation tank 2.

蓄水池顶部设有一井口10,当蓄水池需要清洗和检修时,人员可以通过爬梯11进水蓄水池内部。井口平时建盖密封。The top of the reservoir is provided with a wellhead 10, and when the reservoir needs to be cleaned and overhauled, personnel can enter the interior of the reservoir through a ladder 11. The wellhead is usually sealed with a cover.

在上述蓄水池的各个管道上均安装有启闭阀门,其中,池上的进水管、出水管均采用DN32型号的水管,放空管和溢流管均采用DN80型号的水管Opening and closing valves are installed on each pipeline of the above-mentioned reservoir. Among them, the water inlet and outlet pipes on the pool are all DN32 type water pipes, and the emptying pipe and overflow pipe are both DN80 type water pipes.

所述沉淀池2、生活用水池4及生产用水池7的池底由下往上均由素土层、灰土层、碎石层、C10混凝土及C20混凝土建造;沉淀池2、生活用水池4及生产用水池7的侧壁均采用C25混凝土建造;沉淀池2、生活用水池4及生产用水池7的顶部采用C20混凝土建造。由此保证池身结构牢靠,防止雨水冲刷松塌。The bottom of the sedimentation tank 2, domestic water pool 4 and production water pool 7 are all constructed from plain soil layer, lime soil layer, crushed stone layer, C10 concrete and C20 concrete from bottom to top; sedimentation tank 2, domestic water pool 4 and the side walls of the production pool 7 are all constructed of C25 concrete; the tops of the sedimentation tank 2, the domestic pool 4 and the production pool 7 are constructed of C20 concrete. This ensures that the structure of the pool body is firm and prevents the rainwater from scouring and collapsing.

另外,在池底均设有1%的坡度,这样方便将水引向出口,保证排空后不会有部分水留在池内。In addition, there is a 1% slope at the bottom of the pool, which is convenient to guide the water to the outlet, and ensures that no part of the water will remain in the pool after emptying.

本实用新型可以贮存生活、生产用水,解决用水困难,提高用水水质,保证用水安全。The utility model can store domestic and production water, solve the difficulty of water use, improve water quality and ensure water safety.

Claims (7)

1.一种山区蓄水池,其特征在于:包括沉淀池(2)、生活用水池(4)及生产用水池(7);1. A mountain reservoir, characterized in that it includes a sedimentation tank (2), a domestic water pool (4) and a production water pool (7); 所述沉淀池(2)通过穿孔整流墙(2-2)分成配水区(2-1)和沉淀缓冲区(2-9),其中,配水区(2-1)和沉淀缓冲区(2-9)底部设有多个集泥斗(2-7)和穿孔排泥管(2-8);The sedimentation tank (2) is divided into a water distribution area (2-1) and a sedimentation buffer zone (2-9) through a perforated rectifying wall (2-2), wherein, the water distribution area (2-1) and the sedimentation buffer zone (2- 9) There are multiple mud collecting buckets (2-7) and perforated mud discharge pipes (2-8) at the bottom; 所述生活用水池(4)与沉淀池(2)通过穿孔墙(3)上的通孔(2-6)连通,生活用水池(4)上安装有生活用水池出水管(5)和生活用水池放空管(6);The domestic water pool (4) communicates with the sedimentation tank (2) through the through holes (2-6) on the perforated wall (3), and the domestic water pool (4) is equipped with a domestic water pool outlet pipe (5) and a domestic Use pool vent pipe (6); 所述生产用水池(7)设置在生活用水池(4)一侧,生产用水池(7)上设有生产用水池出水管(14)、溢流管(8)及生产用水池放空管(9)。The production water pool (7) is set on one side of the domestic water pool (4), and the production water pool (7) is provided with a production water pool outlet pipe (14), an overflow pipe (8) and a production water pool vent pipe (9). 2.根据权利要求1所述的一种山区蓄水池,其特征在于:所述该蓄水池为封闭结构,封闭结构顶端设有带盖的井口(10)和排气管(13)。2. A mountain reservoir according to claim 1, characterized in that: the reservoir is a closed structure, and the top of the closed structure is provided with a covered wellhead (10) and an exhaust pipe (13). 3.根据权利要求1所述的一种山区蓄水池,其特征在于:所述沉淀缓冲区(2-9)设有阻流板(2-4)和斜板(2-5)。3. A mountain reservoir according to claim 1, characterized in that: the sedimentation buffer zone (2-9) is provided with a spoiler (2-4) and a sloping plate (2-5). 4.根据权利要求1所述的一种山区蓄水池,其特征在于:所述配水区(2-1)一侧设有进水管(1),进水管(1)上安装有分支管(16),分支管(16)另一端与生活用水池(4)连通。4. A mountainous reservoir according to claim 1, characterized in that: a water inlet pipe (1) is provided on one side of the water distribution area (2-1), and a branch pipe (1) is installed on the water inlet pipe (1) 16), the other end of the branch pipe (16) communicates with the domestic water pool (4). 5.根据权利要求1所述的一种山区蓄水池,其特征在于:所述穿孔整流墙(2-2)下部设有多个配水孔(2-3)。5. The mountain water storage pool according to claim 1, characterized in that: the lower part of the perforated rectifying wall (2-2) is provided with a plurality of water distribution holes (2-3). 6.根据权利要求1所述的一种山区蓄水池,其特征在于:所述沉淀池(2)、生活用水池(4)及生产用水池(7)的池底由下往上均由素土层、灰土层、碎石层、C10混凝土及C20混凝土建造;沉淀池(2)、生活用水池(4)及生产用水池(7)的侧壁均采用C25混凝土建造;沉淀池(2)、生活用水池(4)及生产用水池(7)的顶部采用C20混凝土建造。6. A mountain water storage pond according to claim 1, characterized in that: the bottom of the sedimentation pond (2), the domestic water pond (4) and the production water pond (7) are all arranged from bottom to top The plain soil layer, lime soil layer, crushed stone layer, C10 concrete and C20 concrete are constructed; the side walls of the sedimentation tank (2), domestic water tank (4) and production water tank (7) are all constructed of C25 concrete; the sedimentation tank (2 ), the tops of the domestic water pool (4) and the production water pool (7) are constructed of C20 concrete. 7.根据权利要求1所述的一种山区蓄水池,其特征在于:所述生活用水池出水管(5)上装有管式滤片消毒器(15)。7. A mountain reservoir according to claim 1, characterized in that: the outlet pipe (5) of the domestic water pool is equipped with a tubular filter sterilizer (15).
CN201621068275.XU 2016-09-21 2016-09-21 A kind of mountain area cistern Expired - Fee Related CN206052863U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621068275.XU CN206052863U (en) 2016-09-21 2016-09-21 A kind of mountain area cistern

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621068275.XU CN206052863U (en) 2016-09-21 2016-09-21 A kind of mountain area cistern

Publications (1)

Publication Number Publication Date
CN206052863U true CN206052863U (en) 2017-03-29

Family

ID=58365803

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621068275.XU Expired - Fee Related CN206052863U (en) 2016-09-21 2016-09-21 A kind of mountain area cistern

Country Status (1)

Country Link
CN (1) CN206052863U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107354972A (en) * 2017-08-11 2017-11-17 包头钢铁(集团)有限责任公司 For preventing columns base sludge impurity from entering method and the gear mud weir of absorbing well, absorption well
CN110080345A (en) * 2019-05-28 2019-08-02 中国电建集团贵阳勘测设计研究院有限公司 High-level water pool structure
CN111139897A (en) * 2020-01-19 2020-05-12 宁波大学 Secondary water supply system with purification function and method
CN111138014A (en) * 2020-01-19 2020-05-12 宁波大学 A kind of secondary water supply tank and method
CN111139896A (en) * 2020-01-19 2020-05-12 宁波大学 Secondary water supply system and method with side filtering function

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107354972A (en) * 2017-08-11 2017-11-17 包头钢铁(集团)有限责任公司 For preventing columns base sludge impurity from entering method and the gear mud weir of absorbing well, absorption well
CN110080345A (en) * 2019-05-28 2019-08-02 中国电建集团贵阳勘测设计研究院有限公司 High-level water pool structure
CN111139897A (en) * 2020-01-19 2020-05-12 宁波大学 Secondary water supply system with purification function and method
CN111138014A (en) * 2020-01-19 2020-05-12 宁波大学 A kind of secondary water supply tank and method
CN111139896A (en) * 2020-01-19 2020-05-12 宁波大学 Secondary water supply system and method with side filtering function

Similar Documents

Publication Publication Date Title
CN206052863U (en) A kind of mountain area cistern
CN202117109U (en) Roof rainwater collection and utilization device
CN102182242B (en) A rainwater treatment system and rainwater treatment method thereof
CN102531282B (en) Device and method for quality-based rainwater collection, treatment and utilization
CN204001088U (en) A kind of building rainwater and daily life sewage intermediate water reuse system
CN105089141A (en) Sponge community rainwater comprehensive utilization system and utilization method
CN107965031A (en) A kind of system for collecting, handle, putting aside, utilizing for initial rainwater runoff
CN108797756A (en) Rain penetration purifies savings system in a kind of landscape planting
CN109851165A (en) A kind of small-scale waste water treatment for reuse integration afforestation equipment and method
CN206256510U (en) A kind of new building drainage system against rain
CN101519246B (en) Water cellar system for improving water quality
CN107514045A (en) Concave herbaceous field
CN106902569B (en) A collection and pretreatment system for rainwater in the initial stage of urban surface runoff
CN204138468U (en) A kind of mine wastewater treatment for reuse system
CN208577609U (en) A kind of sewage discharge biochemical treatment system
CN203383144U (en) Bridge floor runoff collection, treatment and emergency system
CN204959950U (en) Rainwater automatic collection emptying devices
CN212881422U (en) A rainwater collection and utilization device
CN203768181U (en) Balcony wastewater and initial rainwater purifier applied to rainwater pipe network
CN202227393U (en) Rainwater discarding device
CN209082658U (en) A kind of town road drainage system
CN207582617U (en) A kind of drainage system with first rain storage pond and online processing storage pond
CN223176887U (en) Rain and flood regulation facility for sponge city
CN217150445U (en) Rainwater regulation and storage system
CN212655610U (en) Landscape water treatment device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170329

Termination date: 20170921

CF01 Termination of patent right due to non-payment of annual fee