CN110080203A - The repeatable processing method and its processing structure adjusted of deep soft soil foundation pile foundation track girder two sides differential settlement - Google Patents

The repeatable processing method and its processing structure adjusted of deep soft soil foundation pile foundation track girder two sides differential settlement Download PDF

Info

Publication number
CN110080203A
CN110080203A CN201910233150.XA CN201910233150A CN110080203A CN 110080203 A CN110080203 A CN 110080203A CN 201910233150 A CN201910233150 A CN 201910233150A CN 110080203 A CN110080203 A CN 110080203A
Authority
CN
China
Prior art keywords
track girder
slip casting
transition plates
sides
pile foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910233150.XA
Other languages
Chinese (zh)
Other versions
CN110080203B (en
Inventor
曾子明
周红星
陈平山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Fourth Harbor Engineering Co Ltd
CCCC Fourth Harbor Engineering Institute Co Ltd
Guangzhou Harbor Engineering Quality Inspection Co Ltd
Original Assignee
CCCC Fourth Harbor Engineering Co Ltd
CCCC Fourth Harbor Engineering Institute Co Ltd
Guangzhou Harbor Engineering Quality Inspection Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Fourth Harbor Engineering Co Ltd, CCCC Fourth Harbor Engineering Institute Co Ltd, Guangzhou Harbor Engineering Quality Inspection Co Ltd filed Critical CCCC Fourth Harbor Engineering Co Ltd
Priority to CN201910233150.XA priority Critical patent/CN110080203B/en
Publication of CN110080203A publication Critical patent/CN110080203A/en
Application granted granted Critical
Publication of CN110080203B publication Critical patent/CN110080203B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • E02D35/005Lowering or lifting of foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0037Clays
    • E02D2300/004Bentonite or bentonite-like

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention belongs to traffic base construction technique fields, the specific repeatable processing method and its processing structure adjusted of open deep soft soil foundation pile foundation track girder two sides differential settlement, processing method comprise the concrete steps that: (1) installation is continuously arranged in the transition plates of track girder two sides;(2) injected hole is reserved;(3) Grouting Pipe is made;(4) Grouting Pipe is buried;(5) slip casting core pipe is put into pre-buried Grouting Pipe to tube bottom;(6) cement injection is carried out inwardly on the outside of track girder;(7) settlement observation is carried out, while carrying out pressure maintaining;(8) after the completion of slip casting, settlement after construction observation is carried out;(9) borehole cleaning extracts slip casting core pipe;(10) restore pavement surface structure appearance.The processing method can effectively solve deficiency present in traditional " bump at bridgehead " issue handling, this method not only operates relative simplicity program, and implementation process cost is less, and treatment effeciency greatly improves, reduce construction risk in treatment process simultaneously, reduces O&M cost.

Description

The repeatable processing method adjusted of deep soft soil foundation pile foundation track girder two sides differential settlement And its processing structure
Technical field
The invention belongs to traffic base construction technique fields, and in particular to deep soft soil foundation pile foundation track girder two sides are different Occurs the processing method of relative settlement between rigidity.
Background technique
Relative settlement is generated, such as asking for bump at bridgehead since the rigidity of different grounds is different in previous pile foundation two sides Topic, bump at bridgehead is a kind of subgrade defect problem relatively conventional in highway construction, and prevention bump at bridgehead problem is one long-term And large order, it needs to include that construction, design and the joint efforts of each side, unit in charge of construction are completed.Crucial disease is road traffic peace One of complete important hidden danger seriously affects the comfort of driving, reduces the travel speed and road passage capability of vehicle, and damage is high The Social benefit and economic benefit of fast highway construction.
In order to ensure bridge and harmony of align ment and smoothly it is necessary to reinforce the design of bridge and bridge platform back roadbed, construction and Maintenance, the phenomenon that solve bump at bridgehead.
Currently, its common solution has: exchange filling method, treatment process of composite foundation, TGXG (net) reinforced earth Treatment Methods, light filler Treatment Methods, injecting treatment method etc..
Above-mentioned traditional processing method has the following disadvantages:
(1) cost is higher, such as uses light filler Treatment Methods, treatment process of composite foundation.
(2) complex process, needs a variety of construction cooperations in scene, and enforcement difficulty is larger.
(3) due to the characteristic of the secondary consolidation of weak soil, creep, the complete settlement after construction duration is longer, after causing basement process There is relative settlement, and is easy to produce continuous maintenance, the poor circulation that relative settlement constantly generates.The maintenance in later period can continue to compare Longer time, and will cause with traditional treatment method it is difficult in maintenance, influence operation use the problem of generate, to increase maintenance Cost, while will increase the security risk in maintenance process.
Therefore, it researches and develops a kind of pair of deep soft soil foundation pile foundation track two sides differential settlement and carries out sustainable adjusting, save punishment The cost of differential settlement reduces the complexity and degree of difficulty of punishment, reduces the construction risk generated in treatment process, reduces O&M The processing method of cost is extremely urgent.
Summary of the invention
The purpose of the present invention is overcome the deficiencies in the prior art, specifically disclose a kind of deep soft soil foundation pile foundation track girder two The repeatable processing method adjusted of side differential settlement, which can effectively solve deposits in traditional " bump at bridgehead " issue handling Deficiency, this method not only operates relative simplicity program, and implementation process cost is less, and treatment effeciency greatly improves, and subtracts simultaneously Lack construction risk in treatment process, reduces O&M cost.
In order to reach above-mentioned technical purpose, the present invention is realized by following technical scheme:
The repeatable processing method adjusted of deep soft soil foundation pile foundation track girder two sides differential settlement of the present invention, tool Steps are as follows for body:
(1) installation is continuously arranged in the transition plates of track girder two sides;
(2) injected hole is reserved: can be in advance in transition plates close to track girder, the both ends far from track girder and corresponding bedding of roadbed Reserve injected hole in position;
(3) make Grouting Pipe: production has a Grouting Pipe of the first thick liquid discharge mouth and check valve, first thick liquid discharge mouth and unidirectional Valve and the bottom interval of transition plates are arranged, the gap grout off between the Grouting Pipe and transition plates;
(4) it buries Grouting Pipe: the Grouting Pipe to complete is buried to predetermined position and absolute altitude;
(5) it when pile foundation track girder two sides, which occurs, in field monitoring excessive relative settlement occurs, is put in pre-buried Grouting Pipe Enter the slip casting core pipe with the second thick liquid discharge mouth and two-way bowl-type rubber valve to tube bottom, and first thick liquid discharge mouth and the second plasma discharge of note The height and position correspondence of mouth is generally corresponding to;
(6) cement injection is carried out inwardly on the outside of track girder;
(7) during carrying out slip casting, settlement observation is carried out to processing region, while carrying out pressure maintaining;
(8) after the completion of slip casting, the settlement after construction observation for carrying out certain time repeats step (5) if completing less effective To step (7), the differential settlement until pile foundation track girder two sides is adjusted until meeting live requirement;
(9) and borehole cleaning is carried out, extracts slip casting core pipe.
(10) restore pavement surface structure appearance.
As the further improvement of above-mentioned technology, in above-mentioned steps (1), in newly-built structures, digging up and filling in It is carried out after sand during pouring track girder, is symmetrically installed the transition plates for being continuously arranged in track girder two sides.
As the further improvement of above-mentioned technology, reserves in injected hole, can be leaned in transition plates in advance in above-mentioned steps (2) Injected hole is reserved in nearly track girder, the both ends far from track girder and corresponding bedding of roadbed position, and the diameter of the injected hole is 50mm, Longitudinal pitch is 0.7m~1.5m.
As the further improvement of above-mentioned technology, in the production Grouting Pipe step of above-mentioned steps (3), the Grouting Pipe Caliber is 48mm, and the check valve is rubber check valve, the bottom of first thick liquid discharge mouth and rubber check valve apart from transition plates For 500mm, the transition plates apex distance is 2000mm~3000mm from bedding of roadbed bottom.
As the further improvement of above-mentioned technology, cement injection is carried out inwardly on the outside of the slave track girder of step (6) In, the cement slurry ratio of mud is 0.7~1.0, and the presetting period of slurries is 1.5h, and grouting pressure is 0.6MPa~1.0MPa, What is selected is marked as 42.5 ordinary portland cements.Slip casting proportion and slip casting standard, need according to scene difference condition, Loading condition in matter condition and live use process, carries out comprehensive analysis, and tested when conditions permit, It is final to determine slip casting proportion and slip casting standard.
As the further improvement of above-mentioned technology, in the settlement observation of the processing region of step (7), settlement observation Standard is 3mm/d or so, if more than this value, then needs to adjust the scheme of slip casting;If be less than this value, illustrate slip casting effect compared with Well, treated, and absolute altitude reaches the requirement of design, is observed, with the validity of verification processing.
As the further improvement of above-mentioned technology, in step (8), after the completion of slip casting, sink after carrying out 3 days or so works Drop observation.
Processing method of the present invention further includes the structures that may be equally suitable for built completion, when pile foundation track When beam two sides occur settling excessive situation, first excessive position pore-forming, opening diameter A110mm, bottom hole depth can be being settled For 2m or so.Then installation has the Grouting Pipe of the first thick liquid discharge mouth and rubber check valve, and carries out length records, manages above ground level 20cm.Gap between drilling is filled with sleeve shell material, the match ratio of sleeve shell material are as follows: cement: bentonite=0.6~0.8: 1.2.Then step (5) to step (10) are repeated.
The invention also discloses the repeatable processing adjusted of the deep soft soil foundation pile foundation track girder two sides differential settlement Structure comprising several transition platess for being continuously installed on track girder two sides, in transition plates close to track girder, two far from track girder End or corresponding bedding of roadbed position are equipped with the injected hole across each transition plates, the inside of the injected hole be successively arranged Grouting Pipe and Slip casting core pipe, the Grouting Pipe are equipped with the first thick liquid discharge mouth and rubber check valve, first thick liquid discharge mouth and rubber check valve with The bottom of transition plates is spaced setting, and the gap between the Grouting Pipe and transition plates is to be blocked with cement, the slip casting Core pipe is equipped with the second thick liquid discharge mouth and two-way bowl-type rubber valve, and the height and position of first thick liquid discharge mouth and the second thick liquid discharge mouth is substantially right It answers.
Specifically: the diameter of the injected hole is 50mm, and longitudinal pitch is 0.7m~1.5m.
The bottom of the thick liquid discharge mouth and rubber check valve apart from transition plates is 500mm, the distance from top road of the transition plates The bottom of foundation base is 2000mm~3000mm.
The slip casting core pipe is equipped with the second thick liquid discharge mouth and two-way bowl-type rubber valve, first thick liquid discharge mouth and the second plasma discharge The height and position of mouth is generally corresponding to.
Compared with prior art, the beneficial effects of the present invention are:
(1) the repeatable processing method adjusted of differential settlement of the present invention is knot on the basis of common abnormal settlement treatment The settlement observation in implementation process is closed, using repeatable slip casting, to reach estimated treatment effect, treatment effeciency is high;
(2) in the repeatable processing method adjusted of differential settlement of the present invention, used mechanical equipment is common, the technique of use Simply, implementation cost is very low, and operability is more convenient, and the influence of versus environmental is smaller, and treatment effeciency is high, the duration of implementation Short, the safe safety of implementation process reduces O&M cost, compensates for the deficiency in conventional treatment, builds item for traffic base Relative settlement processing occurs in mesh and provides a kind of new processing method, application value with higher;
(3) the repeatable processing structure adjusted of differential settlement of the present invention, is simply easily achieved.
Detailed description of the invention
The present invention is described in detail in the following with reference to the drawings and specific embodiments:
Fig. 1 is the processing structure signal for occurring relative settlement between the different-stiffness of deep soft soil foundation pile foundation track girder two sides Figure;
Occurs slip casting implementation diagram in the treatment process of relative settlement in Fig. 2 present invention.
Specific embodiment
Embodiment one:
As shown in Figure 1 and Figure 2, deep soft soil foundation pile foundation track girder two sides differential settlement of the present invention is repeatable is adjusted Processing structure comprising it is several to be continuously installed on the transition platess 2 of 1 two sides of track girder, in transition plates 2 close to track girder 1, separate The both ends of track girder 1 or 3 position of corresponding bedding of roadbed are equipped with the injected hole 8 across each transition plates 2, the inside of the injected hole 8 It is successively arranged Grouting Pipe 4 and slip casting core pipe 5, the Grouting Pipe 4 is equipped with the first thick liquid discharge mouth 41 and rubber check valve 42, and described the The bottom of one thick liquid discharge mouth 41 and rubber check valve 42 and transition plates 2 is spaced setting, between the pipe of slip casting 4 and transition plates 2 Gap is to be blocked with cement, and the slip casting core pipe 5 is equipped with the second thick liquid discharge mouth 51 and two-way bowl-type rubber valve 52, the slip casting Core pipe 5 is equipped with the second thick liquid discharge mouth 51 and two-way bowl-type rubber valve 52, the height of first thick liquid discharge mouth 41 and the second thick liquid discharge mouth 51 Degree position is generally corresponding to.The diameter of the injected hole 8 is 50mm, longitudinal pitch 1.2m, first thick liquid discharge mouth 41 and rubber Bottom of the check valve 42 apart from transition plates is 500mm, and the bottom of the distance from top bedding of roadbed 3 of the transition plates 2 is 2000mm.
The repeatable processing adjusted of deep soft soil foundation pile foundation track girder two sides differential settlement of the present invention described below Structure, the specific steps of which are as follows:
(1) installation is continuously arranged in the transition plates 2 of 1 two sides of track girder: in newly-built structures, after digging up and filling in sand 9 It carries out during pouring track girder 1, is symmetrically installed the transition plates 2 for being continuously arranged in 1 two sides of track girder;
(2) injected hole 8 is reserved: can be in advance in transition plates 2 close to track girder 1, the both ends far from track girder 1 and corresponding roadbed Injected hole 8 is reserved at 3 position A of surface layer, the diameter of the injected hole 8 is 50mm, longitudinal pitch 1.2m.
(3) make Grouting Pipe 4: production has the Grouting Pipe 4 of the first thick liquid discharge mouth 41 and check valve 42, first thick liquid discharge mouth 41 and the bottom interval of check valve 42 and transition plates 2 be arranged, the gap grout off between the Grouting Pipe 4 and transition plates 2; 4 caliber of Grouting Pipe is 48mm, and the check valve 42 is rubber check valve, first thick liquid discharge mouth 41 and rubber check valve 42 Bottom apart from transition plates 2 is 500mm, and 2 apex distance of transition plates is 2000mm from 3 bottom of bedding of roadbed.
(4) it buries Grouting Pipe 4: the Grouting Pipe 4 to complete is buried to predetermined position and absolute altitude;
(5) when 1 two sides of pile foundation track girder, which occurs, in field monitoring excessive relative settlement occurs, in pre-buried Grouting Pipe 4 The slip casting core pipe 5 with the second thick liquid discharge mouth 51 and two-way bowl-type rubber valve 52 is put into tube bottom, the first plasma discharge of the Grouting Pipe 4 Mouth 41 and the height and position of the second thick liquid discharge mouth 51 of slip casting core pipe 5 are generally corresponding to;
(6) carry out cement injection 6 inwardly from 1 outside of track girder: 6 ratio of mud of cement slurry is 0.7~1.0, slurries Presetting period be 1.5h, grouting pressure is 0.6MPa~1.0MPa, and selection is the note marked as 42.5 ordinary portland cements Slurry proportion and slip casting standard are needed according to the loading condition in the difference condition at scene, geological conditions and live use process, Comprehensive analysis is carried out, and is tested when conditions permit, it is final to determine slip casting proportion and slip casting standard;
(7) during carrying out slip casting, settlement observation is carried out to processing region, while carrying out pressure maintaining, the sedimentation of this step The standard of observation is 3mm/d or so, if more than this value, then needs to adjust the scheme of slip casting;If being less than this value, illustrate that slip casting is imitated Fruit is preferable, and the requirement for absolute altitude reaches design that treated is observed, with the validity of verification processing;
(8) after the completion of slip casting, the settlement after construction observation of certain time is carried out, if completing less effective, after the completion of slip casting, into Settlement after construction observation in row 3 days or so, repeats step (5) to step (7), until the differential settlement tune of 1 two sides of pile foundation track girder It is whole until meeting live requirement;
(9) and borehole cleaning is carried out, extracts slip casting core pipe 5.
(10) restore pavement surface structure appearance.
(11) when the excessive situation of the two sides relative settlement for occurring pile foundation 7 and track girder 1 again, step 5 is repeated to step Rapid 10.
Processing method of the invention is seen on the basis of common abnormal settlement treatment in conjunction with the sedimentation in implementation process It surveys, using repeatable slip casting, which can effectively solve deficiency present in traditional " bump at bridgehead " issue handling, should Method not only operates relative simplicity program, and implementation process cost is less, and treatment effeciency greatly improves, while reducing treatment process Middle construction risk reduces O&M cost.
Embodiment two:
The processing method of relative settlement of the present invention may be equally suitable for the structures of built completion, when pile foundation rail When the two sides Dao Liang occur settling excessive situation:
Firstly, settling excessive position pore-forming, opening diameter A110mm, bottom hole depth is 3m;
Then, installation has the Grouting Pipe 4 of the first thick liquid discharge mouth 41 and rubber check valve 42, and carries out length records, Guan Gao Ground 20cm out;Gap between drilling is filled with sleeve shell material, the match ratio of sleeve shell material are as follows: cement: bentonite=0.6~ 0.8:1.2 repeats step 5 to step 10.
It is all that the present invention is not departed to various changes or modifications of the invention the invention is not limited to above embodiment Spirit and scope, if these modification and variations belong within the scope of claim and equivalent technologies of the invention, then this hair It is bright to also imply that comprising these modification and variations.

Claims (10)

1. the repeatable processing method adjusted of deep soft soil foundation pile foundation track girder two sides differential settlement, the specific steps of which are as follows:
(1) installation is continuously arranged in the transition plates of track girder two sides;
(2) injected hole is reserved;
(3) make Grouting Pipe: production has a Grouting Pipe of the first thick liquid discharge mouth and check valve, first thick liquid discharge mouth and check valve with The bottom interval of transition plates is arranged, the gap grout off between the Grouting Pipe and transition plates;
(4) it buries Grouting Pipe: the Grouting Pipe to complete is buried to predetermined position and absolute altitude;
(5) when pile foundation track girder two sides, which occurs, in field monitoring excessive relative settlement occurs, band is put into pre-buried Grouting Pipe There are the second thick liquid discharge mouth and the slip casting core pipe of two-way rubber valve to tube bottom, and the height position of first thick liquid discharge mouth and the second thick liquid discharge mouth It sets and is generally corresponding to;
(6) cement injection is carried out inwardly on the outside of track girder;
(7) during carrying out slip casting, settlement observation is carried out to processing region, while carrying out pressure maintaining;
(8) after the completion of slip casting, the settlement after construction observation of certain time is carried out, if completing less effective, repeats step (5) to step Suddenly (7), the differential settlement until pile foundation track girder two sides adjust until meeting live requirement;
(9) and borehole cleaning is carried out, extracts slip casting core pipe;
(10) restore pavement surface structure appearance.
2. the repeatable processing method adjusted of deep soft soil foundation pile foundation track girder two sides differential settlement according to claim 1, It is characterized by: in newly-built structures, pour the mistake of track girder after digging up and filling in sand in above-mentioned steps (1) Cheng Zhong is symmetrically installed the transition plates for being continuously arranged in track girder two sides.
3. the repeatable processing method adjusted of deep soft soil foundation pile foundation track girder two sides differential settlement according to claim 1, It is characterized by: reserved in injected hole in above-mentioned steps (2), it can be in advance in transition plates close to track girder, two far from track girder Injected hole is reserved in end and corresponding bedding of roadbed position, and the diameter of the injected hole is 50mm, and longitudinal pitch is 0.7m~1.5m.
4. the repeatable processing method adjusted of deep soft soil foundation pile foundation track girder two sides differential settlement according to claim 1, It is characterized by: the Grouting Pipe caliber is 48mm in the production Grouting Pipe step of above-mentioned steps (3), the check valve is Rubber check valve, the bottom of first thick liquid discharge mouth and rubber check valve apart from transition plates are 500mm, the transition plates apex distance It is 2000mm~3000mm from bedding of roadbed bottom.
5. the repeatable processing method adjusted of deep soft soil foundation pile foundation track girder two sides differential settlement according to claim 1, It is characterized by: carrying out in cement injection inwardly on the outside of the slave track girder of above-mentioned steps (6), the cement slurry ratio of mud is 0.7~1.0, the presetting period of slurries is 1.5h, and grouting pressure is 0.6MPa~1.0MPa, and selection is common marked as 42.5 Portland cement.
6. the repeatable processing method adjusted of deep soft soil foundation pile foundation track girder two sides differential settlement according to claim 1, It is characterized by: the standard of settlement observation is 3mm/d or so, in the settlement observation of the processing region of step (7) if more than this Value, then need to adjust the scheme of slip casting;If being less than this value, illustrate that slip casting effect is preferable.
7. the repeatable processing method adjusted of deep soft soil foundation pile foundation track girder two sides differential settlement according to claim 1, It is characterized by: after the completion of slip casting, carrying out settlement after construction observation in 3 days or so in step (8).
It is adjusted 8. deep soft soil foundation pile foundation track girder two sides differential settlement according to any one of claims 1 to 7 is repeatable Processing structure, it is characterised in that: continuously the transition platess of track girder two sides are installed on including several, in transition plates close to track Beam, far from track girder both ends or corresponding bedding of roadbed position be equipped with across each transition plates injected hole, the injected hole it is interior Portion is successively arranged Grouting Pipe and slip casting core pipe, and the Grouting Pipe is equipped with the first thick liquid discharge mouth and rubber check valve, the first row The bottom of slurry mouth and rubber check valve and transition plates is spaced setting, the gap cement between the Grouting Pipe and transition plates into Row blocks, and the slip casting core pipe is equipped with the second thick liquid discharge mouth and two-way bowl-type rubber valve, first thick liquid discharge mouth and the second thick liquid discharge mouth Height and position be generally corresponding to.
9. the repeatable processing structure adjusted of thick-soft base pile foundation track girder two sides differential settlement according to claim 8, It is characterized by: the diameter of the injected hole is 50mm, longitudinal pitch is 0.7m~1.5m.
10. the repeatable processing structure adjusted of thick-soft base pile foundation track girder two sides differential settlement according to claim 9, It is characterized by: the bottom of first thick liquid discharge mouth and rubber check valve apart from transition plates is about 500mm, the top of the transition plates Bottom of the portion apart from bedding of roadbed is about 2000mm~3000mm.
CN201910233150.XA 2019-03-26 2019-03-26 Treatment method and treatment structure for repeatedly adjusting settlement differences at two sides of pile foundation track beam of deep soft soil foundation Active CN110080203B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910233150.XA CN110080203B (en) 2019-03-26 2019-03-26 Treatment method and treatment structure for repeatedly adjusting settlement differences at two sides of pile foundation track beam of deep soft soil foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910233150.XA CN110080203B (en) 2019-03-26 2019-03-26 Treatment method and treatment structure for repeatedly adjusting settlement differences at two sides of pile foundation track beam of deep soft soil foundation

Publications (2)

Publication Number Publication Date
CN110080203A true CN110080203A (en) 2019-08-02
CN110080203B CN110080203B (en) 2024-04-02

Family

ID=67413627

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910233150.XA Active CN110080203B (en) 2019-03-26 2019-03-26 Treatment method and treatment structure for repeatedly adjusting settlement differences at two sides of pile foundation track beam of deep soft soil foundation

Country Status (1)

Country Link
CN (1) CN110080203B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0953237A (en) * 1995-08-11 1997-02-25 Mitsui Home Co Ltd Pit and constructing method of basement utilizing the pit
CN102926303A (en) * 2012-11-22 2013-02-13 河海大学 Method for reinforcing soft soil foundation settlement control pile foundation bracket of high-grade highway in use
CN106759223A (en) * 2015-11-19 2017-05-31 五邑大学 Controllable rigid pile+displacement hull+reinforcement cushion combined composite foundation
CN107513995A (en) * 2017-08-07 2017-12-26 中国水利水电第十工程局有限公司 A kind of bridge struction pile post grouting construction method
CN209975499U (en) * 2019-03-26 2020-01-21 中交四航工程研究院有限公司 Processing structure capable of repeatedly adjusting settlement difference on two sides of pile foundation track beam of deep soft soil foundation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0953237A (en) * 1995-08-11 1997-02-25 Mitsui Home Co Ltd Pit and constructing method of basement utilizing the pit
CN102926303A (en) * 2012-11-22 2013-02-13 河海大学 Method for reinforcing soft soil foundation settlement control pile foundation bracket of high-grade highway in use
CN106759223A (en) * 2015-11-19 2017-05-31 五邑大学 Controllable rigid pile+displacement hull+reinforcement cushion combined composite foundation
CN107513995A (en) * 2017-08-07 2017-12-26 中国水利水电第十工程局有限公司 A kind of bridge struction pile post grouting construction method
CN209975499U (en) * 2019-03-26 2020-01-21 中交四航工程研究院有限公司 Processing structure capable of repeatedly adjusting settlement difference on two sides of pile foundation track beam of deep soft soil foundation

Also Published As

Publication number Publication date
CN110080203B (en) 2024-04-02

Similar Documents

Publication Publication Date Title
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN100580221C (en) Construction method for shallow soil-covered river bed under shield tunnel
CN108166994B (en) A kind of construction method of the grouting reinforced region applied to water-rich sand layer shield tunnel
CN100510274C (en) Construction method of enclosing level rotary-jet pile hole-mouth using double-liquid slip jection method
CN103556579A (en) Box culvert pushing construction method integrating comprehensive grouting, pressure maintaining and pipe roof support
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN106761782A (en) A kind of tunneling construction method for wearing operation tunnel under shield in rich water powder land floor
CN101967794A (en) New technology for treating vehicle bump at bridge ends
CN102535472B (en) Pored-tube filling and high-pressure impacting extruding grouting method
CN110130936A (en) It dashes forward in a kind of shield tunneling process and meets the construction method of untreated solution cavity or crack
CN109944593A (en) The reinforcement means of existing building is worn under a kind of shield tunnel
CN106894428A (en) Multi-channel waterproof plugging method for dewatering well of thick and large raft foundation
CN114233385A (en) Treatment method for mud burst and water burst of inclined shaft
CN106522248A (en) Method for reinforcing soil slope and slope reinforcing device
CN103867216A (en) Soil stabilization structure and method for railway yard shield tunneling construction
CN102838325A (en) Hole sealing grout stop material and grouting hole sealing process
CN112647960A (en) Advanced grouting reinforcement device and method for shield construction
CN110453678A (en) A kind of method of high-pressure rotary jet grouting pile double pipe ruling by law reason highway in loess area sedimentation
CN104452502A (en) Construction method for renovating horizontal deformation hazards of terminal spines of ballastless tracks
CN204112305U (en) Existing railway line excavation section weak subgrade is reinforced and is used multi-functional lobby water system
CN109779636A (en) The ruggedized construction of existing building is worn under a kind of shield tunnel
CN114108609B (en) Construction method for multistage segmented precise filling and deep pile forming in goaf
CN111365005A (en) Reinforcing structure and method for shield tunnel lower-penetrating elevated bridge foundation
CN103615012B (en) Steel construction self-drilling hollow anchor bars reinforces the most wired gear safeguard structure
CN109704656A (en) A kind of bridge joint hillside fields polymer grouting strengthening method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant