CN112647960A - Advanced grouting reinforcement device and method for shield construction - Google Patents

Advanced grouting reinforcement device and method for shield construction Download PDF

Info

Publication number
CN112647960A
CN112647960A CN202011618253.7A CN202011618253A CN112647960A CN 112647960 A CN112647960 A CN 112647960A CN 202011618253 A CN202011618253 A CN 202011618253A CN 112647960 A CN112647960 A CN 112647960A
Authority
CN
China
Prior art keywords
grouting
drilling
slurry
shield
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011618253.7A
Other languages
Chinese (zh)
Inventor
朱六兵
岳川
丁小彬
叶剑平
施钰
石超
董耀俊
薛皓文
韩东霖
陈俊生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
South China University of Technology SCUT
Original Assignee
South China University of Technology SCUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by South China University of Technology SCUT filed Critical South China University of Technology SCUT
Priority to CN202011618253.7A priority Critical patent/CN112647960A/en
Publication of CN112647960A publication Critical patent/CN112647960A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0642Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield having means for additional processing at the front end
    • E21D9/0671Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield having means for additional processing at the front end with means for consolidating the rock in front of the shield by injection of consolidating substances through boreholes
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • E21B15/04Supports for the drilling machine, e.g. derricks or masts specially adapted for directional drilling, e.g. slant hole rigs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • E21B7/046Directional drilling horizontal drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms
    • E21D9/122Working or loading platforms
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • E21D9/087Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physics & Mathematics (AREA)
  • Fluid Mechanics (AREA)
  • Mechanical Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention provides an advanced grouting reinforcement device and method for shield construction, and relates to the field of shields. The device and the method for the advanced grouting reinforcement in shield construction comprise the following specific steps: the construction sequence of the advanced grouting process comprises construction preparation → platform construction → drilling machine construction → slurry material and slurry making → grouting operation → grouting and hole sealing. The invention provides an advanced grouting reinforcement device and method for shield construction, wherein the shield construction has a plurality of risk sources (penetrating through dense building structure groups, entering a bin under pressure for checking and replacing a cutter and passing through a long-distance upper soft lower hard stratum), reinforcement treatment is required, and the ground of the shield does not have reinforcement conditions, so that the reinforcement of a shutdown risk point from a hole by utilizing an advanced grouting hole of the shield is a good choice, and the advanced grouting reinforcement device and method are particularly used under the conditions of deep tunnel burying, poor geological conditions and long shutdown time so as to ensure the safety of the shield construction.

Description

Advanced grouting reinforcement device and method for shield construction
Technical Field
The invention relates to the field of shield construction, in particular to an advanced grouting reinforcement device and method for shield construction.
Background
With the rapid development of social economy, the urbanization rate of China is gradually improved, the urban population is gradually increased, people pay more attention to the quality of life, the requirement on the convenience of travel is improved, and with the enhancement of environmental awareness, new requirements on green travel are also provided, and under the background, the problems of road traffic jam, automobile exhaust emission and noise pollution, convenience and safety of public transport and the like are increasingly concerned by people. Urban rail transit is popular among numerous cities as an electric-energy-driven, fast and convenient public trip mode, the living needs of residents are greatly met, and the urban rail transit is greatly developed under the promotion of national policies. By the end of 2019, the continental region of China has 56 cities (individual projects approved by local governments are not included in statistics) which are 6902.5 kilometers in total line establishment scale (including new commissioning projects which still have construction shows and investment amount happening in the year in part 2019), and the year-on-year growth is 8.3%. Line 279 under construction. In an 6902.5 km line under construction, 5632.8 km underground line accounts for 81.6%, 416.4 km ground line accounts for 6%, 853.2 km overhead line accounts for 12.4%. For urban rail transit underground lines, the construction is mostly carried out by a shield method, however, in urban areas, especially in central areas where underground pipelines are complex and surface structures are criss-cross, a large amount of practical statistical data show that the reasons for causing ground settlement in the subway shield project include stratum loss caused by construction, remolding soil reconsolidation caused by disturbance and shearing damage to the stratum near the subway shield tunnel, and the like, construction excavation has a great influence on the surrounding environment, and serious economic loss and social influence are caused by damage of the underground pipelines caused by excessive deformation and deformation, cracking, even collapse and the like of the upper buildings caused by excessive surface settlement. Therefore, it is very important how to prevent the collapse of surrounding rocks, effectively control the ground settlement caused by excavation and reduce the influence of excavation on the surrounding environment in the tunnel excavation process.
Under the unfavorable geological conditions of hydrogeology (water-rich sand layer, soft silt stratum, upper soft and lower hard stratum), the auxiliary measures currently adopted during the construction of the shield tunneling machine are ground surface mortar anchor rods or ground surface grouting reinforcement, a method for reducing the underground water level, deep mixing pile reinforcement, high-pressure rotary grouting reinforcement, freezing method reinforcement and the like.
The prior art has the following defects: for urban rail transit underground lines, construction is mostly carried out by a shield method, subway projects are built in urban areas, particularly in central areas where underground pipelines are complex and surface structures are criss-cross, at present, stratum reinforcement on the ground is usually affected by the ground structures and the underground pipelines, if the ground structures are built, stratum reinforcement construction cannot be carried out, safety accidents for breaking the pipelines during construction exist when the underground pipelines are longitudinally and transversely crossed, and partial parts cannot be reinforced when the underground pipelines are more, so that the stratum reinforcement effect is affected; due to the fact that the shield machine is buried deeply, when the stratum at the upper part of the shield machine is reinforced, the influence of construction control quality is large, and the expected reinforcing effect cannot be guaranteed; when the ground is reinforced, a lot of influences and inconvenience are brought to road damage, peripheral traffic, pedestrians and daily safe civilized construction.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects of the prior art, the invention provides an advanced grouting reinforcement device and method for shield construction, which solve the problem that part of underground pipelines cannot be reinforced when the number of underground pipelines is large, so that the stratum reinforcement effect is influenced; due to the fact that the shield machine is buried deeply, when the stratum at the upper part of the shield machine is reinforced, the influence of construction control quality is large, and the expected reinforcing effect cannot be guaranteed; the ground reinforcing method has the problems of great influence and inconvenience on road damage, peripheral traffic, pedestrians and daily safe civilized construction.
(II) technical scheme
In order to achieve the purpose, the invention is realized by the following technical scheme: the utility model provides a be used for shield structure method construction advance slip casting reinforcing apparatus, a serial communication port, shield structure method construction advance slip casting reinforcing apparatus is including current shield structure machine, ten advance slip casting holes are reserved to shield structure machine's aircraft nose, shield structure machine's rig is provided with the ring flange in preformed hole drill way position, preformed hole position is provided with the rig, and the drilling rod and the inseparable sliding connection of preformed hole position of rig, be provided with the connecting hole in the drilling rod, and the connecting hole is close to the rig position and is provided with the connecting pipe.
Preferably, the ten advanced grouting holes are formed, six horizontal drill holes are formed in the middle of the machine head, and four drill holes are formed in the top of the machine head.
Preferably, the flange plate is fixedly connected with the side wall of the machine head of the shield tunneling machine through a plurality of fastening bolts, and the position of the connecting pipe is fixedly connected with a gate valve.
Preferably, the method comprises the following specific steps: the construction sequence of the advanced grouting process comprises construction preparation → platform construction → drilling machine construction → slurry material and slurry making → grouting operation → grouting and hole sealing.
Preferably, the construction preparation includes:
s1 drilling parameter setting
The diameter of a preformed hole in a shield body of a shield machine is 100mm, the diameters of a drill rod and a drill bit of a drilling machine are 42mm (the length of a single section of drill rod is 1.5-2.0 m, a grouting pore channel is formed in the drill rod), and a flange plate is arranged at the orifice of the preformed hole for connection and fixation; the drilling depth is 10-18 m, and the specific depth is adjusted according to the actual situation;
s2 slurry parameter settings
The grout is double-grout, the grouting parameters of the double-grout are that the water-cement ratio of cement grout is 1:1, the baume degree of water glass is 40 (1:1 dilution), the volume ratio of cement grout to water glass is 1:1, the deep-setting time of the grout is 20-30 s, the grouting pressure is controlled to be about 0.3-0.5MPa, reverse grouting is adopted, the grouting pressure is adjusted according to monitoring or actual conditions, a forward grouting water-stopping measure is adopted in the drilling process, the grouting grout adopts phosphoric acid, and the grout proportion is that the water and the phosphoric acid are 10:1 (volume ratio);
s3 safety technology crossing bottom
Before operation, related operation personnel are organized to conduct safety technology cross training, the grouting reinforcement intention and specific parameters and requirements of construction are familiar, the specific conditions of the operation environment are known, and whether self labor protection articles are equipped in place or not is checked.
Preferably, the platform is built by adopting a gantry crane and a battery locomotive to convey the drilling machine to a shield tail scaffold building area, then a chain block is hung on the upper part of the shield body to hoist the drilling machine, and the hoisting height is higher than the scaffold platform height; the shield advance drilling and grouting reinforcement construction are carried out on a scaffold platform erected in a shield shell, due to the limitation of operating environment (factors such as an erector, a bridge frame and a slurry pipeline), the scaffold platform is adjusted according to the actual situation on site, the row spacing between scaffolds is not more than 1.5m in principle, the operating platform can use oil cylinders extending out of two sides, pipe pieces on two sides and the bridge frame in the middle as supporting points, the platform plate is a fully-paved stainless steel walkway plate, and in order to offset the impact force during drilling, platform throwing support needs to be arranged on the rear side of the platform according to the actual conditions; after the platform is built, safety guardrails are arranged around the platform.
Preferably, after the platform is erected and passes the acceptance check, the drilling machine is lowered to the scaffold platform; after the drilling machine is in place, the drilling machine is adjusted, the inclination of a drill rod of the drilling machine is adjusted, the drill rod and the reserved hole channel of the shield body are ensured to be aligned, and the drilling machine is debugged before drilling, so that the equipment runs normally; before formal drilling, the equipment at the shield tail of the shield tunneling machine is covered and protected by using color strip cloth, so that the equipment is prevented from being polluted in the drilling process; before the drilling machine is constructed, firstly, the drilling machine is subjected to trial operation, and after the trial operation of the drilling machine is normal, drilling is started; the section number of the drill rod is recorded in detail in the drilling process, so that the accuracy of the drilling depth is ensured; when drilling, slowly operating, and mastering the influence of the stratum on the drilling machine so as to determine drilling parameters under the stratum condition; closely observing the drilling condition, stopping drilling immediately when the drilling is stuck or difficult to drill, and performing construction after analyzing reasons; and recording is made during drilling, the stratum condition is comprehensively reflected, the accurate geological and hydrographic condition is provided for grouting construction, and the recording is made after drilling is finished.
Preferably, the grouting slurry is cement-water glass slurry; the cement is PO.42.5 ordinary portland cement, the used cement is fresh and has no agglomeration, and each batch of the incoming cement has delivery qualification certificate and inspection and analysis report; the water cement ratio of the cement paste is 1:1, the concentration of the original water glass pulp is 40 Baume degrees, and water glass diluent is prepared by water, wherein the cement paste and the water glass diluent are 1:1 (volume ratio); the specific proportion can be adjusted on site according to the on-site condensation time; the pulping equipment is a blade type stirrer; in order to ensure the uniformity of the slurry and not to precipitate in the grouting clearance, two stirring slurry storage barrels are additionally processed, and the capacity is 0.4 cubic meter; in order to facilitate slurry suction, more than two slurry taking ports are arranged on the outer side of the slurry storage barrel so as to ensure the supply of slurry during large-flow grouting; and mixing the slurry according to the selected proportioning parameters of the slurry, wherein the slurry is filtered by a 1 x 1mm mesh screen after being mixed, so that the slurry is ensured to be uniform.
Preferably, adopting a retreating type grouting method, after drilling is finished, sealing, injecting cement-water glass double-liquid slurry after the sealing slurry is condensed, retreating a drill rod after the pressure is reached, performing grouting operation on the lower section, and circulating the steps until the hole is finished; during grouting, lifting a drill rod while grouting, strictly controlling the lifting amplitude, wherein each step is 0.3-0.4 m, withdrawing at a constant speed, paying attention to the change of grouting parameters, continuously lifting the drill rod after the grouting amount or the grouting pressure reaches a designed value, and keeping in mind that grout enters an excavation bin or wraps a shield body due to excessive pressure, wherein the grouting pressure is 0.3-0.5 MPa; the grouting pressure is strictly controlled in the grouting process, the grouting amount is closely concerned, when the pressure suddenly rises or the slurry overflows from a hole wall and a section sand layer, grouting is immediately stopped, and measures such as grouting parameter adjustment or displacement are adopted for re-grouting after reasons are found out; when grouting is needed to be suspended, the water glass slurry suction pipe is taken out and placed into the clear water barrel, then the cement pipe is taken out, the grouting pipe is pulled out for 1m, and grouting is stopped after clear water is injected into the hole, so that the pipeline is kept smooth, and the grouting section is not influenced by water injection; during grouting, the cutter head must be rotated discontinuously to prevent the slurry from flowing into the tunnel face and being fixedly connected to clamp the cutter head.
Preferably, the single-hole grouting finishing standard is controlled in a quantitative and constant-pressure combined mode; the quantitative standard is that when the grouting amount reaches 1.5-2 times of the designed grouting amount, the pressure is not increased, and measures such as quick setting grout and the like can be adopted to finish the hole grouting; the standard of constant pressure is that in the grouting process, the pressure gradually rises, the flow gradually falls, and when the grouting pressure reaches the designed grouting pressure and the slurry suction amount is little or no, the hole grouting can be finished; the end standard is a reference value, and the actual end standard is finally determined through field tests; performing tertiary hole sealing by using phosphoric acid solution in the grouting process, wherein when a drill rod is drilled into a fifth hole for the first time, the drilling position of the drill rod is in a soil bin of the shield machine, hole sealing is needed to prevent slurry in the soil bin from flowing back, the drilling depth is 10-12 meters, the grouting depth is 5.4-7.4 meters, the grouting pressure is 1-2MPa, the dosage of the phosphoric acid solution is 220-440L, the dosage of water glass is 110-220L, and the slurry spreading radius is 1.5 m; when the drill rod drills the ninth drill (the deepest position of grouting) for the second time, the drilling position of the drill rod is the deepest position of grouting, the hole needs to be sealed to prevent the injection solution from overflowing to the outside of the required grouting range, the drilling depth is 16-18 meters, the grouting depth is 9.4-11.4 meters, the grouting pressure is 1-2MPa, the dosage of the phosphoric acid solution is 220-440L, the dosage of the water glass is 110-220L, and the diffusion radius of the slurry is 1.5 m; the third time, when the hole is retreated to the shallowest position (namely the hole grouting completion position), generally when the hole is retreated to the rest 6-7 rods, the hole sealing is finished and the grouting is finished, the drilling depth is 12-14 m, the grouting depth is 5.4-7.4 m, the grouting pressure is 1.4-2.6MPa, the dosage of phosphoric acid solution is 220-440L, the dosage of water glass is 110-220L, and the slurry diffusion radius is 1.5 m.
The working principle is as follows: the working principle comprises the following specific steps: the construction sequence of the advanced grouting process comprises construction preparation → platform construction → drilling machine construction → slurry material and slurry making → grouting operation → grouting and hole sealing.
The construction preparation includes:
s1 drilling parameter setting
The diameter of a preformed hole in a shield body of a shield machine is 100mm, the diameters of a drill rod and a drill bit of a drilling machine are 42mm (the length of a single section of drill rod is 1.5-2.0 m, a grouting pore channel is formed in the drill rod), and a flange plate is arranged at the orifice of the preformed hole for connection and fixation; the drilling depth is 10-18 m, and the specific depth is adjusted according to the actual situation;
s2 slurry parameter settings
The grout is double-grout, the grouting parameters of the double-grout are that the water-cement ratio of cement grout is 1:1, the baume degree of water glass is 40 (1:1 dilution), the volume ratio of cement grout to water glass is 1:1, the deep-setting time of the grout is 20-30 s, the grouting pressure is controlled to be about 0.3-0.5MPa, reverse grouting is adopted, the grouting pressure is adjusted according to monitoring or actual conditions, a forward grouting water-stopping measure is adopted in the drilling process, the grouting grout adopts phosphoric acid, and the grout proportion is that the water and the phosphoric acid are 10:1 (volume ratio);
s3 safety technology crossing bottom
Before operation, related operation personnel are organized to conduct safety technology cross training, the grouting reinforcement intention and specific parameters and requirements of construction are familiar, the specific conditions of the operation environment are known, and whether self labor protection articles are equipped in place or not is checked.
The platform is built by adopting a gantry crane and a battery locomotive to convey the drilling machine to a shield tail scaffold building area, then a chain block is hung on the upper part of a shield body to hoist the drilling machine, and the hoisting height is higher than the scaffold platform height; the shield advance drilling and grouting reinforcement construction are carried out on a scaffold platform erected in a shield shell, due to the limitation of operating environment (factors such as an erector, a bridge frame and a slurry pipeline), the scaffold platform is adjusted according to the actual situation on site, the row spacing between scaffolds is not more than 1.5m in principle, the operating platform can use oil cylinders extending out of two sides, pipe pieces on two sides and the bridge frame in the middle as supporting points, the platform plate is a fully-paved stainless steel walkway plate, and in order to offset the impact force during drilling, platform throwing support needs to be arranged on the rear side of the platform according to the actual conditions; after the platform is built, safety guardrails are arranged around the platform.
After the platform is erected and passes the acceptance check, the drilling machine is lowered to the scaffold platform; after the drilling machine is in place, the drilling machine is adjusted, the inclination of a drill rod of the drilling machine is adjusted, the drill rod and the reserved hole channel of the shield body are ensured to be aligned, and the drilling machine is debugged before drilling, so that the equipment runs normally; before formal drilling, the equipment at the shield tail of the shield tunneling machine is covered and protected by using color strip cloth, so that the equipment is prevented from being polluted in the drilling process; before the drilling machine is constructed, firstly, the drilling machine is subjected to trial operation, and after the trial operation of the drilling machine is normal, drilling is started; the section number of the drill rod is recorded in detail in the drilling process, so that the accuracy of the drilling depth is ensured; when drilling, slowly operating, and mastering the influence of the stratum on the drilling machine so as to determine drilling parameters under the stratum condition; closely observing the drilling condition, stopping drilling immediately when the drilling is stuck or difficult to drill, and performing construction after analyzing reasons; and recording is made during drilling, the stratum condition is comprehensively reflected, the accurate geological and hydrographic condition is provided for grouting construction, and the recording is made after drilling is finished.
The grouting slurry is cement-water glass slurry; the cement is PO.42.5 ordinary portland cement, the used cement is fresh and has no agglomeration, and each batch of the incoming cement has delivery qualification certificate and inspection and analysis report; the water cement ratio of the cement paste is 1:1, the concentration of the original water glass pulp is 40 Baume degrees, and water glass diluent is prepared by water, wherein the cement paste and the water glass diluent are 1:1 (volume ratio); the specific proportion can be adjusted on site according to the on-site condensation time; the pulping equipment is a blade type stirrer; in order to ensure the uniformity of the slurry and not to precipitate in the grouting clearance, two stirring slurry storage barrels are additionally processed, and the capacity is 0.4 cubic meter; in order to facilitate slurry suction, more than two slurry taking ports are arranged on the outer side of the slurry storage barrel so as to ensure the supply of slurry during large-flow grouting; and mixing the slurry according to the selected proportioning parameters of the slurry, wherein the slurry is filtered by a 1 x 1mm mesh screen after being mixed, so that the slurry is ensured to be uniform.
Adopting backward grouting, after drilling, firstly sealing, injecting cement-water glass double-liquid slurry after the sealing slurry is condensed, after the pressure is reached, backward drilling the rod, performing the next-stage grouting operation, and circulating the operation until the hole is finished; during grouting, lifting a drill rod while grouting, strictly controlling the lifting amplitude, wherein each step is 0.3-0.4 m, withdrawing at a constant speed, paying attention to the change of grouting parameters, continuously lifting the drill rod after the grouting amount or the grouting pressure reaches a designed value, and keeping in mind that grout enters an excavation bin or wraps a shield body due to excessive pressure, wherein the grouting pressure is 0.3-0.5 MPa; the grouting pressure is strictly controlled in the grouting process, the grouting amount is closely concerned, when the pressure suddenly rises or the slurry overflows from a hole wall and a section sand layer, grouting is immediately stopped, and measures such as grouting parameter adjustment or displacement are adopted for re-grouting after reasons are found out; when grouting is needed to be suspended, the water glass slurry suction pipe is taken out and placed into the clear water barrel, then the cement pipe is taken out, the grouting pipe is pulled out for 1m, and grouting is stopped after clear water is injected into the hole, so that the pipeline is kept smooth, and the grouting section is not influenced by water injection; during grouting, the cutter head must be rotated discontinuously to prevent the slurry from flowing into the tunnel face and being fixedly connected to clamp the cutter head.
The single-hole grouting ending standard is controlled in a quantitative and constant-pressure combined mode; the quantitative standard is that when the grouting amount reaches 1.5-2 times of the designed grouting amount, the pressure is not increased, and measures such as quick setting grout and the like can be adopted to finish the hole grouting; the standard of constant pressure is that in the grouting process, the pressure gradually rises, the flow gradually falls, and when the grouting pressure reaches the designed grouting pressure and the slurry suction amount is little or no, the hole grouting can be finished; the end standard is a reference value, and the actual end standard is finally determined through field tests; performing tertiary hole sealing by using phosphoric acid solution in the grouting process, wherein when a drill rod is drilled into a fifth hole for the first time, the drilling position of the drill rod is in a soil bin of the shield machine, hole sealing is needed to prevent slurry in the soil bin from flowing back, the drilling depth is 10-12 meters, the grouting depth is 5.4-7.4 meters, the grouting pressure is 1-2MPa, the dosage of the phosphoric acid solution is 220-440L, the dosage of water glass is 110-220L, and the slurry spreading radius is 1.5 m; when the drill rod drills the ninth drill (the deepest position of grouting) for the second time, the drilling position of the drill rod is the deepest position of grouting, the hole needs to be sealed to prevent the injection solution from overflowing to the outside of the required grouting range, the drilling depth is 16-18 meters, the grouting depth is 9.4-11.4 meters, the grouting pressure is 1-2MPa, the dosage of the phosphoric acid solution is 220-440L, the dosage of the water glass is 110-220L, and the diffusion radius of the slurry is 1.5 m; the third time, when the hole is retreated to the shallowest position (namely the hole grouting completion position), generally when the hole is retreated to the rest 6-7 rods, the hole sealing is finished and the grouting is finished, the drilling depth is 12-14 m, the grouting depth is 5.4-7.4 m, the grouting pressure is 1.4-2.6MPa, the dosage of phosphoric acid solution is 220-440L, the dosage of water glass is 110-220L, and the slurry diffusion radius is 1.5 m.
(III) advantageous effects
The invention provides an advanced grouting reinforcement device and method for shield construction. The method has the following beneficial effects:
1. the invention provides a device and a method for advance grouting reinforcement in shield construction, wherein an earth pressure balance shield machine is provided with 10 advance drilling hole positions around a shield body, when grouting reinforcement is needed, a gate valve at the position of the reserved hole is opened, a drilling machine is arranged at the position for drilling and grouting construction, and advance pre-grouting reinforcement in a hole is carried out on a stratum at the front end of a cutter head.
2. The invention provides an advanced grouting reinforcement device and method for shield construction, which are used for pre-performing radioactive pre-grouting treatment in the horizontal direction on a shield path in advance, and compacting soil mass in a range of 4-10 m above an arch part in front of a shield cutter head to form a semicircular closed shell, so that the water permeability of the soil mass is reduced as much as possible, and the overall stability of the soil mass above the front of the shield cutter head is improved.
3. The invention provides a device and a method for advanced grouting reinforcement in shield construction, wherein three times of phosphoric acid solution hole sealing are arranged according to actual engineering conditions in the grouting process, the hole sealing is needed to prevent slurry in a soil bin from flowing back when the hole is drilled into the soil bin of a shield machine for the first time, the hole sealing is needed to prevent the injected solution from overflowing out of the needed grouting range when the hole is drilled into the deepest position of grouting for the second time, and the hole sealing is finished grouting when the hole is retreated from a rod to be grouted to the shallowest position for the third time.
4. The invention provides a device and a method for reinforcing advanced grouting in shield construction, which technically emphasize a geological processing mode during the process that a shield passes through a dense building and a hard stratum at the upper part and the lower part, and has better implementation effect in practical engineering.
5. The invention provides an advanced grouting reinforcement device and method for shield construction, wherein the shield construction has a plurality of risk sources (penetrating through dense building structure groups, entering a bin under pressure for checking and replacing a cutter and passing through a long-distance upper soft lower hard stratum), reinforcement treatment is required, and the ground of the shield does not have reinforcement conditions, so that the reinforcement of a shutdown risk point from a hole by utilizing an advanced grouting hole of the shield is a good choice, and the advanced grouting reinforcement device and method are particularly used under the conditions of deep tunnel burying, poor geological conditions and long shutdown time so as to ensure the safety of the shield construction.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example (b):
the embodiment of the invention provides an advanced grouting reinforcement device for shield construction, which is characterized by comprising an existing shield machine, ten advanced grouting holes are reserved in the machine head of the shield machine, a flange plate is arranged at the orifice position of a preformed hole of a drilling machine of the shield machine, the drilling machine is arranged at the position of the preformed hole, a drilling rod of the drilling machine is closely and slidably connected with the position of the preformed hole, a connecting hole is formed in the drilling rod, and a connecting pipe is arranged at the position, close to the drilling machine, of the connecting hole.
And the ten advanced grouting holes are formed, wherein six horizontal drilling holes are formed in the middle of the machine head, and four drilling holes are formed in the top of the machine head. The flange plate is fixedly connected with the machine head side wall of the shield tunneling machine through a plurality of fastening bolts, and the position of the connecting pipe is fixedly connected with a gate valve.
The method comprises the following specific steps: the construction sequence of the advanced grouting process comprises construction preparation → platform construction → drilling machine construction → slurry material and slurry making → grouting operation → grouting and hole sealing.
The construction preparation comprises the following steps:
s1 drilling parameter setting
The diameter of a preformed hole in a shield body of a shield machine is 100mm, the diameters of a drill rod and a drill bit of a drilling machine are 42mm (the length of a single section of drill rod is 1.5-2.0 m, a grouting pore channel is formed in the drill rod), and a flange plate is arranged at the orifice of the preformed hole for connection and fixation; the drilling depth is 10-18 m, and the specific depth is adjusted according to the actual situation;
s2 slurry parameter settings
The grout is double-grout, the grouting parameters of the double-grout are that the water-cement ratio of cement grout is 1:1, the baume degree of water glass is 40 (1:1 dilution), the volume ratio of cement grout to water glass is 1:1, the deep-setting time of the grout is 20-30 s, the grouting pressure is controlled to be about 0.3-0.5MPa, reverse grouting is adopted, the grouting pressure is adjusted according to monitoring or actual conditions, a forward grouting water-stopping measure is adopted in the drilling process, the grouting grout adopts phosphoric acid, and the grout proportion is that the water and the phosphoric acid are 10:1 (volume ratio);
s3 safety technology crossing bottom
Before operation, related operation personnel are organized to conduct safety technology cross training, the grouting reinforcement intention and specific parameters and requirements of construction are familiar, the specific conditions of the operation environment are known, and whether self labor protection articles are equipped in place or not is checked.
The platform is built by adopting a gantry crane and a battery locomotive to convey the drilling machine to a scaffold building area at the tail of the shield, then a chain block is hung on the upper part of the shield body to hoist the drilling machine, and the hoisting height is higher than the scaffold platform height; the shield advance drilling and grouting reinforcement construction are carried out on a scaffold platform erected in a shield shell, due to the limitation of operating environment (factors such as an erector, a bridge frame and a slurry pipeline), the scaffold platform is adjusted according to the actual situation on site, the row spacing between scaffolds is not more than 1.5m in principle, the operating platform can use oil cylinders extending out of two sides, pipe pieces on two sides and the bridge frame in the middle as supporting points, the platform plate is a fully-paved stainless steel walkway plate, and in order to offset the impact force during drilling, platform throwing support needs to be arranged on the rear side of the platform according to the actual conditions; after the platform is built, safety guardrails are arranged around the platform.
After the platform is erected and passes the acceptance check, the drilling machine is lowered to the scaffold platform; after the drilling machine is in place, the drilling machine is adjusted, the inclination of a drill rod of the drilling machine is adjusted, the drill rod and the reserved hole channel of the shield body are ensured to be aligned, and the drilling machine is debugged before drilling, so that the equipment runs normally; before formal drilling, the equipment at the shield tail of the shield tunneling machine is covered and protected by using color strip cloth, so that the equipment is prevented from being polluted in the drilling process; before the drilling machine is constructed, firstly, the drilling machine is subjected to trial operation, and after the trial operation of the drilling machine is normal, drilling is started; the section number of the drill rod is recorded in detail in the drilling process, so that the accuracy of the drilling depth is ensured; when drilling, slowly operating, and mastering the influence of the stratum on the drilling machine so as to determine drilling parameters under the stratum condition; closely observing the drilling condition, stopping drilling immediately when the drilling is stuck or difficult to drill, and performing construction after analyzing reasons; and recording is made during drilling, the stratum condition is comprehensively reflected, the accurate geological and hydrographic condition is provided for grouting construction, and the recording is made after drilling is finished.
The grouting slurry is cement-water glass slurry; the cement is PO.42.5 ordinary portland cement, the used cement is fresh and has no agglomeration, and each batch of the incoming cement has delivery qualification certificate and inspection and analysis report; the water cement ratio of the cement paste is 1:1, the concentration of the original water glass pulp is 40 Baume degrees, and water glass diluent is prepared by water, wherein the cement paste and the water glass diluent are 1:1 (volume ratio); the specific proportion can be adjusted on site according to the on-site condensation time; the pulping equipment is a blade type stirrer; in order to ensure the uniformity of the slurry and not to precipitate in the grouting clearance, two stirring slurry storage barrels are additionally processed, and the capacity is 0.4 cubic meter; in order to facilitate slurry suction, more than two slurry taking ports are arranged on the outer side of the slurry storage barrel so as to ensure the supply of slurry during large-flow grouting; and mixing the slurry according to the selected proportioning parameters of the slurry, wherein the slurry is filtered by a 1 x 1mm mesh screen after being mixed, so that the slurry is ensured to be uniform.
Adopting backward grouting, after drilling, firstly sealing, injecting cement-water glass double-liquid slurry after the sealing slurry is condensed, after the pressure is reached, backward drilling the rod, performing the next-stage grouting operation, and circulating the operation until the hole is finished; during grouting, lifting a drill rod while grouting, strictly controlling the lifting amplitude, wherein each step is 0.3-0.4 m, withdrawing at a constant speed, paying attention to the change of grouting parameters, continuously lifting the drill rod after the grouting amount or the grouting pressure reaches a designed value, and keeping in mind that grout enters an excavation bin or wraps a shield body due to excessive pressure, wherein the grouting pressure is 0.3-0.5 MPa; the grouting pressure is strictly controlled in the grouting process, the grouting amount is closely concerned, when the pressure suddenly rises or the slurry overflows from a hole wall and a section sand layer, grouting is immediately stopped, and measures such as grouting parameter adjustment or displacement are adopted for re-grouting after reasons are found out; when grouting is needed to be suspended, the water glass slurry suction pipe is taken out and placed into the clear water barrel, then the cement pipe is taken out, the grouting pipe is pulled out for 1m, and grouting is stopped after clear water is injected into the hole, so that the pipeline is kept smooth, and the grouting section is not influenced by water injection; during grouting, the cutter head must be rotated discontinuously to prevent the slurry from flowing into the tunnel face and being fixedly connected to clamp the cutter head.
The single-hole grouting ending standard is controlled in a quantitative and constant-pressure combined mode; the quantitative standard is that when the grouting amount reaches 1.5-2 times of the designed grouting amount, the pressure is not increased, and measures such as quick setting grout and the like can be adopted to finish the hole grouting; the standard of constant pressure is that in the grouting process, the pressure gradually rises, the flow gradually falls, and when the grouting pressure reaches the designed grouting pressure and the slurry suction amount is little or no, the hole grouting can be finished; the end standard is a reference value, and the actual end standard is finally determined through field tests; performing tertiary hole sealing by using phosphoric acid solution in the grouting process, wherein when a drill rod is drilled into a fifth hole for the first time, the drilling position of the drill rod is in a soil bin of the shield machine, hole sealing is needed to prevent slurry in the soil bin from flowing back, the drilling depth is 10-12 meters, the grouting depth is 5.4-7.4 meters, the grouting pressure is 1-2MPa, the dosage of the phosphoric acid solution is 220-440L, the dosage of water glass is 110-220L, and the slurry spreading radius is 1.5 m; when the drill rod drills the ninth drill (the deepest position of grouting) for the second time, the drilling position of the drill rod is the deepest position of grouting, the hole needs to be sealed to prevent the injection solution from overflowing to the outside of the required grouting range, the drilling depth is 16-18 meters, the grouting depth is 9.4-11.4 meters, the grouting pressure is 1-2MPa, the dosage of the phosphoric acid solution is 220-440L, the dosage of the water glass is 110-220L, and the diffusion radius of the slurry is 1.5 m; the third time, when the hole is retreated to the shallowest position (namely the hole grouting completion position), generally when the hole is retreated to the rest 6-7 rods, the hole sealing is finished and the grouting is finished, the drilling depth is 12-14 m, the grouting depth is 5.4-7.4 m, the grouting pressure is 1.4-2.6MPa, the dosage of phosphoric acid solution is 220-440L, the dosage of water glass is 110-220L, and the slurry diffusion radius is 1.5 m.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (10)

1. The utility model provides a be used for shield structure method construction advance slip casting reinforcing apparatus, a serial communication port, shield structure method construction advance slip casting reinforcing apparatus is including current shield structure machine, ten advance slip casting holes are reserved to shield structure machine's aircraft nose, shield structure machine's rig is provided with the ring flange in preformed hole drill way position, preformed hole position is provided with the rig, and the drilling rod and the inseparable sliding connection of preformed hole position of rig, be provided with the connecting hole in the drilling rod, and the connecting hole is close to the rig position and is provided with the connecting pipe.
2. The advanced grouting reinforcement device for shield construction according to claim 1, wherein ten advanced grouting holes are formed, six horizontal drilling holes are formed in the middle of the machine head, and four drilling holes are formed in the top of the machine head.
3. The advanced grouting reinforcement device for shield construction according to claim 1, wherein the flange is fixedly connected with a side wall of a machine head of the shield machine through a plurality of fastening bolts, and the connecting pipe is fixedly connected with a gate valve.
4. The advanced grouting reinforcement method for shield construction according to claim 1, characterized in that: the method comprises the following specific steps: the construction sequence of the advanced grouting process comprises construction preparation → platform construction → drilling machine construction → slurry material and slurry making → grouting operation → grouting and hole sealing.
5. The advanced grouting reinforcement method for shield construction according to claim 4, characterized in that: the construction preparation includes:
s1 drilling parameter setting
The diameter of a preformed hole in a shield body of a shield machine is 100mm, the diameters of a drill rod and a drill bit of a drilling machine are 42mm (the length of a single section of drill rod is 1.5-2.0 m, a grouting pore channel is formed in the drill rod), and a flange plate is arranged at the orifice of the preformed hole for connection and fixation; the drilling depth is 10-18 m, and the specific depth is adjusted according to the actual situation;
s2 slurry parameter settings
The grout is double-grout, the grouting parameters of the double-grout are that the water-cement ratio of cement grout is 1:1, the baume degree of water glass is 40 (1:1 dilution), the volume ratio of cement grout to water glass is 1:1, the deep-setting time of the grout is 20-30 s, the grouting pressure is controlled to be about 0.3-0.5MPa, reverse grouting is adopted, the grouting pressure is adjusted according to monitoring or actual conditions, a forward grouting water-stopping measure is adopted in the drilling process, the grouting grout adopts phosphoric acid, and the grout proportion is that the water and the phosphoric acid are 10:1 (volume ratio);
s3 safety technology crossing bottom
Before operation, related operation personnel are organized to conduct safety technology cross training, the grouting reinforcement intention and specific parameters and requirements of construction are familiar, the specific conditions of the operation environment are known, and whether self labor protection articles are equipped in place or not is checked.
6. The advanced grouting reinforcement method for shield construction according to claim 4, characterized in that: the platform is built by adopting a gantry crane and a battery locomotive to convey the drilling machine to a shield tail scaffold building area, then a chain block is hung on the upper part of a shield body to hoist the drilling machine, and the hoisting height is higher than the scaffold platform height; the shield advance drilling and grouting reinforcement construction are carried out on a scaffold platform erected in a shield shell, due to the limitation of operating environment (factors such as an erector, a bridge frame and a slurry pipeline), the scaffold platform is adjusted according to the actual situation on site, the row spacing between scaffolds is not more than 1.5m in principle, the operating platform can use oil cylinders extending out of two sides, pipe pieces on two sides and the bridge frame in the middle as supporting points, the platform plate is a fully-paved stainless steel walkway plate, and in order to offset the impact force during drilling, platform throwing support needs to be arranged on the rear side of the platform according to the actual conditions; after the platform is built, safety guardrails are arranged around the platform.
7. The advanced grouting reinforcement method for shield construction according to claim 4, characterized in that: after the platform is erected and passes the acceptance check, the drilling machine is lowered to the scaffold platform; after the drilling machine is in place, the drilling machine is adjusted, the inclination of a drill rod of the drilling machine is adjusted, the drill rod and the reserved hole channel of the shield body are ensured to be aligned, and the drilling machine is debugged before drilling, so that the equipment runs normally; before formal drilling, the equipment at the shield tail of the shield tunneling machine is covered and protected by using color strip cloth, so that the equipment is prevented from being polluted in the drilling process; before the drilling machine is constructed, firstly, the drilling machine is subjected to trial operation, and after the trial operation of the drilling machine is normal, drilling is started; the section number of the drill rod is recorded in detail in the drilling process, so that the accuracy of the drilling depth is ensured; when drilling, slowly operating, and mastering the influence of the stratum on the drilling machine so as to determine drilling parameters under the stratum condition; closely observing the drilling condition, stopping drilling immediately when the drilling is stuck or difficult to drill, and performing construction after analyzing reasons; and recording is made during drilling, the stratum condition is comprehensively reflected, the accurate geological and hydrographic condition is provided for grouting construction, and the recording is made after drilling is finished.
8. The advanced grouting reinforcement method for shield construction according to claim 4, characterized in that: the grouting slurry is cement-water glass slurry; the cement is PO.42.5 ordinary portland cement, the used cement is fresh and has no agglomeration, and each batch of the incoming cement has delivery qualification certificate and inspection and analysis report; the water cement ratio of the cement paste is 1:1, the concentration of the original water glass pulp is 40 Baume degrees, and water glass diluent is prepared by water, wherein the cement paste and the water glass diluent are 1:1 (volume ratio); the specific proportion can be adjusted on site according to the on-site condensation time; the pulping equipment is a blade type stirrer; in order to ensure the uniformity of the slurry and not to precipitate in the grouting clearance, two stirring slurry storage barrels are additionally processed, and the capacity is 0.4 cubic meter; in order to facilitate slurry suction, more than two slurry taking ports are arranged on the outer side of the slurry storage barrel so as to ensure the supply of slurry during large-flow grouting; and mixing the slurry according to the selected proportioning parameters of the slurry, wherein the slurry is filtered by a 1 x 1mm mesh screen after being mixed, so that the slurry is ensured to be uniform.
9. The advanced grouting reinforcement method for shield construction according to claim 4, characterized in that: adopting backward grouting, after drilling, firstly sealing, injecting cement-water glass double-liquid slurry after the sealing slurry is condensed, after the pressure is reached, backward drilling the rod, performing the next-stage grouting operation, and circulating the operation until the hole is finished; during grouting, lifting a drill rod while grouting, strictly controlling the lifting amplitude, wherein each step is 0.3-0.4 m, withdrawing at a constant speed, paying attention to the change of grouting parameters, continuously lifting the drill rod after the grouting amount or the grouting pressure reaches a designed value, and keeping in mind that grout enters an excavation bin or wraps a shield body due to excessive pressure, wherein the grouting pressure is 0.3-0.5 MPa; the grouting pressure is strictly controlled in the grouting process, the grouting amount is closely concerned, when the pressure suddenly rises or the slurry overflows from a hole wall and a section sand layer, grouting is immediately stopped, and measures such as grouting parameter adjustment or displacement are adopted for re-grouting after reasons are found out; when grouting is needed to be suspended, the water glass slurry suction pipe is taken out and placed into the clear water barrel, then the cement pipe is taken out, the grouting pipe is pulled out for 1m, and grouting is stopped after clear water is injected into the hole, so that the pipeline is kept smooth, and the grouting section is not influenced by water injection; during grouting, the cutter head must be rotated discontinuously to prevent the slurry from flowing into the tunnel face and being fixedly connected to clamp the cutter head.
10. The advanced grouting reinforcement method for shield construction according to claim 4, characterized in that: the single-hole grouting ending standard is controlled in a quantitative and constant-pressure combined mode; the quantitative standard is that when the grouting amount reaches 1.5-2 times of the designed grouting amount, the pressure is not increased, and measures such as quick setting grout and the like can be adopted to finish the hole grouting; the standard of constant pressure is that in the grouting process, the pressure gradually rises, the flow gradually falls, and when the grouting pressure reaches the designed grouting pressure and the slurry suction amount is little or no, the hole grouting can be finished; the end standard is a reference value, and the actual end standard is finally determined through field tests; performing tertiary hole sealing by using phosphoric acid solution in the grouting process, wherein when a drill rod is drilled into a fifth hole for the first time, the drilling position of the drill rod is in a soil bin of the shield machine, hole sealing is needed to prevent slurry in the soil bin from flowing back, the drilling depth is 10-12 meters, the grouting depth is 5.4-7.4 meters, the grouting pressure is 1-2MPa, the dosage of the phosphoric acid solution is 220-440L, the dosage of water glass is 110-220L, and the slurry spreading radius is 1.5 m; when the drill rod drills the ninth drill (the deepest position of grouting) for the second time, the drilling position of the drill rod is the deepest position of grouting, the hole needs to be sealed to prevent the injection solution from overflowing to the outside of the required grouting range, the drilling depth is 16-18 meters, the grouting depth is 9.4-11.4 meters, the grouting pressure is 1-2MPa, the dosage of the phosphoric acid solution is 220-440L, the dosage of the water glass is 110-220L, and the diffusion radius of the slurry is 1.5 m; the third time, when the hole is retreated to the shallowest position (namely the hole grouting completion position), generally when the hole is retreated to the rest 6-7 rods, the hole sealing is finished and the grouting is finished, the drilling depth is 12-14 m, the grouting depth is 5.4-7.4 m, the grouting pressure is 1.4-2.6MPa, the dosage of phosphoric acid solution is 220-440L, the dosage of water glass is 110-220L, and the slurry diffusion radius is 1.5 m.
CN202011618253.7A 2020-12-30 2020-12-30 Advanced grouting reinforcement device and method for shield construction Pending CN112647960A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011618253.7A CN112647960A (en) 2020-12-30 2020-12-30 Advanced grouting reinforcement device and method for shield construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011618253.7A CN112647960A (en) 2020-12-30 2020-12-30 Advanced grouting reinforcement device and method for shield construction

Publications (1)

Publication Number Publication Date
CN112647960A true CN112647960A (en) 2021-04-13

Family

ID=75364548

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011618253.7A Pending CN112647960A (en) 2020-12-30 2020-12-30 Advanced grouting reinforcement device and method for shield construction

Country Status (1)

Country Link
CN (1) CN112647960A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113236300A (en) * 2021-05-24 2021-08-10 中铁建华南建设有限公司 Advanced grouting method for shield construction
CN113236299A (en) * 2021-05-24 2021-08-10 中铁建华南建设有限公司 Advanced grouting system for shield construction
CN113266377A (en) * 2021-06-21 2021-08-17 中铁十二局集团有限公司 Construction method for filling karst cave by using shield machine advanced grouting pipe
CN113323675A (en) * 2021-05-19 2021-08-31 广州轨道交通建设监理有限公司 Shield under-pressure system and under-pressure warehouse entry reinforcing method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102052079A (en) * 2010-11-19 2011-05-11 中铁一局集团有限公司 Method for exchanging tool of shield machine for tunnel construction
CN110259465A (en) * 2019-06-28 2019-09-20 中铁二局集团有限公司 A kind of method that list shield double mode TBM pre-grouting reinforces fault belt
CN110374606A (en) * 2019-08-02 2019-10-25 中铁十四局集团大盾构工程有限公司 Slurry shield seabed broken formation pre-grouting pressure maintaining construction method
CN111852485A (en) * 2020-07-27 2020-10-30 中交第二公路工程局有限公司 Construction method for shield tunnel downward-penetrating sensitive building group in shallow-buried weak stratum
CN215057361U (en) * 2020-12-30 2021-12-07 华南理工大学 Be used for shield to construct leading slip casting reinforcing apparatus of method construction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102052079A (en) * 2010-11-19 2011-05-11 中铁一局集团有限公司 Method for exchanging tool of shield machine for tunnel construction
CN110259465A (en) * 2019-06-28 2019-09-20 中铁二局集团有限公司 A kind of method that list shield double mode TBM pre-grouting reinforces fault belt
CN110374606A (en) * 2019-08-02 2019-10-25 中铁十四局集团大盾构工程有限公司 Slurry shield seabed broken formation pre-grouting pressure maintaining construction method
CN111852485A (en) * 2020-07-27 2020-10-30 中交第二公路工程局有限公司 Construction method for shield tunnel downward-penetrating sensitive building group in shallow-buried weak stratum
CN215057361U (en) * 2020-12-30 2021-12-07 华南理工大学 Be used for shield to construct leading slip casting reinforcing apparatus of method construction

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113323675A (en) * 2021-05-19 2021-08-31 广州轨道交通建设监理有限公司 Shield under-pressure system and under-pressure warehouse entry reinforcing method
CN113236300A (en) * 2021-05-24 2021-08-10 中铁建华南建设有限公司 Advanced grouting method for shield construction
CN113236299A (en) * 2021-05-24 2021-08-10 中铁建华南建设有限公司 Advanced grouting system for shield construction
CN113266377A (en) * 2021-06-21 2021-08-17 中铁十二局集团有限公司 Construction method for filling karst cave by using shield machine advanced grouting pipe

Similar Documents

Publication Publication Date Title
CN112647960A (en) Advanced grouting reinforcement device and method for shield construction
CN109629455B (en) Construction method for reconstructing bridge of highway
CN101638987B (en) Tunnel construction method for crossing high-pressure water-enriched fracture zone with curtain grouting and grout stopping wall
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN106837351A (en) Tunnel Karst water detects Treatment Methods
CN106837353A (en) Filling karst constructing tunnel processing method
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN110067563A (en) Close on the station entrance-exit main structure construction method of urban architecture and road
CN109972609A (en) A kind of railway traffic engineering construction method of underground continuous wall
CN111997685A (en) Construction method for highway to penetrate through coal seam goaf section
CN110130936B (en) Construction method for sudden encountering untreated karst cave or crack in shield tunneling process
CN111810180B (en) Construction method for ultra-large-diameter earth pressure balance jacking pipe to penetrate through expressway
CN110924967A (en) Fine control construction method for shield proximity sensitive building in water-rich sandy gravel stratum
CN112412496A (en) Full-section advanced curtain grouting construction method for water-rich broken geological zone tunnel
CN110469332B (en) Advanced support consolidation method for tunnel penetrating through debris flow accumulation body
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN110984221A (en) Construction method for reinforcing end socket at initial end of air shaft and guide wall structure
CN109386293A (en) The sealed reception construction method of large section rectangular top pipe
CN111794774A (en) Rapid entering protection structure of half cut single-pressure open cut tunnel and construction method
CN112983456A (en) Water-rich sand layer multi-row pipe jacking surface deformation control method
CN215057361U (en) Be used for shield to construct leading slip casting reinforcing apparatus of method construction
AU2021101943A4 (en) A construction control method for a subway shield to penetrate through existing buildings
CN107339109A (en) The construction method of existing road is worn under super Shallow tunnel with large cross-section
CN104747208B (en) Grouting reinforcement grout diffusion regulation method
CN212563261U (en) Half cut single-pressure type open cut tunnel advances hole protective structure fast

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination