CN110067593A CN201910488795.8A CN201910488795A CN110067593A CN 110067593 A CN110067593 A CN 110067593A CN 201910488795 A CN201910488795 A CN 201910488795A CN 110067593 A CN110067593 A CN 110067593A
Authority
CN
China
Prior art keywords
telescopic tube
tube
tube body
escaping
telescopic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910488795.8A
Other languages
Chinese (zh)
Other versions
CN110067593B (en
Inventor
吴立辉
邵宏杰
王永刚
郝建财
杨壮
刘旭鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Group Co Ltd
Haiwei Engineering Construction Co Ltd of FHEC of CCCC
Original Assignee
CCCC First Highway Engineering Group Co Ltd
Haiwei Engineering Construction Co Ltd of FHEC of CCCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Group Co Ltd, Haiwei Engineering Construction Co Ltd of FHEC of CCCC filed Critical CCCC First Highway Engineering Group Co Ltd
Priority to CN201910488795.8A priority Critical patent/CN110067593B/en
Publication of CN110067593A publication Critical patent/CN110067593A/en
Application granted granted Critical
Publication of CN110067593B publication Critical patent/CN110067593B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F11/00Rescue devices or other safety devices, e.g. safety chambers or escape ways

Abstract

The embodiment of the present application provides a kind of tunnel pipe for escaping, is related to constructing tunnel field.The tunnel pipe for escaping includes basic tube body, including first end and second end;At least one telescopic tube, is set in the second end of basic tube body and whole opposite second end is flexible;Every telescopic tube includes dip section and reserved section;Relative telescopic between adjacent expansion tube body, and in contraction state, the reserved section of every telescopic tube is retained in except the tube body for accommodating the telescopic tube;First movement device is installed on basic tube body, to support and move basic tube body;The second mobile device in each reserved section is set, it is flexible to support the telescopic tube where reserved section and the dip section on the telescopic tube is driven to realize.The tunnel pipe for escaping not only increases carrying and the installation effectiveness of tunnel pipe for escaping, ensure that installation quality, and can be adapted for the country rock construction paragraph of different stage.

Description

Tunnel pipe for escaping
Technical field
The present invention relates to constructing tunnel field, in particular to a kind of tunnel pipe for escaping.
Background technique
With railway with and highway rapid development, the scale and difficulty of constructing tunnel are also increasing, tunnel Cave-in accident also constantly occurs, for this purpose, must be provided with escape route when constructing tunnel.But at present since in-cavity construction operation has Limit, carrying and the installation of tunnel pipe for escaping manually carry out entirely substantially.Pipe for escaping is heavier, manually carries and pacifies Dress, efficiency are very low.It is therefore desirable to develop a kind of tunnel escape tube that can greatly improve handling efficiency and installation accuracy Road.
Summary of the invention
This application provides a kind of tunnel pipe for escaping, which can avoid complete manually carrying and installation, Accelerate carrying and installation speed, improves installation accuracy, and different constructing tunnel conditions can be suitable for.
A kind of tunnel pipe for escaping provided by the embodiments of the present application includes: basic tube body, at least one telescopic tube, first Mobile device and the second mobile device.
Basic tube body includes first end and second end;At least one telescopic tube is set in the second end of the basic tube body And the whole relatively described second end is stretched;The every telescopic tube includes dip section and reserved section;The adjacent telescopic tube Between relative telescopic, and in contraction state, the reserved section of the every telescopic tube is retained in the pipe for accommodating the telescopic tube Except body;First movement device is installed on the basic tube body, to support and move the basic tube body;It is arranged every The second mobile device in a reserved section, to support the telescopic tube where the reserved section and drive this described flexible Dip section on tube body is realized flexible.
During above-mentioned realization, it is flexible that the second mobile device can drive telescopic tube to realize, completes tunnel pipe for escaping Installation, such mounting means can guarantee the concentricity of tunnel pipe for escaping.First movement device and the second mobile device can Driving tunnel pipe for escaping is integrally moved, and manual handling tunnel pipe for escaping is avoided.Telescopic tube can comparative basis tube body Entirety is stretched, can also be with relative telescopic, the scalable design of tunnel pipe for escaping, convenient for construction between adjacent expansion tube body Personnel carry and installation tunnel pipe for escaping.Manual handling in compared with the prior art installs tunnel pipe for escaping, installation Random larger, installation offset distance is also larger, and especially tunnel inverted arch is constructed paragraph, caused by being excavated because of inverted arch ground level difference compared with Greatly, the manually installed concentricity that not can guarantee pipe for escaping at all, the telescopic installation of the tunnel pipe for escaping in the application is not Installation effectiveness is improved only, and is mutually arranged between tube body, ensure that the concentricity for escaping the raw pipeline in tunnel, improves installation essence Degree.
In a kind of possible embodiment, it is fixed that the basis tube body offers first on the tube wall of the second end Position hole;Second location hole is offered on the dip section tube wall of the every telescopic tube;The institute of the every telescopic tube It states and offers third location hole on reserved section tube wall.
During above-mentioned realization, location hole is opened up on basic tube body and telescopic tube, is on the one hand to determination and stretches On the other hand the predetermined collapsing length of draw body is to reach predetermined collapsing length in telescopic tube and tunnel pipe for escaping is complete After installation, immobilizing foundation tube body and telescopic tube prevent being mutually shifted between each tube body and telescopic tube from falling off The case where occur, improve tunnel pipe for escaping stability.
In a kind of possible embodiment, the number of the first positioning hole is one;Every telescopic tube Dip section is equipped with multiple along second location hole arranged in a straight line, the one third positioning of reserved section setting of the every telescopic tube Hole;When the relatively described basic tube body of the telescopic tube is moved to predetermined position, the second location hole is fixed with described first The axle center in position hole is overlapped;When the relatively previous telescopic tube of the telescopic tube is moved to predetermined position, this is described flexible The axle center of the second location hole of tube body is overlapped with the axle center of the third location hole of the previous telescopic tube.
During above-mentioned realization, the dip section of every telescopic tube be equipped with it is multiple along second location hole arranged in a straight line, Different second location holes on every telescopic tube determine the different predetermined collapsing length of the telescopic tube.When on basic tube body When different second location hole axle center is overlapped on first positioning hole telescopic tube adjacent thereto, which reaches different Predetermined collapsing length;When the third location hole of previous telescopic tube is on its adjacent the latter telescopic tube different second When the axle center of location hole is overlapped, the latter telescopic tube reaches different predetermined collapsing lengths.It is multiple on every telescopic tube The design of second location hole allows construction personnel to determine that telescopic tube reaches difference according to the demand of different safe step pitches Predetermined collapsing length, i.e., the tunnel pipe for escaping can be suitable for different grades of country rock construct paragraph, reduce and construct The replacement of pipe for escaping, improves construction efficiency in journey.
In a kind of possible embodiment, the second end of the basis tube body and the every telescopic tube are close to institute The one end for stating reserved section is mounted on sleeve, and the sleeve offers the 4th location hole;The dip section of the every telescopic tube On offer with the 4th location hole cooperation the 5th location hole.
During above-mentioned realization, the setting of sleeve, the 4th location hole and the 5th location hole is on the one hand to determination and stretches The predetermined collapsing length of draw body, and fixed each tube body is to prevent from being mutually shifted or sliding between each tube body;On the other hand, When telescopic tube is in elongation process, if construction personnel fails to stop in time mobile device, that telescopic tube is missed is predetermined flexible When length slides out of previous telescopic tube, the sleeve of previous telescopic tube can accept the telescopic tube a distance, Sound is collided out when the telescopic tube slides Shi Huiyu sleeve out of previous telescopic tube, which can remind construction personnel should Telescopic tube has slid to sleeve, continues to move to so that construction personnel can stop in time mobile device.
In a kind of possible embodiment, the number of the 5th location hole on the every telescopic tube be it is multiple, it is more A 5th location hole is along arranged in a straight line.
During above-mentioned realization, it is different to represent the telescopic tube for the 5th different location holes on every telescopic tube Predetermined collapsing length.Construction personnel can determine that telescopic tube reaches different predetermined stretch according to the demand of different safe step pitches Contracting length, i.e. the tunnel pipe for escaping can be suitable for different grades of country rock construction paragraph, reduce in work progress and escape The replacement of pipeline, improves construction efficiency.
In a kind of possible embodiment, there are two the first movement devices, is separately mounted to the basic tube body First end and second end;The structure of second mobile device is identical as the structure of the first movement device.
During above-mentioned realization, one first movement device is installed respectively in the first end and second end of basic tube body, It on the one hand can be with balance tunnel pipe for escaping, so that the mounting stability of tunnel pipe for escaping is higher;On the other hand can make Tunnel pipe for escaping is more steady quick in moving process.
In a kind of possible embodiment, the first movement device includes support frame and is mounted on support frame as described above Driving device, the walking mechanism with driving device transmission connection is installed on support frame as described above;Support frame as described above is removable It unloads and is connected on the basic tube body.
During above-mentioned realization, settable self-locking device in walking mechanism, self-locking device can use self-locking tire, when After tunnel pipe for escaping reaches specified placement position, walking mechanism is lockked immediately by self-locking tire, prevents tunnel escape tube Road sliding, it is ensured that its is in a safe condition.It is detachably connected between support frame and basic tube body, it, can when mobile device damage Mobile device is disassembled at any time and repairs or replace intact mobile device.
In a kind of possible embodiment, support frame as described above further includes clamp device;The clamp device includes tightening It is socketed Gu set, lower adapter sleeve and the first connecting plate, the upper adapter sleeve and the lower adapter sleeve are configured with the basic tube body Closed-loop, the inner surface of the closed-loop is bonded with the outer surface of the basic tube body;First connecting plate is arranged in institute It states the bottom of lower adapter sleeve and is connect with support frame as described above.
During above-mentioned realization, mobile device is removably set on basic tube body by clamp device, fastening dress The upper adapter sleeve and lower adapter sleeve set connect into a closed-loop by fastening bolt, and the interior circular diameter of the closed-loop is slightly less than base The outer surface of plinth tube body can will adjust the pressure between closing ring inner surface and the outer surface of basic tube body by rotational fastener bolt Power is solidly connected so that mobile device is lifted with base pipe, prevents from being skidded between mobile device and basic tube body so that influencing tunnel The movement of pipe for escaping.
In a kind of possible embodiment, support frame as described above is including the second connecting plate, third connecting plate and positioned at second More elevating levers between connecting plate and third connecting plate;It is connected between first connecting plate and second connecting plate more Root damping spring.
During above-mentioned realization, the adjustable height by adjusting elevating lever can ensure that the concentricity of each tube body keeps one It causes, damping spring can substantially reduce the deformation of pipe for escaping, it is ensured that pipe for escaping passage is smooth, reduces personal injury.
In a kind of possible embodiment, the outer cover of the every damping spring is equipped with telescopic fixing sleeve.
During above-mentioned realization, fixing sleeve includes upper fixes sleeve and lower fixes sleeve, the upper end of upper fixes sleeve with First connecting plate is fixedly connected, and the lower end of lower fixes sleeve is fixedly connected with the second connecting plate, and upper and lower fixes sleeve opposite can stretch Contracting.Fixes sleeve is arranged outside damping spring can prevent damping spring from generating lateral deviation, prevent damping spring from deforming.
In a kind of possible embodiment, the first end of the basis tube body is provided with for being connected another basic tube body Connector.
During above-mentioned realization, when tunnel surrounding is preferable, face and the two safe step pitches of lining increase, and individual tunnel is escaped When raw pipeline is elongated to longest and is also unable to satisfy construction operation requirement, two tunnel pipe for escaping can be connected by connector, To spreading tunnel pipe for escaping length, the requirement of face and the two safe step pitches of lining is had reached.Ring flange can be used in connector, And flange bolt hole connected using bolt it is firm, it is ensured that tunnel escape is safe and reliable.
Detailed description of the invention
Fig. 1 is a kind of contraction state figure of tunnel pipe for escaping provided by the embodiments of the present application;
Fig. 2 is a kind of elongation state figure of tunnel pipe for escaping provided by the embodiments of the present application;
Fig. 3 is a kind of elongation state figure of the tunnel pipe for escaping including sleeve provided by the embodiments of the present application;
Fig. 4 is a kind of sleeve detail view of tunnel pipe for escaping provided by the embodiments of the present application;
Fig. 5 is a kind of structure chart of the first movement device of tunnel pipe for escaping provided by the embodiments of the present application.
Icon: the basis 100- tube body, 110- first end, 120- second end, 200- telescopic tube, 210- dip section, 220- Reserved section, 300- first movement device, the second mobile device of 400-, 130- first positioning hole, 230- second location hole, 240- the Three location holes, 500- sleeve, the 4th location hole of 510-, the 5th location hole of 250-, 310- support frame, 330- driving device, 340- Walking mechanism, 320- clamp device, the upper adapter sleeve of 321-, adapter sleeve under 322-, the first connecting plate of 323-, 324- closed-loop, The second connecting plate of 350-, 360- third connecting plate, 370- elevating lever, 380- damping spring, 390- fixing sleeve, 140- connector.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present application, technical solutions in the embodiments of the present application is described.
It should also be noted that similar label and letter indicate similar terms in following attached drawing, therefore, once a certain Xiang Yi It is defined in a attached drawing, does not then need that it is further defined and explained in subsequent attached drawing.Meanwhile the application's In description, term " first ", " second " etc. are only used for distinguishing description, are not understood to indicate or imply relative importance.
In constructing tunnel, constructing tunnel paragraph includes secondary lining, inverted arch and face.It is escaped according to contingency Facility arrangement code requirement, tunnel pipe for escaping close to do not excavate one end of face and do not excavate between face away from From less than 10 meters, the length that tunnel pipe for escaping protrudes into secondary lining of having constructed is greater than 5 meters.In the wall rock condition of different stage Under, do not excavate that face is different from the safe step pitch of secondary lining, and wall rock condition is better, and safe step pitch is bigger, tunnel escape tube The arrangement length in road is bigger.According to drawing and code requirement: V, VI grade of country rock is constructed paragraph, do not excavate face with it is secondary Safe step pitch≤70m of lining cutting;VI grade of country rock construction paragraph, does not excavate safe step pitch≤90m of face and secondary lining;Ⅲ Grade country rock construction paragraph, does not excavate safe step pitch≤120m of face and secondary lining;I, II grade of country rock construction paragraph, is not opened Dig safe step pitch≤200m of face and secondary lining.
Fig. 1, Fig. 2 are please referred to, Fig. 1 is a kind of contraction state figure of tunnel pipe for escaping provided by the embodiments of the present application, Fig. 2 For a kind of elongation state figure of tunnel pipe for escaping provided by the embodiments of the present application.Tunnel pipe for escaping in the embodiment includes Basic tube body 100, telescopic tube 200, first movement device 300 and the second mobile device 400.Basic tube body 100 includes first End 110 and second end;At least one telescopic tube 200, the second end and whole opposite second end for being set in basic tube body 100 are stretched Contracting;Every telescopic tube 200 includes dip section 210 and reserved section 220;Relative telescopic between adjacent expansion tube body 200, and receiving When contracting state, the reserved section 220 of every telescopic tube 200 is retained in except the tube body for accommodating the telescopic tube 200;First movement Device 300 is installed on basic tube body 100, to support and move basic tube body 100;It is arranged in each reserved section 220 Second mobile device 400, to support the telescopic tube 200 at reserved 220 place of section and drive protruding on the telescopic tube 200 Section 210 is realized flexible.
During above-mentioned realization, telescopic tube 200 can comparative basis tube body 100 be whole stretches, adjacent expansion pipe Between body 200 tunnel can also be carried and installed convenient for construction personnel and is escaped with relative telescopic, the scalable design of tunnel pipe for escaping Raw pipeline.When carrying or storing tunnel pipe for escaping, construction personnel can make tunnel pipe for escaping be in the state shunk, and can mention The efficiency of height carrying reduces artificial loss, saves storage space;When installing tunnel pipe for escaping, construction personnel passes through first Mobile device 300 and the second mobile device 400 driving tunnel pipe for escaping reach designated position, make the first end of basic pipeline 110 at least protrude into 5 in secondary lining of having constructed close to the first end 110 for not excavating either basic pipeline within 10 meters of face Meter, it after the position for determining basic pipeline, keeps basic pipeline motionless, drives the second mobile device 400, make the second mobile dress It sets 400 drive telescopic pipes and is elongated to predetermined collapsing length, complete the installation of tunnel pipe for escaping.Escape the raw pipeline in tunnel by above-mentioned Installation process it is found that manual handling in compared with the prior art installs tunnel pipe for escaping, installation is random larger, peace It is also larger to fill offset distance, especially tunnel inverted arch construction paragraph, ground level difference is larger caused by excavating because of inverted arch, manually installed basic The concentricity of pipe for escaping is not can guarantee, the telescopic installation of the tunnel pipe for escaping in the application not only increases installation effect Rate, and be mutually arranged between tube body, it ensure that the concentricity for escaping the raw pipeline in tunnel, improve installation accuracy.
In a kind of possible embodiment, basic tube body 100 offers first positioning hole on the tube wall of second end 130;Second location hole 230 is offered on 210 tube wall of dip section of every telescopic tube 200;Every telescopic tube 200 it is reserved Third location hole 240 is offered on 220 tube walls of section.
During above-mentioned realization, location hole is opened up on basic tube body 100 and telescopic tube 200 and is on the one hand to really The predetermined collapsing length for determining telescopic tube 200, the second location hole 230 on the telescopic tube 200 adjacent with basic tube body 100 When being overlapped with the axle center of the first positioning hole 130 on basic tube body 100, which reaches predetermined collapsing length, then Use fixed pin connection first positioning hole 130 with second location hole 230 to fix the telescopic tube 200;When the latter telescoping tube It is latter when 240 axle center of third location hole of the second location hole 230 of body 200 previous telescopic tube 200 adjacent thereto is overlapped A telescopic tube 200 reaches predetermined collapsing length.It on the other hand is to reach predetermined collapsing length and tunnel in telescopic tube 200 After road pipe for escaping completes installation, immobilizing foundation tube body 100 and telescopic tube 200, prevent between each tube body be mutually shifted with And telescopic tube 200 the case where falling off, improve the stability of tunnel pipe for escaping.
In a kind of possible embodiment, the number of first positioning hole 130 is one;Every telescopic tube 200 is stretched Enter section 210 be equipped with it is multiple along second location hole 230 arranged in a straight line, every telescopic tube 200 reserve section 220 be arranged a third Location hole 240;When 200 comparative basis tube body 100 of telescopic tube is moved to predetermined position, second location hole 230 and first is determined The axle center in position hole 130 is overlapped;When the relatively previous telescopic tube 200 of telescopic tube 200 is moved to predetermined position, the telescopic tube The axle center of 200 second location hole 230 is overlapped with the axle center of the third location hole 240 of previous telescopic tube 200.
During above-mentioned realization, the dip section 210 of every telescopic tube 200 is equipped with multiple fixed along arranged in a straight line second Position hole 230, the difference second on every telescopic tube 200 determine hole and decide the different predetermined collapsing length of the telescopic tube 200. The design of multiple second location holes 230 on every telescopic tube 200 allows construction personnel according to different safe step pitches Demand determine that telescopic tube 200 reaches different predetermined collapsing lengths, i.e., the tunnel pipe for escaping can be suitable for different etc. The country rock construction paragraph of grade, reduces the replacement of pipe for escaping in work progress, improves construction efficiency.
In a kind of possible embodiment, Fig. 3, Fig. 4 are please referred to, Fig. 3 is that one kind provided by the embodiments of the present application includes The elongation state figure of the tunnel pipe for escaping of sleeve 500, Fig. 4 are a kind of set of tunnel pipe for escaping provided by the embodiments of the present application Cylinder detail view.One end of the second end of basic tube body 100 and the close reserved section 220 of every telescopic tube 200 is mounted on set Cylinder 500, sleeve 500 offers the 4th location hole 510;It is offered on the dip section 210 of every telescopic tube 200 and the 4th positioning The 5th location hole 250 that hole 510 cooperates.
During above-mentioned realization, on the one hand the setting of sleeve 500, the 4th location hole 510 and the 5th location hole 250 is In order to determine the predetermined collapsing length of telescopic tube 200, and fixed each tube body to prevent from being mutually shifted between each tube body or It slides;On the other hand, when telescopic tube 200 is in elongation process, if construction personnel fails to stop mobile device in time to stretch When draw body 200 misses predetermined collapsing length and slides out of previous telescopic tube 200, the sleeve of previous telescopic tube 200 500 can accept 200 a distance of telescopic tube, the meeting when the telescopic tube 200 slides out of previous telescopic tube 200 Sound is collided out with sleeve 500, which can remind construction personnel that the telescopic tube 200 has slid to sleeve 500, so as to Construction personnel can stop in time mobile device and continue to move to.
In a kind of possible embodiment, the number of the 5th location hole 250 on every telescopic tube 200 be it is multiple, Multiple 5th location holes 250 are along arranged in a straight line.
During above-mentioned realization, the 5th different location holes 250 represents the telescopic tube on every telescopic tube 200 200 different predetermined collapsing lengths.Construction personnel can determine that telescopic tube 200 is reached according to the demand of different safe step pitches Different predetermined collapsing lengths, i.e. the tunnel pipe for escaping can be suitable for different grades of country rock construction paragraph, reduce and apply The replacement of pipe for escaping, improves construction efficiency during work.
In a kind of possible embodiment, referring to FIG. 5, Fig. 5 is a kind of tunnel escape provided by the embodiments of the present application The structure chart of the first movement device 300 of pipeline.There are two first movement devices 300, is separately mounted to the of basic tube body 100 One end 110 and second end;The structure of second mobile device 400 is identical as the structure of first movement device 300.
During above-mentioned realization, one first movement is installed respectively in the first end 110 and second end of basic tube body 100 Device 300, on the one hand can be with balance tunnel pipe for escaping, so that the mounting stability of tunnel pipe for escaping is higher;On the other hand Tunnel pipe for escaping can be made more steady quick in moving process.
In a kind of possible embodiment, first movement device 300 includes support frame 310 and is mounted on support frame 310 On driving device 330, the walking mechanism 340 being sequentially connected with driving device 330 is installed on support frame 310;Support frame 310 It is removably connected on basic tube body 100.
During above-mentioned realization, settable self-locking device in walking mechanism 340, self-locking device can be used from lockwheel Walking mechanism 340 is lockked immediately by self-locking tire after tunnel pipe for escaping reaches specified placement position, prevents tunnel by tire Road pipe for escaping sliding, it is ensured that its is in a safe condition.It is detachably connected between support frame 310 and basic tube body 100, works as movement When device damages, mobile device can be disassembled at any time and repair or replace intact mobile device.
In a kind of possible embodiment, support frame 310 further includes clamp device 320;Clamp device 320 includes tightening Admittedly set 321, lower adapter sleeve 322 and the first connecting plate 323, upper adapter sleeve 321 configures and basic tube body with lower adapter sleeve 322 The closed-loop 324 of 100 sockets, the inner surface of closed-loop 324 are bonded with the outer surface of basic tube body 100;First connecting plate 323 is set It sets the bottom in lower adapter sleeve 322 and is connect with support frame 310.
During above-mentioned realization, mobile device is removably set on basic tube body 100 by clamp device 320, The upper adapter sleeve 321 of clamp device 320 connects into a closed-loop 324, the closed-loop by fastening bolt with lower adapter sleeve 322 324 interior circular diameter is slightly less than the outer surface of basic tube body 100, can will adjust table in closed-loop 324 by rotational fastener bolt Pressure between face and the outer surface of basic tube body 100, is solidly connected so that mobile device is lifted with base pipe, prevents mobile device It is skidded between basic tube body 100 so that influencing the movement of tunnel pipe for escaping.
During above-mentioned realization, as shown in Figure 3 and Figure 4, when the second end and every telescopic tube of basic tube body 100 200 when being mounted on sleeve 500 close to one end of the reserved section 220, the first movement dress at the second end of basic tube body 100 Setting 300 clamp device 320 can be set on sleeve 500, the second mobile device 400 in the reserved section 220 of telescopic tube 200 Clamp device 320 can also be set on sleeve 500.
In a kind of possible embodiment, support frame 310 includes the second connecting plate 350, third connecting plate 360 and is located at More elevating levers 370 between second connecting plate 350 and third connecting plate 360;First connecting plate 323 and the second connecting plate 350 Between be connected with more damping springs 380.
During above-mentioned realization, the adjustable height by adjusting elevating lever 370 can ensure that the concentricity of each tube body is kept Unanimously, damping spring 380 can substantially reduce the deformation of pipe for escaping, it is ensured that pipe for escaping passage is smooth, reduces personal injury.
In a kind of possible embodiment, the outer cover of every damping spring 380 is equipped with telescopic fixing sleeve 390.
During above-mentioned realization, fixing sleeve 390 includes upper fixes sleeve 500 and lower fixes sleeve 500, upper fixes sleeve 500 upper end is fixedly connected with the first connecting plate 323, and the lower end of lower fixes sleeve 500 is fixedly connected with the second connecting plate 350, Upper and lower fixes sleeve 500 can relative telescopic.Fixes sleeve 500 is arranged outside damping spring 380 can prevent damping spring 380 from producing Raw transverse direction deviation, prevents damping spring 380 from deforming.
In a kind of possible embodiment, the first end 110 of basic tube body 100 is provided with for being connected another base pipe The connector 140 of body 100.
During above-mentioned realization, when tunnel surrounding is preferable, face and the two safe step pitches of lining increase, and individual tunnel is escaped When raw pipeline is elongated to longest and is also unable to satisfy construction operation requirement, connector 140 can be passed through and connect two tunnel escape tubes Road, so that spreading tunnel pipe for escaping length, has reached the requirement of face and the two safe step pitches of lining.Connector 140 can be used Ring flange, and using bolt flange bolt hole connected it is firm, it is ensured that tunnel escape is safe and reliable.

Claims (10)

1. a kind of tunnel pipe for escaping characterized by comprising
Basic tube body, including first end and second end;
At least one telescopic tube, is set in the second end of the basic tube body and the whole relatively described second end is flexible;Every The telescopic tube includes dip section and reserved section;Relative telescopic between the adjacent telescopic tube, and in contraction state, often The reserved section of telescopic tube described in root is retained in except the tube body for accommodating the telescopic tube;
First movement device is installed on the basic tube body, to support and move the basic tube body;
The second mobile device in each reserved section is set, to support telescopic tube and band where the reserved section It moves the dip section on the telescopic tube and realizes and stretch.
2. tunnel pipe for escaping according to claim 1, which is characterized in that the basis tube body is close to the second end First positioning hole is offered on tube wall;
Second location hole is offered on the tube wall of the dip section of the every telescopic tube;The institute of the every telescopic tube It states and offers third location hole on the tube wall of reserved section.
3. tunnel pipe for escaping according to claim 2, which is characterized in that the number of the first positioning hole is one; The dip section of the every telescopic tube is equipped with multiple along second location hole arranged in a straight line, the reserved section of the every telescopic tube One third location hole is set;
When the relatively described basic tube body of the telescopic tube is moved to predetermined position, the second location hole is fixed with described first The axle center in position hole is overlapped;
When the relatively previous telescopic tube of the telescopic tube is moved to predetermined position, the second of the telescopic tube is fixed The axle center in position hole is overlapped with the axle center of the third location hole of the previous telescopic tube.
4. tunnel pipe for escaping according to claim 1, which is characterized in that the second end of the basis tube body and every The telescopic tube is mounted on sleeve close to one end of the reserved section, and the sleeve offers the 4th location hole;
The 5th location hole with the 4th location hole cooperation is offered on the dip section of the every telescopic tube.
5. tunnel pipe for escaping according to claim 4, which is characterized in that the 5th positioning on the every telescopic tube The number in hole be it is multiple, multiple 5th location holes are along arranged in a straight line.
6. tunnel pipe for escaping according to claim 1, which is characterized in that there are two the first movement devices, respectively It is mounted on the first end and second end of the basic tube body;
The first movement device includes support frame and the driving device that is mounted on support frame as described above, is installed on support frame as described above There is the walking mechanism with driving device transmission connection;Support frame as described above is removably connected on the basic tube body;
The structure of second mobile device is identical as the structure of the first movement device.
7. tunnel pipe for escaping according to claim 6, which is characterized in that support frame as described above further includes clamp device;Institute Stating clamp device includes upper adapter sleeve, lower adapter sleeve and the first connecting plate, and the upper adapter sleeve is configured with the lower adapter sleeve With the closed-loop of the basic tube body socket, the inner surface of the closed-loop is bonded with the outer surface of the basic tube body;It is described First connecting plate is arranged in the bottom of the lower adapter sleeve and connect with support frame as described above.
8. tunnel pipe for escaping according to claim 7, which is characterized in that support frame as described above includes the second connecting plate, the Three connecting plates and the more elevating levers between the second connecting plate and third connecting plate;First connecting plate and described second More damping springs are connected between connecting plate.
9. tunnel pipe for escaping according to claim 8, which is characterized in that the outer cover of the every damping spring is equipped with Telescopic fixing sleeve.
10. tunnel pipe for escaping according to claim 1, which is characterized in that the first end of the basis tube body is provided with For being connected the connector of another basic tube body.
CN201910488795.8A 2019-06-05 2019-06-05 Tunnel escape pipeline Active CN110067593B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910488795.8A CN110067593B (en) 2019-06-05 2019-06-05 Tunnel escape pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910488795.8A CN110067593B (en) 2019-06-05 2019-06-05 Tunnel escape pipeline

Publications (2)

Publication Number Publication Date
CN110067593A true CN110067593A (en) 2019-07-30
CN110067593B CN110067593B (en) 2024-03-22

Family

ID=67372585

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910488795.8A Active CN110067593B (en) 2019-06-05 2019-06-05 Tunnel escape pipeline

Country Status (1)

Country Link
CN (1) CN110067593B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110529659A (en) * 2019-08-08 2019-12-03 浙江恒则熙交通科技有限公司 A kind of auxiliary device for connecting and transporting for pipe for escaping
CN113217085A (en) * 2021-06-23 2021-08-06 中铁二十三局集团有限公司 Tunnel escape pipeline and construction method thereof
CN116122823A (en) * 2023-03-29 2023-05-16 山东鼎昌复合材料有限公司 Tunnel evacuation channel construction device and method
CN116398226A (en) * 2023-05-12 2023-07-07 中铁建安工程设计院有限公司 Telescopic safety channel for tunnel

Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1378561A (en) * 1972-04-27 1974-12-27 Uyeda H Escape equipment
US4244443A (en) * 1978-11-02 1981-01-13 Kabushiki Kaisha Naka Gijutsu Kenkyusho Drawer type emergency escape
WO1990011799A1 (en) * 1989-04-08 1990-10-18 Telescape (Uk) Limited Escape chute
CN203258249U (en) * 2013-05-13 2013-10-30 江苏宏发工程尼龙有限公司 Nylon pipeline expansion joint
CN104213933A (en) * 2014-08-26 2014-12-17 王雅君 Prearranged retractable mine lifesaving pipeline
CN104975874A (en) * 2015-07-09 2015-10-14 中铁城建集团有限公司 Escaping safety channel upon tunnel construction collapse
CN204783099U (en) * 2015-07-21 2015-11-18 福建高新源工程科技有限公司 Load bearing structure of car flees in tunnel
CN204783100U (en) * 2015-07-21 2015-11-18 福建高新源工程科技有限公司 Safe passway for escaping turn to device
CN105089691A (en) * 2015-07-21 2015-11-25 福建高新源工程科技有限公司 Tunnel escape car
KR101691521B1 (en) * 2016-07-01 2016-12-30 주식회사 케이에스메탈 Emergency Rescue System in Tunnel
CN107331232A (en) * 2017-07-03 2017-11-07 天津润木科技有限公司 A kind of tunnel escape experiencing system
CN206903687U (en) * 2017-03-28 2018-01-19 赵志明 A kind of mine emergency survival capsule
CN206957760U (en) * 2017-05-27 2018-02-02 云南公投建设集团隧道工程有限公司 The escape tube for being easy to delivery to install
CN107933228A (en) * 2017-12-31 2018-04-20 许润柱 A kind of multipurpose car and boat
CN207944984U (en) * 2018-03-03 2018-10-09 中交第二航务工程局有限公司 A kind of self-propelled tunnel pipe for escaping
CN109057856A (en) * 2018-07-02 2018-12-21 昆明理工大学 Extension type lightweight survival capsule in a kind of tunnel
US20190063058A1 (en) * 2016-02-29 2019-02-28 FIMARC Bezpieczenstwo i Ochrona Przeciwpozarowa Biuro Ekspertyz, Doradztwa i Nadzoru Emergency escape tunnel
CN208885009U (en) * 2018-08-28 2019-05-21 青岛一建集团有限公司 A kind of adjustable building garden construction shovel
CN209959288U (en) * 2019-06-05 2020-01-17 中交一公局海威工程建设有限公司 Tunnel escape pipeline

Patent Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1378561A (en) * 1972-04-27 1974-12-27 Uyeda H Escape equipment
US4244443A (en) * 1978-11-02 1981-01-13 Kabushiki Kaisha Naka Gijutsu Kenkyusho Drawer type emergency escape
WO1990011799A1 (en) * 1989-04-08 1990-10-18 Telescape (Uk) Limited Escape chute
CN203258249U (en) * 2013-05-13 2013-10-30 江苏宏发工程尼龙有限公司 Nylon pipeline expansion joint
CN104213933A (en) * 2014-08-26 2014-12-17 王雅君 Prearranged retractable mine lifesaving pipeline
CN104975874A (en) * 2015-07-09 2015-10-14 中铁城建集团有限公司 Escaping safety channel upon tunnel construction collapse
CN105089691A (en) * 2015-07-21 2015-11-25 福建高新源工程科技有限公司 Tunnel escape car
CN204783100U (en) * 2015-07-21 2015-11-18 福建高新源工程科技有限公司 Safe passway for escaping turn to device
CN204783099U (en) * 2015-07-21 2015-11-18 福建高新源工程科技有限公司 Load bearing structure of car flees in tunnel
US20190063058A1 (en) * 2016-02-29 2019-02-28 FIMARC Bezpieczenstwo i Ochrona Przeciwpozarowa Biuro Ekspertyz, Doradztwa i Nadzoru Emergency escape tunnel
KR101691521B1 (en) * 2016-07-01 2016-12-30 주식회사 케이에스메탈 Emergency Rescue System in Tunnel
CN206903687U (en) * 2017-03-28 2018-01-19 赵志明 A kind of mine emergency survival capsule
CN206957760U (en) * 2017-05-27 2018-02-02 云南公投建设集团隧道工程有限公司 The escape tube for being easy to delivery to install
CN107331232A (en) * 2017-07-03 2017-11-07 天津润木科技有限公司 A kind of tunnel escape experiencing system
CN107933228A (en) * 2017-12-31 2018-04-20 许润柱 A kind of multipurpose car and boat
CN207944984U (en) * 2018-03-03 2018-10-09 中交第二航务工程局有限公司 A kind of self-propelled tunnel pipe for escaping
CN109057856A (en) * 2018-07-02 2018-12-21 昆明理工大学 Extension type lightweight survival capsule in a kind of tunnel
CN208885009U (en) * 2018-08-28 2019-05-21 青岛一建集团有限公司 A kind of adjustable building garden construction shovel
CN209959288U (en) * 2019-06-05 2020-01-17 中交一公局海威工程建设有限公司 Tunnel escape pipeline

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110529659A (en) * 2019-08-08 2019-12-03 浙江恒则熙交通科技有限公司 A kind of auxiliary device for connecting and transporting for pipe for escaping
CN110529659B (en) * 2019-08-08 2021-04-20 浙江恒则熙交通科技有限公司 Auxiliary device for connecting and transporting escape pipeline
CN113217085A (en) * 2021-06-23 2021-08-06 中铁二十三局集团有限公司 Tunnel escape pipeline and construction method thereof
CN116122823A (en) * 2023-03-29 2023-05-16 山东鼎昌复合材料有限公司 Tunnel evacuation channel construction device and method
CN116122823B (en) * 2023-03-29 2023-08-15 山东鼎昌复合材料有限公司 Tunnel evacuation channel construction device and method
CN116398226A (en) * 2023-05-12 2023-07-07 中铁建安工程设计院有限公司 Telescopic safety channel for tunnel
CN116398226B (en) * 2023-05-12 2023-11-14 中铁建安工程设计院有限公司 Telescopic safety channel for tunnel

Also Published As

Publication number Publication date
CN110067593B (en) 2024-03-22

Similar Documents

Publication Publication Date Title
CN110067593A (en) Tunnel pipe for escaping
NO341353B1 (en) Towers of prefabricated prestressed concrete parts
CN208919476U (en) It is a kind of for fixing the support device of bridge pipeline
CN106438215A (en) Tower drum used for wind driven generator
CN206036390U (en) Pipeline rising -falling tone is put by paper -back edition
CN103451338B (en) Method for installing ascending tubes and five-way balls of blast furnace gas systems
WO2011147481A2 (en) Offshore foundation structure, offshore foundation and method of establishing the same
CN211474127U (en) Shield constructs portal reinforced structure for track traffic
CN209959288U (en) Tunnel escape pipeline
US20100229473A1 (en) Pneumatic Tower Design
CN111424658A (en) Anchor rod construction device for constructional engineering
CN206177510U (en) A multi -functional calibration device for miniature soil pressure cell
CN203890904U (en) Assembly construction platform equipment for steel pipe sheets of large-diameter corrugated steel pipe culvert
CN102776890A (en) Underwater pushing correcting method of steel cofferdam and pushing device of steel cofferdam
CN212510062U (en) Face pipe erects fixed knot and constructs
CN212927858U (en) Concrete pouring device for shield starting base
JP6604458B1 (en) Pile holding jig, pile holding jig assembly, and construction method for holding the position of the pile
CN210766398U (en) Be used for support base stone to reserve bolt hole construction equipment
CN207260629U (en) Adjustable quick basement roof reinforces support system
CN206815191U (en) A kind of full framing space beam-ends cable guide pipe positioner
CN217105835U (en) Fixing device for preventing FRP pipe come-up when concrete placement
CN217815503U (en) Novel structural connection fastening device for civil engineering
CN214572246U (en) Auxiliary supporting mechanism for construction of cathode protection test pile
CN218542250U (en) Device suitable for supplementary check of little hole footpath straight line tunnel
CN113653343B (en) A spill grey device for PHC tubular pile body location mark

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant