CN102776890A - Underwater pushing correcting method of steel cofferdam and pushing device of steel cofferdam - Google Patents

Underwater pushing correcting method of steel cofferdam and pushing device of steel cofferdam Download PDF

Info

Publication number
CN102776890A
CN102776890A CN2012102721674A CN201210272167A CN102776890A CN 102776890 A CN102776890 A CN 102776890A CN 2012102721674 A CN2012102721674 A CN 2012102721674A CN 201210272167 A CN201210272167 A CN 201210272167A CN 102776890 A CN102776890 A CN 102776890A
Authority
CN
China
Prior art keywords
steel cofferdam
pile foundation
thrustor
jacking
pushing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012102721674A
Other languages
Chinese (zh)
Inventor
张鸿
唐衡
何承海
彭琳琳
陈宏宝
许建伦
谢德宽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
CCCC SHEC Fourth Engineering Co Ltd
Original Assignee
CCCC Second Harbor Engineering Co
CCCC SHEC Fourth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co, CCCC SHEC Fourth Engineering Co Ltd filed Critical CCCC Second Harbor Engineering Co
Priority to CN2012102721674A priority Critical patent/CN102776890A/en
Publication of CN102776890A publication Critical patent/CN102776890A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses an underwater pushing correcting method and a pushing device of a steel cofferdam, belonging to the field of a construction method and a construction device of a foundation of a bridge. The method comprises the steps of connecting the deviated one side of the steel cofferdam with a plurality of formed file foundations to be taken as acting points; arranging a plurality of controllable telescopic pushing devices between the deviated steel cofferdam and the formed pile foundation on the outmost side taken as the acting point; starting the pushing devices, and resetting the steel cofferdam by the jacking force applied by the pushing devices; directly lifting the pushing devices to complete the detaching. The pushing devices comprise front bearing jacking supports, rear bearing bases and controllable telescopic mechanisms for connecting the front bearing jacking supports and the rear bearing bases, the shapes of the cross sections of the front sides of the front bearing jacking supports are identical to the shape of the cross section of the inner side of the steel cofferdam, and the shapes of the cross sections of the rear sides of the rear bearing bases are identical to those of the cross sections of the outer sides of the formed pile foundation. According to a deviation correcting method and a deviation correcting device suitable for large-size structure members such as the steel cofferdam disclosed by the invention, a field device can be utilized directly, so that the deviation correcting can be realized simply and rapidly.

Description

A kind of steel cofferdam is the method for correcting error and the thrustor thereof of pushing tow under water
Technical field
The invention belongs to bridge foundation construction method and device field thereof, be applicable to the correction of off normal in heavy steel cofferdam or the open caisson foundation sinking process.
Background technology
Steel cofferdam or open caisson are works important in the bridge foundation.After steel cofferdam adopts on-the-spot spelling to accomplish, adopt locating guide device to transfer.Steel cofferdams etc. mainly rely on guiding device to carry out sinking in place in the sinking process.In the sinking process, in case situation such as steel cofferdam off normal takes place, because steel cofferdam is from great, and entry, the difficulty of correcting off normal is bigger.In at present existing deviation correcting technology, measures such as the outside tractive of the steel cofferdam of employing, uneven prestowage are arranged.In the existing working measure, often need a large amount of temporary measure materials input.The Deviation Correction Construction difficulty is high, operating expenses has high input, the construction period is long.Off normal is corrected very difficulty.
Summary of the invention
The objective of the invention is to: propose the off normal correcting method and the device thereof of large structure such as a kind of suitable steel cofferdam, can directly utilize field device, realize that simply, apace off normal corrects.
The object of the invention realizes through following technical proposals:
A kind of steel cofferdam is the method for correcting error of pushing tow under water, may further comprise the steps successively:
1), select somely to have become pile foundation, and connects, form whole force structure as origin of force in a side of steel cofferdam generation off normal;
2), become to place some controlled flexible thrustors between the pile foundation at steel cofferdam that off normal takes place and aforementioned outermost as origin of force; Concrete laying method is: the position that tilts to the inside to said steel cofferdam is transferred in the suspention of said pushing tow position, and fix at steel cofferdam and become between the pile foundation;
3), start thrustor, load jacking force step by step, the steel cofferdam part of pushing tow generation off normal progressively, the jacking force that applies through thrustor resets steel cofferdam;
4), after the control thrustor retracted for clearance, directly thrustor is promoted and accomplishes dismounting.
As optimal way, in the said step 1), the outside become pile foundation and adjacent inboard to become between pile foundation to form the triangle syndetons through 2 connectors, the pile foundation that becomes in the outside is the summit of triangle syndeton.
A kind of aforementioned steel cofferdam is the special-purpose thrustor of the method for correcting error of pushing tow under water; Pressure-bearing jacking, back pressure-bearing base and the controlled telescoping mechanism that is connected both before comprising; The inboard section configuration of pressure-bearing jacking front side section configuration and steel cofferdam is coincide before said, and back pressure-bearing base rear side section configuration matches with becoming pile foundation outside section configuration.
In the such scheme, preceding pressure-bearing jacking contacts with the steel cofferdam wall body, preceding pressure-bearing jacking front side section configuration should with the inboard crosssection shape design of steel cofferdam, both match.Back pressure-bearing base contacts with becoming pile foundation, and back pressure-bearing base rear side section configuration should match with becoming pile foundation outside section.
As optimal way, said controlled telescoping mechanism comprises the inside and outside conduit of slip socket, and the jack and the length adjustment mechanism that are positioned at inner catheter, and said inner catheter and said preceding pressure-bearing jacking are fixed, and outer catheter and said back pressure-bearing base are fixed.As optimal way, said length adjustment mechanism is some dismountable adjustment cushion blocks being located between jack and the back pressure-bearing base.
As further optimal way, said preceding pressure-bearing jacking front side also is provided with friction pair.
In the such scheme, between steel cofferdam inboard and preceding pressure-bearing jacking front side friction pair is set, prevents slippage.
The course of work is: when steel cofferdam sinks, sink in the outside of pile foundation often.When the off normal of large structures such as steel cofferdam, between the pile foundation and steel cofferdam that the thrustor suspension installation has been become in the cofferdam through the diver.Because this device is telescopic device, starts thrustor and implement pushing tow.During pushing tow, be origin of force to become pile foundation, the steel cofferdam part of pushing tow generation off normal.The jacking force that applies through thrustor resets steel cofferdam.
Beneficial effect of the present invention: the application's method for correcting error directly utilizes and has existingly become pile foundation to carry out the pushing tow steel cofferdam, and to actual stake footpath and steel cofferdam size, between the two not strict demand of spacing.This job practices is simple to operate, and the pushing tow effect is obvious under water.The making of the application's deviation correcting device is simple, can, spacing field fabrication big or small according to actual stake footpath and steel cofferdam.Making, easy to use, the pushing tow effect is obvious.
Description of drawings
Fig. 1 strengthens sketch map local connection of the pile foundation of the one-tenth steel casing of the embodiment of the invention;
Fig. 2 is the steel cofferdam pushing tow position view of the embodiment of the invention;
Fig. 3 is the thrustor mounting plane sketch map of the embodiment of the invention;
Fig. 4 is the thrustor structural representation of the embodiment of the invention;
Wherein 1 for steel cofferdam, 2 for become pile foundation, 3 for the steel casing, 4 for connector, 5 for thrustor, 6 for preceding pressure-bearing jacking, 7 for back pressure-bearing base, 8 for the adjustment cushion block, 9 for inner catheter, 10 for outer catheter, 11 for jack, 12 be friction pair.
The specific embodiment
Following non-limiting examples is used to explain the present invention.
A kind of steel cofferdam is the method for correcting error of pushing tow under water, may further comprise the steps successively:
1) side that, at steel cofferdam 1 off normal takes place is selected somely to have become pile foundation 2 as origin of force; And the steel casing 3 that its outer wall encirclement is fixed couples together through connector 4; Form whole force structure,, do not take place to have become pile foundation 2 impaired to guarantee becoming the stressed reliable of pile foundation 2.According to the size of jacking force, in conjunction with pile base concrete intensity and steel casing wall thickness, material, Modeling Calculation goes out the pile foundation of one-tenth 2 quantity of required connection.As optimal way, become the pile foundation 2 and the adjacent inboard in the outside have become 2 of pile foundations to pass through 2 connectors, 4 formation triangle syndetons, and the pile foundation 2 that becomes in the outside is the summit of triangle syndeton.As shown in Figure 1.
2), become to place some controlled flexible thrustors 5 between the pile foundation 2 at steel cofferdam 1 that off normal takes place and aforementioned outermost as origin of force; Concrete laying method is: the position that tilts to the inside to steel cofferdam 1 is transferred in 5 suspentions of pushing tow position, and fixing is at steel cofferdam 1 with become between the pile foundation 2; Installation can be adopted artificial auxiliary installation of diver under water.Go into the mud degree of depth and the outside, cofferdam soil property situation according to the sword pin, adopt the soil mechanics computational methods, calculate the size of required jacking force, confirm to install the quantity of thrustor 5.Because steel cofferdam 1 pushing tow position 5 is at the position that steel cofferdam 1 tilts to the inside, when thrustor 5 was transferred installation from top to bottom, the inclination screens through steel cofferdam 1 was at steel cofferdam 1 and become between the pile foundation 2 to fix.As shown in Figure 2.
3), start thrustor 5, load jacking force step by step, steel cofferdam 1 part of pushing tow generation off normal progressively, the jacking force that applies through thrustor 5 resets steel cofferdam 1;
4), after control thrustor 5 retracted for clearance, directly thrustor 5 is promoted and accomplishes dismounting.Because thrustor 5 has retractility, after pushing tow resets, directly thrustor 5 is promoted.
Like Fig. 3, shown in 4; A kind of aforementioned steel cofferdam is the special-purpose thrustor of the method for correcting error of pushing tow under water; Pressure-bearing jacking 6, back pressure-bearing base 7 and the controlled telescoping mechanism that is connected both before comprising, preceding pressure-bearing jacking 6 front side section configurations and steel cofferdam 1 inboard section configuration are coincide, and between steel cofferdam 1 inboard and preceding pressure-bearing jacking 6 front sides friction pair 12 are set; Prevent slippage, back pressure-bearing base 7 rear side section configurations match with becoming pile foundation 2 outside section configurations.As optimal way, controlled telescoping mechanism comprises the inside and outside conduit 9,10 of slip socket, and the jack 11 and the length adjustment mechanism that are positioned at inner catheter 9, and inner catheter 9 is fixed with preceding pressure-bearing jacking 6, and outer catheter 10 is fixing with back pressure-bearing base 7.As optimal way, length adjustment mechanism is some dismountable adjustment cushion blocks 8 being located between jack 11 and the back pressure-bearing base 7.Apparatus main body is advisable with structure steel fabrication.Inner catheter 9 and preceding pressure-bearing jacking 6 welding, outer catheter 10 and 7 welding of back pressure-bearing base, outer catheter 10 diameters should be greater than inner catheter 9 diameters, to guarantee that inner catheter 9 is free to slide in outer catheter 10.Whole device is in place through suspention under water under water.
The above is merely preferred embodiment of the present invention, not in order to restriction the present invention, all any modifications of within spirit of the present invention and principle, being done, is equal to and replaces and improvement etc., all should be included within protection scope of the present invention.

Claims (6)

1. the steel cofferdam method for correcting error of pushing tow under water is characterized in that: may further comprise the steps successively:
1), select somely to have become pile foundation, and connects, form whole force structure as origin of force in a side of steel cofferdam generation off normal;
2), become to place some controlled flexible thrustors between the pile foundation at steel cofferdam that off normal takes place and aforementioned outermost as origin of force; Concrete laying method is: the position that tilts to the inside to said steel cofferdam is transferred in the suspention of said pushing tow position, and fix at steel cofferdam and become between the pile foundation;
3), start thrustor, load jacking force step by step, the steel cofferdam part of pushing tow generation off normal progressively, the jacking force that applies through thrustor resets steel cofferdam;
4), after the control thrustor retracted for clearance, directly thrustor is promoted and accomplishes dismounting.
2. steel cofferdam as claimed in claim 1 is the method for correcting error of pushing tow under water; It is characterized in that: in the said step 1); Become pile foundation and the adjacent inboard in the outside have become between pile foundation through 2 connectors formation triangle syndetons, and the pile foundation that becomes in the outside is the summit of triangle syndeton.
3. claim 1 or the 2 described steel cofferdams special-purpose thrustor of the method for correcting error of pushing tow under water; It is characterized in that: pressure-bearing jacking, back pressure-bearing base and the controlled telescoping mechanism that is connected both before comprising; The inboard section configuration of pressure-bearing jacking front side section configuration and steel cofferdam is coincide before said, and back pressure-bearing base rear side section configuration matches with becoming pile foundation outside section configuration.
4. thrustor as claimed in claim 3; It is characterized in that: said controlled telescoping mechanism comprises the inside and outside conduit of slip socket; And the jack and the length adjustment mechanism that are positioned at inner catheter, said inner catheter and said preceding pressure-bearing jacking are fixed, and outer catheter and said back pressure-bearing base are fixed.
5. thrustor as claimed in claim 4 is characterized in that: said length adjustment mechanism is some dismountable adjustment cushion blocks being located between jack and the back pressure-bearing base.
6. like claim 4 or 5 described thrustors, it is characterized in that: pressure-bearing jacking front side also is provided with friction pair before said.
CN2012102721674A 2012-08-02 2012-08-02 Underwater pushing correcting method of steel cofferdam and pushing device of steel cofferdam Pending CN102776890A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012102721674A CN102776890A (en) 2012-08-02 2012-08-02 Underwater pushing correcting method of steel cofferdam and pushing device of steel cofferdam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012102721674A CN102776890A (en) 2012-08-02 2012-08-02 Underwater pushing correcting method of steel cofferdam and pushing device of steel cofferdam

Publications (1)

Publication Number Publication Date
CN102776890A true CN102776890A (en) 2012-11-14

Family

ID=47121986

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012102721674A Pending CN102776890A (en) 2012-08-02 2012-08-02 Underwater pushing correcting method of steel cofferdam and pushing device of steel cofferdam

Country Status (1)

Country Link
CN (1) CN102776890A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110512522A (en) * 2019-07-31 2019-11-29 中铁大桥局集团有限公司 A kind of compartment method and structure for steel boxed cofferdam large volume back cover
CN110761575A (en) * 2019-10-17 2020-02-07 上海市基础工程集团有限公司 Recoverable device for dry operation construction of partial pool wall transformation under full-water operation working condition of pool
CN112323831A (en) * 2020-10-26 2021-02-05 毛小广 A double-walled cofferdam structure for hydraulic and hydroelectric engineering
CN113202104A (en) * 2021-05-06 2021-08-03 中山大学 Grouting plugging method for offshore wind turbine pile foundation

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002364006A (en) * 2001-06-06 2002-12-18 Ohbayashi Corp Construction method for underwater foundation
CN101608453A (en) * 2009-07-06 2009-12-23 广州市第二市政工程有限公司 The process of rectifying deviation of open caisson by jacking balance of jack
CN202730784U (en) * 2012-08-02 2013-02-13 中交二航局第四工程有限公司 Underwater thrusting device used for deviation correction of steel cofferdam

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002364006A (en) * 2001-06-06 2002-12-18 Ohbayashi Corp Construction method for underwater foundation
CN101608453A (en) * 2009-07-06 2009-12-23 广州市第二市政工程有限公司 The process of rectifying deviation of open caisson by jacking balance of jack
CN202730784U (en) * 2012-08-02 2013-02-13 中交二航局第四工程有限公司 Underwater thrusting device used for deviation correction of steel cofferdam

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
于长海等: "大直径钢围堰纠偏技术研究", 《公路》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110512522A (en) * 2019-07-31 2019-11-29 中铁大桥局集团有限公司 A kind of compartment method and structure for steel boxed cofferdam large volume back cover
CN110761575A (en) * 2019-10-17 2020-02-07 上海市基础工程集团有限公司 Recoverable device for dry operation construction of partial pool wall transformation under full-water operation working condition of pool
CN110761575B (en) * 2019-10-17 2021-05-28 上海市基础工程集团有限公司 Recoverable device for dry operation construction of partial pool wall transformation under full-water operation working condition of pool
CN112323831A (en) * 2020-10-26 2021-02-05 毛小广 A double-walled cofferdam structure for hydraulic and hydroelectric engineering
CN113202104A (en) * 2021-05-06 2021-08-03 中山大学 Grouting plugging method for offshore wind turbine pile foundation
CN113202104B (en) * 2021-05-06 2022-06-03 中山大学 Grouting plugging method for offshore wind turbine pile foundation

Similar Documents

Publication Publication Date Title
US10253475B2 (en) Construction device and method for offshore wind turbine foundation with piling performed later
CN105887811B (en) Ultra-deep weak soil pile integral construction method is monitored based on precise informationization
CN106065577A (en) The structure of a kind of new pile foundation underpinning and method
CN102776890A (en) Underwater pushing correcting method of steel cofferdam and pushing device of steel cofferdam
CN104532843B (en) A kind of steel column location straightening method of stand column pile
JP2018100578A (en) Jacket position adjustment mechanism and building method of landing style foundation
CN102011402B (en) Construction method of long auger drilling concrete-grouted back-plugged profile steel piles
CN104453948B (en) A kind of construction technology of big cross section bored tunnel vertical prestressing steel pipe support
CN104631338A (en) Steel boxed cofferdam and positioning construction method
CN109667273A (en) A kind of construction method of deep foundation pit supporting structure
CN106151679B (en) The towed counterpart method in large diameter reinforced concrete pipe road
CN113718799B (en) Quick emergency diagonal bracing for foundation pit rescue and construction method thereof
CN103276729B (en) A kind of movable steel casing and adopt this steel pile casting to carry out cast-in-place pile construction method
CN202595747U (en) Section steel guide frame for piling U-shaped concrete sheet pile
CN202730784U (en) Underwater thrusting device used for deviation correction of steel cofferdam
CN208167749U (en) Stable steel purlin support system in Deep Foundation Pit of Metro Stations digging process
KR100751573B1 (en) Reinforcement apparatus of water pipe in weakness ground
CN110761807A (en) Assembling system and assembling method for prefabricated assembled jacking pipe
CN214366146U (en) Novel high-stress soft rock tunnel advanced grouting anchor pipe
CN208844617U (en) Half floatation type immersed tube tunnel of underwater support
CN207213329U (en) A kind of supporting construction of oil pipeline
KR100900995B1 (en) Messer shield excavator apparatus for curved tunnel excavation and excavation method using the same
CN205371804U (en) Equipment that shallow buried depth push pipe control ground structure warp
CN205171527U (en) Steel sheet pile
CN215594060U (en) Wall structure is led to diaphragm wall that narrow space is close to pipeline

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20121114