CN110061470A - Exempt to lift new construction method based on tunnel cable - Google Patents

Exempt to lift new construction method based on tunnel cable Download PDF

Info

Publication number
CN110061470A
CN110061470A CN201910325614.XA CN201910325614A CN110061470A CN 110061470 A CN110061470 A CN 110061470A CN 201910325614 A CN201910325614 A CN 201910325614A CN 110061470 A CN110061470 A CN 110061470A
Authority
CN
China
Prior art keywords
cable
tunnel
aerial
coaster
special
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910325614.XA
Other languages
Chinese (zh)
Other versions
CN110061470B (en
Inventor
杨曙照
杨留声
董锐
程生安
黄浩军
张弘毅
张迎
李辛欣
孟溪
张明
黄璞
姜涛
刘祥
徐刚良
张迎龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Henan Electric Power Co Zhengzhou Power Supply Co
Zhengzhou Electric Power Design Institute Of China Electric Power Equipment And Technology Co ltd
Zhengzhou Xianghe Group Co ltd
State Grid Corp of China SGCC
Original Assignee
Zhengzhou Xianghe Group Co Ltd Electric Power Installation Branch
State Grid Corp of China SGCC
China Electric Power Equipment and Technology Co Ltd
Zhengzhou Power Supply Co of Henan Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Xianghe Group Co Ltd Electric Power Installation Branch, State Grid Corp of China SGCC, China Electric Power Equipment and Technology Co Ltd, Zhengzhou Power Supply Co of Henan Electric Power Co filed Critical Zhengzhou Xianghe Group Co Ltd Electric Power Installation Branch
Priority to CN201910325614.XA priority Critical patent/CN110061470B/en
Publication of CN110061470A publication Critical patent/CN110061470A/en
Application granted granted Critical
Publication of CN110061470B publication Critical patent/CN110061470B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • H02G1/08Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling
    • H02G1/088Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling using pulling devices movable inside conduits
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/08Installations of electric cables or lines in or on the ground or water in tunnels

Abstract

Exempt to lift new construction method based on tunnel cable the invention discloses one kind, it is laid suitable for high voltage power transmission power tunnel cable, include the following steps: 1) cable tunnel well external equipment arrangement: determining the fixation position of cable reel stent, fixed V-type cable drum, the hanging angle pulley of installation;2) cable is into well: for cable uncoiling on V-type cable drum, passing through hanging angle pulley will be in cable uncoiling to tunnel shaft;3) equipment is arranged in cable tunnel: the aerial quarter block of installation cable, electric traction, which are twisted, unfolds Special-purpose bench coaster with tunnel cable straight line;4) hauling rope is arranged: hauling rope is wrapped in electric traction and is twisted, and pass through tunnel cable straight line unfolding Special-purpose bench coaster and the aerial quarter block of cable, other end connecting cable;5) cable pulling;6) cable position is checked;7) equipment Removal;8) cable laying quality is checked;Construction efficiency of the present invention is high, at low cost, while can reduce the cable fault in work progress.

Description

Exempt to lift new construction method based on tunnel cable
Technical field
The present invention relates to a kind of power cable layer construction methods of installation, and in particular to one kind is exempted from lift based on tunnel cable and applied Work new method belongs to tunnel inner cable installation Technology field.
Background technique
Cable tunnel is the tunnel for being used to be laid with cable, for that can accommodate walking for the cable being largely laid on cable bearer Corridor or tunnel type structures.In power demand today's society growing day by day, especially in city, relative to other laying sides The advantage of formula, cable tunnel is apparent: 1. cable tunnel is disposable investment construction, is equipped with many cable branch in tunnel Frame, after tunnel is built up, it is only necessary to check on time, without proposing new plan to relevant departments, facilitate maintenance, maintenance or more Change cable;2. cable tunnel can be reliably prevented external force destruction, the influence of external condition is reduced, construction is facilitated;3. can accommodate big Cable is measured, and is not influenced vulnerable to external force, cable life is in a disguised form improved.In short, the application of cable tunnel can not for urban development Or lack, the construction technology laid in cable tunnel should also grow with each passing hour.
Technical difficult points are laid in cable tunnel at present to be: 1) cable that laying is completed being promoted to cable bearer, This process still relies primarily on manually at present, and since cable self weight is larger, lifting process need to consume a large amount of manpowers, low efficiency Under;Secondly, space is limited in cable tunnel, cable bearer is metallic facility again, easily causes personnel and cable in work progress Damage.
2) in practice of construction when meeting with tunnel turning, traditional construction technique solution is special in turning setting Personnel pass through bend by dragger tractive force bending cable using crowbar support cable.There are many for conventional construction method Drawback: increasing unnecessary human cost, and speed of application is slow, be easy to cause the damage of personnel and cable.
3) traditional work uses diesel oil motor-driven grinding mill, since space is limited in cable tunnel, unsmooth, conventional diesel engine of divulging information Dynamic the disadvantages of to be twisted that there are noises big, harmful gas emission is big, volume is large-scale handicapped.
Summary of the invention
The technical problems to be solved by the present invention are: overcoming the deficiencies in the prior art, provide a kind of based on tunnel Cable exempts to lift new construction method, so that construction light and fast of the cable at tunnel turning, and it is not necessarily to manpower, improve construction effect Rate reduces construction cost, while reducing the cable fault in work progress.
The present invention is adopted the technical scheme that in order to solve the technical problem: one kind exempting from the new side of lift construction based on tunnel cable Method includes the following steps:
Preparation includes:
1) the outer ground of tunnel shaft is cleared up, is smooth;
2) fence is arranged at tunnel well head;
3) it is disposed available manpower according to work on the spot process and tool equipment.
Operating procedure:
1) well external equipment in cable tunnel is arranged: fixation position of the cable reel stent outside well on ground is determined, in cable reel stent Unpowered V-type cable drum bracket, and fixed V-type cable drum are set up between tunnel well head, hanging turn of installation at tunnel well head To pulley.
2) cable is into well: cable reel is placed on the cable reel stent, by cable uncoiling on the V-type cable drum, And it will be in cable uncoiling to tunnel shaft across the hanging angle pulley.
3) equipment is arranged in cable tunnel: tunnel entrance installs the aerial quarter block of cable, installs electronic lead in tunnel Draw and be twisted, every five meter ampere fills the tunnel cable straight line unfolding Special-purpose bench coaster on tunnel wall mounting, and passes through cunning The long handle bolt of vehicle bottom is fixed as one with tunnel cable bracket;Tunnel turning, by the big of angle of turn and cable size The aerial quarter block of cable, and the adjustable pine of traction device of the aerial quarter block upper end of the cable are installed in small selection Tightly.
4) hauling rope is arranged: the one ends wound of hauling rope being rolled in the mill that the electric traction is twisted, passes through the tunnel Road cable straight line unfolds Special-purpose bench coaster and the aerial quarter block of the cable, other end connecting cable;The hauling rope exhibition It puts when being twisted upper to the cable electric traction, the hauling rope rolls on winding not less than 3 in the mill that the electric traction is twisted Circle, has stayed hauling rope tail rope by special messenger.
5) cable pulling: on inspection equipment install and connect it is errorless after, traction instruction is assigned by operating personnel, described in starting Electric traction is twisted trailing cable, and end sends special messenger's follow-observation cable by coaster situation during cable pulling, when logical When crossing at turning of cable, reducing hauling speed ensures that cable passes through the aerial quarter block of the cable, until cable is whole Traction stops afterwards in place.
6) it checks cable position: checking whether the cable position on cable position and corner cable trough on cable trough arrives Position, when cable is not to the correct position on cable trough, adjustment cable until cable in place.
7) equipment Removal: cable pulling in place after, remove the hauling rope, remove the electric traction and be twisted, remove institute State tunnel cable straight line unfolding Special-purpose bench coaster and the aerial quarter block of the cable.
The method for dismounting of the tunnel cable straight line unfolding Special-purpose bench coaster are as follows: special in tunnel cable straight line unfolding With electronic top cable device is used below half meter or so before and after rack coaster of cable, cable is held up slightly, unclamps pulley and tunnel Long handle bolt between road cable bearer, takes out cable coaster from bracket, and electronic top cable device is dropped down on tunnel cable bracket ?.
The method for dismounting of the aerial quarter block of cable are as follows: loosen the aerial quarter block take-up of the cable, electricity Cable stress is eased, and is twisted cooperation with the electric traction, and cable is placed the tunnel cable bracket at turning by artificial control On suitable position.
After equipment is all removed, cable snake shaped laying is carried out according to design requirement, job step is fixedly mounted.
8) it checks cable laying quality: checking the quality after the completion of cable laying, terminate operation after passed examination.
The beneficial effects of the present invention are: the present invention is lifted this working procedure without cable, cable can be directly on bracket Laying reduces difficulty of construction, reduces personnel needed for constructing, equipment volume is light, simple and quick;It also can avoid applying simultaneously It is contacted between cable and bracket during work, reduces the probability of cable fault.
Detailed description of the invention
Fig. 1 is standard operating procedure figure of the invention;
Fig. 2 is the structural schematic diagram of the aerial quarter block device of cable in Fig. 1;
Fig. 3 is the structural schematic diagram that tunnel cable straight line unfolds Special-purpose bench coaster in Fig. 1;
Fig. 4 is the structural schematic diagram of electronic pre-viewing device in Fig. 1.
Specific embodiment
The present invention will be further explained in the following with reference to the drawings and specific embodiments:
Embodiment: referring to Fig. 1, one kind is exempted to lift new construction method based on tunnel cable, includes the following steps:
Preparation includes:
1) the outer ground of tunnel shaft is cleared up, is smooth;
2) safety measures such as fence are arranged at tunnel well head;
3) it is disposed available manpower according to work on the spot process and tool equipment, tool equipment includes V-type cable drum, hanging steering cunning Wheel, the aerial quarter block of cable, tunnel cable straight line unfolding Special-purpose bench coaster, hauling rope and electric traction are twisted.
Referring to fig. 2, in figure, 1- pulley, 2- long axis, 3- pulley bracket, 31- vertical rack, 32- horizontal bracket, 4- bearing, 5- column idler wheel, 6- framework, 7- opening wear pin, 8- towing pad.
The aerial quarter block of cable includes pulley 1, and pulley 1 is mounted on pulley bracket 3 by long axis 2, pulley bracket 3 by Two parallel 31 bottom of vertical rack connection horizontal brackets 32 form, and long axis 2, which runs through, to be connected under two vertical racks 31 Portion, the both ends of pulley 1 are rotatably connected on the long axis 2 between two vertical racks 31 by bearing 4, two vertical racks 31 Top is rotatably connected to column idler wheel 5 vertically, and the upper end of two vertical racks 31 is also connected with framework 6 and passes through opening The connection of pin 7 is worn, towing pad 8 is arranged in the upper end of framework 6.
Referring to Fig. 3, in figure: 9- side wheel, 10- vertical wheel axis, the horizontal wheel of 11-, 12- horizontal axis, 13-U type pedestal.
Tunnel cable straight line unfolds Special-purpose bench coaster, is made of the connection of three auxiliary pulley groups, and three auxiliary pulley groups include two secondary Side pulley blocks and a secondary bottom pulley group, two secondary side pulley blocks are vertically arranged and lower end passes through bottom pulley group connection composition U-shaped structure, side pulley blocks are made of side wheel 9 and vertical wheel axis 10, and the upper end of vertical wheel axis 10 is through connection side wheel 9, bottom pulley Group is made of horizontal wheel 11, horizontal axis 12 and U-shaped bottom seat 13, and horizontal axis 12 is through the horizontal upper end taken turns 11 and be connected to U-shaped bottom seat 13, vertical wheel Axis 10 is bolted to connection in the side of U-shaped bottom seat 13.
Referring to fig. 4, in figure: 14- motor, 15- mandril, 16- connector, 17- threaded rod, the first pin shaft of 18-, 19- pedestal, 20- adjusting nut, the second pin shaft of 21-, 22-U type bracket, 23- connecting rod, 24- control panel, 25- storage groove, 26-U type groove.
Electronic top cable device, including motor 14 and mandril 15, mandril 15 are connect with motor 14, and the bottom end of mandril 15 passes through company Connector 16 is connect with threaded rod 17, and the first pin shaft 18 is provided on connector 16, and threaded rod 17 is arranged on pedestal 19, mandril 15 Upper end connect with U-shaped anchor ear by the second pin shaft 21, be provided with control panel 24 on 15 outer surface of mandril above motor 14, 24 side of control panel is provided with storage groove.U-shaped anchor ear includes u-bracket 22 and connecting rod 23, the upper end of connecting rod 23 with The u-bracket 22 of cable used in anchor ear connects, and the lower end of connecting rod 23 utilizes the second pin shaft 21 and top by round hole thereon Bar 15 connects.
Operating procedure:
1) well external equipment in cable tunnel is arranged: determining fixed bit of the cable reel stent outside well on ground according to on-site actual situations It sets, unpowered V-type cable drum bracket, and fixed V-type cable drum, tunnel shaft is set up between cable reel stent and tunnel well head The hanging angle pulley of installation at mouthful.
2) cable is into well: cable reel is placed on cable reel stent, by cable uncoiling on V-type cable drum, and is passed through outstanding Empty angle pulley will be in cable uncoiling to tunnel shaft.
3) equipment is arranged in cable tunnel: tunnel entrance installs the aerial quarter block of cable, and cable clearance cable is aerial Quarter block by switching to level vertically, installs electric traction into cable tunnel, in tunnel and is twisted, and every five meters of tunnel wall mounting One tunnel cable straight line unfolding Special-purpose bench coaster is installed, and solid by the long handle bolt of arse and tunnel cable bracket It is set to one;Tunnel turning selects the installation aerial quarter block of cable, and cable by the size of angle of turn and cable size The traction device of aerial quarter block upper end can adjust elastic.
When construction, quarter block device is installed in design height, device is by towing pad 8 via steel wire and opposite tunnel electricity The connection of cable bracket, steel wire length are determined that the opening for opening quarter block device side wears pin 7, by cable by on-site actual situations Traction rope is passed through from 1 top of pulley, and locked opening wears pin 7.Cable laying can be carried out traditionally, cable row to bend, from Quarter block device passes through, and pulley 1 drives cable to form the tractive force of reverse tunnel inner wall, makes cable far from tunnel wall, electricity Cable forms angle of turn, passes through tunnel of turning.
Tunnel cable straight line unfolds the U-shaped bottom seat 5 of Special-purpose bench coaster and cable bearer top surface is horizontally arranged, long with pedestal Handle bolt is fixed, and cable drawing machine hawser is passed through by present apparatus drum overhead in advance, and cable head is promoted to laying by pulley Highly, pass through above present apparatus pulley blocks, sequentially lay.
4) hauling rope is arranged: the one ends wound of hauling rope being rolled in the mill that electric traction is twisted, the cable that passes through tunnel is straight Line unfolds Special-purpose bench coaster and the aerial quarter block of cable, other end connecting cable;Hauling rope is unfolded to cable electric traction When being twisted, hauling rope rolls on winding not less than 3 circles in the mill that electric traction is twisted, and has stayed hauling rope tail rope by special messenger.
5) cable pulling: on inspection equipment install and connect it is errorless after, by operating personnel assign traction instruction, start it is electronic Traction is twisted trailing cable, and end send special messenger's follow-observation cable to pass through coaster situation during cable pulling, when passing through electricity When cable turning, reducing hauling speed ensures that cable passes through the aerial quarter block of cable, until cable is all drawn in place After stop.
6) it checks cable position: checking whether the cable position on cable position and corner cable trough on cable trough arrives Position, when cable is not to the correct position on cable trough, adjustment cable until cable in place;
7) equipment Removal: cable pulling in place after, remove hauling rope, remove electric traction and be twisted, remove tunnel cable straight line exhibition Put Special-purpose bench coaster and the aerial quarter block of cable.
The method for dismounting of the aerial quarter block of cable are as follows: after the completion of laying, open a side opening and wear pin 7, unclamp connection steel Silk, removes quarter block device, and cable stress is eased, and is twisted cooperation with electric traction, and cable is placed in artificial control to be turned Suitable position on the tunnel cable bracket of crook.
The method for dismounting of tunnel cable straight line unfolding Special-purpose bench coaster are as follows: sliding in tunnel cable straight line unfolding Special-purpose bench Electronic top cable device is used below the cable of the later half rice of Chinese herbaceous peony or so, cable is held up slightly, unclamps pulley and tunnel cable branch Long handle bolt between frame, takes out cable coaster from bracket, and electronic top cable device is dropped down on tunnel cable bracket;
Electronic top cable device work when, using coaxial three-fold block by tunnel cable draw in place (height of cable at this time with The cable bearer of cable will be placed in tunnel with height) after, first in suitable position arranged orthogonal, and utilize 17 He of threaded rod Gimbal base 19 come adjust height, then by the present apparatus u-bracket 22 be aligned construction cable, using handheld terminal or open Close button starting hydraulic electric motor 14 cable is promoted, cable reach need height (cable lower surface has been higher by coaster highest Point) after, stop cable and rise operation, a groove profile slide plate is placed between the cable bearer on wall both sides, removes cable laying coaster Device on whereabouts cable to groove profile slide plate, and the electronic mandril 15 to have relaxed one's efforts is adjusted to the angle of needs, cable is pushed into Suitable position on tunnel cable bracket.
After equipment is all removed, cable snake shaped laying is carried out according to design requirement, job step is fixedly mounted.
8) it checks cable laying quality: checking the quality after the completion of cable laying, terminate operation after passed examination.
The present invention is lifted this working procedure without cable, and cable can directly be laid on bracket, reduces difficulty of construction, Personnel needed for constructing are reduced, equipment volume is light, simple and quick;It is also can avoid in work progress simultaneously between cable and bracket Contact, reduces the probability of cable fault.
The above described is only a preferred embodiment of the present invention, be not intended to limit the present invention in any form, it is all It is any simple modification, equivalent change and modification to the above embodiments according to the technical essence of the invention, still falls within In the range of technical solution of the present invention.

Claims (6)

1. one kind is exempted to lift new construction method based on tunnel cable, characterized by the following steps:
Preparation includes:
1) the outer ground of tunnel shaft is cleared up, is smooth;
2) fence is arranged at tunnel well head;
3) it is disposed available manpower according to work on the spot process and tool equipment;
Operating procedure:
1) well external equipment in cable tunnel is arranged: fixation position of the cable reel stent outside well on ground is determined, in cable reel stent Unpowered V-type cable drum bracket, and fixed V-type cable drum are set up between tunnel well head, hanging turn of installation at tunnel well head To pulley;
2) cable is into well: cable reel is placed on the cable reel stent, by cable uncoiling on the V-type cable drum, and is worn Crossing the hanging angle pulley will be in cable uncoiling to tunnel shaft;
3) equipment is arranged in cable tunnel: tunnel entrance installs the aerial quarter block of cable, and installation electric traction twists in tunnel It grinds, installation tunnel cable straight line unfolds Special-purpose bench coaster on tunnel wall mounting, and multiple cables are installed at tunnel turning Aerial quarter block;
4) hauling rope is arranged: the one ends wound of hauling rope being rolled in the mill that the electric traction is twisted, passes through the tunnel electricity Cable straight line unfolds Special-purpose bench coaster and the aerial quarter block of the cable, other end connecting cable;
5) cable pulling: on inspection equipment install and connect it is errorless after, by operating personnel assign traction instruction, start it is described electronic Traction is twisted trailing cable, and cable stops traction afterwards in place;
6) check cable position: in place whether the cable position on cable position and corner cable trough on inspection cable trough, electric When cable is not to the correct position on cable trough, adjustment cable until cable in place;
7) equipment Removal: cable pulling in place after, remove the hauling rope, remove the electric traction and be twisted, remove the tunnel Road cable straight line unfolds Special-purpose bench coaster and the aerial quarter block of the cable;
8) it checks cable laying quality: checking the quality after the completion of cable laying, terminate operation after passed examination.
2. according to claim 1 exempt to lift new construction method based on tunnel cable, it is characterised in that: operating procedure 3) in, In tunnel linear road, every five meter ampere fills the tunnel cable straight line unfolding Special-purpose bench coaster, and passes through arse Long handle bolt is fixed as one with tunnel cable bracket;Tunnel turning is selected to pacify by the size of angle of turn and cable size Fill the aerial quarter block of the cable, and the traction device of the aerial quarter block upper end of the cable can adjust it is elastic.
3. according to claim 1 exempt to lift new construction method based on tunnel cable, it is characterised in that: operating procedure 4) in, The hauling rope unfolds when being twisted upper to the cable electric traction, and the hauling rope is rolled in the mill that the electric traction is twisted Winding has stayed hauling rope tail rope by special messenger not less than 3 circles.
4. according to claim 1 exempt to lift new construction method based on tunnel cable, it is characterised in that: operating procedure 5) in, End sends special messenger's follow-observation cable by coaster situation during cable pulling, and when by turning of cable, reduction is led Drawing speed ensures that cable passes through the aerial quarter block of the cable, until cable is all drawn in place.
5. according to claim 1 exempt to lift new construction method based on tunnel cable, it is characterised in that: operating procedure 7) in, The method for dismounting of the tunnel cable straight line unfolding Special-purpose bench coaster are as follows: sliding in tunnel cable straight line unfolding Special-purpose bench Electronic top cable device is used below the cable of the later half rice of Chinese herbaceous peony or so, cable is held up slightly, unclamps pulley and tunnel cable branch Long handle bolt between frame, takes out cable coaster from bracket, and electronic top cable device is dropped down on tunnel cable bracket;It is described The method for dismounting of the aerial quarter block of cable are as follows: loosen the aerial quarter block take-up of the cable, cable stress is delayed Solution, is twisted cooperation with the electric traction, and cable is placed the suitable position on the tunnel cable bracket at turning by artificial control ?.
6. according to claim 1 exempt to lift new construction method based on tunnel cable, it is characterised in that: operating procedure 8) in, After equipment is all removed, cable snake shaped laying is carried out according to design requirement, job step is fixedly mounted.
CN201910325614.XA 2019-04-22 2019-04-22 Novel lifting-free construction method based on tunnel cable Active CN110061470B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910325614.XA CN110061470B (en) 2019-04-22 2019-04-22 Novel lifting-free construction method based on tunnel cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910325614.XA CN110061470B (en) 2019-04-22 2019-04-22 Novel lifting-free construction method based on tunnel cable

Publications (2)

Publication Number Publication Date
CN110061470A true CN110061470A (en) 2019-07-26
CN110061470B CN110061470B (en) 2020-08-28

Family

ID=67320065

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910325614.XA Active CN110061470B (en) 2019-04-22 2019-04-22 Novel lifting-free construction method based on tunnel cable

Country Status (1)

Country Link
CN (1) CN110061470B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110620354A (en) * 2019-11-01 2019-12-27 夏文杰 Multifunctional winching machine
CN112310890A (en) * 2020-10-21 2021-02-02 中色十二冶金建设有限公司 Comprehensive pipe rack cable traction and displacement laying system and application method
CN112952661A (en) * 2021-04-08 2021-06-11 北京市第三建筑工程有限公司 Installation structure and construction method for laying cable in narrow space
CN115000880A (en) * 2022-05-30 2022-09-02 广东顺德电力设计院有限公司 Laying method and laying structure of large-length high-voltage cable

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101364718A (en) * 2007-08-08 2009-02-11 上海宝冶建设有限公司 Heavy cable laying system and laying method
CN102856841A (en) * 2012-10-11 2013-01-02 山东铝业工程有限公司 Mechanical laying method for large-section overhead cable
CN103241586A (en) * 2013-04-27 2013-08-14 兖矿东华建设有限公司 Opened cable conveyor, transformation method and novel cable laying construction method
CN105896398A (en) * 2016-05-18 2016-08-24 中国十九冶集团有限公司 Large-section cable laying method
CN106505484A (en) * 2016-12-27 2017-03-15 二十二冶集团天津建设有限公司 Piping lane cable laying method
CN106505479A (en) * 2016-11-29 2017-03-15 郑州祥和集团电力安装有限公司 High-rise shelf cable laying method and device in tunnel

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101364718A (en) * 2007-08-08 2009-02-11 上海宝冶建设有限公司 Heavy cable laying system and laying method
CN102856841A (en) * 2012-10-11 2013-01-02 山东铝业工程有限公司 Mechanical laying method for large-section overhead cable
CN103241586A (en) * 2013-04-27 2013-08-14 兖矿东华建设有限公司 Opened cable conveyor, transformation method and novel cable laying construction method
CN105896398A (en) * 2016-05-18 2016-08-24 中国十九冶集团有限公司 Large-section cable laying method
CN106505479A (en) * 2016-11-29 2017-03-15 郑州祥和集团电力安装有限公司 High-rise shelf cable laying method and device in tunnel
CN106505484A (en) * 2016-12-27 2017-03-15 二十二冶集团天津建设有限公司 Piping lane cable laying method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110620354A (en) * 2019-11-01 2019-12-27 夏文杰 Multifunctional winching machine
CN112310890A (en) * 2020-10-21 2021-02-02 中色十二冶金建设有限公司 Comprehensive pipe rack cable traction and displacement laying system and application method
CN112952661A (en) * 2021-04-08 2021-06-11 北京市第三建筑工程有限公司 Installation structure and construction method for laying cable in narrow space
CN112952661B (en) * 2021-04-08 2021-12-21 北京市第三建筑工程有限公司 Installation structure and construction method for laying cable in narrow space
CN115000880A (en) * 2022-05-30 2022-09-02 广东顺德电力设计院有限公司 Laying method and laying structure of large-length high-voltage cable
CN115000880B (en) * 2022-05-30 2024-04-05 广东顺德电力设计院有限公司 Laying method and laying structure of long-length high-voltage cable

Also Published As

Publication number Publication date
CN110061470B (en) 2020-08-28

Similar Documents

Publication Publication Date Title
CN110061470A (en) Exempt to lift new construction method based on tunnel cable
CN104993422B (en) Line inspection robot on-line and off-line device and line inspection robot on-line and off-line system provided with same
CN201240810Y (en) Novel manual hoister
CN105129627B (en) The folding suspension arm assembly that electric pole is supported
CN102290742B (en) Tension stringing construction technology
CN102227070B (en) High-altitude crimping apparatus of power transmission line
CN105048336B (en) Automatic up-and-down device of line patrol robot of strain tower
CN111469717B (en) No-cross arrangement construction method for contact network at 42# turnout
CN209554495U (en) A kind of power ampere puts line apparatus
CN202004385U (en) Aloft crimping connecting device for power transmission lines
CN209193252U (en) Steering cable roller
CN208631793U (en) A kind of cable unwinding device
CN216129274U (en) Automobile overhaul device
CN113998528B (en) Paying-off device for power transmission line
CN207061699U (en) A kind of large-scale tower crane tower section introduces jacking system
CN203180430U (en) Electric winch
CN205676052U (en) Bench type transformer crane device
CN115980099A (en) High-altitude unmanned ray detection system for power transmission line and detection working method
CN109346996A (en) A kind of power construction wire tensioning device and line tightening method
CN204625053U (en) A kind of winch rope guide
CN108726371A (en) A kind of substation's GIS device hanging apparatus
CN210394970U (en) Device convenient for winding steel wire rope
CN111874745A (en) High-speed rail trackless constant-tension contact line erecting technology and device
CN112339617A (en) High-speed rail trackless constant-tension carrier cable erecting technology and device
CN208401377U (en) A kind of inspection platform for power station high voltage switchyard

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231026

Address after: 450000 Huaihe West Road, Zhongyuan District, Zhengzhou, Henan Province, 19

Patentee after: STATE GRID HENAN ELECTRIC POWER COMPANY ZHENGZHOU POWER SUPPLY Co.

Patentee after: ZHENGZHOU XIANGHE GROUP Co.,Ltd.

Patentee after: ZHENGZHOU ELECTRIC POWER DESIGN INSTITUTE OF CHINA ELECTRIC POWER EQUIPMENT AND TECHNOLOGY CO.,LTD.

Patentee after: STATE GRID CORPORATION OF CHINA

Address before: 450000 Huaihe West Road, Zhongyuan District, Zhengzhou, Henan Province, 19

Patentee before: STATE GRID HENAN ELECTRIC POWER COMPANY ZHENGZHOU POWER SUPPLY Co.

Patentee before: Zhengzhou Xianghe Group Co.,Ltd. Electric Power Installation Branch