CN110055850A CN201910336114.6A CN201910336114A CN110055850A CN 110055850 A CN110055850 A CN 110055850A CN 201910336114 A CN201910336114 A CN 201910336114A CN 110055850 A CN110055850 A CN 110055850A
Authority
CN
China
Prior art keywords
foundation pit
concrete layer
tire
vehicle
safety feature
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910336114.6A
Other languages
Chinese (zh)
Other versions
CN110055850B (en
Inventor
彭燕萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shengzhou Wanrui Technology Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910336114.6A priority Critical patent/CN110055850B/en
Publication of CN110055850A publication Critical patent/CN110055850A/en
Application granted granted Critical
Publication of CN110055850B publication Critical patent/CN110055850B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C9/00Special pavings; Pavings for special parts of roads or airfields
    • E01C9/007Vehicle decelerating or arresting surfacings or surface arrangements, e.g. arrester beds ; Escape roads, e.g. for steep descents, for sharp bends
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F15/00Safety arrangements for slowing, redirecting or stopping errant vehicles, e.g. guard posts or bollards; Arrangements for reducing damage to roadside structures due to vehicular impact
    • E01F15/14Safety arrangements for slowing, redirecting or stopping errant vehicles, e.g. guard posts or bollards; Arrangements for reducing damage to roadside structures due to vehicular impact specially adapted for local protection, e.g. for bridge piers, for traffic islands

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Road Paving Structures (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The invention discloses a kind of town road passive safety feature and its installation methods, concrete layer on the ground is poured including one, the inside of the concrete layer has poured steel reinforcement cage, steel reinforcement cage is arranged in parallel with multilayer above and below, the slope surface that a gradient is 3 ~ 6 ° is formed after the concrete layer pours, in vehicle bumper, vehicle is hoisted traveling by the low side of the slope surface, and the lateral length after the completion of the concrete layer pours is 200 ~ 300 meters;It is slow that vehicle may be implemented in this product.

Description

A kind of town road passive safety feature and its installation method
Technical field
The present invention relates to a kind of town road passive safety feature and its installation methods.
Background technique
Transfer loader, vehicle load is usually at 10 tons or more, during driving, since loading capacity is larger, because Situations such as high temperature, locking, often occurs for this brake, especially leads to brake due to frequently braking in long descending section Heat fade is extremely serious, and often there is a situation where brake failures, and since descending section is longer, vehicle can be with the mistake of brake The continuous passive acceleration of effect, finally goes out guardrail, causes extremely serious traffic accident, and existing method is under road Buffering path is built at the position of slope, buffering path is the simple structure of gravel and sand, it is sagging by being carried out to wheel, reduce the attached of wheel Put forth effort, and then play slow effect, but we will often find that, rest on the thing of the loading vehicles rollover on buffering path It is sagging serious due to ground therefore the reason is that be, cause vehicle towards the serious inclination in side, finally results in vehicle side It turns over.
Based on the above issues, we devise it is a kind of may be implemented the slow town road passive safety feature of vehicle and its Installation method.
Summary of the invention
The slow town road passive security dress of vehicle may be implemented the technical problem to be solved in the present invention is to provide a kind of It sets and its installation method.
To solve the above problems, the present invention adopts the following technical scheme:
A kind of town road passive safety feature pours concrete layer on the ground, the inside of the concrete layer including one Steel reinforcement cage is poured, steel reinforcement cage is arranged in parallel with multilayer above and below, and it is 3 ~ 6 ° that a gradient is formed after the concrete layer pours Slope surface, in vehicle bumper, vehicle is hoisted traveling by the low side of the slope surface, the concrete layer pour after the completion of transverse direction Length be 200 ~ 300 meters, a recessed foundation pit is formed after pouring in the slope surface, the depth of foundation pit is 10 ~ 20cm, Tiling has buffer mixture in the foundation pit, and the setting of foundation pit is primarily to filling buffer mixture connects when the vehicle is running Buffer mixture is touched, leads to sinking for wheel, realizes the deceleration of vehicle, it, will not since the depth of foundation pit only has 10 ~ 20cm The excessive inclination for causing vehicle, avoids vehicle from turning on one's side during buffering, and the lower section of foundation pit is concrete, and concrete has foot Enough support strengths, can satisfy the support needs of vehicle, and steel reinforcement cage has been poured in concrete, can further increase The structural strength of concrete layer, being arranged side by side at the close leftward position of the foundation pit has multiple bumper posts, the bumper post It is formed including multiple waste tires stacked above and below, and the rod piece being threaded through between multiple waste tires, the rod piece Lower end is downwardly into after passing through multiple waste tires to the concrete layer, the upper end of rod piece oblique bending rear support to the left At the top of concrete layer, multiple lateral defensive first have been poured at the top of the concrete layer, along the foundation pit The diameter of waste tire, the first waste tire is greater than 60cm, and tire is wider than 22.5cm, and the first waste tire is in casting concrete layer When, that is, fixation being poured, is not necessarily to later period others fixed form, the first waste tire is to play lateral buffer protection effect, When stop failure occurs for vehicle, the direction of vehicle is usual or controllable, therefore the setting of the first waste tire can be reminded The direction of driver's traveling, avoids more line, while when vehicle is uncontrollable, bears the shock of vehicle, reduces vehicle damage, also reduces vehicle Sweep away the risk on slope.
Preferably, every layer of steel reinforcement cage includes the more spirals being staggered in transverse and longitudinal, the diameter of spiral For 8mm ~ 12mm, ligation fixation, the spacing of laterally adjacent spiral are carried out by steel tied silk at spiral intervening portion For 20 ~ 30cm, the spacing of longitudinally adjacent spiral is 15 ~ 30cm.
Preferably, the buffer mixture includes 20 ~ 30% middle sand, and 20 ~ 25% stone, surplus is melon seeds piece, flat When paving, it is laid with again after being mixed by mixing apparatus;Above-mentioned each material is simple and easy to get, and has well after stress Deformability, be easy to cooperate wheel to realize and slow down.
Preferably, the rod piece uses diameter for the hollow steel pipe of 6cm ~ 8cm, and material is Q235 common carbon structural steel, Wall thickness is 1cm ~ 2cm.
Preferably, more tire broken wall bars are provided in the bottom of the foundation pit, close to array at the bumper post position, Pyramid shape is processed into the upper end of tire broken wall bar, and the dry lower end of tire broken wall is cast in concrete layer, and the upper end is by institute Buffer mixture to be stated to be covered, under normality, tire broken wall bar is submerged in buffer mixture, when vehicle drives into, and When travel speed is too fast, the sagging deformation of buffer mixture will cause, and then tire broken wall bar is allowed to contact with wheel, realize wheel Broken wall, the tire after broken wall generates biggish rolling resistance, helps vehicle deceleration, buffers the impact force to bumper post.
Preferably, in the inside of the bumper post, a space is formed by waste tire, should be filled in the space Rough sand can increase the ability of anti-deformation of waste tire, increase the anticollision ability of this product after filling rough sand, reduce by Routed probability after power;
Preferably, in the inside of the bumper post, a space is formed by waste tire, is banketed in the space, and plant Plant seedlings wood, cooperates nursery stock, and the mark of finishing line may be implemented, and reminds driver to carry out collision and prepares, while nursery stock can also play The effect of anticollision;
Preferably, nursery stock is one of metasequoia tree, diversiform-leaved poplar tree.
A kind of installation method of town road passive safety feature, comprising the following steps:
1) installation site of the terminal in the long descending section of super expressway as this structure is selected first;
2) leveling that the position of pre-installation is carried out to ground after leveling, forms the structure of a V-shaped relative to descending section, When vehicle is when stop failure occurs for descending section, the upward slope by flattening section, which is realized, to slow down;
3) on section after the completion of leveling, it is laid with steel reinforcement cage, every one layer of steel reinforcement cage of laying pours a layer concrete, until mixed Until solidifying soil layer pours completion, in casting concrete, need to build the wooden template for forming the foundation pit above, After concreting completion is dry and hard, the foundation pit is formed, then removes template again;
4) multiple waste tires are carried out to vertical stacking, are then inserted into rod piece, rod piece is downwardly into, and can be opened up in foundation pit The hole of insertion insertion rod piece, the upper end of rod piece are bent before factory by bending device, so that the lower end of rod piece is being inserted After entering to concrete layer, the upper surface of end in contact concrete layer thereon forms diagonal brace, wherein it is waste and old to need that there are at least one Tire is located in the foundation pit;
5) buffer mixture is filled to foundation pit, is then compacted using road roller, buffering composite soil covering is located at foundation pit Interior waste tire.
The beneficial effects of the present invention are: can be realized in the long descending section of super expressway after the completion of the present invention must mat formation Safeguard protection can drive into the present invention when stop failure occurs for vehicle, the deceleration of vehicle is realized by buffer mixture, The shock of vehicle is born by bumper post, reduces vehicle damage, this product is easy to mat formation, and condition of molding is simple, can reduce large size Traffic accident is suitble to promote the use of.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with It obtains other drawings based on these drawings.
Fig. 1 is the partial schematic diagram under overlooking state of the invention;
Fig. 2 is cross-sectional view of the invention;
Fig. 3 is the top view of steel reinforcement cage;
Fig. 4 is the top view of foundation pit;
Fig. 5 is the scheme of installation of tire broken wall bar;
Fig. 6 is top view of the present invention under implementation state;
Fig. 7 is top view of the present invention under implementation state.
Specific embodiment
All features disclosed in this specification or disclosed all methods or in the process the step of, in addition to mutually exclusive Feature and/or step other than, can combine in any way.
Any feature disclosed in this specification (including any accessory claim, abstract and attached drawing), except non-specifically chatting It states, can be replaced by other alternative features that are equivalent or have similar purpose.That is, unless specifically stated, each feature is only It is an example in a series of equivalent or similar characteristics.
In the description of the present invention, it is to be understood that, term " one end ", " other end ", " outside ", "upper", " inside ", The orientation or positional relationship of the instructions such as "horizontal", " coaxial ", " center ", " end ", " length ", " outer end " is based on shown in attached drawing Orientation or positional relationship, be merely for convenience of description of the present invention and simplification of the description, rather than the device of indication or suggestion meaning Or element must have a particular orientation, be constructed and operated in a specific orientation, therefore be not considered as limiting the invention.
In addition, in the description of the present invention, the meaning of " plurality " is at least two, such as two, three etc., unless otherwise Clear specific restriction.
In the present invention unless specifically defined or limited otherwise, term " setting ", " socket ", " connection ", " running through ", Terms such as " grafting " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral;It can be with It is mechanical connection, is also possible to be electrically connected;It can be directly connected, two can also be can be indirectly connected through an intermediary The interaction relationship of connection or two elements inside a element, unless otherwise restricted clearly.For the common of this field For technical staff, the specific meanings of the above terms in the present invention can be understood according to specific conditions.
Embodiment 1
Refering to fig. 1 with a kind of town road passive safety feature shown in Fig. 2, concrete layer 1 on the ground is poured including one, Concrete layer pours with a thickness of 50cm, and the longitudinal width of concrete layer poured is 300cm, the concrete layer 1 it is interior Portion has poured steel reinforcement cage 2, and steel reinforcement cage is arranged in parallel with multilayer above and below, forms a gradient after the concrete layer 1 pours and is 3.5 ° of slope surface 101, in vehicle bumper, vehicle is hoisted traveling by the low side of the slope surface 101, and the concrete layer 1 pours Lateral length after the completion is 240 meters, and the load-carrying of lorry is larger, and the braking distance of the chief minister's seal is also longer, in the slope surface 101 A recessed foundation pit 102 is formed after pouring, the depth of foundation pit 102 is 14cm, and tiling has buffering to mix in the foundation pit 102 Object 3, the setting of foundation pit 102 is primarily to filling buffer mixture 3 contacts buffer mixture 3, cause when the vehicle is running Sinking for wheel, realizes the deceleration of vehicle, since the depth of foundation pit 102 only has 14cm, not will cause the excessive side of vehicle To incline, vehicle is avoided to turn on one's side during buffering, the lower section of foundation pit 102 is concrete, and concrete has enough support strengths, It can satisfy the support needs of vehicle, and poured steel reinforcement cage 2 in concrete, the knot of concrete layer 1 can be further increased Structure intensity, being arranged side by side at the close leftward position of the foundation pit 102 has multiple bumper posts 4, and the bumper post 4 includes multiple The waste tire 401 stacked above and below forms, and the rod piece 402 being threaded through between multiple waste tires 401, the rod piece 402 lower end is downwardly into after passing through multiple waste tires 401 to the concrete layer 1, and the upper end of rod piece 402 rolls to the left Unsymmetrical bending rear support at the top of concrete layer 1, the top of the concrete layer 1, poured along the foundation pit 102 it is multiple Lateral defensive first waste tire 5, the diameter of the first waste tire 5 are 60cm, and tire width is 23.5cm, the first waste tire 5 in casting concrete layer, that is, is poured fixation, is not necessarily to later period others fixed form, and the first waste tire 5 is to play laterally Buffer protection effect, when stop failure occurs for vehicle, the direction of vehicle is usual or controllable, therefore the first waste tire Setting can remind driver travel direction, avoid more line, while when vehicle is uncontrollable, bear the shock of vehicle, reduce Vehicle damage also reduces the risk that vehicle sweeps away slope.
Embodiment 2
As shown in fig.3, every layer of steel reinforcement cage 2 includes the more spirals being staggered in transverse and longitudinal, spiral it is straight Diameter is 10mm, carries out ligation fixation by steel tied silk at spiral intervening portion, and the spacing of laterally adjacent spiral is 24cm, the spacing of longitudinally adjacent spiral are 20cm.
Embodiment 3
The buffer mixture 3 include 30% middle sand, 25% stone, 45% melon seeds piece, tiling when, pass through mixing apparatus It is laid with again after being mixed;Above-mentioned each material is simple and easy to get, and has good deformability after stress, is easy to match It closes wheel and realizes and slow down.
Embodiment 4
The rod piece 402 uses diameter for the hollow steel pipe of 8cm, and material is Q235 common carbon structural steel, wall thickness 2cm.
Embodiment 5
Refering to shown in Fig. 4 and Fig. 5, more are provided in the bottom of the foundation pit 102, close to array at 4 position of bumper post Pyramid shape is processed into tire broken wall bar 6, the upper end of tire broken wall bar 6, and the lower end of tire broken wall dry 6 is cast in concrete layer In 1, the upper end is covered by the buffer mixture 3, and under normality, tire broken wall bar 6 is submerged in buffer mixture 3 , when vehicle drives into, and travel speed is too fast, it will cause the sagging deformation of buffer mixture 3, and then allow tire broken wall bar 6 contact with wheel, realize the broken wall of wheel, and the tire after broken wall generates biggish rolling resistance, help vehicle deceleration, buffering pair The impact force of bumper post.
Embodiment 6
As shown in fig.6, forming a space in the inside of the bumper post 4 by waste tire, should being filled in the space There is rough sand 444, after filling rough sand, the ability of anti-deformation of waste tire can be increased, increase the anticollision ability of this product, subtract Routed probability after few stress;
Embodiment 7
As shown in fig.7, forming a space in the inside of the bumper post 4 by waste tire, banketing in the space 445, and nursery stock is planted, cooperate nursery stock, the mark of finishing line may be implemented, reminds driver to carry out collision and prepare, while nursery stock The effect of anticollision can also be played;
Embodiment 8
Nursery stock is metasequoia tree.
The basic principles, main features and advantages of the present invention have been shown and described above.The technology of the industry Personnel are it should be appreciated that the present invention is not limited to the above embodiments, and the above embodiments and description only describe this The principle of invention, various changes and improvements may be made to the invention without departing from the spirit and scope of the present invention, these changes Change and improvement all fall within the protetion scope of the claimed invention.The claimed scope of the invention by appended claims and its Equivalent defines.

Claims (9)

1. a kind of town road passive safety feature, it is characterised in that: concrete layer on the ground is poured including one, it is described mixed The inside of solidifying soil layer has poured steel reinforcement cage, and steel reinforcement cage is arranged in parallel with multilayer above and below, forms one after the concrete layer pours A gradient is 3 ~ 6 ° of slope surface, and in vehicle bumper, vehicle is hoisted traveling by the low side of the slope surface, and the concrete layer pours Lateral length after the completion is 200 ~ 300 meters, and a recessed foundation pit, the depth of foundation pit are formed after pouring in the slope surface For 10 ~ 20cm, tiling has buffer mixture in the foundation pit, at close the leftward position of the foundation pit it is arranged side by side have it is more A bumper post, the bumper post include it is multiple stack above and below waste tires composition, and be threaded through multiple waste tires it Between rod piece, the lower end of the rod piece is downwardly into after passing through multiple waste tires to the concrete layer, the upper end of rod piece Oblique bending rear support has poured at the top of concrete layer at the top of the concrete layer, along the foundation pit to the left Multiple lateral defensive first waste tires, the diameter of the first waste tire are greater than 60cm, and tire is wider than 22.5cm.
2. according to town road passive safety feature described in claim 1, it is characterised in that: every layer of steel reinforcement cage includes more The diameter of the spiral being staggered in transverse and longitudinal, spiral is 8mm ~ 12mm, passes through steel at spiral intervening portion Tied silk carries out ligation fixation, and the spacing of laterally adjacent spiral is 20 ~ 30cm, and the spacing of longitudinally adjacent spiral is 15 ~30cm。
3. town road passive safety feature according to claim 1, it is characterised in that: the buffer mixture includes 20 ~ 30% middle sand, 20 ~ 25% stone, surplus are that melon seeds piece is spread after being mixed by mixing apparatus again in tiling If.
4. town road passive safety feature according to claim 1, it is characterised in that: the rod piece use diameter for The hollow steel pipe of 6cm ~ 8cm, material are Q235 common carbon structural steel, and wall thickness is 1cm ~ 2cm.
5. town road passive safety feature according to claim 1, it is characterised in that: the foundation pit bottom, lean on Array is provided with more tire broken wall bars at the nearly bumper post position, and pyramid shape is processed into the upper end of tire broken wall bar, wheel The dry lower end of tire broken wall is cast in concrete layer, and the upper end is covered by the buffer mixture, and under normality, tire is broken Wall bar is submerged in buffer mixture, when vehicle drives into, and travel speed is too fast, will cause under buffer mixture Deformation is fallen into, and then tire broken wall bar is allowed to contact with wheel, realizes the broken wall of wheel, the tire after broken wall generates biggish rolling resistance Power helps vehicle deceleration, buffers the impact force to bumper post.
6. town road passive safety feature according to claim 1, it is characterised in that: in the inside of the bumper post, A space is formed by waste tire, rough sand should be filled in the space.
7. town road passive safety feature according to claim 1, it is characterised in that: in the inside of the bumper post, A space is formed by waste tire, is banketed in the space, and plant nursery stock.
8. town road passive safety feature according to claim 7, it is characterised in that: nursery stock is metasequoia tree, diversiform-leaved poplar tree One of.
9. a kind of installation method of town road passive safety feature any one of claims 1 to 8, feature exist In: the following steps are included: selecting installation site of the terminal in the long descending section of super expressway as this structure first;It will pacify in advance The position of dress carries out the leveling on ground, after leveling, the structure of a V-shaped is formed relative to descending section, when vehicle is in descending When stop failure occurs for section, the upward slope by flattening section, which is realized, to slow down;On section after the completion of leveling, it is laid with reinforcing bar Cage, every one layer of steel reinforcement cage of laying pours a layer concrete, until concrete layer pours completion, in casting concrete, It needs to build the wooden template for forming the foundation pit above, after concreting completion is dry and hard, forms the base Hole, then removes template again;Multiple waste tires are carried out to vertical stacking, are then inserted into rod piece, rod piece is downwardly into, The hole of insertion insertion rod piece can be opened up in foundation pit, the upper end of rod piece is bent before factory by bending device, so that The lower end of rod piece is after being inserted into concrete layer, and the upper surface of end in contact concrete layer, forms diagonal brace, wherein needing to stay thereon There is at least one waste tire to be located in the foundation pit;Buffer mixture is filled to foundation pit, is then pressed using road roller Real, buffering composite soil covering is located at the waste tire in foundation pit.
CN201910336114.6A 2019-04-24 2019-04-24 Municipal road passive safety device and mounting method thereof Active CN110055850B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910336114.6A CN110055850B (en) 2019-04-24 2019-04-24 Municipal road passive safety device and mounting method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910336114.6A CN110055850B (en) 2019-04-24 2019-04-24 Municipal road passive safety device and mounting method thereof

Publications (2)

Publication Number Publication Date
CN110055850A true CN110055850A (en) 2019-07-26
CN110055850B CN110055850B (en) 2020-05-01

Family

ID=67320607

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910336114.6A Active CN110055850B (en) 2019-04-24 2019-04-24 Municipal road passive safety device and mounting method thereof

Country Status (1)

Country Link
CN (1) CN110055850B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110552270A (en) * 2019-09-05 2019-12-10 杨鸿苍 speed-reducing road capable of reducing speed of vehicle
CN112227264A (en) * 2020-10-22 2021-01-15 章柯 Road central authorities separate buffer for road administration engineering

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200317158Y1 (en) * 2003-03-25 2003-06-25 주식회사 남원건설엔지니어링 Emergency braking facility using waste tire
CN1704531A (en) * 2004-05-26 2005-12-07 李幸洪 Method for building road isolation green belt guard-rail using waste tyres
CN202730573U (en) * 2012-07-27 2013-02-13 长安大学 Emergency lane
CN108411724A (en) * 2018-03-27 2018-08-17 邓海军 A kind of municipal administration buffer channel
CN108755313A (en) * 2018-08-23 2018-11-06 新疆工程学院 Novel buffer type emergency lane

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200317158Y1 (en) * 2003-03-25 2003-06-25 주식회사 남원건설엔지니어링 Emergency braking facility using waste tire
CN1704531A (en) * 2004-05-26 2005-12-07 李幸洪 Method for building road isolation green belt guard-rail using waste tyres
CN202730573U (en) * 2012-07-27 2013-02-13 长安大学 Emergency lane
CN108411724A (en) * 2018-03-27 2018-08-17 邓海军 A kind of municipal administration buffer channel
CN108755313A (en) * 2018-08-23 2018-11-06 新疆工程学院 Novel buffer type emergency lane

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110552270A (en) * 2019-09-05 2019-12-10 杨鸿苍 speed-reducing road capable of reducing speed of vehicle
CN112227264A (en) * 2020-10-22 2021-01-15 章柯 Road central authorities separate buffer for road administration engineering

Also Published As

Publication number Publication date
CN110055850B (en) 2020-05-01

Similar Documents

Publication Publication Date Title
CN204401447U (en) A kind of structure preventing bumping at bridge-head
CN101718086B (en) Concrete-enrockment mixed dam and construction method thereof
CN110670433B (en) Construction structure for constructing road on soft soil foundation
CN105951537B (en) A kind of medium-and low-speed maglev is low to put circuit rib post distributing track switch foundation structure
CN110055850A (en) A kind of town road passive safety feature and its installation method
CN103334357A (en) Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method
CN107740588B (en) A kind of hoisting transportation method of narrow location construction material in city
CN104499502B (en) A kind of river course arch barrier wall structure and construction method thereof
CN102535502A (en) Method for preventing settling and cracking of terrace with large area by utilizing combined prestressing concrete beams at region with soft soil layer
CN109338840B (en) Construction method of high-strength pavement
CN203334154U (en) Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct
EP2744942B1 (en) Railway track support system
CN113481770A (en) Construction method of foam concrete danger-avoiding lane
CN109252434A (en) A kind of asphalt pavement structure and its construction method
CN206359995U (en) Reinforced concrete cast-in-situ retaining wall
CN206070542U (en) A kind of new stone blocking net Cable Structure for avalanche preventing and treating
CN201924249U (en) Transition roadbed for dealing with vehicle bump
CN211872447U (en) Side wide roadbed structure
CN212611699U (en) Be used for high-speed railway reinforced structure, road bed subassembly and road bed system
CN108411724B (en) Buffer channel for municipal administration
CN103215948A (en) V-shaped prestress fender post and construction method thereof
CN207974143U (en) Applied to the stake Torquay beam barricade in steep slope subgrade
CN103174163A (en) Heightening method and heightening structure of opening of prefabricated column foundation
CN110777570A (en) Expansive soil large-deformation anti-upwarp foundation structure and construction method of foundation structure
CN208965490U (en) A kind of novel barge transport harbour

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20200401

Address after: Room 1001, 555 Guanhen Road, Sanjiang Street, Shengzhou City, Shaoxing City, Zhejiang Province

Applicant after: Shengzhou Wanrui Technology Co.,Ltd.

Address before: 518000 Longhua District, Shenzhen City, Guangdong Province

Applicant before: Peng Yanping

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20190726

Assignee: SHENGZHOU WANZHI NETWORK TECHNOLOGY CO.,LTD.

Assignor: Shengzhou Wanrui Technology Co.,Ltd.

Contract record no.: X2023980050141

Denomination of invention: A passive safety device for municipal roads and its installation method

Granted publication date: 20200501

License type: Common License

Record date: 20231205

EE01 Entry into force of recordation of patent licensing contract
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A passive safety device for municipal roads and its installation method

Effective date of registration: 20231207

Granted publication date: 20200501

Pledgee: Hua Xia Bank Co.,Ltd. Shaoxing Shengzhou Sub branch

Pledgor: Shengzhou Wanrui Technology Co.,Ltd.

Registration number: Y2023980069577

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20200501

Pledgee: Hua Xia Bank Co.,Ltd. Shaoxing Shengzhou Sub branch

Pledgor: Shengzhou Wanrui Technology Co.,Ltd.

Registration number: Y2023980069577