CN110042766A - A kind of CFST Arch Bridge insulation film construction method - Google Patents

A kind of CFST Arch Bridge insulation film construction method Download PDF

Info

Publication number
CN110042766A
CN110042766A CN201910448158.8A CN201910448158A CN110042766A CN 110042766 A CN110042766 A CN 110042766A CN 201910448158 A CN201910448158 A CN 201910448158A CN 110042766 A CN110042766 A CN 110042766A
Authority
CN
China
Prior art keywords
insulation film
arch bridge
filled steel
steel tubular
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910448158.8A
Other languages
Chinese (zh)
Inventor
石拓
郭晓
邓年春
于孟生
唐志宇
李顥旭
韦韩
姚鑫玉
杨阳
唐鹏飞
周大为
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi University
Original Assignee
Guangxi University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi University filed Critical Guangxi University
Priority to CN201910448158.8A priority Critical patent/CN110042766A/en
Publication of CN110042766A publication Critical patent/CN110042766A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of CFST Arch Bridge insulation film construction methods, the following steps are included: insulation film, the top of Filled Steel Tubular Arch Bridge is sent to using insulation film automatic conveyor by a, the setting insulation film automatic conveyor at Filled Steel Tubular Arch Bridge;B, insulation film is removed on Filled Steel Tubular Arch Bridge, and insulation film is coated on to the periphery of Filled Steel Tubular Arch Bridge.The present invention transports film using the heat preservation automatic conveyor, cooling rate can be effectively reduced by being laid with one layer of heat preservation film to package outside the arch rib of CFST Arch Bridge, reduce pipe inner concrete internal-external temperature difference, effectively reduces the inhomogeneous deformation of pipe inner concrete and the generation of unsticking, problem of coming to nothing.

Description

A kind of CFST Arch Bridge insulation film construction method
Technical field
The present invention relates to CFST Arch Bridge Winter Construction Techniques fields, specifically, being related to a kind of concrete filled steel tube Arch bridge insulation film construction method.
Background technique
CFST Arch Bridge is quickly grown, and with rigidity, the good advantage of big, good economy performance, durability, especially exists It is more highlighted in railroad bridge.
Under the background that line is built energetically in Sichuan-Tibet, since built environment is severe, the completion time of project is tight, the task factors shadow such as again It rings, winter low temperature construction is difficult to avoid that.However after CFST Arch Bridge is closed up, pipe inner concrete jacks pumping construction and needs one Fixed ambient temperature requirements.Pipe inner concrete jacking pumping construction is carried out at a temperature of low temperature environment in winter, pipe inner concrete is first First hy-dration reaction, temperature steeply rise.After hydration heat temperature reaches peak value, since ambient temperature effect declines immediately, directly To reaching environment temperature.In the process, since concrete heating conduction is bad, the concrete temperature close to steel pipe wall is by ring Border temperature is affected, and core concrete is impacted smaller, will lead to and generates the larger temperature difference in arch rib section.Especially in pipe During concrete temperature drop, the huge temperature difference can cause pipe inner concrete inhomogeneous deformation, so that it is de- to form steel pipe concrete arch rib It glues, problem of coming to nothing, influences construction quality.
Summary of the invention
The technical problems to be solved by the present invention are: providing a kind of CFST Arch Bridge insulation film construction method, utilize Device transports film, and cooling speed can be effectively reduced by being laid with one layer of heat preservation film to package outside the arch rib of CFST Arch Bridge Degree reduces pipe inner concrete internal-external temperature difference, effectively reduces the inhomogeneous deformation and unsticking, problem of coming to nothing of pipe inner concrete It generates.
In order to solve the above technical problems, the technical scheme is that
A kind of CFST Arch Bridge insulation film construction method, comprising the following steps:
A, insulation film automatic conveyor is set at Filled Steel Tubular Arch Bridge, utilizes insulation film automatic conveyor Insulation film is sent to the top of Filled Steel Tubular Arch Bridge;
B, insulation film is removed on Filled Steel Tubular Arch Bridge, and insulation film is coated on Filled Steel Tubular Arch Bridge Periphery.
As a further improvement, the insulation film automatic conveyor includes being set to Filled Steel Tubular Arch Bridge one end The hoist engine at place, and the fixed pulley above the Filled Steel Tubular Arch Bridge other end, the output shaft of the hoist engine On be wound with transmission rope, one end of the transmission rope is fixedly connected with the output shaft of the hoist engine, the transmission rope it is another End is fixedly connected after bypassing the fixed pulley with the output shaft of the hoist engine;Link is equipped at intervals on the lower surface of transmission rope; Insulation film interval is hung on the transmission rope on the downside of the fixed pulley, starts hoist engine, drives the transmission rope clockwise It is run around the fixed pulley, sequentially drives insulation film to the top of Filled Steel Tubular Arch Bridge.
As a further improvement, between the hoist engine and the fixed pulley, and it is located at Filled Steel Tubular Arch Bridge Top be equipped at intervals with support wheel, the support wheel is fixed pulley.
As a further improvement, the transmission rope is the nylon rope or cable wire of ring seal.
As a further improvement, the spacing distance of the adjacent link is not more than the length of a roll of insulation film.
As a further improvement, the insulation film automatic conveyor includes being respectively arranged on Filled Steel Tubular Arch Bridge Bracket at both ends, rope is connected between the bracket at both ends, and the rope is equipped with cable loop wheel machine, the end of the rope Portion extends to ground, and is connected with earth anchor.
As a further improvement, the insulation film is polyethylene plastic film.
As a further improvement, in the step b, insulation film circumferentially coats the outer of Filled Steel Tubular Arch Bridge It encloses.
As a further improvement, at least two pieces heat preservations are coated in same section of peripheral surface of Filled Steel Tubular Arch Bridge Film, the neighboring edge overlapping of two pieces of adjacent insulation films.
As a further improvement, the insulation film edge be arranged velcro, two pieces of adjacent insulation films it is adjacent heavy Folded edge is pasted by the velcro to be connected.
After above-mentioned technical proposal, the beneficial effects of the present invention are:
CFST Arch Bridge insulation film construction method of the invention transports film using device, to concrete-filled steel tube arch Package, which is laid with one layer of heat preservation film, outside the arch rib of bridge can effectively reduce cooling rate, reduce pipe inner concrete internal-external temperature difference, Effectively reduce the inhomogeneous deformation of pipe inner concrete and the generation of unsticking, problem of coming to nothing.And film is transported using device auxiliary Onto the arch rib of CFST Arch Bridge, does not have to again artificial transport, greatly reduce labor intensity, improve efficiency.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples:
Fig. 1 is a kind of structural schematic diagram of the insulation film automatic conveyor in the present invention;
Fig. 2 is the usage state diagram for the arch rib that Fig. 1 is applied to CFST Arch Bridge;
Fig. 3 is longitudinal schematic cross-sectional view of Fig. 2;
Fig. 4 is a kind of longitudinal schematic cross-sectional view of the arch rib cladding film of the CFST Arch Bridge in Fig. 2;
Fig. 5 is another structural schematic diagram of the insulation film automatic conveyor in the present invention;
In figure: 1- Filled Steel Tubular Arch Bridge;2- hoist engine;3- fixed pulley;4- support wheel;5- transmission rope;6- link; 7- insulation film;8- velcro;9- bracket;10- rope;11- earth anchor;12- cable loop wheel machine.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
As shown in Figures 1 to 4, CFST Arch Bridge insulation film construction method of the invention, comprising the following steps:
A, insulation film automatic conveyor is set at Filled Steel Tubular Arch Bridge 1, automatically delivers dress using insulation film Set the top that insulation film 7 is sent to Filled Steel Tubular Arch Bridge 1;
B, insulation film 7 is removed on Filled Steel Tubular Arch Bridge 1, and insulation film 7 is coated on CFST Arch Bridge arch The periphery of rib 1.
Wherein, insulation film automatic conveyor can be taken with flowering structure:
Hoist engine 2 is set at 1 one end of Filled Steel Tubular Arch Bridge, on 1 other end of Filled Steel Tubular Arch Bridge Fixed pulley 3 is set at side, transmission rope 5, one end of transmission rope 5 and the output shaft of hoist engine 2 are wound on the output shaft of hoist engine 2 It is fixedly connected, the other end of transmission rope 5 is fixedly connected after bypassing fixed pulley 3 with the output shaft of hoist engine 2;The following table of transmission rope 5 Link 6 is equipped at intervals on face.Nylon rope or cable wire can be used in transmission rope 5.
Between hoist engine 2 and fixed pulley 3, and the top for being located at Filled Steel Tubular Arch Bridge 1 is equipped at intervals with support wheel 4. Support wheel 4 is fixed pulley 3.
The spacing distance of adjacent link 6 is not more than the length of a roll of insulation film.
Insulation film 7 is spaced when use on the transmission rope 5 for hanging over 3 downside of fixed pulley, starts hoist engine 2, drives transmission rope 5 It is run clockwise about fixed pulley 3, sequentially drives insulation film to the top of Filled Steel Tubular Arch Bridge 1;
As a further improvement, in the step b, insulation film 7 circumferentially coats the outer of Filled Steel Tubular Arch Bridge 1 It encloses.
Referring to Fig. 5, insulation film automatic conveyor can also be taken with flowering structure, the two of Filled Steel Tubular Arch Bridge 1 Bracket 9 is set at end, rope 10 is connected between the bracket 9 at both ends, rope 10 is equipped with cable loop wheel machine 12, the end of rope 10 Ground is extended to, and is connected with earth anchor 11, forms cable Lift-on/Lift-off System.It is the system that CFST Arch Bridge sets up installation, It can utilize very well, set up institution without repeating.After Filled Steel Tubular Arch Bridge closes up, the cable of handling arch rib is utilized Thermal insulation material is hung in lifting place and starts to lift by crane, is then hoisted to designated position, mat formation by rope Lift-on/Lift-off System.
Wherein, polyethylene plastic film can be used in insulation film 7.It is a thin layer of as plating after bubble chamber film by blow moulded polyethyene Aluminium film.Light weight, thickness is thin, and heat insulation effect is good.As a further improvement, same section of week of Filled Steel Tubular Arch Bridge 1 At least two pieces of insulation films, the neighboring edge overlapping of two pieces of adjacent insulation films are coated on surface.
As a further improvement, velcro 8 is arranged in the edge of insulation film 7, follows the principle of " upper pressure ", connection position It sets using velcro firm pasting and the laying that partly overlaps, the adjacent overlapping edges of two pieces of adjacent insulation films 7 is made to pass through magic Patch 8 pastes connection.When being laid with using two pieces or four pieces of insulation films, it is laid with according to the sequence of " outside after in elder generation ".
After the completion of full-bridge insulation film is laid with, filling concrete construction can be carried out.It is reduced to hydration heat of concrete temperature I.e. about after a week close to after environment temperature, insulation film can be recycled.Velcro is pulled open, insulation film is spooled, uses cable hoisting System transports insulation film segmentation back.Recycling heat preservation membrane material, rolls storage, can repeatedly utilize.
The above is the citing of best mode for carrying out the invention, wherein the part that do not address in detail is that this field is common The common knowledge of technical staff.Protection scope of the present invention is based on the contents of the claims, any based on technology of the invention The equivalent transformation of enlightenment and progress, also within protection scope of the present invention.

Claims (10)

1. a kind of CFST Arch Bridge insulation film construction method, which comprises the following steps:
A, insulation film automatic conveyor is set at Filled Steel Tubular Arch Bridge, will be protected using insulation film automatic conveyor Warm film is sent to the top of Filled Steel Tubular Arch Bridge;
B, insulation film is removed on Filled Steel Tubular Arch Bridge, and insulation film is coated on the outer of Filled Steel Tubular Arch Bridge It encloses.
2. CFST Arch Bridge insulation film construction method according to claim 1, it is characterised in that: the insulation film is certainly Dynamic transmission device includes the hoist engine at Filled Steel Tubular Arch Bridge one end, and is set to Filled Steel Tubular Arch Bridge Fixed pulley above the other end, is wound with transmission rope on the output shaft of the hoist engine, one end of the transmission rope with it is described The output shaft of hoist engine is fixedly connected, and the other end of the transmission rope is around the output shaft after the fixed pulley with the hoist engine It is fixedly connected;Link is equipped at intervals on the lower surface of transmission rope;Insulation film interval is hung over to the biography on the downside of the fixed pulley In dynamic search, start hoist engine, the transmission rope is driven to run clockwise about the fixed pulley, sequentially drives insulation film mixed to steel pipe The top of solidifying soil arch rib.
3. CFST Arch Bridge insulation film construction method according to claim 2, it is characterised in that: the hoist engine with Between the fixed pulley, and it is located above Filled Steel Tubular Arch Bridge and is equipped at intervals with support wheel, the support wheel is fixed sliding Wheel.
4. CFST Arch Bridge insulation film construction method according to claim 3, it is characterised in that: the transmission rope is The nylon rope or cable wire of ring seal.
5. CFST Arch Bridge insulation film construction method according to claim 4, it is characterised in that: the adjacent link Spacing distance be not more than the length of a roll of insulation film.
6. CFST Arch Bridge insulation film construction method according to claim 1, it is characterised in that: the insulation film is certainly Dynamic transmission device includes the bracket being respectively arranged at Filled Steel Tubular Arch Bridge both ends, is connected between the bracket at both ends Rope, the rope are equipped with cable loop wheel machine, and the end of the rope extends to ground, and is connected with earth anchor.
7. CFST Arch Bridge insulation film construction method according to any one of claims 1 to 6, it is characterised in that: institute Stating insulation film is polyethylene plastic film.
8. CFST Arch Bridge insulation film construction method according to claim 7, it is characterised in that: in the step b, Insulation film circumferentially coats the periphery of Filled Steel Tubular Arch Bridge.
9. CFST Arch Bridge insulation film construction method according to claim 8, it is characterised in that: concrete-filled steel tube arch At least two pieces of insulation films, the neighboring edge overlapping of two pieces of adjacent insulation films are coated in same section of peripheral surface of bridge arch rib.
10. CFST Arch Bridge insulation film construction method according to claim 9, it is characterised in that: the insulation film Edge velcro is set, the adjacent overlapping edges of two pieces of adjacent insulation films paste connection by the velcro.
CN201910448158.8A 2019-05-27 2019-05-27 A kind of CFST Arch Bridge insulation film construction method Pending CN110042766A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910448158.8A CN110042766A (en) 2019-05-27 2019-05-27 A kind of CFST Arch Bridge insulation film construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910448158.8A CN110042766A (en) 2019-05-27 2019-05-27 A kind of CFST Arch Bridge insulation film construction method

Publications (1)

Publication Number Publication Date
CN110042766A true CN110042766A (en) 2019-07-23

Family

ID=67283682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910448158.8A Pending CN110042766A (en) 2019-05-27 2019-05-27 A kind of CFST Arch Bridge insulation film construction method

Country Status (1)

Country Link
CN (1) CN110042766A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501520A (en) * 2020-05-08 2020-08-07 重庆交通大学 Pouring process for preventing concrete filled steel tube from being emptied

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101519864A (en) * 2009-03-30 2009-09-02 中铁二十三局集团第三工程有限公司 Method for mounting box arch bridge
KR20110121380A (en) * 2010-04-30 2011-11-07 김숙자 Apparatus of opening and shutting cover for green house
CN102535872A (en) * 2012-01-16 2012-07-04 中交第一公路工程局有限公司 Thermal insulation method and concrete thermal insulation cover for winter construction of pier column
CN102808379A (en) * 2012-08-22 2012-12-05 株洲时代新材料科技股份有限公司 Device for arch bridge inspection
CN103255712A (en) * 2013-05-29 2013-08-21 株洲时代新材料科技股份有限公司 Device and method suitable for inspecting and maintaining different steel arch bridge arches
CN103891550A (en) * 2014-04-17 2014-07-02 郑西江 Three-layer vegetable tunnel with single heat preservation quilt
CN205378610U (en) * 2016-02-23 2016-07-13 宁夏地德科技有限公司 Inside and outside heat -preservation type sunlight greenhouse
CN105839546A (en) * 2016-06-01 2016-08-10 中交四公局第五工程有限公司 Arch rib buckling and hanging installing structure of steel pipe arch bridge
KR20180012134A (en) * 2016-07-26 2018-02-05 배기웅 A winder of blankets and vinyl cover in greenhouses
CN108660935A (en) * 2018-05-29 2018-10-16 广西路桥工程集团有限公司 A kind of construction method of reinforced concrete arch bridge
CN109577174A (en) * 2019-01-17 2019-04-05 中交四公局第十工程有限公司 Attemperator and its application method after a kind of pier stud concrete demoulding

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101519864A (en) * 2009-03-30 2009-09-02 中铁二十三局集团第三工程有限公司 Method for mounting box arch bridge
KR20110121380A (en) * 2010-04-30 2011-11-07 김숙자 Apparatus of opening and shutting cover for green house
CN102535872A (en) * 2012-01-16 2012-07-04 中交第一公路工程局有限公司 Thermal insulation method and concrete thermal insulation cover for winter construction of pier column
CN102808379A (en) * 2012-08-22 2012-12-05 株洲时代新材料科技股份有限公司 Device for arch bridge inspection
CN103255712A (en) * 2013-05-29 2013-08-21 株洲时代新材料科技股份有限公司 Device and method suitable for inspecting and maintaining different steel arch bridge arches
CN103891550A (en) * 2014-04-17 2014-07-02 郑西江 Three-layer vegetable tunnel with single heat preservation quilt
CN205378610U (en) * 2016-02-23 2016-07-13 宁夏地德科技有限公司 Inside and outside heat -preservation type sunlight greenhouse
CN105839546A (en) * 2016-06-01 2016-08-10 中交四公局第五工程有限公司 Arch rib buckling and hanging installing structure of steel pipe arch bridge
KR20180012134A (en) * 2016-07-26 2018-02-05 배기웅 A winder of blankets and vinyl cover in greenhouses
CN108660935A (en) * 2018-05-29 2018-10-16 广西路桥工程集团有限公司 A kind of construction method of reinforced concrete arch bridge
CN109577174A (en) * 2019-01-17 2019-04-05 中交四公局第十工程有限公司 Attemperator and its application method after a kind of pier stud concrete demoulding

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501520A (en) * 2020-05-08 2020-08-07 重庆交通大学 Pouring process for preventing concrete filled steel tube from being emptied

Similar Documents

Publication Publication Date Title
US3706125A (en) Pipe line construction method
CN110042766A (en) A kind of CFST Arch Bridge insulation film construction method
CN108952733A (en) Separate launching shield technique application construction method in municipal sewerage engineering
CN206956671U (en) A kind of rock-fill concrete special precast template system
CN104712146B (en) The construction method of reinforcing bar colligation in wall construction
CN105256817B (en) Underwater mould bag sand weir body construction method
CN203284084U (en) Suspension type transporter at cave top
JPS6127235B2 (en)
CN108222069A (en) A kind of underwater immersed tube, the device and construction method for setting up underwater immersed tube
CN112575682A (en) Pier shaft maintenance device that is under construction winter
CN205525151U (en) High resistant two coating anti -corrosion tube package machines of waiting
CN105952008B (en) Large-scale full containing low-temperature storage tank resilient felt tapestry method
CN210737607U (en) A hang braced system for reverse construction method beam slab construction
CN111498678A (en) Special lifting appliance for lifting cast-in-place pile overlong reinforcement cage and lifting method thereof
CN207633847U (en) A kind of chimney steel beam hydraulic promotion high-altitude integral slipping hanging apparatus
CN213923950U (en) Civil engineering elevating gear
CN206859211U (en) A kind of elastic steel cylinder of drilled pile solution cavity leak stopping
CN103882871B (en) A kind of antiseepage dam, salt pan fast construction method
CN210031551U (en) Steel pipe concrete arch bridge heat preservation membrane construction equipment
CN209494144U (en) Waterproof roll laying apparatus
CN114348882A (en) Hoisting method of refining tower
CN108590168A (en) Silo sliding formwork template cool-down method under hot environment
CN111691396A (en) Novel drainage plate vacuum preloading geotextile construction equipment and construction method thereof
CN210315565U (en) Device for laying underwater film bag
CN206141900U (en) A pipe collecting device for on automatic packaging system of steel pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination