CN110030015A - A kind of control ultra-deep ventilating shaft strengthening control construction method - Google Patents

A kind of control ultra-deep ventilating shaft strengthening control construction method Download PDF

Info

Publication number
CN110030015A
CN110030015A CN201910213158.XA CN201910213158A CN110030015A CN 110030015 A CN110030015 A CN 110030015A CN 201910213158 A CN201910213158 A CN 201910213158A CN 110030015 A CN110030015 A CN 110030015A
Authority
CN
China
Prior art keywords
ventilating shaft
side plate
construction
supporting mechanism
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910213158.XA
Other languages
Chinese (zh)
Other versions
CN110030015B (en
Inventor
陆跃
梁超
明刚
王圣涛
张转转
董邦所
刘海峰
赵新华
车晨阳
程冲
李文潜
肖怀全
高晨斌
杜洪波
邹科
邹智波
高大凯
张德银
徐洪强
赵星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201910213158.XA priority Critical patent/CN110030015B/en
Publication of CN110030015A publication Critical patent/CN110030015A/en
Application granted granted Critical
Publication of CN110030015B publication Critical patent/CN110030015B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D15/00Props; Chocks, e.g. made of flexible containers filled with backfilling material

Abstract

The invention discloses a kind of control ultra-deep ventilating shaft strengthening control construction methods, comprising the following steps: 1) preparation of construction, 2) construction of waterproof layer, 3) one layer of side plate supporting, 4) steel reinforcement cage laying, 5) two layers of side plate supporting, 6) bracing means construction, 7) concrete construction and 8) final acceptance of construction.Reinforced construction method of the invention is able to satisfy the ultra-deep ventilating shaft strengthening construction of different depth, the safety in utilization for substantially increasing ventilating shaft prevents the time from having grown and causes to collapse, and construction procedure is simple and convenient, influence more preferable compared to existing ventilating shaft consolidation effect, when reducing shield-tunneling construction to ventilating shaft entirety.

Description

A kind of control ultra-deep ventilating shaft strengthening control construction method
Technical field
The present invention relates to a kind of control ultra-deep ventilating shaft strengthening control construction methods.
Background technique
It is typically necessary in the middle part of construction section during construction of underground tunnel and ventilating shaft is set, to meet the need blown in tunnel The load capacity of shield machine when wanting, while needing to meet shield-tunneling construction.With the continuous maturation of technology, generally using shield method into Row tunnel excavation, existing ventilating shaft generally take into account the function of launching shaft, received well or construction shaft, hang to meet shield Out or the function that originates, the project scale of ventilating shaft is larger, and depth is deeper, ventilating shaft reinforce it is not in place tend to cause it is subsequent The loosening or collapsing of wall, there is only some potential safety problemss, and will increase the difficulty of construction.
Summary of the invention
Present invention aims at provide a kind of control ultra-deep ventilating shaft strengthening control for deficiency of the prior art The technical solution of construction method, the reinforced construction method are able to satisfy the ultra-deep ventilating shaft strengthening construction of different depth, substantially increase The safety in utilization of ventilating shaft prevents the time from having grown and causes to collapse, and construction procedure is simple and convenient, compares existing ventilating shaft consolidation effect More preferably, influence when reducing shield-tunneling construction to ventilating shaft entirety.
In order to solve the above-mentioned technical problem, the present invention adopts the following technical scheme:
A kind of control ultra-deep ventilating shaft strengthening control construction method, it is characterised in that the following steps are included:
1) preparation of construction
A, unwrapping wire is measured to ventilating shaft first, measures absolute altitude, the length and width of ventilating shaft, carries out review measurement, and survey The verticality for measuring each side of ventilating shaft, is checked with design requirement, flat with drilling machine drill to the side exceeded, it is ensured that each side Angle between face is matched with design requirement;
B, leveling processing then is carried out to the bottom surface of ventilating shaft and each side, removes stone exposed on bottom surface and side, It is smoothed out with mortar, mortar levelling is used to the rough position in bottom surface or side, then with rammer compacter to the bottom surface and side of ventilating shaft Face carries out compacting processing, is compacted the clay of bottom surface or side;
C, then set up scaffold in ventilating shaft, and the bottom surface of scaffold and ventilating shaft be fixedly connected, scaffold with Spacing between each side of ventilating shaft is greater than 1m;
2) construction of waterproof layer
A, first according to the suitable splash guard of the selection of dimension of ventilating shaft, holdfast is equidistantly installed at the back side of splash guard, Each side of ventilating shaft from left to right, successively splice splash guard from the bottom up, by the holdfast insertion ventilating shaft side on splash guard In soil layer, it is bonded splash guard completely with the side of ventilating shaft;
B, then splash guard is cleaned out, the lap joint on splash guard is staggeredly arranged with construction joint, the distance being staggered Not less than 20cm, double slit welding is carried out using hot weld by bonding machine, the lap of splice between two splash guards is not less than 20cm, when welding, weld from top to bottom;
C, geotechnological non-woven fabrics bed course then is laid in the front of splash guard, geotechnological non-woven fabrics is fixed on waterproof with support bar On plate, on the splash guard of side and bottom water-swellable item is installed respectively and is sealed;
D, finally to guiding gutter is opened up on the bottom surface of ventilating shaft, drainpipe, and layer overlay geotechnique's nothing are installed in guiding gutter Woven fabric, then be backfilling and compacted with clay;
3) one layer of side plate supporting
After to construction of waterproof layer, according to the corresponding side plate of the selection of dimension of ventilating shaft side, by hoisting machine by side plate Be hoisted to the respective side of ventilating shaft, side plate be fixedly connected on corresponding support bar by screw, make side plate and splash guard it Between be completely embedded, when laying one layer of side plate, sequence from the bottom up, from left to right is laid, and guarantees that left and right is adjacent, neighbouring Two sides side plate between spacing be less than 1cm;
4) steel reinforcement cage is laid
A, the main reinforcement and girder rib for choosing design requirement according to the lateral dimension of ventilating shaft first, pass through the company of straight screw sleeve It connects mode to be attached main reinforcement, and equidistantly intersects between two neighboring main reinforcement and lay girder rib, girder rib is passed through into weldering It connects and is fixedly connected with main reinforcement, be spliced into required steel reinforcement cage;
B, hoisting point position is then determined on steel reinforcement cage, and the safety of hanging ring and suspender is checked, and passes through welding Hanging ring is mounted on hoisting point position, while spacer pad being installed respectively in the bottom of steel reinforcement cage and front and rear sides, every layer is laid 5 ~6 pieces;
C, then the steel reinforcement cage that splicing is completed is lifted to ventilating shaft in order by suspender, by each steel reinforcement cage close to phase The ventilating shaft side answered, the bottom surface of the bottom and ventilating shaft that make steel reinforcement cage are fixedly connected, the trailing flank of steel reinforcement cage and one layer of side plate It is fixedly connected, after four steel reinforcement cages are fixed in a ring round ventilating shaft medial surface, will be carried out between two neighboring steel reinforcement cage It is welded and fixed, and hole needed for reserving shield-tunneling construction area, sealing plate is installed in the position of reserving hole;
5) two layers of side plate supporting
After to steel reinforcement cage construction, corresponding side plate is chosen according to the spacing between opposite two steel reinforcement cages, by hanging Side plate is hoisted to the respective side of ventilating shaft by installation, and side plate is fixedly connected on corresponding steel reinforcement cage by screw, makes side plate It is completely embedded between steel reinforcement cage, the sequence when laying two layers of side plate from the bottom up, from left to right is laid, and guarantees left and right phase Spacing between adjacent, neighbouring two sides side plate is less than 1cm, adjacent side plate is connected and sealed, to two layers of side plate branch After the completion of shield, scaffold is removed, and to clearing up in ventilating shaft;
6) bracing means is constructed
A, appropriate number of supporting mechanism is chosen according to the depth of ventilating shaft first, supporting mechanism is uniformly folded from the bottom up Add, the supporting mechanism positioned at bottom carry out along the inside corner of ventilating shaft it is uniformly distributed, make supporting mechanism and side wall corner it Between spacing be greater than 30cm, while guaranteeing each supporting mechanism keeping parallelism;
B, after all installation is fixed after the supporting mechanism of bottom design, the two neighboring supporting mechanism of right angle is passed through into company Linkage is fixed, and is respectively mounted side wall reinforcement block at the both ends of link mechanism, and side wall reinforcement block is made to resist corresponding side The supporting mechanism of side plate, two neighboring right angle is fixedly connected also by link mechanism, two adjacent connecting rod machines of left and right Structure is interspersed up and down;
C, rotating mechanism is then socketed at the center of supporting mechanism, when left and right, two adjacent side plates are obliquely installed, First support bar is installed between two adjacent rotating mechanisms of left and right, by first support bar by the support of different obliquities Mechanism is fixedly connected, while installing side wall reinforcement block by fixed link on rotating mechanism, makes side wall reinforcement block and corresponding Side plate vertically connected;
D, after to the bracing means installation of bottom, second layer support is fixedly mounted in the corresponding supporting mechanism top of bottom Mechanism is located at the supporting mechanism of second layer supporting mechanism and bottom on same vertical line, complete to the supporting mechanism on the second layer After portion's installation is fixed, the two neighboring supporting mechanism of right angle is fixed by link mechanism, and the two of link mechanism End is respectively mounted side wall reinforcement block, and side wall reinforcement block is made to resist the side plate of corresponding side, the supporting mechanism of two neighboring right angle It is fixedly connected by link mechanism, two adjacent link mechanisms of left and right are interspersed up and down;
E, rotating mechanism is then socketed at the center of supporting mechanism, when left and right, two adjacent side plates are obliquely installed, First support bar is installed between two adjacent rotating mechanisms of left and right, by first support bar by the support of different obliquities Mechanism is fixedly connected, while installing side wall reinforcement block by fixed link on rotating mechanism, makes side wall reinforcement block and corresponding Side plate vertically connected;
F, successively remaining bracing means is installed by above-mentioned construction procedure;
7) concrete construction
After the installation is completed to bracing means, selecting grade is the concrete of C40, and seepage-resistant grade P12 stirs concrete Concrete continuous is injected between one layer of side plate and two layers of side plate by diversion trench after uniformly, is put into casting and shocks stick, shaken Tamper is equidistantly placed along each side of ventilating shaft, is made to shock stick and is located at bottom, is started while continuous concrete placing Stick is shocked, after concrete is completely covered and shocks stick, stick is each shocked and vibrates 20~30 seconds, and uniformly it is lifted up 40~ 60cm continues to vibrate 20~30 seconds, then is lifted up 40~60cm, until the concrete shake between one layer of side plate and two layers of side plate It smashes and finishes;
8) final acceptance of construction
After to concrete construction, place is cleared up, when link mechanism or first support bar influence shield-tunneling construction When, the only link mechanism or first support bar when need to remove shield-tunneling construction in perpendicular circumference range, and to entirely applying Work carries out an acceptance inspection.
The reinforced construction method is able to satisfy the ultra-deep ventilating shaft strengthening construction of different depth, substantially increases the use peace of ventilating shaft Quan Xing prevents the time from having grown and causes to collapse, and construction procedure is simple and convenient, more preferable compared to existing ventilating shaft consolidation effect, reduces shield Influence when structure is constructed to ventilating shaft entirety.
Further, the supporting mechanism in step 6) includes column, and the top and bottom end of column are symmetrically arranged with supporting block, is stood The first pilot hole and the second pilot hole are provided on the side of column, the first pilot hole is mutually perpendicular to the second pilot hole, whirler Structure is located at the center of column, by the design of supporting block, not only increases the bonding strength between column and ventilating shaft bottom surface, and And connection stability and reliability between two supporting mechanisms up and down is improved, support strength is further increased, ventilating shaft is improved Consolidation effect, the first pilot hole and the second pilot hole can be used for positioning linkage rod mechanism, improve two neighboring supporting mechanism it Between the stability that connects.
Further, supporting block is hemispherical, and there are two location hole and two limited posts, positioning for setting on the top surface of supporting block Hole and limited post are in distributed rectangular, and two location holes, two limited posts are diagonally arranged respectively, limited post and location hole phase To match, limit hole is provided on limited post, first through hole is provided on the side of supporting block, first through hole matches with limit hole, First through hole and limit hole are passed through by fastening bolt, realizes being fixedly connected for upper and lower two supporting blocks, hemispheric supporting block Design not only increases the intensity of supporting block, and can effectively carry out bearing distribution, improves stability when connection, location hole With the design of limited post, bonding strength and stability between neighbouring two supporting mechanisms can be improved, fastening bolt is just In installing and dismounting, the Fast Installation or disassembly between two supporting mechanisms up and down are realized.
Further, the link mechanism in step 6) includes second support bar, third support rod and joining rod, the second support Bar, third support rod match with the first pilot hole and the second pilot hole, and joining rod is located at second support bar and third support Between bar, second support bar connects joining rod by position-limit mechanism, and the other end of joining rod is provided with threaded post, third support rod One end be provided with internal screw thread, threaded post matches with internal screw thread, and the first pilot hole, the second pilot hole can be respectively to second Strut and third support rod are positioned, the spacing between the adjustable second support bar of joining rod and third support rod, are met The side wall support of different length, joining rod are rotatably connected on the end of second support bar by position-limit mechanism, improve length adjustment When flexibility, the spacing between threaded post and the adjustable joining rod of internal screw thread and third support rod, so meet support when Fine tuning.
Further, position-limit mechanism includes T-shaped block and T-slot, and T-shaped block is fixedly connected on the end face center of second support bar Place, T-slot are located at the end face center of joining rod, and T-shaped block matches with T-slot, and the side of T-shaped block resists T shape by ball The design of the medial surface of slot, T-shaped block and T-slot not only increases the bonding strength between second support bar and joining rod, and Joining rod may be implemented by ball to rotate around the end of second support bar, reduce frictional force, reduce abrasion, extend limit The service life of mechanism.
Further, the side wall reinforcement block in step 6) includes arc-shaped cover and sleeve, and sleeve is fixedly connected on the interior of arc-shaped cover At portion center, be evenly arranged with stiffening plate between sleeve and arc-shaped cover, the design of arc-shaped cover not only increase side wall reinforcement block with Contact area between two layers of side plate, and the support strength of side wall reinforcement block is improved, sleeve can play the role of positioning, Stiffening plate improves the intensity connected between sleeve and arc-shaped cover, improves the stability of strutting system of entire side wall reinforcement block.
Further, the rotating mechanism in step 6) includes cylinder, and the upper and lower ends of cylinder are symmetrically arranged with annular slab, annular It is evenly arranged with the second through-hole in the outside circumference of plate, annular groove, upper and lower two annulars are provided between annular slab and cylinder There are three guide plates, guide plate to pass through the second through-hole by lock-screw and be fixed on cylinder for mobile connection between slot, and cylinder is solid Surely it is connected on column, plays the role of support positioning, guide plate can be not only used for connection first support bar, and can connect Side wall reinforcement block is connect, the support on different inclined-planes is met, after guide plate is moved to setting position, passes through second by lock-screw Through-hole realizes that guide plate is fixed in a ring groove.
Further, threaded hole is provided at the center of the guide plate in step 6), the two sides up and down of guide plate are symmetrical arranged There is arc conducting bar, arc conducting bar matches with annular groove, and wear plate is provided on arc conducting bar, and the design of arc conducting bar can mention Stability when high guide plate is mobile, while positioning can be played the role of when fixed, lock-screw can be improved in wear plate Reliability when connection.
The present invention is by adopting the above-described technical solution, have the advantages that
1, the reinforced construction method is able to satisfy the ultra-deep ventilating shaft strengthening construction of different depth, substantially increases the use of ventilating shaft Safety prevents the time from having grown and causes to collapse, and construction procedure is simple and convenient, more preferable compared to existing ventilating shaft consolidation effect, reduces To the influence of ventilating shaft entirety when shield-tunneling construction.
2, by the design of supporting block, the bonding strength between column and ventilating shaft bottom surface is not only increased, and is improved Connection stability and reliability between upper and lower two supporting mechanisms, further increases support strength, improves the reinforcing effect of ventilating shaft Fruit, the first pilot hole and the second pilot hole can be used for positioning linkage rod mechanism, improves and connects between two neighboring supporting mechanism Stability.
3, the first pilot hole, the second pilot hole can respectively position second support bar and third support rod, linking Spacing between the adjustable second support bar of bar and third support rod, meets the side wall support of different length, and joining rod passes through Position-limit mechanism is rotatably connected on the end of second support bar, improves flexibility when length adjustment, and threaded post and internal screw thread can be with The spacing between joining rod and third support rod is adjusted, and then meets fine tuning when support.
4, cylinder is fixedly connected on column, plays the role of support positioning, and guide plate can be not only used for connection first Support rod, and can connect side wall reinforcement block, meet the support on different inclined-planes, after guide plate is moved to setting position, leads to Lock-screw is crossed across the second through-hole, realizes that guide plate is fixed in a ring groove.
Detailed description of the invention
The present invention will be further explained below with reference to the attached drawings:
Fig. 1 is the structural schematic diagram of bracing means in a kind of control ultra-deep ventilating shaft strengthening control construction method of the present invention;
Fig. 2 is the connection schematic diagram in the present invention between rotating mechanism and supporting mechanism;
Fig. 3 is the connection schematic diagram in the present invention between upper and lower two supporting mechanisms;
Fig. 4 is the structural schematic diagram of link mechanism in the present invention;
Fig. 5 is the partial enlarged view in Fig. 4 at I;
Fig. 6 is the structural schematic diagram of rotating mechanism in the present invention;
Fig. 7 is the structural schematic diagram of guide plate in the present invention;
Fig. 8 is the structural schematic diagram of side wall reinforcement block in the present invention.
In figure: 1- supporting mechanism;2- link mechanism;3- side wall reinforcement block;4- first support bar;5- column;6- whirler Structure;The first pilot hole of 7-;The second pilot hole of 8-;9- supporting block;10- location hole;11- first through hole;12- limited post;13- limit Hole;14- fastening bolt;15- second support bar;16- third support rod;17- joining rod;18- threaded post;19-T shape block;20-T Shape slot;21- ball;22- annular slab;The second through-hole of 23-;24- annular groove;25- guide plate;26- lock-screw;27- arc is led Item;28- threaded hole;29- wear plate;30- sleeve;31- stiffening plate;32- arc-shaped cover;33- cylinder.
Specific embodiment
A kind of control ultra-deep ventilating shaft strengthening control construction method of the present invention, comprising the following steps:
1) preparation of construction
A, unwrapping wire is measured to ventilating shaft first, measures absolute altitude, the length and width of ventilating shaft, carries out review measurement, and survey The verticality for measuring each side of ventilating shaft, is checked with design requirement, flat with drilling machine drill to the side exceeded, it is ensured that each side Angle between face is matched with design requirement;
B, leveling processing then is carried out to the bottom surface of ventilating shaft and each side, removes stone exposed on bottom surface and side, It is smoothed out with mortar, mortar levelling is used to the rough position in bottom surface or side, then with rammer compacter to the bottom surface and side of ventilating shaft Face carries out compacting processing, is compacted the clay of bottom surface or side;
C, then set up scaffold in ventilating shaft, and the bottom surface of scaffold and ventilating shaft be fixedly connected, scaffold with Spacing between each side of ventilating shaft is greater than 1m;
2) construction of waterproof layer
A, first according to the suitable splash guard of the selection of dimension of ventilating shaft, holdfast is equidistantly installed at the back side of splash guard, Each side of ventilating shaft from left to right, successively splice splash guard from the bottom up, by the holdfast insertion ventilating shaft side on splash guard In soil layer, it is bonded splash guard completely with the side of ventilating shaft;
B, then splash guard is cleaned out, the lap joint on splash guard is staggeredly arranged with construction joint, the distance being staggered Not less than 20cm, double slit welding is carried out using hot weld by bonding machine, the lap of splice between two splash guards is not less than 20cm, when welding, weld from top to bottom;
C, geotechnological non-woven fabrics bed course then is laid in the front of splash guard, geotechnological non-woven fabrics is fixed on waterproof with support bar On plate, on the splash guard of side and bottom water-swellable item is installed respectively and is sealed;
D, finally to guiding gutter is opened up on the bottom surface of ventilating shaft, drainpipe, and layer overlay geotechnique's nothing are installed in guiding gutter Woven fabric, then be backfilling and compacted with clay;
3) one layer of side plate supporting
After to construction of waterproof layer, according to the corresponding side plate of the selection of dimension of ventilating shaft side, by hoisting machine by side plate Be hoisted to the respective side of ventilating shaft, side plate be fixedly connected on corresponding support bar by screw, make side plate and splash guard it Between be completely embedded, when laying one layer of side plate, sequence from the bottom up, from left to right is laid, and guarantees that left and right is adjacent, neighbouring Two sides side plate between spacing be less than 1cm;
4) steel reinforcement cage is laid
A, the main reinforcement and girder rib for choosing design requirement according to the lateral dimension of ventilating shaft first, pass through the company of straight screw sleeve It connects mode to be attached main reinforcement, and equidistantly intersects between two neighboring main reinforcement and lay girder rib, girder rib is passed through into weldering It connects and is fixedly connected with main reinforcement, be spliced into required steel reinforcement cage, the tolerance of steel reinforcement cage is as shown in table 1;
B, hoisting point position is then determined on steel reinforcement cage, and the safety of hanging ring and suspender is checked, and passes through welding Hanging ring is mounted on hoisting point position, while spacer pad being installed respectively in the bottom of steel reinforcement cage and front and rear sides, every layer is laid 5 ~6 pieces;
C, then the steel reinforcement cage that splicing is completed is lifted to ventilating shaft in order by suspender, by each steel reinforcement cage close to phase The ventilating shaft side answered, the bottom surface of the bottom and ventilating shaft that make steel reinforcement cage are fixedly connected, the trailing flank of steel reinforcement cage and one layer of side plate It is fixedly connected, after four steel reinforcement cages are fixed in a ring round ventilating shaft medial surface, will be carried out between two neighboring steel reinforcement cage It is welded and fixed, and hole needed for reserving shield-tunneling construction area, sealing plate is installed in the position of reserving hole;
The tolerance of 1 steel reinforcement cage of table
5) two layers of side plate supporting
After to steel reinforcement cage construction, corresponding side plate is chosen according to the spacing between opposite two steel reinforcement cages, by hanging Side plate is hoisted to the respective side of ventilating shaft by installation, and side plate is fixedly connected on corresponding steel reinforcement cage by screw, makes side plate It is completely embedded between steel reinforcement cage, the sequence when laying two layers of side plate from the bottom up, from left to right is laid, and guarantees left and right phase Spacing between adjacent, neighbouring two sides side plate is less than 1cm, adjacent side plate is connected and sealed, to two layers of side plate branch After the completion of shield, scaffold is removed, and to clearing up in ventilating shaft;
6) bracing means is constructed
A, appropriate number of supporting mechanism 1 is chosen according to the depth of ventilating shaft first, supporting mechanism 1 is uniformly folded from the bottom up Add, the supporting mechanism 1 positioned at bottom is uniformly distributed along the inside corner progress of ventilating shaft, makes supporting mechanism 1 and side wall corner Between spacing be greater than 30cm, while guaranteeing each 1 keeping parallelism of supporting mechanism;
B, after after the supporting mechanism 1 of bottom design, all installation is fixed, the two neighboring supporting mechanism 1 of right angle is passed through Link mechanism 2 is fixed, and is respectively mounted side wall reinforcement block 3 at the both ends of link mechanism 2, resists side wall reinforcement block 3 accordingly The supporting mechanism 1 of the side plate of side, two neighboring right angle is fixedly connected also by link mechanism 2, left and right it is adjacent two A about 2 link mechanism is interspersed;
C, rotating mechanism 6 is then socketed at the center of supporting mechanism 1, two adjacent side plates are obliquely installed when left and right When, first support bar 4 is installed between two adjacent rotating mechanisms 6 of left and right, by first support bar 4 by different obliquities Supporting mechanism 1 be fixedly connected, while on rotating mechanism 6 by fixed link install side wall reinforcement block 3, reinforce side wall Block 3 is vertical with corresponding side plate to be connected;
D, after to the bracing means installation of bottom, second layer branch is fixedly mounted in corresponding 1 top of supporting mechanism of bottom Support mechanism 1 is located at second layer supporting mechanism 1 and the supporting mechanism 1 of bottom on same vertical line, to the support machine on the second layer After the whole installations of structure 1 are fixed, the two neighboring supporting mechanism 1 of right angle is fixed by link mechanism 2, and in connecting rod machine The both ends of structure 2 are respectively mounted side wall reinforcement block 3, and side wall reinforcement block 3 is made to resist the side plate of corresponding side, the branch of two neighboring right angle Support mechanism 1 is fixedly connected also by link mechanism 2, and about 2 adjacent two link mechanisms of left and right are interspersed;
E, rotating mechanism 6 is then socketed at the center of supporting mechanism 1, two adjacent side plates are obliquely installed when left and right When, first support bar 4 is installed between two adjacent rotating mechanisms 6 of left and right, by first support bar 4 by different obliquities Supporting mechanism 1 be fixedly connected, while on rotating mechanism 6 by fixed link install side wall reinforcement block 3, reinforce side wall Block 3 is vertical with corresponding side plate to be connected;
F, successively remaining bracing means is installed by above-mentioned construction procedure;
As shown in Figures 1 to 8, supporting mechanism 1 includes column 5, and the top and bottom end of column 5 are symmetrically arranged with supporting block 9, The first pilot hole 7 and the second pilot hole 8 are provided on the side of column 5, the first pilot hole 7 is mutually perpendicular to the second pilot hole 8, Rotating mechanism 6 is located at the center of column 5, by the design of supporting block 9, not only increases between column 5 and ventilating shaft bottom surface Bonding strength, and connection stability and reliability between two supporting mechanisms 1 up and down is improved, it is strong to further increase support Degree improves the consolidation effect of ventilating shaft, and the first pilot hole 7 and the second pilot hole 8 can be used for positioning linkage rod mechanism 2, improves adjacent The stability connected between two supporting mechanisms 1.
Supporting block 9 is hemispherical, and there are two location hole 10 and two limited posts 12, positioning for setting on the top surface of supporting block 9 Hole 10 and limited post 12 are in distributed rectangular, and the diagonal setting respectively of two location holes, 10, two limited posts 12, limited post 12 and fixed Position hole 10 matches, and limit hole 13 is provided on limited post 12, and first through hole 11 is provided on the side of supporting block 9, and first is logical Hole 11 matches with limit hole 13, passes through first through hole 11 and limit hole 13 by fastening bolt 14, realizes two supports up and down Block 9 is fixedly connected, and hemispheric supporting block 9 designs the intensity for not only increasing supporting block 9, and can effectively carry out stress Distribution, improves stability when connection, and neighbouring two supporting mechanisms can be improved in the design of location hole 10 and limited post 12 Bonding strength and stability between 1, fastening bolt 14 are easily installed disassembly, realize fast between two supporting mechanisms 1 up and down Speed installation or removal.
Link mechanism 2 includes second support bar 15, third support rod 16 and joining rod 17, second support bar 15, third branch Strut 16 matches with the first pilot hole 7 and the second pilot hole 8, and joining rod 17 is located at second support bar 15 and third support rod Between 16, second support bar 15 connects joining rod 17 by position-limit mechanism, and the other end of joining rod 17 is provided with threaded post 18, the One end of three support rods 16 is provided with internal screw thread, and threaded post 18 matches with internal screw thread, and the first pilot hole 7, the second pilot hole 8 can To be positioned respectively to second support bar 15 and third support rod 16, the adjustable second support bar 15 of joining rod 17 and third Spacing between support rod 16, meets the side wall support of different length, and joining rod 17 is rotatably connected on second by position-limit mechanism Flexibility when length adjustment, threaded post 18 and the adjustable joining rod 17 of internal screw thread and third are improved in the end of support rod 15 Spacing between support rod 16, and then meet fine tuning when support.
Position-limit mechanism includes T-shaped block 19 and T-slot 20, and T-shaped block 19 is fixedly connected on the end face center of second support bar 15 Place, T-slot 20 are located at the end face center of joining rod 17, and T-shaped block 19 matches with T-slot 20, and the side of T-shaped block 19 passes through rolling Pearl 21 resists the medial surface of T-slot 20, and the design of T-shaped block 19 and T-slot 20 not only increases second support bar 15 and joining rod Bonding strength between 17, and joining rod 17 may be implemented by ball 21 and rotated around the end of second support bar 15, subtract Small frictional force reduces abrasion, extends the service life of position-limit mechanism.
Side wall reinforcement block 3 includes arc-shaped cover 32 and sleeve 30, and sleeve 30 is fixedly connected at the inside center of arc-shaped cover 32, Be evenly arranged with stiffening plate 31 between sleeve 30 and arc-shaped cover 32, the design of arc-shaped cover 32 not only increase side wall reinforcement block 3 with Contact area between two layers of side plate, and the support strength of side wall reinforcement block 3 is improved, sleeve 30 can play the work of positioning With stiffening plate 31 improves the intensity connected between sleeve 30 and arc-shaped cover 32, improves the supporting & stablizing of entire side wall reinforcement block 3 Property.
Rotating mechanism 6 includes cylinder 33, and the upper and lower ends of cylinder 33 are symmetrically arranged with annular slab 22, the outer circle of annular slab 22 It is evenly arranged with the second through-hole 23 on all sides, annular groove 24, upper and lower two annulars are provided between annular slab 22 and cylinder 33 There are three guide plates 25, guide plate 25 to pass through the second through-hole 23 by lock-screw 26 and be fixed on cylinder for mobile connection between slot 24 On 33, cylinder 33 is fixedly connected on column 5, plays the role of support positioning, and guide plate 25 can be not only used for connection first Support rod 4, and can connect side wall reinforcement block 3, meet the support on different inclined-planes, when guide plate 25 is moved to setting position Afterwards, the second through-hole 23 is passed through by lock-screw 26, realizes that guide plate 25 is fixed in annular groove 24.
Threaded hole 28 is provided at the center of guide plate 25, the two sides up and down of guide plate 25 are symmetrically arranged with arc conducting bar 27, arc conducting bar 27 matches with annular groove 24, is provided with wear plate 29 on arc conducting bar 27, and the design of arc conducting bar 27 can be with The stability when movement of guide plate 25 is improved, while positioning can be played the role of when fixed, lock can be improved in wear plate 29 Reliability when tight screw 26 connects.
7) concrete construction
After the installation is completed to bracing means, selecting grade is the concrete of C40, and seepage-resistant grade P12 stirs concrete Concrete continuous is injected between one layer of side plate and two layers of side plate by diversion trench after uniformly, is put into casting and shocks stick, shaken Tamper is equidistantly placed along each side of ventilating shaft, is made to shock stick and is located at bottom, is started while continuous concrete placing Stick is shocked, after concrete is completely covered and shocks stick, stick is each shocked and vibrates 20~30 seconds, and uniformly it is lifted up 40~ 60cm continues to vibrate 20~30 seconds, then is lifted up 40~60cm, until the concrete shake between one layer of side plate and two layers of side plate It smashes and finishes;
8) final acceptance of construction
After to concrete construction, place is cleared up, when link mechanism 2 or first support bar 4 influence shield and apply Working hour, link mechanism 2 or first support bar 4 when only need to remove shield-tunneling construction in perpendicular circumference range, and to whole A construction carries out an acceptance inspection.
The reinforced construction method is able to satisfy the ultra-deep ventilating shaft strengthening construction of different depth, substantially increases the use peace of ventilating shaft Quan Xing prevents the time from having grown and causes to collapse, and construction procedure is simple and convenient, more preferable compared to existing ventilating shaft consolidation effect, reduces shield Influence when structure is constructed to ventilating shaft entirety.
The above is only specific embodiments of the present invention, but technical characteristic of the invention is not limited thereto.It is any with this hair Based on bright, to realize essentially identical technical effect, made ground simple change, equivalent replacement or modification etc. are all covered Among protection scope of the present invention.

Claims (8)

1. a kind of control ultra-deep ventilating shaft strengthening control construction method, it is characterised in that the following steps are included:
1) preparation of construction
A, unwrapping wire is measured to ventilating shaft first, measures absolute altitude, the length and width of ventilating shaft, carries out review measurement, and measure wind The verticality of each side of well, is checked with design requirement, flat with drilling machine drill to the side that exceeds, it is ensured that each side it Between angle matched with design requirement;
B, leveling processing then is carried out to the bottom surface of ventilating shaft and each side, removes stone exposed on bottom surface and side, uses sand Slurry smoothes out, and uses mortar levelling to the rough position in bottom surface or side, then with rammer compacter to the bottom surface of ventilating shaft and side into Row compacting processing, is compacted the clay of bottom surface or side;
C, scaffold is then set up in ventilating shaft, and the bottom surface of scaffold and ventilating shaft is fixedly connected, scaffold and ventilating shaft Each side between spacing be greater than 1m;
2) construction of waterproof layer
A, first according to the suitable splash guard of the selection of dimension of ventilating shaft, holdfast is equidistantly installed at the back side of splash guard, in ventilating shaft Each side from left to right, successively splice splash guard from the bottom up, by splash guard holdfast insertion ventilating shaft side soil layer It is interior, it is bonded splash guard completely with the side of ventilating shaft;
B, then splash guard is cleaned out, the lap joint on splash guard is staggeredly arranged with construction joint, the distance being staggered is not small In 20cm, double slit welding is carried out using hot weld by bonding machine, the lap of splice between two splash guards is not less than 20cm, weldering It is welded from top to bottom when connecing;
C, geotechnological non-woven fabrics bed course then is laid in the front of splash guard, geotechnological non-woven fabrics is fixed on splash guard with support bar On, on the splash guard of side and bottom water-swellable item is installed respectively and is sealed;
D, finally to guiding gutter is opened up on the bottom surface of ventilating shaft, drainpipe, and layer overlay geotechnique's non-woven fabrics are installed in guiding gutter, It is backfilling and compacted again with clay;
3) one layer of side plate supporting
After to construction of waterproof layer, according to the corresponding side plate of the selection of dimension of ventilating shaft side, by hoisting machine by side plate handling To the respective side of ventilating shaft, side plate is fixedly connected on corresponding support bar by screw, makes to connect between side plate and splash guard Connect close, the sequence when laying one layer of side plate from the bottom up, from left to right is laid, guarantee left and right it is adjacent, neighbouring two Spacing between the side plate of side is less than 1cm;
4) steel reinforcement cage is laid
A, the main reinforcement and girder rib for choosing design requirement according to the lateral dimension of ventilating shaft first, pass through the connection side of straight screw sleeve Main reinforcement is attached by formula, and between two neighboring main reinforcement equidistantly intersect lay girder rib, by girder rib by welding with Main reinforcement is fixedly connected, and is spliced into required steel reinforcement cage;
B, hoisting point position is then determined on steel reinforcement cage, and the safety of hanging ring and suspender is checked, and will be hung by welding Ring is mounted on hoisting point position, while installing spacer pad respectively in the bottom of steel reinforcement cage and front and rear sides, and every layer is laid 5~6 Block;
C, then the steel reinforcement cage that splicing is completed is lifted to ventilating shaft in order by suspender, by each steel reinforcement cage close to corresponding The bottom surface of ventilating shaft side, the bottom and ventilating shaft that make steel reinforcement cage is fixedly connected, and the trailing flank of steel reinforcement cage is carried out with one layer of side plate It is fixedly connected, after four steel reinforcement cages are fixed in a ring round ventilating shaft medial surface, will be welded between two neighboring steel reinforcement cage It is fixed, and hole needed for reserving shield-tunneling construction area, sealing plate is installed in the position of reserving hole;
5) two layers of side plate supporting
After to steel reinforcement cage construction, corresponding side plate is chosen according to the spacing between opposite two steel reinforcement cages, passes through hoisting machine Side plate is hoisted to the respective side of ventilating shaft, side plate is fixedly connected on corresponding steel reinforcement cage by screw, makes side plate and steel Be completely embedded between muscle cage, when laying two layers of side plate, sequence from the bottom up, from left to right is laid, guarantee left and right it is adjacent, on Under spacing between adjacent two sides side plate be less than 1cm, adjacent side plate is connected and sealed, is completed to two layers of side plate supporting Afterwards, scaffold is removed, and to clearing up in ventilating shaft;
6) bracing means is constructed
A, appropriate number of supporting mechanism is chosen according to the depth of ventilating shaft first, supporting mechanism is uniformly superimposed from the bottom up, position Supporting mechanism in bottom is uniformly distributed along the inside corner progress of ventilating shaft, between making between supporting mechanism and side wall corner Away from 30cm is greater than, while guaranteeing each supporting mechanism keeping parallelism;
B, after all installation is fixed after the supporting mechanism of bottom design, the two neighboring supporting mechanism of right angle is passed through into connecting rod machine Structure is fixed, and is respectively mounted side wall reinforcement block at the both ends of link mechanism, and side wall reinforcement block is made to resist the side plate of corresponding side, The supporting mechanism of two neighboring right angle is fixedly connected also by link mechanism, above and below two adjacent link mechanisms of left and right It is interspersed;
C, rotating mechanism is then socketed at the center of supporting mechanism, when two adjacent side plates are obliquely installed when left and right, on a left side First support bar is installed between right two adjacent rotating mechanisms, by first support bar by the supporting mechanism of different obliquities It is fixedly connected, while side wall reinforcement block is installed by fixed link on rotating mechanism, make side wall reinforcement block and corresponding side Plate is vertically connected;
D, after to the bracing means installation of bottom, the corresponding supporting mechanism top of bottom is fixedly mounted the second layer and supports machine Structure is located at the supporting mechanism of second layer supporting mechanism and bottom on same vertical line, whole to the supporting mechanism on the second layer After installation is fixed, the two neighboring supporting mechanism of right angle is fixed by link mechanism, and at the both ends of link mechanism It is respectively mounted side wall reinforcement block, side wall reinforcement block is made to resist the side plate of corresponding side, the supporting mechanism of two neighboring right angle also leads to It crosses link mechanism to be fixedly connected, two adjacent link mechanisms of left and right are interspersed up and down;
E, rotating mechanism is then socketed at the center of supporting mechanism, when two adjacent side plates are obliquely installed when left and right, on a left side First support bar is installed between right two adjacent rotating mechanisms, by first support bar by the supporting mechanism of different obliquities It is fixedly connected, while side wall reinforcement block is installed by fixed link on rotating mechanism, make side wall reinforcement block and corresponding side Plate is vertically connected;
F, successively remaining bracing means is installed by above-mentioned construction procedure;
7) concrete construction
After the installation is completed to bracing means, selecting grade is the concrete of C40, and seepage-resistant grade P12 stirs evenly concrete Concrete continuous is injected between one layer of side plate and two layers of side plate by diversion trench afterwards, is put into casting and shocks stick, shock stick It is equidistantly placed along each side of ventilating shaft, makes to shock stick and be located at bottom, started while continuous concrete placing and shock Stick each shocks stick and vibrates 20~30 seconds, and be uniformly lifted up 40~60cm after concrete is completely covered and shocks stick, after It is continuous to vibrate 20~30 seconds, then it is lifted up 40~60cm, until the concrete between one layer of side plate and two layers of side plate is shocked and is finished;
8) final acceptance of construction
After to concrete construction, place is cleared up, when link mechanism or first support bar influence shield-tunneling construction, only Link mechanism or first support bar when need to remove shield-tunneling construction in perpendicular circumference range, and entire construction is carried out It checks and accepts.
2. a kind of control ultra-deep ventilating shaft strengthening control construction method according to claim 1, it is characterised in that: in step 6) The supporting mechanism include column, the top and bottom end of the column are symmetrically arranged with supporting block, on the side of the column It is provided with the first pilot hole and the second pilot hole, first pilot hole is mutually perpendicular to second pilot hole, the rotation Mechanism is located at the center of the column.
3. a kind of control ultra-deep ventilating shaft strengthening control construction method according to claim 2, it is characterised in that: the support Block is hemispherical, and setting is there are two location hole and two limited posts on the top surface of the supporting block, the location hole and the limit Position column is in distributed rectangular, and the diagonal setting respectively of two location holes, two limited posts, the limited post with it is described fixed Position hole matches, and limit hole is provided on the limited post, is provided with first through hole on the side of the supporting block, and described first Through-hole matches with the limit hole, passes through the first through hole and the limit hole by fastening bolt, realizes two up and down The supporting block is fixedly connected.
4. a kind of control ultra-deep ventilating shaft strengthening control construction method according to claim 2, it is characterised in that: in step 6) The link mechanism include second support bar, third support rod and joining rod, the second support bar, the third support rod Match with first pilot hole and second pilot hole, the joining rod is located at the second support bar and described Between three support rods, the second support bar connects the joining rod, the other end setting of the joining rod by position-limit mechanism There is threaded post, one end of the third support rod is provided with internal screw thread, and the threaded post matches with the internal screw thread.
5. a kind of control ultra-deep ventilating shaft strengthening control construction method according to claim 4, it is characterised in that: the limit Mechanism includes T-shaped block and T-slot, and the T-shaped block is fixedly connected at the end face center of the second support bar, the T-slot At the end face center of the joining rod, the T-shaped block matches with the T-slot, and the side of the T-shaped block passes through ball Resist the medial surface of the T-slot.
6. a kind of control ultra-deep ventilating shaft strengthening control construction method according to claim 1, it is characterised in that: in step 6) The side wall reinforcement block include arc-shaped cover and sleeve, the sleeve is fixedly connected at the inside center of the arc-shaped cover, institute It states and is evenly arranged with stiffening plate between sleeve and the arc-shaped cover.
7. a kind of control ultra-deep ventilating shaft strengthening control construction method according to claim 1, it is characterised in that: in step 6) The rotating mechanism include cylinder, the upper and lower ends of the cylinder are symmetrically arranged with annular slab, the excircle of the annular slab It is evenly arranged with the second through-hole on side, annular groove, upper and lower two rings are provided between the annular slab and the cylinder There are three guide plate, the guide plate is fixed on by lock-screw across second through-hole described mobile connection between shape slot On cylinder.
8. a kind of control ultra-deep ventilating shaft strengthening control construction method according to claim 7, it is characterised in that: in step 6) The guide plate center at be provided with threaded hole, the two sides up and down of the guide plate are symmetrically arranged with arc conducting bar, described Arc conducting bar matches with the annular groove, is provided with wear plate on the arc conducting bar.
CN201910213158.XA 2019-03-20 2019-03-20 Reinforcing control construction method for controlling ultra-deep air shaft Active CN110030015B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910213158.XA CN110030015B (en) 2019-03-20 2019-03-20 Reinforcing control construction method for controlling ultra-deep air shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910213158.XA CN110030015B (en) 2019-03-20 2019-03-20 Reinforcing control construction method for controlling ultra-deep air shaft

Publications (2)

Publication Number Publication Date
CN110030015A true CN110030015A (en) 2019-07-19
CN110030015B CN110030015B (en) 2020-07-10

Family

ID=67236253

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910213158.XA Active CN110030015B (en) 2019-03-20 2019-03-20 Reinforcing control construction method for controlling ultra-deep air shaft

Country Status (1)

Country Link
CN (1) CN110030015B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5631926A (en) * 1979-08-22 1981-03-31 Kumagai Gumi Ltd Water-stop protection for landslide
JP2000291147A (en) * 1999-04-06 2000-10-17 Takenaka Komuten Co Ltd Dome roof construction method without timbering
CN201972711U (en) * 2011-01-10 2011-09-14 上海陆家嘴金融贸易区联合发展有限公司 Device for controlling deformation of near metro tunnel caused by super-deep foundation pit evacuation in soft soil areas
CN105332722A (en) * 2015-11-29 2016-02-17 辽宁工程技术大学 Coal mine rock burst timbering device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5631926A (en) * 1979-08-22 1981-03-31 Kumagai Gumi Ltd Water-stop protection for landslide
JP2000291147A (en) * 1999-04-06 2000-10-17 Takenaka Komuten Co Ltd Dome roof construction method without timbering
CN201972711U (en) * 2011-01-10 2011-09-14 上海陆家嘴金融贸易区联合发展有限公司 Device for controlling deformation of near metro tunnel caused by super-deep foundation pit evacuation in soft soil areas
CN105332722A (en) * 2015-11-29 2016-02-17 辽宁工程技术大学 Coal mine rock burst timbering device

Also Published As

Publication number Publication date
CN110030015B (en) 2020-07-10

Similar Documents

Publication Publication Date Title
CN109629455B (en) Construction method for reconstructing bridge of highway
CN106958256B (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN104652290B (en) Steel truss beam bridge Horizontal Swing Construction method
CN105804089B (en) Locally increase deep support system and its construction method after a kind of former deep foundation pit construction
CN108915696B (en) Construction organization method for complete mechanical equipment of tunnel
CN108824220A (en) A kind of cast-in-place support and construction method of the rigid structure of cantilever T-type
CN110485429A (en) A kind of prestressing force fashioned iron assembled combination inner support construction method
CN114164764B (en) Construction method of high-filling bridge bearing platform structure
CN109488347B (en) Excavation construction method for special stratum chamber
CN110905523A (en) Subway vertical shaft construction method
CN108331000A (en) Caisson sinking construction method
CN109611102A (en) Construction of the flyover method is worn under a kind of cold excavation
CN107964976A (en) Steel pipe-conversion steel platform tower crane top-down construction method
CN110847195A (en) Construction method for stable treatment of side and upward slope of large-block-diameter loose rock pile body opening
CN111119198A (en) A reinforced structure that is used for SMW worker method stake to strut system
CN106835992B (en) A kind of arcuate structure clear-water concrete construction of cast-in-situ box-beam method
CN110748701A (en) Pipe-jacking working pit construction method
CN101994314A (en) Longhole rectangular terraced antiskid pile jump-preventing excavating construction
CN205576934U (en) Part increases ramus profundus watch box system behind former deep foundation pit construction
CN105970992B (en) Large section high inclination-angle tunnel type pile foundation construction process
CN109137873A (en) A method of wet and soft foundation is handled using precast square pile
CN110030015A (en) A kind of control ultra-deep ventilating shaft strengthening control construction method
CN112281873A (en) Construction method of anchoring pile
CN208618287U (en) A kind of cast-in-place support of the rigid structure of cantilever T-type
CN218322863U (en) Well body reinforcing system for inspection well

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant