CN110004962A - A kind of prefabricated reinforced concrete sump loose tool structure and its construction method - Google Patents

A kind of prefabricated reinforced concrete sump loose tool structure and its construction method Download PDF

Info

Publication number
CN110004962A
CN110004962A CN201910291859.5A CN201910291859A CN110004962A CN 110004962 A CN110004962 A CN 110004962A CN 201910291859 A CN201910291859 A CN 201910291859A CN 110004962 A CN110004962 A CN 110004962A
Authority
CN
China
Prior art keywords
loose tool
sump
reinforced concrete
prefabricated reinforced
tool structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910291859.5A
Other languages
Chinese (zh)
Inventor
姚民立
秦毅
章根祥
杜冠卿
潘建树
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 7 Group Co Ltd
Shanghai No 7 Construction Co Ltd
Original Assignee
Shanghai No 7 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai No 7 Construction Co Ltd filed Critical Shanghai No 7 Construction Co Ltd
Priority to CN201910291859.5A priority Critical patent/CN110004962A/en
Publication of CN110004962A publication Critical patent/CN110004962A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/22Lining sumps in trenches or other foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention provides a kind of prefabricated reinforced concrete sump loose tool structure and its construction method.A kind of prefabricated reinforced concrete sump loose tool structure, including the precast concrete loose tool being set in well slot and the brick mold vertically arranged along precast concrete loose tool periphery.Prefabricated reinforced concrete sump loose tool structure of the invention, precast concrete loose tool makes outside well slot, after production, reaches certain requirement to intensity, then install into well slot, then carries out the masonry of brick mold.In this way, the production of precast concrete loose tool not will receive the influence of ponding, to solve the problems, such as to cause the loose tool of sump to build difficulty because dewatering effect is undesirable, masonry workload is decreased, labour is saved, Economic model is preferable.

Description

A kind of prefabricated reinforced concrete sump loose tool structure and its construction method
Technical field
The present invention relates to a kind of sump loose tool structure, in particular to a kind of prefabricated reinforced concrete sump loose tool structure And its construction method.
Background technique
During the foundation pit construction in soft foundation region, especially in the work progress of sump, underground water is easy to It penetrates into hole, dewatering operation is caused to be unable to reach desired effect, built so as to cause sump position brick mold difficult.And it uses Conventional " throwing bagged cement pours bed course, builds brick mold " though mode can improve the effect of dewatering operation, waste of material Huge, heavy workload.
Summary of the invention
In order to solve " in the work progress of sump, to cause the loose tool masonry of sump tired because dewatering effect is undesirable It is difficult " the problem of, the present invention provides a kind of prefabricated reinforced concrete sump loose tool structure and its construction method.
A kind of technical solution of prefabricated reinforced concrete sump loose tool structure of the invention is as follows:
A kind of prefabricated reinforced concrete sump loose tool structure, including be set in well slot precast concrete loose tool, with And the brick mold vertically arranged along precast concrete loose tool periphery.
Prefabricated reinforced concrete sump loose tool structure of the invention, precast concrete loose tool make outside well slot, production After, reach certain requirement to intensity, then install into well slot, then carries out the masonry of brick mold.In this way, precast concrete The production of loose tool not will receive the influence of ponding, cause the loose tool of sump to build because dewatering effect is undesirable to solve Difficult problem is built, masonry workload is decreased, saves labour, Economic model is preferable.In addition, along described prefabricated mixed The vertically arranged brick mold in solidifying soil loose tool periphery, that is, can guarantee the system of the height of prefabricated reinforced concrete sump loose tool structure One, convenient for production, and can save material, mitigate self weight be easy to lift transport.
Further, in the prefabricated reinforced concrete sump loose tool structure, specifically, the mark on the brick mold top It is high identical as the absolute altitude at well slot hole.
Further, in the prefabricated reinforced concrete sump loose tool structure, the precast concrete loose tool includes bottom Plate and the side wall for being set to floor peripheral, the brick mold are set to the top of the side wall.The setting of side wall can play gear Water effect, to be further ensured that going on smoothly for brick mold building process.
Further, in the prefabricated reinforced concrete sump loose tool structure, in order to facilitate precast concrete loose tool Installation, further includes several suspension hooks for being set to the side wall upper part.Precast concrete loose tool can be lifted to peace by suspension hook Holding position.
Further, in the prefabricated reinforced concrete sump loose tool structure, specifically, the precast concrete loose tool Concrete strength be C20,12@of Φ, 150 single-layer bidirectional distributing bar is matched in inside, the bottom plate and side wall with a thickness of 100mm, the suspension hook are made of the Q235 round steel of diameter 18mm, the brick mold with a thickness of 100mm.
The present invention also provides a kind of construction methods of prefabricated reinforced concrete sump loose tool structure.
The technical solution of the construction method of prefabricated reinforced concrete sump loose tool structure of the invention is as follows including as follows Step:
The first step makes precast concrete loose tool according to sump size;
Second step excavates well slot in sump position;
Precast concrete loose tool is mounted in well slot by third step;
4th step builds brick mold on precast concrete loose tool periphery;
5th step is backfilled and is tamped to the well slot on the outside of brick mold after brick mold reaches some strength;
6th step carries out plastering and the waterproof construction of the inner wall of prefabricated reinforced concrete sump loose tool structure, Yi Jiji The laying of plinth bottom plate.
The construction method of prefabricated reinforced concrete sump loose tool structure of the invention, precast concrete loose tool is outside well slot Production, after production, reaches certain requirement to intensity, then install into well slot, then carries out the masonry of brick mold.In this way, The production of precast concrete loose tool not will receive the influence of ponding, cause to catchment because dewatering effect is undesirable to solve The loose tool of well builds difficult problem, decreases masonry workload, saves labour, and Economic model is preferable.In addition, edge The vertically arranged brick mold in precast concrete loose tool periphery can guarantee prefabricated reinforced concrete sump loose tool structure The unification of height, convenient for production, and can save material, mitigate self weight be easy to lift transport.
Further, in the construction method of the prefabricated reinforced concrete sump loose tool structure, in order in zone of reasonableness Inside accelerate construction progress, in third step, i.e. collapsible die when the intensity of precast concrete loose tool reaches the 75% of design strength, and pacify It is filled in well slot.
Further, in the construction method of the prefabricated reinforced concrete sump loose tool structure, in order to more accurate Precast concrete loose tool is installed, in third step, before precast concrete loose tool is mounted in well slot, is first drawn at the top of well slot White line is for controlling prefabricated reinforced concrete sump loose tool structure riding position.
Detailed description of the invention
Fig. 1 is a kind of schematic diagram of prefabricated reinforced concrete sump loose tool structure of the invention.
Specific embodiment
The present invention is described in further detail below in conjunction with the drawings and specific embodiments.It is wanted according to following explanation and right Book is sought, advantages and features of the invention will become apparent from.It should be noted that attached drawing is all made of very simplified form and using non- Accurately ratio, only for the purpose of facilitating and clarifying the purpose of the embodiments of the invention.
Embodiment 1:
With reference to Fig. 1, a kind of prefabricated reinforced concrete sump loose tool structure of the present embodiment, including be set in well slot 1 Precast concrete loose tool 2 and the brick mold 3 vertically arranged along 2 periphery of precast concrete loose tool.
The prefabricated reinforced concrete sump loose tool structure of the present embodiment, precast concrete loose tool 2 make outside well slot 1, After production, reach certain requirement to intensity, then install into well slot 1, then carries out the masonry of brick mold 3.In this way, prefabricated Concrete moulding bed 2 production not will receive the influence of ponding, cause sump because dewatering effect is undesirable to solve Loose tool build difficult problem, decrease masonry workload, save labour, Economic model is preferable.In addition, along institute The vertically arranged brick mold 3 in 2 periphery of precast concrete loose tool is stated, that is, can guarantee prefabricated reinforced concrete sump loose tool structure The unification of height, convenient for production, and can save material, mitigate self weight be easy to lift transport.
As preferable embodiment, in the prefabricated reinforced concrete sump loose tool structure, specifically, the brick tire The absolute altitude on 3 top of mould is identical as the absolute altitude at 1 hole of well slot.
As preferable embodiment, in the prefabricated reinforced concrete sump loose tool structure, the precast concrete Loose tool 2 includes that bottom plate 2a and the side wall 2b for being set to the periphery bottom plate 2a, the brick mold 3 are set to the upper of the side wall 2b Portion.The setting of side wall 2b can play the role of water blocking, to be further ensured that going on smoothly for 3 building process of brick mold.
Further, in the prefabricated reinforced concrete sump loose tool structure, in order to facilitate precast concrete loose tool 2 Installation, further includes several suspension hooks 4 for being set to the top the side wall 2b.Precast concrete loose tool 2 can be lifted by suspension hook 4 To installation site.
Further, in the prefabricated reinforced concrete sump loose tool structure, specifically, the precast concrete loose tool 2 concrete strength is C20, and 12@of Φ, 150 single-layer bidirectional distributing bar, the thickness of the bottom plate 2a and side wall 2b are matched in inside For 100mm, the suspension hook 4 is made of the Q235 round steel of diameter 18mm, the brick mold 3 with a thickness of 100mm.
Embodiment 2:
With reference to Fig. 1, the present embodiment provides a kind of applying for prefabricated reinforced concrete sump loose tool structure described in embodiment 1 Work method, includes the following steps:
The first step makes precast concrete loose tool 2 according to sump size;
Second step excavates well slot 1 in sump position;
Precast concrete loose tool 2 is mounted in well slot 1 by third step;
4th step builds brick mold 3 on 2 periphery of precast concrete loose tool;
5th step is backfilled and is tamped to the well slot 1 in 3 outside of brick mold after brick mold 3 reaches some strength;
6th step carries out plastering and the waterproof construction of the inner wall of prefabricated reinforced concrete sump loose tool structure, Yi Jiji The laying of plinth bottom plate 5.
The construction method of the prefabricated reinforced concrete sump loose tool structure of the present embodiment, precast concrete loose tool 2 is in well It is made outside slot 1, after production, reaches certain requirement to intensity, then install into well slot 1, then carry out the block of brick mold 3 It builds.In this way, the production of precast concrete loose tool 2 not will receive the influence of ponding, to solve because dewatering effect is undesirable And cause the loose tool of sump to build difficult problem, decrease masonry workload, save labour, Economic model compared with It is good.In addition, the brick mold 3 vertically arranged along 2 periphery of precast concrete loose tool, that is, can guarantee that prefabricated reinforced concrete catchments The unification of the height of well loose tool structure, convenient for production, and can save material, mitigate self weight be easy to lift transport.
Further, in the construction method of the prefabricated reinforced concrete sump loose tool structure, in order in zone of reasonableness Inside accelerate construction progress, in third step, i.e. collapsible die when the intensity of precast concrete loose tool 2 reaches the 75% of design strength, and Installation is into well slot 1.
Further, in the construction method of the prefabricated reinforced concrete sump loose tool structure, in order to more accurate Precast concrete loose tool 2 is installed, in third step, before precast concrete loose tool 2 is mounted in well slot 1, is first pushed up in well slot 1 Draw white line for controlling prefabricated reinforced concrete sump loose tool structure riding position in portion.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Range.

Claims (8)

1. a kind of prefabricated reinforced concrete sump loose tool structure, which is characterized in that prefabricated mixed in well slot (1) including being set to Solidifying soil loose tool (2) and the brick mold (3) vertically arranged along precast concrete loose tool (2) periphery.
2. prefabricated reinforced concrete sump loose tool structure as described in claim 1, which is characterized in that the brick mold (3) The absolute altitude on top is identical as the absolute altitude at well slot (1) hole.
3. prefabricated reinforced concrete sump loose tool structure as described in claim 1, which is characterized in that the precast concrete Loose tool (2) includes bottom plate (2a) and the side wall (2b) for being set to the periphery bottom plate (2a), and the brick mold (3) is set to the side The top of wall (2b).
4. prefabricated reinforced concrete sump loose tool structure as claimed in claim 3, which is characterized in that further include being set to institute State several suspension hooks (4) on the top side wall (2b).
5. prefabricated reinforced concrete sump loose tool structure as claimed in claim 4, which is characterized in that the precast concrete The concrete strength of loose tool (2) is C20, and 12@of Φ, 150 single-layer bidirectional distributing bar, the bottom plate (2a) and side wall are matched in inside (2b) with a thickness of 100mm, the suspension hook (4) is made of the Q235 round steel of diameter 18mm, the brick mold (3) with a thickness of 100mm。
6. the construction method of any one prefabricated reinforced concrete sump loose tool structure, special in a kind of such as claim 1 to 5 Sign is, includes the following steps:
The first step makes precast concrete loose tool (2) according to sump size;
Second step excavates well slot (1) in sump position;
Precast concrete loose tool (2) is mounted in well slot (1) by third step;
4th step builds brick mold (3) on precast concrete loose tool (2) periphery;
5th step is backfilled and is tamped to the well slot (1) on the outside of brick mold (3) after brick mold (3) reaches some strength;
6th step carries out plastering and the waterproof construction of the inner wall of prefabricated reinforced concrete sump loose tool structure, and basic bottom The laying of plate (5).
7. the construction method of prefabricated reinforced concrete sump loose tool structure as claimed in claim 6, which is characterized in that third In step, i.e. collapsible die when the intensity of precast concrete loose tool (2) reaches the 75% of design strength, and install into well slot (1).
8. the construction method of prefabricated reinforced concrete sump loose tool structure as claimed in claim 6, which is characterized in that third In step, before precast concrete loose tool (2) is mounted in well slot (1), first draw white line pre- for controlling at the top of well slot (1) Reinforced concrete water collection well loose tool structure riding position processed.
CN201910291859.5A 2019-04-12 2019-04-12 A kind of prefabricated reinforced concrete sump loose tool structure and its construction method Pending CN110004962A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910291859.5A CN110004962A (en) 2019-04-12 2019-04-12 A kind of prefabricated reinforced concrete sump loose tool structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910291859.5A CN110004962A (en) 2019-04-12 2019-04-12 A kind of prefabricated reinforced concrete sump loose tool structure and its construction method

Publications (1)

Publication Number Publication Date
CN110004962A true CN110004962A (en) 2019-07-12

Family

ID=67171266

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910291859.5A Pending CN110004962A (en) 2019-04-12 2019-04-12 A kind of prefabricated reinforced concrete sump loose tool structure and its construction method

Country Status (1)

Country Link
CN (1) CN110004962A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203049588U (en) * 2013-01-15 2013-07-10 龙元建设集团股份有限公司 Pit-in-pit cylindrical mould
CN104358275A (en) * 2014-11-19 2015-02-18 武汉一冶建筑安装工程有限责任公司 Construction method for deeper elevator well or water collecting well
CN106930307A (en) * 2017-03-21 2017-07-07 中国十七冶集团有限公司 The foundation beam prefabricated board and its assembly construction method of a kind of replacement brick fetal membrane
CN107443550A (en) * 2017-08-07 2017-12-08 佛山市万科置业有限公司 Prefabricated cushion cap template and its installation method
CN107653894A (en) * 2017-07-25 2018-02-02 浙江省建工集团有限责任公司 A kind of construction technology that foundation platform is made by precast concrete
CN108708384A (en) * 2018-04-13 2018-10-26 五冶集团上海有限公司 A kind of construction method for building sump brick mold using precast frame template
CN210238546U (en) * 2019-04-12 2020-04-03 上海建工七建集团有限公司 Prefabricated reinforced concrete sump pit child mould structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203049588U (en) * 2013-01-15 2013-07-10 龙元建设集团股份有限公司 Pit-in-pit cylindrical mould
CN104358275A (en) * 2014-11-19 2015-02-18 武汉一冶建筑安装工程有限责任公司 Construction method for deeper elevator well or water collecting well
CN106930307A (en) * 2017-03-21 2017-07-07 中国十七冶集团有限公司 The foundation beam prefabricated board and its assembly construction method of a kind of replacement brick fetal membrane
CN107653894A (en) * 2017-07-25 2018-02-02 浙江省建工集团有限责任公司 A kind of construction technology that foundation platform is made by precast concrete
CN107443550A (en) * 2017-08-07 2017-12-08 佛山市万科置业有限公司 Prefabricated cushion cap template and its installation method
CN108708384A (en) * 2018-04-13 2018-10-26 五冶集团上海有限公司 A kind of construction method for building sump brick mold using precast frame template
CN210238546U (en) * 2019-04-12 2020-04-03 上海建工七建集团有限公司 Prefabricated reinforced concrete sump pit child mould structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
湖北水总水利水电建设股份有限公司: "《模板工程施工》", 31 January 2018, 中国环境科学出版社, pages: 155 - 158 *

Similar Documents

Publication Publication Date Title
CN101818527B (en) Assembled integral shear wall structure system and construction method thereof
CN201687102U (en) Assembled integral type shear wall structure system
CN101985856B (en) Removal-free prefabricated reinforced concrete template with cross holes inside and manufacturing method thereof
CN205975626U (en) Strut integrated configuration with stagnant water unification in soft soil layer foundation ditch
CN106638940A (en) Fabricated high-rise residence precast concrete component construction method
CN108726348B (en) Horizontal prefabrication, overturning and hoisting method for pipe gallery segments
CN204098486U (en) The concrete of building basement roof ater-casting hangs mould
CN101487293A (en) Concrete pouring method for beam-column joints with different strength grades
CN202730579U (en) Recyclable prefabricated concrete block for hardening construction plant
CN104328790B (en) Cast-in-situ sprayed concrete hidden bearing platform and hidden ground beam molding bed
CN107227845A (en) One kind filling wall construction post mold method
CN206928323U (en) A kind of ring muscle fastens assembled pipe gallery
CN110005200A (en) The closely knit construction technology of horizontal concealed beam concreting
CN202954490U (en) Rolling type cushion block for hoisting reinforcement cage
CN210238546U (en) Prefabricated reinforced concrete sump pit child mould structure
CN204418691U (en) A kind of for cast-in-place vertical member and horizontal member junction concrete blocking apparatus
CN110004962A (en) A kind of prefabricated reinforced concrete sump loose tool structure and its construction method
CN108978699B (en) Land integral prefabricated bearing platform and production and installation method thereof
CN207513002U (en) A kind of concrete prefabricated wallboard
CN207891904U (en) A kind of prefabricated basic component of additional elevator of existing building
CN207376661U (en) A kind of plugging structure of poured band of outer wall of basement
CN207526118U (en) For pre-buried and closure unwrapping wire hole unwrapping wire punch die
CN109267578A (en) A kind of inclined-plane plain concrete construction and its construction method
CN105544561B (en) The construction method of friction pile breast wall concrete Quick pouring
CN208803700U (en) Precast concrete cushion block between sinking

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination