CN109986524A - A kind of hanging ladder tooling peculiar to vessel and its application method - Google Patents
A kind of hanging ladder tooling peculiar to vessel and its application method Download PDFInfo
- Publication number
- CN109986524A CN109986524A CN201910248986.7A CN201910248986A CN109986524A CN 109986524 A CN109986524 A CN 109986524A CN 201910248986 A CN201910248986 A CN 201910248986A CN 109986524 A CN109986524 A CN 109986524A
- Authority
- CN
- China
- Prior art keywords
- stringer
- tooling
- strap
- hanging ladder
- peculiar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 15
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 4
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 15
- 230000001681 protective effect Effects 0.000 claims description 13
- 235000005121 Sorbus torminalis Nutrition 0.000 claims description 3
- 244000152100 Sorbus torminalis Species 0.000 claims description 3
- 239000007787 solid Substances 0.000 claims description 2
- 238000011017 operating method Methods 0.000 abstract 1
- 238000009434 installation Methods 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 230000011218 segmentation Effects 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 230000009471 action Effects 0.000 description 2
- 230000009194 climbing Effects 0.000 description 2
- 230000007547 defect Effects 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 239000003973 paint Substances 0.000 description 2
- 238000003825 pressing Methods 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 239000002994 raw material Substances 0.000 description 2
- FGRBYDKOBBBPOI-UHFFFAOYSA-N 10,10-dioxo-2-[4-(N-phenylanilino)phenyl]thioxanthen-9-one Chemical compound O=C1c2ccccc2S(=O)(=O)c2ccc(cc12)-c1ccc(cc1)N(c1ccccc1)c1ccccc1 FGRBYDKOBBBPOI-UHFFFAOYSA-N 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B25—HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
- B25H—WORKSHOP EQUIPMENT, e.g. FOR MARKING-OUT WORK; STORAGE MEANS FOR WORKSHOPS
- B25H5/00—Tool, instrument or work supports or storage means used in association with vehicles; Workers' supports, e.g. mechanics' creepers
Abstract
The invention discloses a kind of hanging ladder toolings peculiar to vessel, including four stringers, several job platforms are arranged at intervals at the inside of four stringers, job platform includes rectangular frame and the grid that is set in rectangular frame, manhole and manhole cover are additionally provided on grid, manhole cover one end and grid or rectangular frame are articulated and connected, even level is set to the first stringer and the second stringer to several crosspieces respectively, second stringer and third stringer, on third stringer and the 4th stringer, strap and supporting leg are respectively equipped on the outside of the upper and lower side of first stringer and the 4th stringer, the lower edge that strap one end is fixedly connected with the other end with stringer is equipped with open slot, one side edge of the open slot close to strap end is equipped with baffle, baffle is equipped with threaded hole and clamping screw, one end of supporting leg is fixedly connected with the other end with stringer equipped with sucker;Application method includes placing, position and reinforcing.The tooling and operating procedure are simple, and do not damage to hull, strong applicability.
Description
Technical field
The invention belongs to shipbuilding technical fields, and in particular to a kind of hanging ladder tooling peculiar to vessel and its application method.
Background technique
Large ship in the prior art is fabricated using group mode of construction in segmentation, wherein the group in shipbuilding segmentation
In berth combination production process, needs to assemble the place of closing up on the outside of ship side, weld.In the process, it needs making
Set up the workbench of multi-layer in industry region.Currently, mostly being welded at outside plate along plate using steel tube fastener formula scaffold or on the quarter
The fixed anchor point of tooling is installed along plate tooling foot hand, but two kinds of toolings are respectively present following problems in use:
1, steel tube fastener formula scaffold need to set up a large amount of foot hand, set up foot hand complex procedures, time-consuming and take a lot of work, work effect
Rate is low.
2, plate tooling foot hand after operation, needs aloft to the fixation along plate tooling although it is shorter to set up the time
Anchor point carry out welding dismounting, needed after dismounting to leg carry out grinding process, not only break up shell ontology paint, and working efficiency compared with
It is low.
Therefore, it is necessary to design it is a traditional scaffold can be overcome to build inefficiency, and do not damage the extension peculiar to vessel of hull
Ladder work's dress, to improve the installation effectiveness of group and scaffold in berth combination production process in shipbuilding segmentation.
Summary of the invention
It is an object of the present invention to overcome defect existing in the prior art, a kind of hanging ladder tooling peculiar to vessel is provided and its is made
With method, the tool structure is simple, and the installation procedure of the tooling is simple, on the one hand overcomes conventional steel design of coupler scaffold
The defect of installation procedure complexity does not need the paint for destroying hull surface, and the tooling when on the other hand the tooling is installed and used
Stability and safety are higher, practical.
To achieve the above object, the technical scheme is to design a kind of hanging ladder toolings peculiar to vessel, including the first stringer,
Two stringers, third stringer, the 4th stringer, several job platforms and several crosspieces, first stringer, the second stringer, third are vertical
Beam and the 4th stringer are parallel to each other and are successively located on four vertex of rectangle, and several job platforms are arranged at intervals at
The inside of first stringer, the second stringer, third stringer and the 4th stringer, the job platform include rectangular frame and setting
In the grid in rectangular frame, manhole and manhole cover, manhole cover one end and grid or rectangular frame are additionally provided on the grid
Articulated connection, uniform intervals are set to the first stringer between adjacent job platform and the second stringer, the to several crosspieces respectively
On two stringers and third stringer, third stringer and the 4th stringer, distinguish in the top and bottom of first stringer, the 4th stringer
It is described equipped with the strap and supporting leg for extending to first stringer, the second stringer, third stringer and the 4th rail outer
Strap and support leg are parallel to each other and vertical with the plane where the second stringer and third stringer respectively, the strap
Plate face it is longitudinally disposed, one end of strap is equipped with the lower edge that the first stringer or the 4th stringer are fixedly connected with the other end
Open slot is equipped with baffle in one side edge of the open slot close to strap end, is additionally provided with screw thread on the baffle
Hole and clamping screw, one end of the supporting leg are fixedly connected with the other end with the first stringer or the 4th stringer equipped with sucker.
The machine frame structure is simple, and three sides that four stringers constitute frame structure are equipped with crosspiece, and crosspiece is on the one hand
As the pedal of climbing, support and booster action on the other hand are played to hanging ladder, the side direction for being not provided with crosspiece is made
Industry area, convenient for the constructing operation of staff;The job platform of the hanging ladder is equipped with manhole and manhole cover, and it is work that manhole cover, which is closed,
Make personnel's operation table top, it is staff only that manhole cover, which is opened, makes staff's hanging ladder above and below lower portion, ensure that
The safety when hanging ladder up and down of staff;The hanging ladder upper end is equipped with strap, lower end is equipped with supporting leg, and strap
End is equipped with the open slot for being clamped ship side edge, and the end of supporting leg is equipped with sucker, and the two ensure that hanging ladder peculiar to vessel uses
Fastness and stability.
For the ease of the clamping and fixation of strap upper open slot and ship side edge, preferred technical solution is, described
One end that strap is fixedly connected with the first stringer or the 4th stringer is equipped with the L shape guide groove to stand upside down, in first stringer
Upper end is equipped with the first through hole through the first stringer ontology, is equipped with the through the 4th stringer ontology in the 4th stringer upper end
The axis of two through-holes, the first through hole and the second through-hole is located on the same line, and the L shape of the handstand of the strap is led
It is fixedly connected to slot by the first through hole on bolt and the first stringer or the second through-hole on the 4th stringer.The L shape of handstand is led
Strap can be made to be adjusted in vertical and horizontal to slot, convenient for being fixedly connected between strap and ship side.
In order to make tooling that there is optimal working space under conditions of putting into using minimum raw material, to guarantee work
Personnel use the working efficiency when tooling, and further preferred technical solution is in addition, first stringer and the 4th stringer, the
Spacing range between two stringers and third stringer is 1~1.5m, and first stringer and the second stringer, third stringer and the 4th are vertical
Spacing range between beam is 60~80cm, and the spacing range of the adjacent job platform is 1.8~2m, between the adjacent rungs
It is 50~80cm away from range.
On the one hand on the other hand logical inside the hanging ladder convenient for staff in order to guarantee the secure of the tooling
It crosses, further preferred technical solution is in addition, the manhole cover is alternately disposed at the left and right side of adjacent job platform.
On the one hand in order to guarantee personal safety when staff's operation, on the other hand prevent tool from falling to ground staff
It damages, further preferred technical solution is described anti-in addition, be additionally provided with protective net at the edge of the rectangular frame upper end
The outside of protective net is welded to connect with first stringer, the second stringer, third stringer and the 4th stringer respectively, the protective net
Height is 50~80cm.
For the ease of the carrying and lifting of the hanging ladder tooling, further preferred technical solution in addition, further include pedestal and
Controller is equipped with peace compatible with first stringer, the second stringer, third stringer and the 4th stringer in the pedestal upper end
Tankage is equipped with driving motor in the base interior, and the lower end in the pedestal is uniformly provided with several idler wheels, the idler wheel
On be respectively equipped with locking member, the wheel shaft of the idler wheel passes through the output axis connection of transmitting device and driving motor, described first
Stringer, the second stringer, third stringer and the 4th stringer upper end be respectively equipped with lifting lug.
For the ease of accurately controlling the size of pressing force between supporting leg and hull outer wall, guarantee the stability of hanging ladder, it is excellent
The technical solution of choosing is in addition, the supporting leg is cylinder, and the sucker is set to the pistons end of the cylinder, in the piston
End is additionally provided with pressure sensor, and the cylinder and pressure sensor are connect with controller.
Staff slides on job platform in order to prevent, while being also prevented from upper layer job platform to lower layer's operation
Platform falls sundries, and further preferred technical solution is in addition, the grid of the job platform and the upper surface of manhole cover are set as
One of salient point, anti-skid chequer or frosted structure are additionally provided with non-slip mat in the upper surface of the job platform, and the non-slip mat is remote
One end from manhole is fixedly connected with rectangular frame.
For the smooth implementation and industrialization promotion and application of the tooling, it is proposed that a kind of above-mentioned hanging ladder tooling peculiar to vessel makes
With method, include the following steps:
S1: the placement of tooling starts driving motor by controller, hanging ladder tooling is moved to operation area designated position,
And idler wheel is locked;
S2: the positioning of tooling is adjusted the bolt between loose strap and the first stringer or the 4th stringer, is made on strap
Open slot blocks ship side top edge, and the clamping screw on controllable register is fixedly connected with strap with ship side, adjusts fixing clamp
Bolt between plate and the first stringer or the 4th stringer is fixedly connected with strap with the first stringer or the 4th stringer;
S3: the reinforcing of tooling sets the pressure value between sucker and hull outer wall by controller, starts on pedestal
Cylinder makes sucker fit with hull outer wall, and when the pressure between sucker and hull outer wall reaches setup pressure value, cylinder stops
Only work.
The application method of the hanging ladder tooling is simple, is convenient for industrializing implementation and popularization and application.
The advantages and beneficial effects of the present invention are:
1, the machine frame structure is simple, and three sides that four stringers constitute frame structure are equipped with crosspiece, one side of crosspiece
Pedal of the face as climbing, on the other hand plays support and booster action to hanging ladder, is not provided with a side direction of crosspiece
Operation area, convenient for the constructing operation of staff;The job platform of the hanging ladder is equipped with manhole and manhole cover, and manhole cover closing is
Staff's operation table top, it is staff only that manhole cover, which is opened, makes staff's hanging ladder above and below lower portion, is guaranteed
The safety when hanging ladder up and down of staff;The hanging ladder upper end is equipped with strap, lower end is equipped with supporting leg, and strap
End be equipped with open slot for being clamped ship side edge, the end of supporting leg is equipped with sucker, and the two ensure that hanging ladder peculiar to vessel makes
Fastness and stability.
2, one end that the strap is fixedly connected with the first stringer or the 4th stringer is equipped with the L shape guide groove to stand upside down,
It is equipped with the first through hole through the first stringer ontology in first stringer upper end, is equipped in the 4th stringer upper end through the
The axis of second through-hole of four stringer ontologies, the first through hole and the second through-hole is located on the same line, the fixing clamp
The L shape guide groove of the handstand of plate connects by the way that bolt and the first through hole on the first stringer or the second through-hole on the 4th stringer are fixed
It connects.The L shape guide groove of handstand can be such that strap is adjusted in vertical and horizontal, convenient for consolidating between strap and ship side
Fixed connection.
3, the spacing range between first stringer and the 4th stringer, the second stringer and third stringer is 1~1.5m, described
Spacing range between first stringer and the second stringer, third stringer and the 4th stringer is 60~80cm, the adjacent job platform
Spacing range be 1.8~2m, the spacing ranges of the adjacent rungs is 50~80cm.In order to make tooling use minimum former material
There is optimal working space under conditions of material investment, to guarantee working efficiency of the staff using the tooling when.
4, the manhole cover is alternately disposed at the left and right side of adjacent job platform.On the one hand in order to guarantee the tooling
On the other hand secure passes through inside the hanging ladder convenient for staff.
5, protective net is additionally provided at the edge of the rectangular frame upper end, the outside of the protective net is respectively with described first
Stringer, the second stringer, third stringer and the 4th stringer are welded to connect, and the height of the protective net is 50~80cm.On the one hand it is
Guarantee personal safety when staff's operation, on the other hand prevents tool from falling ground staff is damaged.
6, the supporting leg is cylinder, and the sucker is set to the pistons end of the cylinder, the pistons end also
Equipped with pressure sensor, the cylinder and pressure sensor are connect with controller.For the ease of accurately controlling supporting leg and ship
The size of pressing force, guarantees the stability of hanging ladder between external wall.
7, the application method of the hanging ladder tooling is simple, is convenient for industrializing implementation and popularization and application.
Detailed description of the invention
Fig. 1 is the side view of present invention hanging ladder tooling peculiar to vessel;
Fig. 2 is the top view of present invention hanging ladder tooling peculiar to vessel;
Fig. 3 is the structural schematic diagram of present invention hanging ladder tooling job platform peculiar to vessel.
In figure: 1, the first stringer;2, the second stringer;3, third stringer;4, the 4th stringer;5, job platform;6, rectangle frame
Frame;7, grid;8, manhole;9, manhole cover;10, strap;11, supporting leg;12, open slot;13, baffle;14, locking screw
Bolt;15, sucker;16, the L shape guide groove to stand upside down;17, bolt;18, protective net;19, pedestal;20, controller;21, driving electricity
Machine;22, idler wheel;23, locking member;24, lifting lug;25, pressure sensor.
Specific embodiment
With reference to the accompanying drawings and examples, further description of the specific embodiments of the present invention.Following embodiment is only
For clearly illustrating technical solution of the present invention, and not intended to limit the protection scope of the present invention.
As shown in Figures 1 to 3, the present invention is a kind of hanging ladder tooling peculiar to vessel, including the first stringer 1, the second stringer 2, third are indulged
Beam 3, the 4th stringer 4, several job platforms 5 and several crosspieces, first stringer 1, the second stringer 2, third stringer 3 and the 4th
Stringer 4 is parallel to each other and is successively located on four vertex of rectangle, and several job platforms 5 are arranged at intervals at described
The inside of one stringer 1, the second stringer 2, third stringer 3 and the 4th stringer 4, the job platform 5 include rectangular frame 6 and setting
In the grid 7 in rectangular frame 6, manhole 8 and manhole cover 9,9 one end of manhole cover and grid 7 or square are additionally provided on the grid 7
The connection of shape frame articulation, uniform intervals are set to the first stringer 1 and second between adjacent job platform 5 to several crosspieces respectively
On stringer 2, the second stringer 2 and third stringer 3, third stringer 3 and the 4th stringer 4, in first stringer 1, the 4th stringer 4
Top and bottom, which are respectively equipped with, extends to consolidating outside first stringer 1, the second stringer 2, third stringer 3 and the 4th stringer 4
Clamp plate 10 and supporting leg 11, the strap 10 and support leg be parallel to each other and respectively with the second stringer 2 and third stringer 3
The plane at place is vertical, and the plate face of the strap 10 is longitudinally disposed, one end of strap 10 and the first stringer 1 or the 4th
The lower edge that stringer 4 is fixedly connected with the other end is equipped with open slot 12, in the open slot 12 close to 10 end of strap
One side edge is equipped with baffle 13, and threaded hole and clamping screw 14, one end of the supporting leg 11 are additionally provided on the baffle 13
The other end is fixedly connected with the first stringer 1 or the 4th stringer 4 equipped with sucker 15.The strap 10 and the first stringer 1 or the
One end that four stringers 4 are fixedly connected is equipped with the L shape guide groove 16 to stand upside down, is equipped in 1 upper end of the first stringer vertical through first
The first through hole of 1 ontology of beam, 4 upper end of the 4th stringer be equipped with through 4 ontology of the 4th stringer the second through-hole, described first
The axis of through-hole and the second through-hole is located on the same line, and the L shape guide groove 16 of the handstand of the strap 10 passes through spiral shell
Bolt 17 is fixedly connected with the first through hole on the first stringer 1 or the second through-hole on the 4th stringer 4.On the rectangular frame 6
The edge at end is additionally provided with protective net 18, and the outside of the protective net 18 is vertical with first stringer 1, the second stringer 2, third respectively
Beam 3 and the 4th stringer 4 are welded to connect, and the height of the protective net 18 is 50~80cm.It further include pedestal 19 and controller 20,
19 upper end of pedestal is equipped with installation compatible with first stringer 1, the second stringer 2, third stringer 3 and the 4th stringer 4
Slot is equipped with driving motor 21 inside the pedestal 19, and the lower end in the pedestal 19 is uniformly provided with several idler wheels 22, institute
It states and is respectively equipped with locking member 23 on idler wheel 22, the wheel shaft of the idler wheel 22 is connected by the output shaft of transmitting device and driving motor 21
It connects, is respectively equipped with lifting lug 24 in the upper end of first stringer 1, the second stringer 2, third stringer 3 and the 4th stringer 4.The branch
Support leg 11 is cylinder, and the sucker 15 is set to the pistons end of the cylinder, is additionally provided with pressure sensing in the pistons end
Device 25, the cylinder and pressure sensor 25 are connect with controller 20.
In order to make tooling that there is optimal working space under conditions of putting into using minimum raw material, to guarantee work
Personnel use the working efficiency when tooling, and further preferred technical solution is in addition, first stringer and the 4th stringer, the
Spacing range between two stringers and third stringer is 1~1.5m, and first stringer and the second stringer, third stringer and the 4th are vertical
Spacing range between beam is 60~80cm, and the spacing range of the adjacent job platform is 1.8~2m, between the adjacent rungs
It is 50~80cm away from range.
On the one hand on the other hand logical inside the hanging ladder convenient for staff in order to guarantee the secure of the tooling
It crosses, further preferred technical solution is in addition, the manhole cover is alternately disposed at the left and right side of adjacent job platform.
Staff slides on job platform in order to prevent, while being also prevented from upper layer job platform to lower layer's operation
Platform falls sundries, and further preferred technical solution is in addition, the grid of the job platform and the upper surface of manhole cover are set as
One of salient point, anti-skid chequer or frosted structure are additionally provided with non-slip mat in the upper surface of the job platform, and the non-slip mat is remote
One end from manhole is fixedly connected with rectangular frame.
For the smooth implementation and industrialization promotion and application of the tooling, it is proposed that a kind of above-mentioned hanging ladder tooling peculiar to vessel makes
With method, include the following steps:
S1: the placement of tooling starts driving motor 21 by controller 20, hanging ladder tooling is moved to operation area specific bit
It sets, and idler wheel 22 is locked;
S2: the positioning of tooling adjusts the bolt 17 between loose strap 10 and the first stringer 1 or the 4th stringer 4, makes fixing clamp
Open slot 12 on plate 10 blocks ship side top edge, and the clamping screw 14 on controllable register 13 keeps strap 10 and ship side solid
Fixed connection, adjusts the bolt 17 between strap 10 and the first stringer 1 or the 4th stringer 4, makes strap 10 and the first stringer 1
Or the 4th stringer 4 be fixedly connected;
S3: the reinforcing of tooling sets the pressure value between sucker 15 and hull outer wall by controller 20, starts pedestal
Cylinder on 19 makes sucker 15 fit with hull outer wall, when the pressure between sucker 15 and hull outer wall reaches setting pressure
When value, cylinder stops working.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, without departing from the technical principles of the invention, several improvements and modifications can also be made, these improvements and modifications
Also it should be regarded as protection scope of the present invention.
Claims (9)
1. a kind of hanging ladder tooling peculiar to vessel, which is characterized in that if including the first stringer, the second stringer, third stringer, the 4th stringer,
Dry job platform and several crosspieces, first stringer, the second stringer, third stringer and the 4th stringer are parallel to each other and successively divide
Wei Yu not be on four vertex of rectangle, it is vertical that several job platforms are arranged at intervals at first stringer, the second stringer, third
The inside of beam and the 4th stringer, the job platform includes rectangular frame and the grid that is set in rectangular frame, in the lattice
Manhole and manhole cover are additionally provided on grid, manhole cover one end and grid or rectangular frame are articulated and connected, and several crosspiece difference are equal
Even the first stringer being arranged at intervals between adjacent job platform and the second stringer, the second stringer and third stringer, third stringer and
On 4th stringer, it is respectively equipped in the top and bottom of first stringer, the 4th stringer and extends to first stringer, second
The strap and supporting leg of stringer, third stringer and the 4th rail outer, the strap and support leg be parallel to each other and
Vertical with the plane where the second stringer and third stringer respectively, the plate face of the strap is longitudinally disposed, strap
The lower edge that one end is fixedly connected with the other end with the first stringer or the 4th stringer is equipped with open slot, in the open slot close to solid
The one side edge of clamp plate end is equipped with baffle, and threaded hole and clamping screw are additionally provided on the baffle, the supporting leg
One end is fixedly connected with the other end with the first stringer or the 4th stringer equipped with sucker.
2. hanging ladder tooling peculiar to vessel as described in claim 1, which is characterized in that the strap and the first stringer the 4th are indulged
One end that beam is fixedly connected is equipped with the L shape guide groove to stand upside down, is equipped in first stringer upper end through the first stringer ontology
First through hole is equipped with the second through-hole through the 4th stringer ontology, the first through hole and second in the 4th stringer upper end
The axis of through-hole is located on the same line, and the L shape guide groove of the handstand of the strap passes through on bolt and the first stringer
First through hole or the 4th stringer on the second through-hole be fixedly connected.
3. hanging ladder tooling peculiar to vessel as claimed in claim 2, which is characterized in that first stringer and the 4th stringer, second vertical
Spacing range between beam and third stringer is 1~1.5m, between first stringer and the second stringer, third stringer and the 4th stringer
Spacing range be 60~80cm, the spacing range of the adjacent job platform is 1.8~2m, the spacing model of the adjacent rungs
It encloses for 50~80cm.
4. hanging ladder tooling peculiar to vessel as claimed in claim 3, which is characterized in that the manhole cover is alternately disposed at adjacent operation horizontal
The left and right side of platform.
5. hanging ladder tooling peculiar to vessel as claimed in claim 4, which is characterized in that be additionally provided at the edge of the rectangular frame upper end
Protective net, the outside of the protective net is welded with first stringer, the second stringer, third stringer and the 4th stringer respectively to be connected
It connects, the height of the protective net is 50~80cm.
6. hanging ladder tooling peculiar to vessel as claimed in claim 5, which is characterized in that further include pedestal and controller, in the pedestal
Upper end is equipped with mounting groove compatible with first stringer, the second stringer, third stringer and the 4th stringer, in the pedestal
Portion is equipped with driving motor, and the lower end in the pedestal is uniformly provided with several idler wheels, is respectively equipped with locking member on the idler wheel,
The wheel shaft of the idler wheel passes through the output axis connection of transmitting device and driving motor, in first stringer, the second stringer, third
The upper end of stringer and the 4th stringer is respectively equipped with lifting lug.
7. hanging ladder tooling peculiar to vessel as claimed in claim 6, which is characterized in that the supporting leg is cylinder, the sucker setting
In the pistons end of the cylinder, be additionally provided with pressure sensor in the pistons end, the cylinder and pressure sensor with
Controller connection.
8. hanging ladder tooling peculiar to vessel as claimed in claim 7, which is characterized in that the grid of the job platform and manhole cover it is upper
End face is set as one of salient point, anti-skid chequer or frosted structure, is additionally provided with non-slip mat in the upper surface of the job platform, described
Non-slip mat is fixedly connected far from one end of manhole with rectangular frame.
9. a kind of application method of hanging ladder tooling peculiar to vessel, which is characterized in that hanging ladder tooling peculiar to vessel as claimed in claim 8 makes
With method, include the following steps:
S1: the placement of tooling starts driving motor by controller, hanging ladder tooling is moved to operation area designated position, and will
Idler wheel is locked;
S2: the positioning of tooling adjusts the bolt between loose strap and the first stringer or the 4th stringer, makes the opening on strap
Slot blocks ship side top edge, and the clamping screw on controllable register is fixedly connected with strap with ship side, adjust strap with
Bolt between first stringer or the 4th stringer is fixedly connected with strap with the first stringer or the 4th stringer;
S3: the reinforcing of tooling sets the pressure value between sucker and hull outer wall by controller, starts the gas on pedestal
Cylinder makes sucker fit with hull outer wall, and when the pressure between sucker and hull outer wall reaches setup pressure value, cylinder stops
Work.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910248986.7A CN109986524A (en) | 2019-03-29 | 2019-03-29 | A kind of hanging ladder tooling peculiar to vessel and its application method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910248986.7A CN109986524A (en) | 2019-03-29 | 2019-03-29 | A kind of hanging ladder tooling peculiar to vessel and its application method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109986524A true CN109986524A (en) | 2019-07-09 |
Family
ID=67131731
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910248986.7A Pending CN109986524A (en) | 2019-03-29 | 2019-03-29 | A kind of hanging ladder tooling peculiar to vessel and its application method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109986524A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112478063A (en) * | 2020-11-05 | 2021-03-12 | 中船澄西船舶修造有限公司 | 40000 ton self-unloading ship shaft generator hoisting tool |
CN114876351A (en) * | 2022-05-30 | 2022-08-09 | 中船广西船舶及海洋工程有限公司 | Hanging ladder with telescopic function for shipbuilding operation |
CN115092377A (en) * | 2022-06-30 | 2022-09-23 | 上海外高桥造船有限公司 | Auxiliary hook dismounting device and method for rudder horn after hoisting |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2158045A1 (en) * | 1971-11-23 | 1973-05-24 | Fiala Kg Martin | MOBILE SHIP LOADING FRAME |
DE9016576U1 (en) * | 1990-01-10 | 1991-02-21 | Adronit-Werk Hermann Aderhold Gmbh & Co, 5802 Wetter, De | |
CN2337241Y (en) * | 1998-07-23 | 1999-09-08 | 金美华 | Fixing support |
CN101439757A (en) * | 2008-10-24 | 2009-05-27 | 武汉理工大学 | Large-sized aerial work platform for shipbuilding |
CN102673753A (en) * | 2012-05-10 | 2012-09-19 | 沪东中华造船(集团)有限公司 | Suspension-type movable scaffold for ship |
US8616335B1 (en) * | 2011-06-08 | 2013-12-31 | Tim Mosier | Ladder securing apparatus |
CN105350759A (en) * | 2015-12-07 | 2016-02-24 | 江苏大津重工有限公司 | Suspended scaffold |
CN205574235U (en) * | 2016-04-28 | 2016-09-14 | 中船黄埔文冲船舶有限公司 | Bulk freighter wing tank section construction stores pylon |
CN107191131A (en) * | 2017-07-28 | 2017-09-22 | 国网河南省电力公司濮阳供电公司 | A kind of anti-skidding outdoor substation insulating ladder |
CN210161128U (en) * | 2019-03-29 | 2020-03-20 | 中船澄西船舶修造有限公司 | Marine ladder hanging tool |
-
2019
- 2019-03-29 CN CN201910248986.7A patent/CN109986524A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2158045A1 (en) * | 1971-11-23 | 1973-05-24 | Fiala Kg Martin | MOBILE SHIP LOADING FRAME |
DE9016576U1 (en) * | 1990-01-10 | 1991-02-21 | Adronit-Werk Hermann Aderhold Gmbh & Co, 5802 Wetter, De | |
CN2337241Y (en) * | 1998-07-23 | 1999-09-08 | 金美华 | Fixing support |
CN101439757A (en) * | 2008-10-24 | 2009-05-27 | 武汉理工大学 | Large-sized aerial work platform for shipbuilding |
US8616335B1 (en) * | 2011-06-08 | 2013-12-31 | Tim Mosier | Ladder securing apparatus |
CN102673753A (en) * | 2012-05-10 | 2012-09-19 | 沪东中华造船(集团)有限公司 | Suspension-type movable scaffold for ship |
CN105350759A (en) * | 2015-12-07 | 2016-02-24 | 江苏大津重工有限公司 | Suspended scaffold |
CN205574235U (en) * | 2016-04-28 | 2016-09-14 | 中船黄埔文冲船舶有限公司 | Bulk freighter wing tank section construction stores pylon |
CN107191131A (en) * | 2017-07-28 | 2017-09-22 | 国网河南省电力公司濮阳供电公司 | A kind of anti-skidding outdoor substation insulating ladder |
CN210161128U (en) * | 2019-03-29 | 2020-03-20 | 中船澄西船舶修造有限公司 | Marine ladder hanging tool |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112478063A (en) * | 2020-11-05 | 2021-03-12 | 中船澄西船舶修造有限公司 | 40000 ton self-unloading ship shaft generator hoisting tool |
CN112478063B (en) * | 2020-11-05 | 2022-03-08 | 中船澄西船舶修造有限公司 | 40000 ton self-unloading ship shaft generator hoisting tool |
CN114876351A (en) * | 2022-05-30 | 2022-08-09 | 中船广西船舶及海洋工程有限公司 | Hanging ladder with telescopic function for shipbuilding operation |
CN115092377A (en) * | 2022-06-30 | 2022-09-23 | 上海外高桥造船有限公司 | Auxiliary hook dismounting device and method for rudder horn after hoisting |
CN115092377B (en) * | 2022-06-30 | 2024-02-02 | 上海外高桥造船有限公司 | Auxiliary unhooking device and unhooking method for rudder horn after hoisting |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109986524A (en) | A kind of hanging ladder tooling peculiar to vessel and its application method | |
CN206970008U (en) | Hang code | |
CN106400691B (en) | Anti-collision wall mould bases integrated construction technique | |
CN104499619B (en) | A kind of plug-in wall bottom adjusting parts of PC | |
CN206467994U (en) | A kind of novel hanging basket support | |
CN205840761U (en) | A kind of packaged type construction raises ladder | |
CN108487201A (en) | A kind of tail water cooler apparatus for examination and repair avoiding underwater operation | |
CN207048345U (en) | Construction discharge platform device | |
CN209210319U (en) | It drives a vehicle dedicated maintenance hanging basket | |
CN206285368U (en) | A kind of substation equipment maintenance and repair safety belt suspension device | |
CN208686053U (en) | A kind of elevator well sizing climbing platforms device | |
CN202280256U (en) | Lifting tool for unit curtain wall | |
CN208715425U (en) | Recyclable device is launched by underwater unmanned robot waterborne | |
CN109594697A (en) | Super High built-in type unit glass curtain wall construction method and its structure | |
CN110130644A (en) | A kind of construction method of high-altitude steel structure bottom metal curtain wall | |
CN203494080U (en) | Safety rope suspension device for transformer | |
CN110056176A (en) | A kind of elevator mobile platform and application method | |
CN206220460U (en) | For the operating platform of tower | |
CN209637679U (en) | The segmented assembly formula ladder to pass through up and down for high altitude operation personnel | |
CN208686048U (en) | A kind of civil engineering work construction bracket | |
CN209210243U (en) | The hanging apparatus of curtain wall lighting roof | |
CN209584862U (en) | Steel Bridge construction multifunctional operating platform | |
CN207144533U (en) | The horizontal protective of building hoist basis conversion | |
CN208472681U (en) | Surface low road movable overhaul platform in a kind of power station | |
CN208358728U (en) | Nuclear steam turbine low pressure (LP) cylinder inspection platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |