CN109973142A - A kind of pair of underworkings carries out the method and filling system of sold stowing - Google Patents
A kind of pair of underworkings carries out the method and filling system of sold stowing Download PDFInfo
- Publication number
- CN109973142A CN109973142A CN201910252294.XA CN201910252294A CN109973142A CN 109973142 A CN109973142 A CN 109973142A CN 201910252294 A CN201910252294 A CN 201910252294A CN 109973142 A CN109973142 A CN 109973142A
- Authority
- CN
- China
- Prior art keywords
- gangue
- underground
- filling
- slurry
- stowboard
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 238000000034 method Methods 0.000 title claims abstract description 19
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 19
- 230000005484 gravity Effects 0.000 claims abstract description 18
- 239000000463 material Substances 0.000 claims abstract description 10
- 239000002002 slurry Substances 0.000 claims description 30
- 239000000203 mixture Substances 0.000 claims description 12
- 239000011268 mixed slurry Substances 0.000 claims description 10
- 238000000926 separation method Methods 0.000 claims description 10
- 238000003860 storage Methods 0.000 claims description 9
- 239000011440 grout Substances 0.000 claims description 6
- 238000003756 stirring Methods 0.000 claims description 6
- 239000004568 cement Substances 0.000 claims description 4
- 238000007789 sealing Methods 0.000 claims description 4
- 230000003068 static effect Effects 0.000 claims description 4
- 230000003014 reinforcing effect Effects 0.000 claims description 3
- 239000007921 spray Substances 0.000 claims description 3
- 230000015572 biosynthetic process Effects 0.000 claims description 2
- 239000000945 filler Substances 0.000 claims description 2
- 230000003139 buffering effect Effects 0.000 claims 1
- 239000010881 fly ash Substances 0.000 description 6
- 239000003245 coal Substances 0.000 description 5
- 238000005429 filling process Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 239000011230 binding agent Substances 0.000 description 1
- 239000013065 commercial product Substances 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 230000003028 elevating effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 230000004927 fusion Effects 0.000 description 1
- -1 gangue Substances 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000011343 solid material Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
- E21F15/005—Methods or devices for placing filling-up materials in underground workings characterised by the kind or composition of the backfilling material
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
- E21F15/06—Filling-up mechanically
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The invention discloses methods and filling system that a kind of pair of underworkings carries out sold stowing, it is mainly on the basis of water rushes spoil wriggling gravity flow stowboard lower part, the top that spoil fills up closely knit tunnel is blown using impact disturbance, emphasis carries out cementing material filling to Delta Region on stowboard, to realize the filling density and crushing resistance in whole tunnel, working face pack effectiveness is improved, enhances gangue sold stowing intensity, particularly suitable for consolidated fill Work places.
Description
Technical field
The invention belongs to coal mine filling production technique fields, and it is cementing closely knit to be particularly suitable for a kind of underworkings gangue
The method of filling.
Background technique
China is in coal industry great development period, and coal mine filling production technique makes rapid progress, according to filling material used
Material is different with mode of movement, and the filling process of China's application mainly has dry stowing, slush, consolidated fill, filling-up pneumatically
Deng especially consolidated fill is widely applied in underground mine, nonferrous metal mine.
The filling method is to mix cementitious material with solid materials such as gangue, flyash, improves consolidating for obturation
Change intensity, when filling, rushes object gravity flow filling process using water and mixture slurry is flow to goaf, the glue in controllable time
Knot, cohesion, reach filling design strength, to realize bashing deformation controlling for rock surrounding gateways, avoid surface subsidence.Because filling is starched
Body rushes the gravity flow of object fluid by water and is fills up to the realization sold stowing of excavating lane lower part, but goaf upper space exists
Gap and uncompacted problem especially cannot achieve sold stowing in the upper Delta Region in nearly horizontal filling face, cause to fill
Triangle cannot sufficiently connect top and the low problem of pack effectiveness on lane.
Summary of the invention
In order to solve the problems, such as goaf upper space, there are gaps and uncompacted, especially solve in nearly horizontal filling
The upper Delta Region in face cannot achieve sold stowing, cause triangle on filling lane that cannot sufficiently connect top and the low difficulty of pack effectiveness
Topic, the present invention provide the method that a kind of pair of underworkings carries out sold stowing.
In order to adapt to the above method, present invention simultaneously provides a set of filling systems.
In order to achieve the above objectives, the technical solution adopted by the present invention is that:
The method that a kind of pair of underworkings carries out sold stowing, it is characterised in that: including following measures:
First: the gangue behind ground and underground coal-gangue separation being delivered to filling after two-stage crushing, sorting in advance
The gangue surge bunker of working face;
Second: the slurry can on ground is temporarily stored in after filler is uniformly mixed into slurry by ground slurry preparing station in proportion;
Third: filling goaf tunnel, specific placement method are as follows:
1. the first block pulp wall is arranged in underground goaf stowboard lower port first, and sealing and reinforcing is handled;
2. the mixed slurry of slurry can is transported to filling operation face using static pressure, it is delivered to the mixing in filling operation face
Slurry proportionally discharges with the gangue for being stored in gangue surge bunker, is being self-possessed under the double action with water flow, along coal seam
Inclination angle is mixed in flowing, is ultimately formed using spoil as aggregate, cement and is fills up to goaf for the mixture gravity flow of cementing material
Stowboard stops filling when can not form wriggling gravity flow close to level angle until being fills up to tunnel top half, at this moment exists
Gravity flow fill area is formed in goaf filling tunnel;
3. the second block pulp wall is arranged in stowboard upper port in underground goaf;
4. by the gangue of gangue surge bunker using wind model to the second block pulp wall upper port, in the second block pulp wall
Upper port gangue merges formation filling mixture with the mixed slurry spray from slurry can, is fills up to stowboard
More than the upper triangle portion of level angle, to be carried out to the upper Delta Region that goaf filling tunnel is more than level angle close
Real filling.
In order to implement the above method, the present invention provides a kind of filling system, specifically includes: on well and the two large divisions of underground,
Wherein:
Well-surface part includes multiple batch cans, pond, blender, slurry can, spoil heap storage on well;
Underground part include gangue surge bunker, coal-gangue separation spoil surge bunker, underground blender, wind model system,
Water pump, the first block pulp wall for being located at stowboard lower port and the second block pulp wall for being located at stowboard upper port;The well
Apparatus for lower wind transportation system includes blastower and wind conducting pipe;
It is moved towards according to slurry and spoil, the above-mentioned connection relationship respectively formed is:
Batch can discharge port passes through pipeline with the water outlet in pond respectively and communicates with stirring machine inlet on well, stirs on well
Machine discharge port is communicated with slurry can, and slurry can discharge port divides two-way by grout pipe line, leads to second gear slurry wall upper port all the way
It is connected with wind model pipeline end, wind model pipeline enters filling operation face by the upper end of the second block pulp wall 15;It is another
Underground stirring machine inlet is led on road, and underground blender discharge port is by pipeline and pump tube side by side together from stowboard
Upper port is passed through goaf;
Spoil heap storage passes through pipeline and underground gangue surge bunker phase with underground coal-gangue separation spoil surge bunker respectively on well
It is logical;Underground gangue surge bunker discharge port divides two-way, communicates all the way with underground filling-up pneumatically machine inlet, blastower goes out
Material mouth leads to the second block pulp wall upper port by wind conducting pipe, and another way is communicated with underground stirring machine inlet.
Each composition that filling system of the present invention uses is commercial product, and what the present invention protected is not the tool of each composition
Body structure, protection be each composition arrangement relation and mutual positional relationship.In addition, blastower of the present invention
Connection relationship and working method with wind conducting pipe are the prior art, and this will not be detailed here.
The invention has the advantages that the present invention utilizes impact on the basis of water rushes spoil wriggling gravity flow stowboard lower part
Disturbance blows the top that spoil fills up closely knit tunnel, and emphasis carries out cementing material filling to Delta Region on stowboard, thus
The filling density and crushing resistance for realizing whole tunnel, improve working face pack effectiveness, enhance gangue sold stowing intensity,
Particularly suitable for consolidated fill Work places.
Detailed description of the invention
Fig. 1 is filling system embodiment arrangement schematic diagram of the present invention.
In figure: 1- cementing tank, 2- flyash silo, the pond 3-, blender on 4- well, 5- slurry can, 6- grout pipe line, 7-
Spoil heap storage, 8- coal-gangue separation spoil surge bunker, 9- gangue surge bunker, the underground 10- blender, 11- water pump, 12- gravity flow
Fill area, 13- blastower, 14- wind model pipeline, 15- the second block pulp wall, the upper triangle obturation of 16-, 17- first
Block pulp wall.
Specific embodiment
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will to embodiment or
Attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only
Some embodiments of the present invention, for those of ordinary skill in the art, without creative efforts, also
Other drawings may be obtained according to these drawings without any creative labor.
Such as Fig. 1, filling system of the present invention includes underground part and underground two large divisions, in which:
Well-surface part includes cementing tank 1, flyash silo 2, pond 3, blender 4, slurry can 5 and spoil heap storage 7 on well;
Underground part includes grout pipe line 6, and the coal-gangue separation spoil surge bunker 8 of coal working face is arranged in, and setting is being filled
Gangue surge bunker 9, underground blender 10, blastower 13, wind model pipeline 14 and the water pump 13 of working face are filled out,
The the first block pulp wall 17 for being located at stowboard lower port and the second block pulp wall 15 for being located at stowboard upper port.
Move towards to describe the connection relationship of each composition below according to slurry and spoil.
The water outlet in the discharge port of cementing tank 1 and flyash silo 2 and pond 3 pass through on pipeline and well respectively blender 4 into
Material mouth communicates, and 4 discharge port of blender is communicated with slurry can 5 on well, and 5 discharge port of slurry can divides two-way by grout pipe line 6, and one
Road leads to 15 upper port of the second block pulp wall and is connected with 14 end of wind model pipeline, and wind model pipeline 14 passes through the second block pulp
The upper end of wall 15 enters filling operation face, and another way leads to underground blender 10, and underground blender 10 leads to stowboard upper end
Mouthful;
Spoil heap storage 7 is given with coal-gangue separation spoil surge bunker 8 through pipeline and 9 phase of underground gangue surge bunker on well
It is logical;Gangue surge bunker 9 discharge port in underground divides two-way, communicates all the way with 13 feed inlet of underground blastower, blastower
13 discharge ports lead to 15 upper port of the second block pulp wall, another way and 10 feed inlet of underground blender by wind model pipeline 14
It communicates, underground blender 10 leads to stowboard upper port.
The method that sold stowing is carried out to underworkings using above-mentioned filling system are as follows:
First: the spoil of ground spoil heap storage 7 being vertically put into underground transportation lane by defeated cash hole in advance, together with underground
After the spoil of coal-gangue separation spoil surge bunker 8 is crushed respectively, sorted machine sub-elects the spoil that partial size is 20~25mm and passes through band
Formula conveyer, elevating conveyor reach the gangue surge bunker 9 in filling operation face;
Second: carrying out rational proportion by the water of cementing tank 1, flyash silo 2 and pond 3, (slurrying proportion is cement
15%, flyash 25%, water 50%), it is sufficiently stirred after entering back into blender 4, filling mining is made and is sent with mixed slurry to storage
Tank 5 is starched, mixed slurry is delivered to underground filling work face by grout pipe line 6 using static pressure;
Third: filling goaf filling tunnel, specific placement method are as follows:
3.1st: the first block pulp wall 17 being set in underground goaf tunnel lower port first, and sealing and reinforcing is handled;
3.2nd: the mixed slurry of slurry can 5 being transported to filling operation face using static pressure, is delivered to filling operation face
Mixed slurry and the gangue proportionally 1:2 discharging for being stored in gangue surge bunker 9, in 11 water pipe of Gravitative Loads and water pump
Under road is washed away, by seam inclination, the mixing of the side Bian Liudong, it is cementing for ultimately forming by aggregate, cement of the spoil of certain partial size
The mixture gravity flow of material is fills up to goaf filling tunnel, gravity flow fill area 12 is formed, until being fills up to tunnel upper half
Part stops filling when can not form wriggling gravity flow close to level angle;
3.3rd: while water rushes logistics gravity flow bashing stowboard lower part, in goaf filling tunnel
The first block pulp wall 15, sealing, consolidation process is arranged in upper port;
3.4th: the gangue of the gangue surge bunker 9 in filling operation face is utilized into blastower 13, it is defeated by wind-force
Send in pipeline 14 and be delivered to filling operation face, the first block pulp wall 15 upper port by the spoil of wind model pipeline 14, with it is defeated
Mixed slurry in slurry pipeline 6 carries out spray fusion, and be allowed to form certain partial size is as aggregate, with mixture slurry using spoil
The mixture of binder is fills up to the upper triangle portion that stowboard is more than level angle, forms closely knit upper triangle filling
Body 16.
Present invention design combines gravity flow and wind-power to fill advantage, can be right in the operation of gravity flow filling operation face
The mined out region of triangle carries out sold stowing on stowboard top, improves pack effectiveness, solving Delta Region can not be close
The problem of real filling, realizes that obturation substantially 100% connects top, is particularly suitable for gravity flow Lian Cailian and fills Work places.
More than, only a specific embodiment of the invention, but scope of protection of the present invention is not limited thereto, it is any not
The change or replacement expected by creative work, should be covered by the protection scope of the present invention.Therefore, of the invention
Protection scope should be determined by the scope of protection defined in the claims.
Claims (2)
1. the method that a kind of pair of underworkings carries out sold stowing, which is characterized in that including following measures:
First: the gangue behind ground and underground coal-gangue separation being delivered to filling operation after two-stage crushing, sorting in advance
The gangue surge bunker in face;
Second: the slurry can on ground is temporarily stored in after filler is uniformly mixed into slurry by ground slurry preparing station in proportion;
Third: filling goaf tunnel, specific placement method are as follows:
3.1: the first block pulp wall being set in underground goaf stowboard lower port first, and sealing and reinforcing is handled;
3.2: the mixed slurry of slurry being transported to filling operation face using static pressure, is delivered to the mixed slurry in filling operation face
It proportionally discharges, is being self-possessed under the double action with water flow, along seam inclination with the gangue for being stored in gangue surge bunker
It is mixed in flowing, ultimately forms using spoil as aggregate, cement and be fills up to goaf filling for the mixture gravity flow of cementing material
Tunnel stops filling when can not form wriggling gravity flow close to level angle until being fills up to tunnel top half, at this moment mined out
Gravity flow fill area is formed in area's stowboard;
3.3: in underground goaf, the second block pulp wall is arranged in stowboard upper port;
3.4: by the gangue of gangue surge bunker using wind model to the second block pulp wall upper port, in the second block pulp wall upper end
Mouth gangue merges formation filling mixture with the mixed slurry spray from slurry can, and being fills up to stowboard is more than water
The upper triangle portion of straight angle degree, to carry out sold stowing to the upper Delta Region that goaf filling tunnel is more than level angle.
2. a kind of filling system for implementing the method described in claim 1 for carrying out sold stowing to underworkings, feature exist
In specifically including on well and underground two large divisions, in which:
Well-surface part includes multiple batch cans, pond, blender, slurry can, spoil heap storage on well;
Underground part include gangue surge bunker, coal-gangue separation spoil surge bunker, underground blender, wind model system, water pump,
It is located at the first block pulp wall of stowboard lower port and is located at the second block pulp wall of stowboard upper port;The underground wind-force
Transportation system includes blastower and wind conducting pipe;
It is moved towards according to slurry and spoil, the above-mentioned connection relationship respectively formed is:
Batch can discharge port passes through pipeline with the water outlet in pond respectively and communicates with stirring machine inlet on well, and blender discharges on well
Mouth is communicated with slurry can, and slurry can discharge port divides two-way by grout pipe line, leads to second gear slurry wall upper port and wind-force all the way
Transfer pipeline end is connected, and wind model pipeline enters filling operation face by the upper end of the second block pulp wall 15;Another way is led to
Machine inlet is stirred in underground, and underground blender discharge port is logical from stowboard upper port together side by side by pipeline and pump tube
Enter goaf;
Spoil heap storage passes through pipeline with underground coal-gangue separation spoil surge bunker respectively and communicates with underground gangue surge bunker on well;Well
Lower gangue buffering bin discharge port external divides two-way, communicates all the way with underground filling-up pneumatically machine inlet, blastower discharge port is logical
It crosses wind conducting pipe and leads to the second block pulp wall upper port, another way is communicated with underground stirring machine inlet.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910252294.XA CN109973142A (en) | 2019-03-29 | 2019-03-29 | A kind of pair of underworkings carries out the method and filling system of sold stowing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910252294.XA CN109973142A (en) | 2019-03-29 | 2019-03-29 | A kind of pair of underworkings carries out the method and filling system of sold stowing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109973142A true CN109973142A (en) | 2019-07-05 |
Family
ID=67081832
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910252294.XA Withdrawn CN109973142A (en) | 2019-03-29 | 2019-03-29 | A kind of pair of underworkings carries out the method and filling system of sold stowing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109973142A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111807061A (en) * | 2020-09-09 | 2020-10-23 | 天津美腾科技股份有限公司 | Dual-power wind conveying system and underground gangue conveying line |
CN114370301A (en) * | 2022-01-12 | 2022-04-19 | 内蒙古鄂托克旗昊源煤焦化有限责任公司 | Energy-saving grouting mining system based on automatic detection of coal seam inclination |
CN116877187A (en) * | 2023-05-18 | 2023-10-13 | 赤峰荣邦矿业有限责任公司 | Automatic tailing filling device and filling method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101701527A (en) * | 2009-11-05 | 2010-05-05 | 冀中能源邯郸矿业集团有限公司 | Goaf open-type packing method |
CN102418555A (en) * | 2011-08-11 | 2012-04-18 | 安徽大昌矿业集团有限公司 | Method for filling mine goaf by utilizing high-concentration all tailing cement |
RU2471069C1 (en) * | 2011-04-20 | 2012-12-27 | Учреждение Российской академии наук Институт проблем комплексного освоения недр Российской академии наук (УРАН ИПКОН РАН) | Method for underground mining of sloping and inclined ore bodies in cryolite zone |
CN203146013U (en) * | 2013-03-15 | 2013-08-21 | 金川集团股份有限公司 | Material slurry filling multipoint lime feeding device |
CN106194252A (en) * | 2016-09-29 | 2016-12-07 | 路彬 | A kind of coal mining totipotency end pipeline conveying Paste-filling System and method |
CN108442930A (en) * | 2018-03-15 | 2018-08-24 | 中南大学 | A kind of Medium Thickness And Medium Slope Angle metal ore mining methods |
-
2019
- 2019-03-29 CN CN201910252294.XA patent/CN109973142A/en not_active Withdrawn
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101701527A (en) * | 2009-11-05 | 2010-05-05 | 冀中能源邯郸矿业集团有限公司 | Goaf open-type packing method |
RU2471069C1 (en) * | 2011-04-20 | 2012-12-27 | Учреждение Российской академии наук Институт проблем комплексного освоения недр Российской академии наук (УРАН ИПКОН РАН) | Method for underground mining of sloping and inclined ore bodies in cryolite zone |
CN102418555A (en) * | 2011-08-11 | 2012-04-18 | 安徽大昌矿业集团有限公司 | Method for filling mine goaf by utilizing high-concentration all tailing cement |
CN203146013U (en) * | 2013-03-15 | 2013-08-21 | 金川集团股份有限公司 | Material slurry filling multipoint lime feeding device |
CN106194252A (en) * | 2016-09-29 | 2016-12-07 | 路彬 | A kind of coal mining totipotency end pipeline conveying Paste-filling System and method |
CN108442930A (en) * | 2018-03-15 | 2018-08-24 | 中南大学 | A kind of Medium Thickness And Medium Slope Angle metal ore mining methods |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111807061A (en) * | 2020-09-09 | 2020-10-23 | 天津美腾科技股份有限公司 | Dual-power wind conveying system and underground gangue conveying line |
CN114370301A (en) * | 2022-01-12 | 2022-04-19 | 内蒙古鄂托克旗昊源煤焦化有限责任公司 | Energy-saving grouting mining system based on automatic detection of coal seam inclination |
CN116877187A (en) * | 2023-05-18 | 2023-10-13 | 赤峰荣邦矿业有限责任公司 | Automatic tailing filling device and filling method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107246279B (en) | Underground, which picks up sieve and mixes, fills the cementing construction filling system of integrated spoil and method | |
CN102865101B (en) | Filling method and system of coal mine goaf | |
CN112814732B (en) | Waste stone and tailing mixed slurry preparation and pumping filling device | |
CN203035256U (en) | Waste rock bashing device capable of preventing waste rock from being lifted to ground from well | |
CN109973142A (en) | A kind of pair of underworkings carries out the method and filling system of sold stowing | |
WO2018176892A1 (en) | Network integrated and coordinated control system and method for thin coal seam comprehensive mining and gas control | |
CN102493839B (en) | Method for filling gob | |
CN106194252A (en) | A kind of coal mining totipotency end pipeline conveying Paste-filling System and method | |
CN101215976B (en) | Down-hole gangue pump packing system and method | |
CN203925502U (en) | The system that a kind of hydraulic coal mining and filling are synchronously carried out | |
CN110030031A (en) | The method that coal column is left in a kind of longwell recycling house column type goaf | |
CN112343651A (en) | Process and equipment for filling mining by using coal gangue | |
CN109209491A (en) | A kind of waste filling method | |
CN103590851A (en) | Underground waste-rock concrete preparation, pumping and filling system and method | |
Krupnik et al. | Backfilling technology in Kazakhstan mines | |
CN111365067A (en) | Paste filling mining method | |
CN103133033A (en) | Mine phosphogypsum cemented fill slurrying process | |
CN106050300A (en) | Filling roof connecting method used for upward drift ultrahigh undersampling | |
CN201982137U (en) | Underground preparation device taking waste rock as aggregate concrete filling material | |
CN106194249A (en) | A kind of coal mine gob totipotency Paste-filling System and method | |
CN210343417U (en) | Realize closely knit filling system that full roof was met in collecting space area filling tunnel in pit | |
CN112796829A (en) | Underground original gangue filling system and method for caving area of fully mechanized caving face | |
Liu | Technologies and practices of mechanized backfill mining for water protection with aeolian sand paste-like | |
CN209990500U (en) | Grouting filling system | |
CN102661170A (en) | Process and device for continuously stirring and filling paste-like body for mine manufactured by use of building waste |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20190705 |