CN109972666A - Excavation of subway foundation pit controls the existing construction method for closing on pipeline disturbance - Google Patents

Excavation of subway foundation pit controls the existing construction method for closing on pipeline disturbance Download PDF

Info

Publication number
CN109972666A
CN109972666A CN201910318383.XA CN201910318383A CN109972666A CN 109972666 A CN109972666 A CN 109972666A CN 201910318383 A CN201910318383 A CN 201910318383A CN 109972666 A CN109972666 A CN 109972666A
Authority
CN
China
Prior art keywords
pipeline
foundation pit
excavation
closing
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910318383.XA
Other languages
Chinese (zh)
Other versions
CN109972666B (en
Inventor
龚建昌
盖青山
李桂林
李青东
陆阳
叶朝阳
胡利平
秦立志
张方
马景威
肖彦增
田家乐
宋战平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Bridge Engineering Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201910318383.XA priority Critical patent/CN109972666B/en
Publication of CN109972666A publication Critical patent/CN109972666A/en
Application granted granted Critical
Publication of CN109972666B publication Critical patent/CN109972666B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/08Restraining of underground water by employing open ditches arranged below the level of the water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/02Dredgers or soil-shifting machines for special purposes for digging trenches or ditches
    • E02F5/06Dredgers or soil-shifting machines for special purposes for digging trenches or ditches with digging elements mounted on an endless chain
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Mechanical Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Soil Sciences (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

Excavation of subway foundation pit controls the existing construction method for closing on pipeline disturbance, it is related to technical field of building construction.The present invention solves the method that existing excavation of subway foundation pit control closes on pipeline disturbance and there is the construction not being able to satisfy apart from the closer pipeline of foundation pit, foundation pit side aviation fuel pipeline has seriously affected the excavation construction of the Metro station excavation soil body, the problem of increasing the difficulty of subway construction, and easily leading to pipeline deformation.A kind of excavation of subway foundation pit of the invention control it is existing close on pipeline disturbance construction method through the following steps that realize, Step 1: determine reinforcing area;Step 2: the soil body in reinforcing area squeezes into downwards the different steel floral tube of three row's length from earth's surface;Step 3: first carrying out slip casting to short steel floral tube, slip casting then is carried out to long steel floral tube again;Step 4: being laid with steel plate in reinforcing area earth's surface;Step 5: construction TRD water-stop curtain;Step 6: construction drill bored concrete pile.The present invention is for realizing the control for closing on pipeline disturbance to foundation pit.

Description

Excavation of subway foundation pit controls the existing construction method for closing on pipeline disturbance
Technical field
The present invention relates to technical field of building construction, control the existing pipeline that closes on more particularly to a kind of excavation of subway foundation pit and disturb Dynamic construction method.
Background technique
With the propulsion of urbanization, the density of population in city, inlet flow rate constantly increase, for the hair for pushing urban transportation Exhibition, urban underground space obtain swift and violent exploitation, and many cities in China have started construction and built with operation a plurality of tracks, but due to In down town, building, underground utilities are numerous for subway construction, increase the difficulty of subway construction, reduce subway foundation pit and open Dig the main problem to be solved become during subway construction to the influence of periphery pipeline.The control that traditional construction disturbs pipeline Mainly by adjusting each construction parameter, being adjusted to wall mode, accelerate speed of application etc., and by reinforcing pipeline and the periphery soil body It monitors, the reinforcement protection that takes reasonable measure in time of finding the problem.But conventional control mode is not able to satisfy and compares apart from foundation pit Close pipeline, therefore seek the control that closes on pipeline disturbance of the new method realization of one kind to foundation pit.
It is not able to satisfy in conclusion the method that existing excavation of subway foundation pit control closes on pipeline disturbance exists apart from foundation pit The excavation construction that pipeline has seriously affected the Metro station excavation soil body is closed in the construction of closer pipeline, foundation pit side, increases The difficulty of subway construction, and the problem of easily lead to pipeline deformation.
Summary of the invention
The method that the present invention closes on pipeline disturbance in order to solve the control of existing excavation of subway foundation pit exist be not able to satisfy away from The construction of the pipeline closer from foundation pit, foundation pit side, which closes on pipeline and seriously affected the excavation of the Metro station excavation soil body, applies Work, increases the difficulty of subway construction, and the problem of easily lead to pipeline deformation, and then provides a kind of control of excavation of subway foundation pit both There is the construction method for closing on pipeline disturbance.
The technical scheme is that
Excavation of subway foundation pit controls the existing construction method for closing on pipeline disturbance, and the method is through the following steps that realize ,
Step 1: determining reinforcing area:
The pipeline side soil body that closes on of foundation pit is determined to soil mass consolidation boundary of works area;
Step 2: pilot hole, installation steel floral tube:
The different steel floral tube of three row's length is squeezed into downwards from earth's surface in the soil body of fixed reinforcing area, is first constructed close The short steel floral tube of two rows for closing on pipeline, then constructs again close to the long steel floral tube of one row of foundation pit;
Step 3: downward grouting is reinforced:
Slip casting is carried out to steel floral tube, slip casting first is carried out to short steel floral tube, slip casting then is carried out to long steel floral tube again;
Step 4: being laid with steel plate:
It is laid with steel plate in reinforcing area earth's surface, steel plate is laid with no less than 1 layer, and the steel plate is machine-walking region;
Step 5: construction TRD water-stop curtain:
It first constructs close to the TRD water-stop curtain for closing on pipeline side, then constructs again far from the TRD sealing curtain for closing on pipeline Curtain;
Step 6: cast-in-situ bored pile:
The construction drill bored concrete pile between foundation pit and TRD water-stop curtain, the bored concrete pile is as foundation pit supporting construction one Point.
Further, in the step 1, soil stabilization range are as follows: close on pipeline to the distance of foundation pit in 1 times of foundation pit depth Spend the soil body within range.
Further, in the step 2, steel floral tube, which is squeezed into, will close on pipeline to foundation pit edge apart from equal part, the short spray of molten steel Length of tube is 1.5 times for closing on line depth, and long spray of molten steel length of tube is 1.3 times of foundation depth, and spray of molten steel pipe diameter is 108mm.
Further, in the step 3, injecting paste material is C30 striaght cement slurries, and grouting pressure is 0.3~0.6MPa, Grouting amount is 100L/m.
Further, in the step 4, steel plate thickness 2cm.
Further, in the step 5, TRD water-stop curtain thickness of wall body is 600mm, using P.O42.5 grades of ordinary silicons Acid salt cement, Cement for walls volume 22%, ratio of mud 1:1 use sodium bentonite mixing at tank liquor.
Further, in the step 6, pile diameter 1000mm, stake spacing is 1200mm, and 15cm is used between stake Thick C20 in-network processing.
Further, the TRD water-stop curtain construction includes the following steps: to excavate leading for 0.7m wide along TRD center line of wall Slot;Hang the provided box of storage chain cutter;It is in place that host is carried out according to the positioning of wall center line;Chain is lifted from provided box Shape cutter is attached with host;Cutting, the solidify liquid injection, cement of the wall soil body are carried out after chain Cutting tool installation manner to designed elevation Soil is at wall.
Further, the bored pile construction includes the following steps: in the cast-in-situ bored pile provided according to design Heart point carries out the setting-out of stake position;Manually embedded casing is carried out according to the stake position center of setting-out;According to embedded casing and stake position cross hairs It is in place to carry out drilling machine;The system of slurry coat method is mixed;Drilling machine drilling construction;Fabrication of reinforcing cage, lifting and installation;Conduit installation;Conduit Borehole cleaning is carried out after being installed ensures that sediment meets design requirement;Underwater gliders.
Further, in the step 4, when the steel plate number of plies that reinforcing area earth's surface is laid with is equal to 1, the steel plate exists Middle line on length direction is vertically arranged with pipeline is closed on;
When reinforcing area earth's surface be laid with the steel plate number of plies be greater than 1 when, the middle line of first layer steel plate in the longitudinal direction with face Nearly pipeline is vertically arranged, the middle line of second layer steel plate in the longitudinal direction and the median perpendicular of first layer steel plate in the longitudinal direction Setting ... ..., the median perpendicular setting of the middle line and (n-1)th layer of steel plate of n-th layer steel plate in the longitudinal direction in the longitudinal direction.
The present invention has the effect that compared with prior art
1, the optimization of the invention by closing on pipeline perturbation motion method to Traditional control, using steel floral tube to aviation fuel pipe periphery soil Body carries out pre-reinforcement, heavy-duty machinery operating area takes steel plate to be laid with to reduce and go along with sb. to guard him knot to ground load, first construction foundation pit Branch mark structure minimizes the disturbance of bored pile construction, cast-in-situ bored pile has been formed for the TRD water-stop curtain formation of structure At working procedures arrangement and the technical measures such as foundation pit enclosure structure, can be with effective solution Metro station excavation soil excavation pair The influence of pipeline is closed in side, reduces the deformation of pipeline, and when reinforcing area earth's surface is laid with steel plate, steel plate is laid with no less than 1 layer, It is laid with respectively parallel and perpendicular to pipeline direction, prevents the region from receiving mechanical load parameter differential settlement;Stop in construction TRD When water curtain, the water-stop curtain for closing on pipeline is first beaten, and is moved back the direction far from pipeline and is constructed, to reduce the extruding to pipeline.
Detailed description of the invention
Fig. 1 is the schematic diagram that reinforcing area is determined described in step 1 of the present invention;
Fig. 2 is enlarged drawing of the Fig. 1 at M;
Fig. 3 is the schematic diagram that steel floral tube is installed described in step 2 of the present invention;
Fig. 4 is enlarged drawing of the Fig. 3 at N;
Fig. 5 is the schematic diagram that downward grouting described in step 3 of the present invention is reinforced;
Fig. 6 is enlarged drawing of the Fig. 5 at O;
Fig. 7 is the schematic diagram that steel plate is laid with described in step 4 of the present invention;
Fig. 8 is enlarged drawing of the Fig. 7 at P;
Fig. 9 is construction direction schematic diagram when reinforcing area of the invention reaches some strength;
Figure 10 is enlarged drawing of the Fig. 9 at Q.
Specific embodiment
Specific embodiment 1: illustrating present embodiment, the excavation of subway foundation pit control of present embodiment in conjunction with Fig. 1 to Figure 10 Make it is existing close on pipeline disturbance construction method, the method through the following steps that realize,
Step 1: determining reinforcing area 3:
The 2 side soil body of pipeline that closes on of foundation pit 1 is determined to soil mass consolidation boundary of works area;
Step 2: pilot hole, installation steel floral tube 4:
The different steel floral tube 4 of three row's length is squeezed into downwards from earth's surface in the soil body of fixed reinforcing area 3, and first construction is leaned on The short steel floral tube 4-1 of two rows for closely closing on pipeline 2, then constructs again close to the long steel floral tube 4-2 of 1 one row of foundation pit;
Step 3: downward grouting is reinforced:
Slip casting is carried out to steel floral tube 4, slip casting first is carried out to short steel floral tube 4-1, then long steel floral tube 4-2 is infused again Slurry;
Step 4: being laid with steel plate:
It is laid with steel plate in 3 earth's surface of reinforcing area, steel plate is laid with no less than 1 layer, and the steel plate is machine-walking region 5, is prevented Only the region is by mechanical load parameter differential settlement;
Step 5: construction TRD water-stop curtain 6:
It first constructs close to the TRD water-stop curtain 6 for closing on 2 side of pipeline, then constructs and stop far from the TRD for closing on pipeline 2 again Water curtain 6;
Step 6: cast-in-situ bored pile 7:
The construction drill bored concrete pile 7 between foundation pit 1 and TRD water-stop curtain 6, the bored concrete pile 7 are used as 1 supporting construction of foundation pit A part.
Specific embodiment 2: illustrate present embodiment in conjunction with Fig. 1 and Fig. 2, and in the step 1 of present embodiment, soil Body reinforcing scope are as follows: close on pipeline 2 and arrive the soil body of the distance of foundation pit 1 within 1 times of foundation depth range.So set, according to Aviation fuel pipe is analyzed apart from the foundation pit degree of approach, the feature bigger apart from the nearlyr construction disturbance of foundation pit, on the influence aviation fuel before construction The soil body in area under control domain constructed before reinforcing, reduce the sedimentation of aviation fuel pipe and the aviation fuel pipe periphery soil body with maximum limit. Other compositions and connection relationship are same as the specific embodiment one.
Specific embodiment 3: illustrate present embodiment in conjunction with Fig. 3 and Fig. 4, and in the step 2 of present embodiment, steel Floral tube 4, which is squeezed into, will close on pipeline 2 to 1 edge of foundation pit apart from equal part, and short steel floral tube 4-1 length is close on 2 depth of pipeline 1.5 Times, long steel floral tube 4-2 length is 1.3 times of foundation depth, and 4 diameter of steel floral tube is 108mm.Close to two rows of steel floral tubes of aviation fuel pipe Be it is shorter, be about 8.5m;A row close to 1 side of foundation pit is longer, length about 18.8m.So set, surveying soil close to foundation pit Body forms the whole soil body after reinforcing have certain bracing effect, reinforces purpose close to the soil at both sides of pipeline and mainly solves aviation fuel Pipeline is in the characteristics of unstable silt soil strata.Other compositions and connection relationship are the same as one or two specific embodiments.
Specific embodiment 4: illustrate present embodiment in conjunction with Fig. 5 and Fig. 6, and in the step 3 of present embodiment, note Slurry takes the mode of downstriker delamination pour slurry, and slip casting depth is tube bottom to aviation fuel pipe or less 0.5m, and injecting paste material is C30 striaght cement Slurries, grouting pressure are 0.3~0.6MPa, grouting amount 100L/m.So set, the mode of downward grouting is taken to contain in thickness Pre grouting from the surface is used in water layer, can be preferably layered, is segmented progress soil stabilization, grouting pressure control is no more than 0.6Mpa, To maximally reduce the disturbance of the mortar depositing construction team soil body.Other compositions and connection relationship and specific embodiment one, two or Three is identical.
Specific embodiment 5: in the step 4 of present embodiment, steel plate thickness 2cm.It can according to monitoring situation Increase and is laid with the steel plate number of plies.So set, steel plate is laid in construction ground, with the maximum heavy duty equipment that reduces to the lotus on ground It carries, reduces sedimentation, it is ensured that the sedimentation of aviation fuel pipeline reaches minimum.Other compositions and connection relationship and specific embodiment one, two, Three or four is identical.
Specific embodiment 6: illustrate present embodiment in conjunction with Fig. 7 and Fig. 8, in the step 5 of present embodiment, 6 thickness of wall body of TRD water-stop curtain is 600mm, using P.O42.5 grades of ordinary portland cements, Cement for walls volume 22%, water ash Than using sodium bentonite mixing at tank liquor for 1:1.So set, cutting soil improves its workability using sodium bentonite The slot that collapses can be prevented, the volume that curing agent (cement) in solidify liquid is improved during slip casting forms intensity height, the impermeability of wall By force, guarantee that construction disturbance is small, the construction disturbance for the reduction cast-in-situ bored pile 7 that the bracing effect of TRD wall itself can be bigger, from And reduce the deformation of the aviation fuel pipe periphery soil body and aviation fuel pipe.Other compositions and connection relationship and specific embodiment one, two, three, Four or five is identical.
Specific embodiment 7: illustrate present embodiment in conjunction with Fig. 9 and Figure 10, in the step 6 of present embodiment, 7 diameter of bored concrete pile is 1000mm, and stake spacing is 1200mm, and the C20 in-network processing of 15cm thickness is used between stake.So set, stake Between net spray apply spray in time and can reduce to the greatest extent the loss of inter-pile soil body, to reduce the deformation of foundation pit enclosure structure itself, Controlling foundation pit deformation is also to guarantee one of indeformable most important measure of aviation fuel pipe.It is other composition and connection relationship with specifically Embodiment one, two, three, four, five or six are identical.
Specific embodiment 8: the TRD water-stop curtain 6 construction of present embodiment includes the following steps: along TRD wall The guide groove of heart line excavation 0.7m wide;Hang the provided box of storage chain cutter;Host is carried out just according to the positioning of wall center line Position;Chain cutter is lifted from provided box to be attached with host;The wall soil body is carried out after chain Cutting tool installation manner to designed elevation Cutting, solidify liquid injection, soil cement are at wall.Other compositions and connection relationship and specific embodiment one, two, three, four, five, six Or seven is identical.
Specific embodiment 9: the construction of the cast-in-situ bored pile 7 of present embodiment includes the following steps: to be mentioned according to design The central point of the cast-in-situ bored pile 7 of confession carries out the setting-out of stake position;Manually embedded casing is carried out according to the stake position center of setting-out;According to burying If it is in place that casing and stake position cross hairs carry out drilling machine;The system of slurry coat method is mixed;Drilling machine drilling construction;Fabrication of reinforcing cage, lifting and Installation;Conduit installation;Conduit, which carries out borehole cleaning after being installed, ensures that sediment meets design requirement;Underwater gliders.It is other Composition and connection relationship and specific embodiment one, two, three, four, five, six, seven or eight are identical.
Specific embodiment 10: in the step 4, it is described when the steel plate number of plies that 3 earth's surface of reinforcing area is laid with is equal to 1 The middle line of steel plate in the longitudinal direction is vertically arranged with pipeline 2 is closed on;
When 3 earth's surface of reinforcing area be laid with the steel plate number of plies be greater than 1 when, the middle line of first layer steel plate in the longitudinal direction with face Nearly pipeline 2 is vertically arranged, and the middle line of second layer steel plate in the longitudinal direction and the middle line of first layer steel plate in the longitudinal direction hang down Straight setting ... ..., the middle line of n-th layer steel plate in the longitudinal direction is set with the median perpendicular of (n-1)th layer of steel plate in the longitudinal direction It sets.

Claims (10)

1. excavation of subway foundation pit control it is existing close on pipeline disturbance construction method, it is characterised in that: the method be by with What lower step was realized,
Step 1: determining reinforcing area (3):
Pipeline (2) the side soil body that closes on of foundation pit (1) is determined to soil mass consolidation boundary of works area;
Step 2: pilot hole, installation steel floral tube (4):
The different steel floral tube (4) of three row's length is squeezed into downwards from earth's surface in the soil body of fixed reinforcing area (3), and first construction is leaned on The short steel floral tube (4-1) of two rows for closely closing on pipeline (2), then constructs again close to the long steel floral tube (4-2) of (1) one row of foundation pit;
Step 3: downward grouting is reinforced:
Slip casting is carried out to steel floral tube (4), slip casting first is carried out to short steel floral tube (4-1), then long steel floral tube (4-2) is infused again Slurry;
Step 4: being laid with steel plate:
It is laid with steel plate in reinforcing area (3) earth's surface, steel plate is laid with no less than 1 layer, and the steel plate is machine-walking region (5);
Step 5: construction TRD water-stop curtain (6):
It first constructs close to the TRD water-stop curtain (6) for closing on pipeline (2) side, then constructs again far from the TRD for closing on pipeline (2) Water-stop curtain (6);
Step 6: cast-in-situ bored pile (7):
The construction drill bored concrete pile (7) between foundation pit (1) and TRD water-stop curtain (6), the bored concrete pile (7) are propped up as foundation pit (1) Protection structure a part.
2. excavation of subway foundation pit according to claim 1 controls the existing construction method for closing on pipeline disturbance, feature exists In: in the step 1, soil stabilization range are as follows: close on the distance of pipeline (2) to foundation pit (1) in (1) times foundation depth range Within the soil body.
3. excavation of subway foundation pit according to claim 2 controls the existing construction method for closing on pipeline disturbance, feature exists In: in the step 2, steel floral tube (4), which is squeezed into, will close on pipeline (2) to foundation pit (1) edge apart from equal part, short steel floral tube (4- 1) length is 1.5 times for closing on line depth, and long steel floral tube (4-2) length is 1.3 times of foundation depth, steel floral tube (4) diameter For 108mm.
4. excavation of subway foundation pit according to claim 3 controls the existing construction method for closing on pipeline disturbance, feature exists In: in the step 3, injecting paste material is C30 striaght cement slurries, and grouting pressure is 0.3~0.6MPa, grouting amount 100L/m.
5. excavation of subway foundation pit according to claim 4 controls the existing construction method for closing on pipeline disturbance, feature exists In: in the step 4, steel plate thickness 2cm.
6. excavation of subway foundation pit according to claim 5 controls the existing construction method for closing on pipeline disturbance, feature exists In: in the step 5, TRD water-stop curtain (6) thickness of wall body is 600mm, using P.O42.5 grades of ordinary portland cements, wall Body cement mixing content 22%, ratio of mud 1:1 use sodium bentonite mixing at tank liquor.
7. excavation of subway foundation pit according to claim 6 controls the existing construction method for closing on pipeline disturbance, feature exists In: in the step 6, bored concrete pile (7) diameter is 1000mm, and stake spacing is 1200mm, nets spray using the C20 of 15cm thickness between stake Concrete.
8. excavation of subway foundation pit according to claim 1 or 6 controls the existing construction method for closing on pipeline disturbance, feature Be: TRD water-stop curtain (6) construction includes the following steps: the guide groove that 0.7m wide is excavated along TRD center line of wall;It hangs and deposits Put the provided box of chain cutter;It is in place that host is carried out according to the positioning of wall center line;From provided box lift chain cutter with Host is attached;The cutting, solidify liquid injection, soil cement of the wall soil body are carried out after chain Cutting tool installation manner to designed elevation into wall.
9. excavation of subway foundation pit according to claim 1 or claim 7 controls the existing construction method for closing on pipeline disturbance, feature Be: cast-in-situ bored pile (7) construction includes the following steps: that the center of the cast-in-situ bored pile (7) provided according to design clicks through Row stake position setting-out;Manually embedded casing is carried out according to the stake position center of setting-out;It is bored according to embedded casing and stake position cross hairs Machine is in place;The system of slurry coat method is mixed;Drilling machine drilling construction;Fabrication of reinforcing cage, lifting and installation;Conduit installation;Conduit installs Ensure that sediment meets design requirement at rear progress borehole cleaning;Underwater gliders.
10. excavation of subway foundation pit controls the existing construction method for closing on pipeline disturbance according to claim 1 or 5, special Sign is: in the step 4, when the steel plate number of plies that reinforcing area (3) earth's surface is laid with is equal to 1, the steel plate is in length direction On middle line be vertically arranged with pipeline (2) is closed on;
When reinforcing area (3) earth's surface be laid with the steel plate number of plies be greater than 1 when, the middle line of first layer steel plate in the longitudinal direction with close on Pipeline (2) is vertically arranged, and the middle line of second layer steel plate in the longitudinal direction and the middle line of first layer steel plate in the longitudinal direction hang down Straight setting ... ..., the middle line of n-th layer steel plate in the longitudinal direction is set with the median perpendicular of (n-1)th layer of steel plate in the longitudinal direction It sets.
CN201910318383.XA 2019-04-19 2019-04-19 Construction method for controlling disturbance of existing adjacent pipeline in excavation of subway foundation pit Active CN109972666B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910318383.XA CN109972666B (en) 2019-04-19 2019-04-19 Construction method for controlling disturbance of existing adjacent pipeline in excavation of subway foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910318383.XA CN109972666B (en) 2019-04-19 2019-04-19 Construction method for controlling disturbance of existing adjacent pipeline in excavation of subway foundation pit

Publications (2)

Publication Number Publication Date
CN109972666A true CN109972666A (en) 2019-07-05
CN109972666B CN109972666B (en) 2020-12-11

Family

ID=67085389

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910318383.XA Active CN109972666B (en) 2019-04-19 2019-04-19 Construction method for controlling disturbance of existing adjacent pipeline in excavation of subway foundation pit

Country Status (1)

Country Link
CN (1) CN109972666B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453687A (en) * 2019-07-31 2019-11-15 南京林业大学 A kind of Metro station excavation excavates the protection structure and construction method of pipeline
CN116427417A (en) * 2023-03-15 2023-07-14 广州万构建筑工程设计有限公司 Construction method and system for controlling disturbance of existing adjacent pipelines in foundation pit excavation

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002004286A (en) * 2000-06-23 2002-01-09 Japan Steel & Tube Constr Co Ltd Construction method for forming drainage basin and earth retaining box used therefor
CN204326080U (en) * 2014-11-18 2015-05-13 中大建设有限公司 A kind of next-door neighbour's existing building pit maintenance soil structure
CN106065628A (en) * 2016-01-26 2016-11-02 中铁三局集团有限公司 Based on the major diameter running water pipe security protection construction method forever facing the theory of combination

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002004286A (en) * 2000-06-23 2002-01-09 Japan Steel & Tube Constr Co Ltd Construction method for forming drainage basin and earth retaining box used therefor
CN204326080U (en) * 2014-11-18 2015-05-13 中大建设有限公司 A kind of next-door neighbour's existing building pit maintenance soil structure
CN106065628A (en) * 2016-01-26 2016-11-02 中铁三局集团有限公司 Based on the major diameter running water pipe security protection construction method forever facing the theory of combination

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453687A (en) * 2019-07-31 2019-11-15 南京林业大学 A kind of Metro station excavation excavates the protection structure and construction method of pipeline
CN110453687B (en) * 2019-07-31 2024-03-19 南京林业大学 Protection structure of subway station foundation pit excavation pipeline and construction method
CN116427417A (en) * 2023-03-15 2023-07-14 广州万构建筑工程设计有限公司 Construction method and system for controlling disturbance of existing adjacent pipelines in foundation pit excavation
CN116427417B (en) * 2023-03-15 2024-04-26 浙江聚贤建设股份有限公司 Construction method and system for controlling disturbance of existing adjacent pipelines in foundation pit excavation

Also Published As

Publication number Publication date
CN109972666B (en) 2020-12-11

Similar Documents

Publication Publication Date Title
CN101413266B (en) Processing method of interlayer defect injection concrete of drill filling pile
CN203846485U (en) Long pile percussion drill hole forming construction device
CN102286984A (en) Water-stop curtain and construction method thereof
CN105804761A (en) Construction method suitable for making shield penetrate through building in close range on liquefied sandy soil stratum
CN104631438B (en) Long auger guncreting uplift pile construction method
CN102286981A (en) Waterproof curtain and construction method thereof
CN202194148U (en) Waterproof curtain
CN107503362A (en) A kind of compound antiskid piling wall retaining structure and construction method suitable for reservoir stability
CN104612179A (en) Construction method for underground diaphragm wall penetrating through super-thick silt layer
CN114108649A (en) Foundation pit reinforcing construction method for mucky soil layer
CN207211165U (en) A kind of compound antiskid piling wall retaining structure suitable for reservoir stability
CN109972666A (en) Excavation of subway foundation pit controls the existing construction method for closing on pipeline disturbance
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN110258512A (en) It constructs in a kind of basement rock the method for diaphram wall
CN102995647B (en) Underground water control method used for grouting and seepage insulation of pile hole
CN110331715A (en) A kind of construction method of underground continuous wall in urban construction
CN110158630A (en) A kind of deep covering layer area large-span arch bridge annular ground continuous wall base
CN104863183B (en) Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction
CN110409511A (en) A kind of interlocking pile and ground-connecting-wall seam crossing water-stopping method
CN103866787B (en) A kind of spacious reverse masonry method concrete cut that digs builds construction technology
CN215718763U (en) Shield constructs end reinforced structure
CN102191770B (en) Geology improving method for trenchless construction
CN109989346A (en) Bridge major diameter precast concrete tubular column basis and its construction method
CN114809094A (en) Pipe jacking working well for complex stratum and construction process thereof
CN109024621A (en) The compound retaining wall supporting construction of embankment high slope tubular pole and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant