CN110409511A - A water-stopping method for joints between occlusal piles and ground-connected walls - Google Patents

A water-stopping method for joints between occlusal piles and ground-connected walls Download PDF

Info

Publication number
CN110409511A
CN110409511A CN201910669418.4A CN201910669418A CN110409511A CN 110409511 A CN110409511 A CN 110409511A CN 201910669418 A CN201910669418 A CN 201910669418A CN 110409511 A CN110409511 A CN 110409511A
Authority
CN
China
Prior art keywords
wall
pile
ground
occlusal
interlocking pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910669418.4A
Other languages
Chinese (zh)
Other versions
CN110409511B (en
Inventor
郭海涛
韩超
宁凯飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao University of Technology
Fourth Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Original Assignee
China Railway 20th Bureau Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 20th Bureau Group Corp filed Critical China Railway 20th Bureau Group Corp
Priority to CN201910669418.4A priority Critical patent/CN110409511B/en
Publication of CN110409511A publication Critical patent/CN110409511A/en
Application granted granted Critical
Publication of CN110409511B publication Critical patent/CN110409511B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明属于建筑工程技术领域,涉及一种咬合桩与地下连续墙接缝处止水方法,咬合桩硂桩与咬合桩素桩间隔排列,相互咬合形成咬合桩,地连墙与相邻咬合桩素桩咬合,钢花管焊接在地连墙与相邻咬合桩素桩相邻侧的钢筋笼上,注浆管埋设在咬合桩素桩与地连墙接缝处外侧,旋喷桩设在咬合桩素桩与地连墙接缝处外侧,通过地连墙与相邻桩体咬合,地连墙墙体与咬合桩间埋设钢花管,地连墙和咬合桩接缝外侧打设双排注浆管,以及咬合桩与地连墙外侧进行旋喷桩加固等一系列结构及措施,解决了咬合桩与地下连续墙接缝处止水问题,提高接缝处的防水及抗渗漏性能,增强基坑的稳定性与安全性。

The invention belongs to the technical field of construction engineering, and relates to a water-stopping method at the joint of an occlusal pile and an underground continuous wall. The occlusal piles and the occlusal piles are arranged at intervals and interlocked to form an occlusal pile. The ground connection wall and the adjacent occlusal piles The plain pile is occluded, the steel flower tube is welded on the steel cage on the adjacent side of the ground connection wall and the adjacent occlusal pile plain pile, the grouting pipe is buried outside the joint between the occlusal pile plain pile and the ground connection wall, and the rotary grouting pile is installed on the occlusion The outer side of the joint between the plain pile and the ground connection wall is occluded with the adjacent pile body through the ground connection wall, steel flower pipes are buried between the ground connection wall wall and the occlusal pile, and double-row grout is placed outside the joint between the ground connection wall and the occlusal pile. A series of structures and measures such as the grout pipe, and the rotary grouting pile reinforcement on the outside of the occlusal pile and the ground connection wall have solved the problem of water-stopping at the joint between the occlusal pile and the underground diaphragm wall, and improved the waterproof and anti-leakage performance of the joint. Enhance the stability and safety of the foundation pit.

Description

一种咬合桩与地连墙接缝处止水方法A water-stopping method for joints between occlusal piles and ground-connected walls

技术领域:Technical field:

本发明属于建筑工程技术领域,涉及一种基坑支护结构的咬合桩与地下连续墙接缝处止水方法。The invention belongs to the technical field of construction engineering, and relates to a water-stopping method at the joint between an occlusal pile and an underground continuous wall of a foundation pit support structure.

背景技术:Background technique:

随着我国地铁工程越来越多,城市地铁基坑周边各类建筑密集,周围环境和水土地质条件复杂,施工难度大,这就要探索新的基坑支护方式。With more and more subway projects in our country, all kinds of buildings around the foundation pits of urban subways are dense, the surrounding environment and water and land geological conditions are complex, and the construction is difficult. It is necessary to explore new foundation pit support methods.

目前,地铁工程常用的基坑支护形式有咬合桩和地下连续墙等。咬合桩是指平面布置的排桩间相邻桩由钢筋混凝土桩和素桩相互咬合而形成的基坑支护结构,以此来作为地铁工程的基坑支护结构。咬合桩比地下连续墙配筋率较低,因为采用钢筋混凝土柱和素混凝土桩间隔布置的施工方式,可以很大程度降低支护结构的配筋率、节约资金。咬合桩的抗渗能力强,因为它是连续施工的,柱间不存在施工冷缝也不夹杂泥土,而地下连续墙分幅接头处的施工冷缝,往往是防渗的薄弱环节,若地下连续墙刷壁效果不到位会留下渗水隐患。咬合桩施工灵活,因为咬合桩可以根据需要转折变线,所以更适合于应用于一些基坑边壁多变的基坑支护。At present, the foundation pit support forms commonly used in subway engineering include occlusal piles and underground diaphragm walls. The occlusal pile refers to the foundation pit support structure formed by the interlocking of reinforced concrete piles and plain piles between the adjacent piles in the row of piles arranged in the plane, which is used as the foundation pit support structure of the subway project. The reinforcement ratio of the occlusal pile is lower than that of the underground diaphragm wall, because the construction method of interspersed arrangement of reinforced concrete columns and plain concrete piles can greatly reduce the reinforcement ratio of the supporting structure and save money. The anti-seepage ability of the occlusal pile is strong, because it is continuously constructed, there is no construction cold joint between the columns and no soil is mixed, and the construction cold joint at the joint of the underground diaphragm wall is often the weak link of anti-seepage, if the underground If the wall brushing effect of the continuous wall is not in place, there will be hidden dangers of water seepage. The construction of the occlusal pile is flexible, because the occlusal pile can be turned and changed according to the needs, so it is more suitable for the support of some foundation pits with changeable side walls.

地下连续墙是利用各种挖槽机械,借助泥浆的护壁作用,在设计位置挖出一定尺寸的沟槽,然后起吊下放钢筋笼,浇注混凝土而形成一道兼具防渗、挡土和承重作用的连续地下墙体。地下连续墙施工时振动较小,噪音较低,对周边影响较小,适合在城市施工。地下连续墙刚度大,基坑开挖后能承受较大的土压力,在工程应用中极少发生地基沉降或塌方事故,而且地下连续墙墙体本身防渗性能较好,如果接头形式和施工方法得当地下连续墙的止水防渗效果较好。地下连续墙适用于多种地质条件,应用范围广泛。The underground continuous wall is to use various digging machines to dig out a groove of a certain size at the design position with the help of the wall retaining function of the mud, then hoist and lower the steel cage, and pour concrete to form a wall with anti-seepage, soil retaining and load-bearing functions. Continuous underground wall. During the construction of the underground diaphragm wall, the vibration is small, the noise is low, and the impact on the surrounding area is small, so it is suitable for construction in cities. The underground diaphragm wall has high rigidity and can withstand large earth pressure after excavation of the foundation pit. In engineering applications, foundation settlement or landslide accidents rarely occur, and the underground diaphragm wall itself has good anti-seepage performance. If the joint form and construction The waterproof and anti-seepage effect of the underground diaphragm wall is better if the method is proper. The underground diaphragm wall is suitable for a variety of geological conditions and has a wide range of applications.

若将咬合桩与地下连续墙相结合,在同一工程中根据地质条件同时使用两种支护结构,可以充分利用两者的优点。但咬合桩与地下连续墙接缝处的止水问题是重难点,咬合桩与地连墙接缝一旦发生渗漏水情况,不仅堵漏工作十分困难,而且将会影响到基坑和周边环境的安全。目前还没有一种行之有效的系统施工方法。因此,设计一种咬合桩与地连墙接缝处止水方法迫在眉睫。If the occlusal pile is combined with the underground diaphragm wall, the advantages of both can be fully utilized by using both types of support structures in the same project according to the geological conditions. However, the problem of water-stopping at the joints between the occlusal piles and the underground diaphragm wall is a major and difficult point. Once water leakage occurs at the joints between the occlusal piles and the underground diaphragm wall, not only is it very difficult to stop the leakage, but it will also affect the foundation pit and the surrounding environment safety. At present, there is no effective systematic construction method. Therefore, it is imminent to design a water-stopping method at the joint between the occlusal pile and the ground connection wall.

发明内容:Invention content:

本发明的目的在于克服现有技术存在的缺点,针对咬合桩与地连墙接缝处渗漏水问题,设计提供一种咬合桩与地下连续墙接缝处的止水方法,提高接缝处的防水及抗渗漏性能,增强基坑的稳定性与安全性。The purpose of the present invention is to overcome the shortcomings of the prior art, aiming at the problem of water leakage at the joint between the joint pile and the ground connection wall, it is designed to provide a water-stopping method at the joint between the joint pile and the underground continuous wall, so as to improve the water quality of the joint. Excellent waterproof and anti-leakage performance, enhance the stability and safety of the foundation pit.

为了实现上述目的,本发明通过咬合桩与地连墙接缝处止水结构实现,具体过程为:In order to achieve the above object, the present invention realizes the water-stop structure at the joint between the occlusal pile and the ground connection wall, and the specific process is as follows:

步骤1:进行咬合桩的施工,与地连墙咬合的为咬合桩素桩,放线定位后,钻机就位,取土成孔直至设计孔底标高,如为咬合桩硂桩在成孔检查合格后吊放钢筋笼,后浇筑混凝土拔管成桩;Step 1: Carry out the construction of occlusal piles. The occlusal piles that are occluded with the ground connection wall are plain piles. After setting out and positioning, the drilling rig is in place, and the soil is taken to form a hole until the design hole bottom elevation. After passing the test, hang the reinforcement cage, and then pour the concrete and pull out the pipe to form a pile;

步骤2:地连墙施工的准备工作,采用现有工艺进行地连墙的放线定位导墙施工,制备泥浆,然后试成槽;Step 2: Preparatory work for the construction of the ground connection wall, use the existing technology to carry out the setting-out and positioning guide wall construction of the ground connection wall, prepare the mud, and then try to form a groove;

步骤3:地连墙常规成槽,根据设计要求及导墙确定地连墙的位置,成槽机进行开挖作业,成槽时采用泥浆护壁,直至深度与相邻咬合桩埋深相同,并对槽孔进行验收;Step 3: The ground connection wall is conventionally grooved, and the position of the ground connection wall is determined according to the design requirements and the guide wall. Check and accept the slot;

步骤4:地连墙成槽时,靠近咬合桩素桩一侧采用旋挖钻扩大成槽墙体宽度至少200mm,确保浇筑混凝土时,混凝土能绕流过槽钢背面,与咬合桩素桩紧密结合,使咬合桩素桩与地连墙间连接牢固;Step 4: When the ground connection wall is grooved, use a rotary drill to expand the wall width of the groove to at least 200mm on the side close to the plain pile of the occlusal pile, so as to ensure that the concrete can flow around the back of the channel steel when pouring concrete, and be closely connected to the plain pile of the occlusal pile. Combined to make the connection between the occlusal pile plain pile and the ground connection wall firm;

步骤5:采用旋挖钻钻除部分接缝处咬合桩素桩,使地连墙与相邻咬合桩素桩至少有300mm咬合,施工过程中注意控制泥浆比重在1.1g/cm3~1.25g/cm3,直至墙底高程为止;Step 5: Use a rotary drill to drill out some of the seam piles at the joints, so that the ground connection wall and the adjacent seam piles have at least 300mm of seam. During the construction process, pay attention to controlling the specific gravity of the mud at 1.1g/cm 3 ~ 1.25g /cm 3 , up to the height of the bottom of the wall;

步骤6:成槽后进行清底、清孔作业,清底采用抓捞法,清孔可采用正循环清孔作业,待槽内的泥浆置换完成后停止清底;Step 6: After the tank is formed, carry out bottom cleaning and hole cleaning operations. The bottom cleaning adopts the fishing method, and the cleaning hole can be cleaned by positive circulation. Stop cleaning the bottom after the mud replacement in the tank is completed;

步骤7:成槽后,采用钢丝刷反复清理相邻咬合桩素桩侧壁,确保侧壁不粘泥,确保与地连墙连接紧密,采用刷壁器上下往复洗刷不少于20次,刷完壁后及时将刷壁器上的泥皮清洗干净,并检查钢丝状况,如有损耗及时修补;Step 7: After the groove is formed, use a wire brush to repeatedly clean the side walls of the adjacent occlusal piles to ensure that the side walls are not sticky with mud and that they are closely connected to the ground wall. After the wall is finished, clean the mud skin on the wall brusher in time, and check the condition of the steel wire, and repair it in time if there is any loss;

步骤8:进行钢筋笼的制作,制作前先对钢筋除锈,采用胎具法成型工艺制作钢筋笼,焊接时严格控制焊接质量,根据咬合桩素桩位置确定钢筋笼制作宽度;Step 8: Carry out the production of the reinforcement cage, remove the rust of the reinforcement before the production, use the molding method to manufacture the reinforcement cage, strictly control the welding quality during welding, and determine the width of the reinforcement cage according to the position of the occlusal pile plain pile;

步骤9:在地连墙墙体与相邻咬合桩素桩之间埋设两根钢花管,两根钢花管之间焊接后绑扎在与咬合桩素桩侧钢筋笼上,两根钢花管平行布置,埋设至地连墙墙底设计高度,便于浇筑混凝土进行注浆止水补强,注浆管位置应适当靠近接缝槽钢处;Step 9: Lay two steel flower tubes between the wall of the ground connection wall and the adjacent occlusal pile. After welding, the two steel flower tubes are bound to the reinforcement cage on the side of the occlusal pile. The two steel flower tubes are arranged in parallel , buried to the design height of the bottom of the ground connection wall, which is convenient for pouring concrete for grouting and waterproof reinforcement, and the position of the grouting pipe should be properly close to the joint channel steel;

步骤10:进行钢筋笼的吊装,吊装时控制该段钢筋笼槽钢位置尽量靠近已成桩咬合桩素桩,减少之间的空隙,使地连墙与咬合桩素桩间连接牢靠;Step 10: Carry out hoisting of the reinforcement cage. During hoisting, control the channel steel position of this section of the reinforcement cage as close as possible to the plain pile of the occlusal pile of the completed pile, reduce the gap between them, and make the connection between the ground connection wall and the occlusal pile plain pile firm;

步骤11:浇筑该段墙体混凝土,浇筑时注意确保水下砼较好的流动性,确保砼墙体质量,开浇后需保证混凝土连续浇注,在接头部位浇注中,使注浆管做30cm上下运动,确保浇筑质量;Step 11: Pour the concrete of this section of the wall. When pouring, pay attention to ensure good fluidity of the underwater concrete to ensure the quality of the concrete wall. After the pouring, the continuous pouring of the concrete must be ensured. During the pouring of the joint, the grouting pipe should be 30cm long. Movement up and down to ensure the pouring quality;

步骤12:沿地连墙与咬合桩素桩的接缝外侧打设双排注浆管,注浆管的数量与间距根据具体工程地质水文条件确定,进行注浆施工,保证该接缝止水加强;Step 12: Drill double rows of grouting pipes along the outside of the joint between the ground connection wall and the occlusal pile. The number and spacing of the grouting pipes are determined according to the specific engineering geological and hydrological conditions, and the grouting construction is carried out to ensure that the joint is watertight strengthen;

步骤13:地连墙施工完成3天后,对预埋钢花管进行注水,以保证注浆管路的畅通及环状管的劈裂,为注水泥浆做好准备,注水时,随时注意水面的下降位置及压浆泵的输出压力0.5MPa~0.7MPa,压水不宜太多也不宜太少,钢花管5注水疏通后注水泥浆加固,确保接缝处止水质量。Step 13: Three days after the construction of the ground connection wall is completed, inject water into the pre-embedded steel flower pipe to ensure the smooth flow of the grouting pipeline and the splitting of the annular pipe, and prepare for the grouting. When injecting water, pay attention to the drop of the water level at any time The position and the output pressure of the grouting pump are 0.5MPa~0.7MPa. The pressure water should not be too much or too little. After the steel flower pipe 5 is watered and dredged, it is reinforced with grout to ensure the quality of water stop at the joints.

步骤14:在咬合桩素桩与地连墙外侧处采用双排旋喷桩加固,旋喷桩的直径及数量根据具体工程地质水文条件确定,旋喷桩桩间至少咬合200mm,放线定位时避开咬合桩与地连墙接头外侧埋设的双排注浆,钻孔时采用泥浆护壁回转钻进,维持孔壁稳定,至少采用标号42.5的普通硅酸盐水泥,加固深度为地面至地下连续墙墙底设计标高;Step 14: Double-row jet grouting piles are used for reinforcement on the outside of the occlusal piles and the ground connection wall. The diameter and quantity of the jet grouting piles are determined according to the specific engineering geological and hydrological conditions. Avoid the double-row grouting buried outside the joint between the occlusal pile and the ground wall. When drilling, use the mud retaining wall to drill to maintain the stability of the hole wall. At least use ordinary portland cement with a label of 42.5. The design elevation of the wall bottom;

步骤15:如果后期接缝出现渗流现象,对墙面进行剔凿清理,然后用双快水泥进行封堵;严重时剔凿清理漏水点,插入导流管,涂抹封堵材料(封堵灵、快硬水泥等)封堵导流管,最后在围护结构外侧或漏水点下方进行注浆处理,补充注浆加固,渗漏水封堵完成后方能继续开挖。Step 15: If there is seepage in the joints in the later stage, clean the wall surface by chiseling, and then seal it with Shuangkuai cement; if it is serious, clean the leaking point by chiseling, insert a diversion tube, and apply sealing materials (sealing spirit, Rapid hardening cement, etc.) to block the diversion pipe, and finally carry out grouting treatment on the outside of the enclosure structure or below the leakage point, supplement grouting reinforcement, and continue excavation after the leakage water is sealed.

本发明所述注浆用的注浆材料选用425#抗硫酸盐水泥(抵抗硫酸盐侵蚀),水灰比为0.5,浆液中掺加0.2%的玄武岩纤维提高抗裂性能(纤维单丝直径12=3um,密度2.65kg/m3,平均长度6mm,抗拉强度2000MPa,弹性模量90GPa,极限延伸率3.5%)。The grouting material that grouting of the present invention is used selects 425# anti-sulphate cement (resistance to sulfate erosion), and water-cement ratio is 0.5, and the basalt fiber of admixing 0.2% improves crack resistance performance (fiber monofilament diameter 12 in the grout) =3um, density 2.65kg/m3, average length 6mm, tensile strength 2000MPa, elastic modulus 90GPa, ultimate elongation 3.5%).

本发明所述护壁用泥浆的配比(%)为水∶膨润土∶羧甲基纤维素∶重晶石=100∶10∶0.3∶0.02,其中,控制槽内液面标高高于地下水位1m;泥浆比重控制在1.05~1.15之间;泥浆粘度控制在20~22s;泥浆PH值不超过10.5,具有浮悬钻渣、冷却钻头、润滑钻具的作用,能增大静水压力,并在槽壁形成泥皮,隔断槽内外渗流,防止护壁防塌。The proportioning (%) of mud for retaining wall of the present invention is water: bentonite: carboxymethyl cellulose: barite=100: 10: 0.3: 0.02, wherein, the liquid level elevation in the control tank is higher than groundwater level 1m; The specific gravity of the mud is controlled between 1.05 and 1.15; the viscosity of the mud is controlled between 20 and 22s; the PH value of the mud does not exceed 10.5, which has the functions of suspending drilling slag, cooling the drill bit, and lubricating the drilling tool, and can increase the hydrostatic pressure. A mud skin is formed to cut off seepage inside and outside the groove, preventing the retaining wall from collapsing.

本发明所述咬合桩与地连墙接缝处止水结构的主体结构包括地连墙、咬合桩素桩、咬合桩硂桩、旋喷桩、钢花管和注浆管;咬合桩硂桩与咬合桩素桩间隔排列,相互咬合形成咬合桩,地连墙与相邻咬合桩素桩咬合,地下连续墙埋深与相邻咬合桩素桩埋深相同;钢花管焊接在地连墙与相邻咬合桩素桩相邻侧的钢筋笼上,埋深与地连墙埋深相同;注浆管埋设在咬合桩素桩与地连墙接缝处外侧,埋深根据具体工程地质条件确定;旋喷桩设在咬合桩素桩与地连墙接缝处外侧,埋深与地连墙埋深相同。The main structure of the water-stopping structure at the seam between the occlusal pile and the ground connection wall of the present invention includes a ground connection wall, a occlusion pile plain pile, a occlusal pile 硂 pile, a rotary spray pile, a steel flower pipe and a grouting pipe; the occlusion pile 硂 pile and the The occlusal piles and plain piles are arranged at intervals and occluded with each other to form occlusal piles. The ground connection wall is occluded with the adjacent occlusal piles. The buried depth of the underground diaphragm wall is the same as that of the adjacent occlusal piles; On the reinforcement cage adjacent to the plain pile of the occlusal pile, the burial depth is the same as that of the ground connection wall; the grouting pipe is buried outside the joint between the plain pile of the occlusal pile and the ground connection wall, and the burial depth is determined according to the specific engineering geological conditions; The rotary grouting pile is located outside the joint between the occlusal pile and the ground connection wall, and the buried depth is the same as that of the ground connection wall.

本发明所述地连墙的厚度、幅宽与埋深根据具体工程地质情况与咬合桩的尺寸确定,地下连续墙幅宽不大于6m,埋深为10m至50m,厚度为0.5m至1.2m,且小于相邻咬合桩素桩直径至少200mm,以便两者紧密连接;咬合桩素桩的直径和埋深根据工程地质条件确定,直径不小于1000mm,至少用C25超缓凝混凝土浇筑,与相邻桩桩间咬合不小于300mm;咬合桩硂桩的直径和埋深应根据工程地质条件确定,直径不小于1000mm,至少用C45水下混凝混凝土浇筑,与相邻桩桩间咬合不小于300mm;旋喷桩的直径与咬合桩直径相同,至少用标号42.5的普通硅酸盐水泥,与咬合桩硂桩、咬合桩素桩、地连墙桩相切,加固深度为地面至咬合桩桩底标高;钢花管的直径根据具体工程地质情况确定,一般采用A42钢花管,钢管间采用焊接连接;注浆管的直径、埋深应应根据具体工程地质情况确定,钢管间采用丝扣连接。The thickness, width and buried depth of the ground connection wall described in the present invention are determined according to the specific engineering geological conditions and the size of the occlusal pile. The width of the underground continuous wall is not more than 6m, the buried depth is 10m to 50m, and the thickness is 0.5m to 1.2m. , and at least 200mm smaller than the diameter of the adjacent occlusal pile, so that the two can be closely connected; the diameter and buried depth of the occlusal pile are determined according to the engineering geological conditions, and the diameter is not less than 1000mm. The interlocking between adjacent piles is not less than 300mm; the diameter and buried depth of the interlocking piles should be determined according to the engineering geological conditions, the diameter is not less than 1000mm, at least C45 underwater concrete is poured, and the interlocking between adjacent piles is not less than 300mm ; The diameter of the rotary grouting pile is the same as that of the occlusal pile, and at least ordinary Portland cement with a label of 42.5 is used, tangent to the occlusal pile, the occlusal pile, and the ground-connected wall pile, and the reinforcement depth is from the ground to the bottom of the occlusal pile Elevation; the diameter of the steel flower pipe shall be determined according to the specific engineering geological conditions. Generally, A42 steel flower pipes shall be used, and the steel pipes shall be connected by welding; the diameter and buried depth of the grouting pipe shall be determined according to the specific engineering geological conditions, and the steel pipes shall be connected by screws.

本发明与现有技术相比,为咬合桩与地下连续墙接缝处止水问题,提供了一个行之有效的接缝处止水结构及方法,通过地连墙与相邻桩体咬合,地连墙墙体与咬合桩间埋设钢花管,地连墙和咬合桩接缝外侧打设双排注浆管,以及咬合桩与地连墙外侧进行旋喷桩加固等一系列结构及措施,解决了咬合桩与地下连续墙接缝处止水问题,提高接缝处的防水及抗渗漏性能,增强基坑的稳定性与安全性。Compared with the prior art, the present invention provides an effective joint water-stop structure and method for the problem of water-stopping at the joint between the occlusal pile and the underground continuous wall. A series of structures and measures, such as laying steel flower pipes between the ground wall and the occlusal piles, laying double rows of grouting pipes on the outside of the joints between the ground wall and the occlusal piles, and strengthening the occlusal piles and the outside of the ground wall with rotary grouting piles, etc. It solves the problem of water stop at the joint between the occlusal pile and the underground diaphragm wall, improves the waterproof and anti-leakage performance of the joint, and enhances the stability and safety of the foundation pit.

附图说明:Description of the drawings:

图1为本发明中咬合桩与地下连续墙接缝处止水结构的整体平面示意图。Fig. 1 is an overall plan view of the water-stop structure at the joint between the occlusal pile and the underground diaphragm wall in the present invention.

图2为本发明中咬合桩与地下连续墙接缝处止水结构的1-1剖面图,其中1为地下连续墙,2为咬合桩素桩,3为咬合桩荤桩,4为旋喷桩,5为钢花管,6为注浆管,H1为地面至地连墙墙底深度,H2为注浆管埋深。Fig. 2 is the 1-1 sectional view of the water-stop structure at the seam of the occlusal pile and the underground diaphragm wall in the present invention, wherein 1 is the underground diaphragm wall, 2 is the occlusal pile element pile, 3 is the occlusal pile meat pile, and 4 is the rotary jetting Pile, 5 is the steel flower pipe, 6 is the grouting pipe, H1 is the depth from the ground to the bottom of the ground connecting wall, and H2 is the buried depth of the grouting pipe.

具体实施方式:Detailed ways:

下面通过具体实例并结合附图对本发明做进一步详细说明。但不应将此理解为本发明上述主题的范围仅限于以下的实例,凡基于本发明内容所实现的技术均属于本发明的范围。The present invention will be described in further detail below through specific examples and in conjunction with the accompanying drawings. However, it should not be understood that the scope of the above-mentioned themes of the present invention is limited to the following examples, and all technologies realized based on the contents of the present invention belong to the scope of the present invention.

实施例1:Example 1:

本实施例所述咬合桩与地连墙接缝处止水结构的主体结构包括地连墙1、咬合桩素桩2、咬合桩硂桩3、旋喷桩4、钢花管5和注浆管6;咬合桩硂桩3与咬合桩素桩2间隔排列,相互咬合形成咬合桩,地连墙1与相邻咬合桩素桩2咬合,地下连续墙1埋深与相邻咬合桩素桩2埋深相同;钢花管5焊接在地连墙1与相邻咬合桩素桩2相邻侧的钢筋笼上,埋深与地连墙1埋深相同;注浆管6埋设在咬合桩素桩2与地连墙1接缝处外侧,埋深根据具体工程地质条件确定;旋喷桩4设在咬合桩素桩2与地连墙1接缝处外侧,埋深与地连墙1埋深相同。The main structure of the water-stop structure at the joint between the occlusal pile and the ground connection wall in this embodiment includes the ground connection wall 1, the occlusion pile 2, the occlusion pile 3, the rotary spray pile 4, the steel flower pipe 5 and the grouting pipe 6. The occlusal piles and the occlusal piles 3 and the occlusal piles 2 are arranged at intervals, interlocking to form an occlusal pile, the ground connection wall 1 is occluded with the adjacent occlusal pile 2, and the buried depth of the underground diaphragm wall 1 is the same as that of the adjacent occlusal pile 2. The burial depth is the same; the steel flower tube 5 is welded on the reinforcement cage on the adjacent side of the ground connection wall 1 and the adjacent occlusal pile 2, and the burial depth is the same as that of the ground connection wall 1; the grouting pipe 6 is buried in the occlusion pile 2 and the ground connection wall 1 outside the joint, the buried depth is determined according to the specific engineering geological conditions; same.

本实施例所述地连墙1的厚度、幅宽与埋深根据具体工程地质情况与咬合桩的尺寸确定,地下连续墙幅宽不大于6m,埋深为10m至50m,厚度为0.5m至1.2m,且小于相邻咬合桩素桩2直径至少200mm,以便两者紧密连接;咬合桩素桩2的直径和埋深根据工程地质条件确定,直径不小于1000mm,至少用C25超缓凝混凝土浇筑,与相邻桩桩间咬合不小于300mm;咬合桩硂桩3的直径和埋深应根据工程地质条件确定,直径不小于1000mm,至少用C45水下混凝混凝土浇筑,与相邻桩桩间咬合不小于300mm;旋喷桩4的直径与咬合桩直径相同,至少用标号42.5的普通硅酸盐水泥,与咬合桩硂桩3、咬合桩素桩2、地连墙1桩相切,加固深度为地面至咬合桩桩底标高;钢花管5的直径根据具体工程地质情况确定,一般采用A42钢花管,钢管间采用焊接连接;注浆管6的直径、埋深应应根据具体工程地质情况确定,钢管间采用丝扣连接。The thickness, width and buried depth of the ground connecting wall 1 described in this embodiment are determined according to the specific engineering geological conditions and the size of the occlusal pile. 1.2m, and at least 200mm smaller than the diameter of the adjacent occlusal pile 2, so that the two can be closely connected; the diameter and buried depth of the occlusal pile 2 are determined according to the engineering geological conditions, the diameter is not less than 1000mm, and at least C25 ultra-retarded concrete is used For pouring, the interlocking with the adjacent piles shall not be less than 300mm; the diameter and buried depth of the interlocking piles and piles 3 shall be determined according to the engineering geological conditions, and the diameter shall not be less than 1000mm, and shall be poured with at least C45 underwater concrete. The inter-occlusion is not less than 300mm; the diameter of the rotary grouting pile 4 is the same as that of the occlusal pile, and at least ordinary portland cement with a label of 42.5 is used to tangent to the occlusal pile 3, the occlusal pile 2, and the ground-connected wall 1. The reinforcement depth is from the ground to the elevation of the occlusal pile bottom; the diameter of the steel flower tube 5 is determined according to the specific engineering geological conditions, generally A42 steel flower tubes are used, and the steel pipes are connected by welding; the diameter and buried depth of the grouting pipe 6 should be determined according to the specific engineering geological conditions If the situation is determined, the steel pipes shall be connected with threaded fasteners.

实施例2:Example 2:

本实施例将实施例1所述咬合桩与地连墙接缝处止水结构应用于某口地铁站咬合桩与地下连续墙接缝处,所述咬合桩与地连墙接缝处止水结构的主体结构包括地连墙1,墙厚800mm,幅宽6.0m,埋深26m,采用C45水下混凝土浇筑;咬合桩素桩2,直径1000mm,与相邻桩桩距700mm,咬合300mm,埋深26m,采用C25超缓凝混凝土浇筑;咬合桩硂桩3,直径1000mm,与相邻桩桩距700mm,咬合300mm,埋深26m,采用C45水下混凝土浇筑;旋喷桩4,直径1000mm,埋深26m,旋喷桩4间相互咬合300mm,与地连墙1、咬合桩素桩2、咬合桩硂桩3相切,用标号42.5的普通硅酸盐水泥浇筑;钢花管5用A42钢花管,管壁厚3mm,管壁四周为8mm压浆孔,钢花管间采用焊接,埋深26m;注浆管6用A42注浆管,管壁厚3mm,管壁四周为8mm压浆孔,注浆管间采用丝扣连接,埋深26m;咬合桩素桩2与咬合桩硂桩3桩间距700mm,咬合300mm,咬合桩素桩2与地连墙1相邻,便于与地连墙1咬合;将两根A42钢花管5绑扎在地连墙1接缝侧的钢筋笼上,埋深26m。进行地连墙1施工,使地连墙1与相邻咬合桩素桩间咬合200mm;在地连墙1与咬合桩外侧打设双排A42注浆管6,间距1m,共8根,埋深12m;在地连墙1与咬合桩外侧加设双排旋喷桩4共9根,直径1000mm,旋喷桩4间相互咬合300mm,共9根,与地连墙1、咬合桩素桩2、咬合桩荤桩3相切。In this embodiment, the water-stopping structure at the joint between the occlusal pile and the ground wall described in Example 1 is applied to the joint between the occlusal pile and the underground diaphragm wall in a certain subway station, and the water-stop at the joint between the occlusal pile and the ground wall The main structure of the structure includes the ground connection wall 1, the wall thickness is 800mm, the width is 6.0m, and the buried depth is 26m. It is poured with C45 underwater concrete; The burial depth is 26m, poured with C25 ultra-retarded concrete; 3 occlusal piles, 1000mm in diameter, 700mm away from adjacent piles, 300mm in occlusal, 26m deep, poured with C45 underwater concrete; 4 rotary grouting piles, 1000mm in diameter , with a buried depth of 26m, 4 rotary grouting piles interlocked by 300mm, tangent to the ground connection wall 1, occlusal pile 2, and occlusal pile 3, poured with ordinary Portland cement with a label of 42.5; steel flower pipe 5 with A42 Steel flower pipe, pipe wall thickness 3mm, 8mm grouting holes around the pipe wall, welding between steel flower pipes, buried depth 26m; grouting pipe 6 uses A42 grouting pipe, pipe wall thickness 3mm, 8mm grouting holes around the pipe wall , the grouting pipes are connected by screws, and the burial depth is 26m; the distance between the occlusal pile 2 and the occlusal pile 3 is 700mm, and the occlusion is 300mm. The occlusal pile 2 is adjacent to the ground wall 1, which is convenient for the ground wall 1 Bite; Bind two A42 steel flower pipes 5 to the steel cage on the joint side of the ground connection wall 1, and the depth of burial is 26m. Carry out the construction of the ground connection wall 1, so that the ground connection wall 1 and the adjacent occlusal piles are engaged by 200mm; on the outside of the ground connection wall 1 and the occlusal piles, a double row of A42 grouting pipes 6 is drilled, with a distance of 1m, a total of 8 pieces, buried The depth is 12m; on the outside of the ground connection wall 1 and the occlusal piles, a total of 9 double-row jet grouting piles 4 are added, with a diameter of 1000mm. 2. The occlusal pile and meat pile are 3 tangent.

本实施例的具体实施方法为:The concrete implementation method of this embodiment is:

步骤1:采用Φ1000@700mm套管咬合桩,进行咬合桩的施工时,与地连墙1相邻的咬合桩为素桩2,便于地连墙1与相邻咬合桩素桩2间咬合;放线定位后,钻机就位,取土成孔直至设计孔底标高,如为咬合桩硂桩在成孔检查合格后吊放钢筋笼,后浇筑混凝土拔管成桩;Step 1: Use Φ1000@700mm casing occlusal piles. When constructing occlusal piles, the occlusal pile adjacent to ground connection wall 1 is plain pile 2, which facilitates the interlocking between ground connection wall 1 and adjacent occlusal pile plain piles 2; After laying out and positioning, the drilling rig is in place, and the soil is taken to form a hole until the design hole bottom elevation. For the occlusal pile, the steel cage is lifted after the hole inspection is qualified, and then the concrete is poured and the pipe is pulled out to form a pile;

步骤2:地连墙成槽的准备工作,进行地连墙1的放线定位及导墙施工,制备泥浆,然后试成槽,试成槽具体施工过程同正常成槽施工;Step 2: Preparation of the ground connection wall for groove formation, the setting-out positioning of the ground connection wall 1 and the construction of the guide wall, the preparation of mud, and then a test groove. The specific construction process of the test groove is the same as the normal groove construction;

步骤3:地连墙常规成槽,根据设计图纸及导墙确定地连墙1位置,成槽机进行开挖作业,本实例中用徐工480型液压抓斗成槽机成槽,成槽时采用泥浆护壁,直至深度与相邻咬合桩埋深相同,再进行槽孔验收;Step 3: The ground connection wall is conventionally grooved, and the position of the ground connection wall 1 is determined according to the design drawings and the guide wall, and the groove forming machine is used for excavation. In this example, the XCMG 480 hydraulic grab groove machine is used to form the groove. Use mud to protect the wall until the depth is the same as the buried depth of adjacent occlusal piles, and then carry out slot hole acceptance;

步骤4:地连墙1成槽时,靠近咬合桩素桩2一侧采用旋挖钻扩大成槽墙体宽度至1000mm,确保浇筑混凝土时,混凝土能绕流过槽钢背面,与咬合桩素桩2紧密结合,使咬合桩素桩2与地连墙1间的连接更牢固;Step 4: When the ground connection wall 1 is grooved, use a rotary drill to expand the width of the grooved wall to 1000mm on the side close to the interlocking pile plain pile 2, so as to ensure that the concrete can flow around the back of the channel steel when pouring concrete, and connect with the interlocking pile element. The piles 2 are tightly combined, so that the connection between the occlusal pile plain pile 2 and the ground connection wall 1 is firmer;

步骤5:采用旋挖钻钻除部分接缝处咬合桩素桩2,使地连墙1与相邻咬合桩素桩2至少有300mm咬合,过程中注意控制泥浆比重在1.1g/cm3~1.25g/cm3,确保孔壁不塌孔,直至墙底高程为止,所述泥浆采用膨润土、纯碱、CMC、重晶石、防漏剂和自来水作原料,原料配比为100:4:1:1:2:1000,通过清浆冲拌和混合搅拌二次拌合而成;Step 5: Use the rotary drilling drill to remove the occlusal piles 2 at some joints, so that the ground connection wall 1 and the adjacent occlusal piles 2 have at least 300 mm of occlusal. During the process, pay attention to controlling the specific gravity of the mud at 1.1g/cm 3 ~ 1.25g/cm 3 , to ensure that the hole wall does not collapse until the bottom of the wall is reached. The mud uses bentonite, soda ash, CMC, barite, anti-leakage agent and tap water as raw materials, and the ratio of raw materials is 100:4:1 : 1: 2: 1000, it is formed through the second mixing of cleaning slurry, mixing and mixing;

步骤6:地连墙1成槽后进行清底、清孔作业,本实例采用旋挖钻捞抓法清底。捞抓完成后,采用正循环进行清孔作业,保证槽底沉渣不大于50mm,清孔后槽底泥浆比重不大于1.15;Step 6: Clean the bottom and clean the holes after the ground connection wall 1 is grooved. In this example, the rotary drilling and fishing method is used to clean the bottom. After the fishing is completed, use positive circulation to clean the hole to ensure that the sediment at the bottom of the tank is not greater than 50mm, and the specific gravity of the mud at the bottom of the tank after cleaning the hole is not greater than 1.15;

步骤7:成槽后,采用钢丝刷反复清理相邻成品桩素桩2侧壁,确保侧壁不粘泥,确保墙体间连接紧密,采用刷壁器上下往复洗刷不少于20次,刷完壁后及时将刷壁器上的泥皮清洗干净,并检查钢丝状况,如有损耗应及时修补;。Step 7: After the groove is formed, use a wire brush to repeatedly clean the side walls of the adjacent finished pile plain pile 2 to ensure that the side walls are not sticky and the walls are tightly connected. After the wall is finished, clean the mud on the wall brusher in time, and check the condition of the steel wire, and repair it in time if there is any loss;

步骤8:进行钢筋笼的制作,制作前先钢筋除锈,采用胎具法成型工艺制作钢筋笼,焊接时严格控制焊接质量,应根据咬合桩素桩2位置及直径确定钢筋笼制作宽度,便于地连墙1与相邻咬合桩2咬合;Step 8: Carry out the production of the reinforcement cage, remove the rust of the reinforcement before the production, use the molding method to manufacture the reinforcement cage, strictly control the welding quality during welding, and determine the width of the reinforcement cage according to the position and diameter of the occlusal pile plain pile 2, which is convenient The ground connection wall 1 is engaged with the adjacent occlusal pile 2;

步骤9:在地连墙墙体1与相邻咬合桩素桩2之间埋设2根钢花管5,两根钢花管5间用焊接连接,绑扎在接缝侧钢筋笼上,两根钢花管5平行布置,间距400mm,埋设至地连墙墙底设计高度,便于砼浇筑进行注浆止水补强,导管位置应适当靠近接缝槽钢;Step 9: Lay two steel flower tubes 5 between the ground wall body 1 and the adjacent occlusal pile 2, and connect the two steel flower tubes with welding, and bind them to the reinforcement cage on the side of the seam, and the two steel flower tubes 5 Arranged in parallel, with a spacing of 400mm, buried to the design height of the bottom of the ground connection wall, which is convenient for concrete pouring for grouting, water sealing and reinforcement, and the position of the conduit should be appropriately close to the joint channel steel;

步骤10:进行钢筋笼吊装,吊装时控制该段钢筋笼槽钢位置尽量靠近已成桩咬合桩桩体2,减少之间空隙,使浇筑混凝土后地连墙1与相邻咬合桩素桩2间连接牢固;Step 10: Hoist the reinforcement cage. During hoisting, control the position of the channel steel of this section of the reinforcement cage as close as possible to the occlusal pile body 2 of the completed pile to reduce the gap between them, so that the ground connection wall 1 and the adjacent occlusal pile plain pile 2 after pouring concrete The connection is firm;

步骤11:采用C45水下混凝土浇筑该段墙体混凝土,浇筑时注意确保水下砼较好的流动性,确保砼墙体质量,开浇后需保证混凝土连续浇注,在接头部位浇注中,使导管做30cm上下运动,确保浇筑质量;Step 11: Use C45 underwater concrete to pour the concrete of this section of the wall. When pouring, pay attention to ensure the good fluidity of the underwater concrete to ensure the quality of the concrete wall. After the pouring, the continuous pouring of the concrete must be ensured. The conduit moves 30cm up and down to ensure the pouring quality;

步骤12:沿接缝外侧打设双排注浆管6,进行注浆施工,保证该接缝止水加强,地连墙1混凝土浇筑完成后,在咬合桩素桩2与地连墙1接缝外侧打设双排A42注浆管,间距1m,共8根,钢管间采用丝扣连接,管壁厚度3mm,本工程加固深度至地面下12m,伸入粉质粘土层1m;采用钻孔机在地连墙与咬合桩接缝的外侧成孔,然后用人工将注浆管垂直打入成孔内;进行注浆作业时,注浆压力控制在2~4Mpa,配制浆液所用水泥为标号42.5普通硅酸盐水泥,先采用重量比为1:1的水泥浆试注两个孔,如可注性较好,调整水灰比至0.5~0.6的比例;Step 12: Drill double rows of grouting pipes 6 along the outside of the joint, and carry out grouting construction to ensure that the joint is watertight and strengthened. Double rows of A42 grouting pipes are drilled on the outside of the seam, with a distance of 1m, a total of 8 pieces. The steel pipes are connected by screws, and the thickness of the pipe wall is 3mm. The reinforcement depth of this project is 12m below the ground and 1m into the silty clay layer; The machine makes a hole on the outside of the joint between the ground connection wall and the occlusal pile, and then manually drives the grouting pipe vertically into the hole; during the grouting operation, the grouting pressure is controlled at 2-4Mpa, and the cement used to prepare the grout is the label 42.5 Ordinary Portland cement, first use cement slurry with a weight ratio of 1:1 to inject two holes, if the injectability is good, adjust the water-cement ratio to 0.5-0.6;

步骤13:地连墙1施工完成3天后,对预埋钢花管5进行注水,以保证注浆管路的畅通及环状管的劈裂,为以后注水泥浆做好准备,注水时,随时注意水面的下降位置及压浆泵的输出压力,压水不宜太多也不宜太少,疏通后用带压力表的注浆泵注浆,浆液用标号42.5的普通硅酸盐水泥配制,注浆压力为2~4Mpa,先采用重量比为1:1的水泥浆试注两个孔,空隙较大则可调整水灰比至0.5~0.6的比例;Step 13: Three days after the construction of the ground connection wall 1 is completed, inject water into the pre-embedded steel flower tube 5 to ensure the smooth flow of the grouting pipeline and the splitting of the annular tube, and prepare for the grouting in the future. When injecting water, pay attention at any time The lowering position of the water surface and the output pressure of the grouting pump should not be too much or too little. After dredging, use a grouting pump with a pressure gauge to grout. The grout is prepared with ordinary Portland cement with a label of 42.5. 2-4Mpa, first use cement slurry with a weight ratio of 1:1 to try to inject two holes, if the gap is large, adjust the water-cement ratio to 0.5-0.6;

步骤14:在咬合桩素桩2与地连墙1外侧处采用双排旋喷桩4加固,本实例中旋喷桩4共设9根,桩间咬合300mm,放线定位时避开咬合桩与地连墙接头外侧埋设的双排注浆管,钻孔时采用泥浆护壁回转钻进,维持孔壁稳定,采用标号42.5的普通硅酸盐水泥,加固深度为地面至地下连续墙1墙底设计标高;Step 14: Use double-row jet grouting piles 4 on the outer side of the occlusal piles 2 and the ground connection wall 1. In this example, there are 9 rotary grouting piles 4, and the occlusion between the piles is 300mm. Avoid the occlusal piles when positioning the lines The double-row grouting pipes buried outside the joint with the ground connection wall are drilled with mud retaining wall rotary drilling to maintain the stability of the hole wall. Ordinary Portland cement with a label of 42.5 is used, and the reinforcement depth is from the ground to the bottom of the underground diaphragm wall 1 design elevation;

步骤15:如果后期接缝出现渗流现象,可以对墙面进行剔凿清理,然后用双快水泥进行封堵;严重时剔凿清理漏水点,插入导流管,涂抹封堵材料(封堵灵、快硬水泥等),封堵导流管,最后在围护结构外侧或漏水点下方进行注浆处理,补充注浆加固,渗漏水封堵完成后继续开挖。Step 15: If there is seepage in the joints in the later stage, you can chisel and clean the wall, and then use Shuangkuai cement to seal it; if it is serious, chisel to clean the leaking point, insert the diversion tube, and apply the sealing material (sealing spirit , rapid hardening cement, etc.), block the diversion pipe, and finally perform grouting treatment on the outside of the enclosure structure or below the leakage point, supplement grouting reinforcement, and continue excavation after the leakage water is sealed.

本实施例所述注浆用的注浆材料选用425#抗硫酸盐水泥(抵抗硫酸盐侵蚀),水灰比为0.5,浆液中掺加0.2%的玄武岩纤维提高抗裂性能(纤维单丝直径12=3um,密度2.65kg/m3,平均长度6mm,抗拉强度2000MPa,弹性模量90GPa,极限延伸率3.5%)。The grouting material used for grouting described in this embodiment selects 425# sulfate-resistant cement (resistance to sulfate erosion), and the water-cement ratio is 0.5, and 0.2% basalt fiber is added in the slurry to improve crack resistance (fiber monofilament diameter 12=3um, density 2.65kg/m3, average length 6mm, tensile strength 2000MPa, elastic modulus 90GPa, ultimate elongation 3.5%).

本实施例所述护壁用泥浆的配比(%)为水∶膨润土∶羧甲基纤维素∶重晶石=100∶10∶0.3∶0.02,其中,控制槽内液面标高高于地下水位1m;泥浆比重控制在1.05~1.15之间;泥浆粘度控制在20~22s;泥浆PH值不超过10.5,具有浮悬钻渣、冷却钻头、润滑钻具的作用,能增大静水压力,并在槽壁形成泥皮,隔断槽内外渗流,防止护壁防塌。The proportioning (%) of the wall protection mud described in this embodiment is water: bentonite: carboxymethyl cellulose: barite=100: 10: 0.3: 0.02, wherein the liquid level in the control tank is higher than the groundwater level by 1m The specific gravity of the mud is controlled between 1.05 and 1.15; the viscosity of the mud is controlled between 20 and 22s; the PH value of the mud does not exceed 10.5, and it has the functions of suspending drilling slag, cooling the drill bit, and lubricating the drilling tool, and can increase the hydrostatic pressure. The wall forms a mud skin, and the seepage inside and outside the partition groove prevents the retaining wall from collapsing.

Claims (3)

1. a kind of interlocking pile and ground-connecting-wall seam crossing water-stopping method, it is characterised in that pass through interlocking pile and ground-connecting-wall seam crossing sealing Structure realization, detailed process are as follows:
Step 1: carrying out the construction of interlocking pile, being engaged with ground-connecting-wall is interlocking pile element stake, and after unwrapping wire positioning, drilling machine is in place, takes For native pore-forming until design bottom hole absolute altitude, for example Yao He Zhuan Quan hang steel reinforcement cage, after-pouring concrete after pore-forming passed examination Tube drawing pile;
Step 2: the preparation of ground-connecting-wall construction positions construction of guide wall, preparation using the unwrapping wire that prior art carries out ground-connecting-wall Then mud tries grooving;
Step 3: ground-connecting-wall routine grooving according to design requirement and leads the position that wall determines ground-connecting-wall, and chute forming machine carries out excavation work Industry uses mud off when grooving, until depth is identical as adjacent interlocking pile buried depth, and carries out an acceptance inspection to slot;
Step 4: when ground-connecting-wall grooving, grooving width of wall body at least 200mm is expanded using churning driven close to interlocking pile element stake side, When ensuring casting concrete, concrete can combine closely around the channel steel back side is flowed through with interlocking pile element stake, make the stake of interlocking pile element and ground Even it is connected firmly between wall;
Step 5: being bored using churning driven except interlocking pile element stake at Partial seams, make ground-connecting-wall and adjacent interlocking pile element stake at least 300mm is engaged, and pays attention to control mud balance in 1.1g/cm in work progress3~1.25g/cm3, until the elevation of wall bottom;
Step 6: clear bottom, borehole cleaning operation are carried out after grooving, using fishing method is grabbed, direct circulation borehole cleaning operation is can be used in borehole cleaning at clear bottom, to Stop clear bottom after the completion of mud displacement in slot;
Step 7: after grooving, clearing up adjacent interlocking pile element stake side wall repeatedly using wire brush, it is ensured that side wall not foundry loam, it is ensured that with ground Even wall is completely embedded, and is up and down reciprocatingly scrubbed no less than 20 times using brush wall device, has been brushed in time that the mudcake on brush wall device is clear after wall Wash clean, and check steel wire situation, such as lossy timely repairing;
Step 8: carrying out the production of steel reinforcement cage, first derust to reinforcing bar before production, steel reinforcement cage, weldering are made using mould method moulding process Strict control welding quality when connecing determines fabrication of reinforcing cage width according to interlocking pile element stake position;
Step 9: two steel floral tubes are buried between ground-connecting-wall wall and adjacent interlocking pile element stake, after welding between two steel floral tubes With on the steel reinforcement cage of interlocking pile element stake side, two steel floral tube parallel arrangements are buried to ground-connecting-wall wall bottom design height, are convenient for for binding Casting concrete carries out ejection for water plugging reinforcement, and Grouting Pipe position should be appropriate at seam channel steel;
Step 10: carrying out the lifting of steel reinforcement cage, when lifting controls this section of steel reinforcement cage channel steel position as close as possible to pile interlocking pile Plain stake, the gap between reduction, it is firm to make to connect between ground-connecting-wall and interlocking pile element stake;
Step 11: pouring this section of walls concrete, pay attention to ensuring Underwater Concrete preferable mobility when pouring, it is ensured that concrete wall matter Amount, opening needs to guarantee concrete continuous casting after pouring, and in joint area casting, so that Grouting Pipe is done 30cm up and down motion, it is ensured that pour Build quality;
Step 12: double rows slip casting pipe, the quantity and spacing root of Grouting Pipe are set on the outside of ground-connecting-wall and the seam of interlocking pile element stake It is determined according to concrete engineering geological hydrology condition, carries out mortar depositing construction, guarantee that the joint seal is reinforced;
Step 13: after ground-connecting-wall construction is completed 3 days, pre-buried steel floral tube being filled the water, to guarantee the unimpeded and ring of grouting pipeline The splitting of shape pipe, is ready for cement injection, when water filling, pays attention to the down position of the water surface and the output pressure of mudjack at any time The MPa of 0.5 MPa~0.7, pressure water should not be also unsuitable very little too much, and the water filling dredging post-infusion cement slurry of steel floral tube 5 is reinforced, it is ensured that is connect Sealing quality at seam.
Step 14: being reinforced in the stake of interlocking pile element and ground-connecting-wall outside using double rotary churning pile, the diameter and quantity root of rotary churning pile It is determined according to concrete engineering geological hydrology condition, 200mm is at least engaged between rotary churning pile stake, and unwrapping wire avoids interlocking pile and ground even when positioning Inbuilt double rows slip casting on the outside of wall joint uses mud off rotary drilling when drilling, and hole wall is maintained to stablize, and at least uses label 42.5 ordinary portland cement, reinforcement depth are ground to underground continuous wall bottom designed elevation;
Step 15: if percolation phenomenon occurs in later period seam, metope being carried out to pick chisel cleaning, is then sealed with double-quick cement It is stifled;Chisel cleaning leakage point is picked when serious, is inserted into diversion pipe, is smeared plugging material and is blocked diversion pipe, finally on the outside of building enclosure Or injecting treatment is carried out below leakage point, grouting and reinforcing is supplemented, percolating water can continue to excavate after the completion of blocking.
2. interlocking pile and ground-connecting-wall seam crossing water-stopping method according to claim 1, it is characterised in that the interlocking pile and ground Even wall seam crossing water sealing structure main structure include ground-connecting-wall, the stake of interlocking pile element, Yao He Zhuan Quan, rotary churning pile, steel floral tube and Grouting Pipe;Yao He Zhuan Quan are alternatively arranged with interlocking pile element stake, are mutually twisted to form interlocking pile, ground-connecting-wall and adjacent interlocking pile element Stake occlusion, diaphram wall buried depth are identical as adjacent interlocking pile element stake buried depth;Steel floral tube is welded on ground-connecting-wall and adjacent interlocking pile On the steel reinforcement cage of plain stake sides adjacent, buried depth is identical as ground-connecting-wall buried depth;Grouting Pipe is embedded in the stake of interlocking pile element and ground-connecting-wall seam Place outside, buried depth are determined according to concrete engineering geological conditions;Rotary churning pile is located on the outside of the stake of interlocking pile element and ground-connecting-wall seam crossing, is buried It is deep identical as ground-connecting-wall buried depth.
3. interlocking pile and ground-connecting-wall seam crossing water-stopping method according to claim 2, it is characterised in that the thickness of the ground-connecting-wall Degree, breadth and buried depth determine that diaphram wall breadth is not more than 6m according to the size of concrete engineering geological condition and interlocking pile, bury Depth is 10m to 50m, with a thickness of 0.5m to 1.2m, and is less than adjacent interlocking pile element stake diameter at least 200mm, so that the two is close Connection;The diameter and buried depth of interlocking pile element stake determine that diameter is not less than 1000mm according to engineering geological condition, at least super with C25 Retarded concrete pours, and is engaged between adjacent studs stake not less than 300mm;The diameter and buried depth of Yao He Zhuan Quan should according to engineering Matter condition determines that diameter is engaged not small not less than 1000mm at least with the underwater coagulation concreting of C45 between adjacent studs stake In 300mm;The diameter of rotary churning pile is identical as interlocking pile diameter, the ordinary portland cement of label 42.5 is at least used, with interlocking pile Quan, the stake of interlocking pile element, ground-connecting-wall stake it is tangent, reinforcement depth is ground to interlocking pile stake bottom absolute altitude;The diameter of steel floral tube according to Concrete engineering geological condition determines, generally uses A42 steel floral tube, uses and be welded to connect between steel pipe;Diameter, the buried depth of Grouting Pipe are answered It should be determined according to concrete engineering geological condition, screwed connection is used between steel pipe.
CN201910669418.4A 2019-07-24 2019-07-24 Water-stopping method at joint between occlusal pile and ground connecting wall Expired - Fee Related CN110409511B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910669418.4A CN110409511B (en) 2019-07-24 2019-07-24 Water-stopping method at joint between occlusal pile and ground connecting wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910669418.4A CN110409511B (en) 2019-07-24 2019-07-24 Water-stopping method at joint between occlusal pile and ground connecting wall

Publications (2)

Publication Number Publication Date
CN110409511A true CN110409511A (en) 2019-11-05
CN110409511B CN110409511B (en) 2021-10-08

Family

ID=68362672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910669418.4A Expired - Fee Related CN110409511B (en) 2019-07-24 2019-07-24 Water-stopping method at joint between occlusal pile and ground connecting wall

Country Status (1)

Country Link
CN (1) CN110409511B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112095582A (en) * 2020-09-24 2020-12-18 叶倩文 Impervious concrete precast pile based on acid soil
CN112962578A (en) * 2021-02-03 2021-06-15 上海兴庚基础工程有限公司 Construction process of underground diaphragm wall
CN114718071A (en) * 2021-12-30 2022-07-08 中铁十四局集团有限公司 Plugging method suitable for junction of secant pile and continuous wall
CN115928737A (en) * 2022-11-30 2023-04-07 广西容梧高速公路有限公司 A construction method and system for eliminating the weakening effect of pile-wall joint mud skin
CN116624159A (en) * 2023-05-12 2023-08-22 中铁隧道局集团有限公司 The Method of Changing Tool of Shield Under Normal Pressure in Water-rich Sand and Pebble Stratum
CN116971364A (en) * 2023-07-27 2023-10-31 上海市基础工程集团有限公司 Construction method of joint connection between underground diaphragm wall and bite pile in deep foundation pit project

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0347320A (en) * 1989-04-11 1991-02-28 Mitsui Constr Co Ltd Base structure by inverted placing method
JPH0959984A (en) * 1995-08-28 1997-03-04 Kajima Corp Simple underground construction structure
CN103726513A (en) * 2013-12-12 2014-04-16 安徽省建筑科学研究设计院 Waterproof structure for underground diaphragm wall joint and construction method thereof
CN104153396A (en) * 2014-07-17 2014-11-19 中国十七冶集团有限公司 Anti-seepage continuous wall construction method
CN104404960A (en) * 2014-11-26 2015-03-11 中建三局第二建设工程有限责任公司 Grouting device for joint of underground diaphragm wall and construction method
CN105780815A (en) * 2015-12-09 2016-07-20 中建七局(上海)有限公司 Anti-seepage construction device and method for continuous wall
CN105862875A (en) * 2016-04-15 2016-08-17 肖锐 Support structure and construction method thereof
CN206916753U (en) * 2017-07-14 2018-01-23 浙江之江工程项目管理有限公司 A kind of water sealing structure of diaphram wall and its seam crossing
CN109208637A (en) * 2018-08-08 2019-01-15 北京建工土木工程有限公司 Increase the construction method of open-cut station newly on the basis of existing tunnel

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0347320A (en) * 1989-04-11 1991-02-28 Mitsui Constr Co Ltd Base structure by inverted placing method
JPH0959984A (en) * 1995-08-28 1997-03-04 Kajima Corp Simple underground construction structure
CN103726513A (en) * 2013-12-12 2014-04-16 安徽省建筑科学研究设计院 Waterproof structure for underground diaphragm wall joint and construction method thereof
CN104153396A (en) * 2014-07-17 2014-11-19 中国十七冶集团有限公司 Anti-seepage continuous wall construction method
CN104404960A (en) * 2014-11-26 2015-03-11 中建三局第二建设工程有限责任公司 Grouting device for joint of underground diaphragm wall and construction method
CN105780815A (en) * 2015-12-09 2016-07-20 中建七局(上海)有限公司 Anti-seepage construction device and method for continuous wall
CN105862875A (en) * 2016-04-15 2016-08-17 肖锐 Support structure and construction method thereof
CN206916753U (en) * 2017-07-14 2018-01-23 浙江之江工程项目管理有限公司 A kind of water sealing structure of diaphram wall and its seam crossing
CN109208637A (en) * 2018-08-08 2019-01-15 北京建工土木工程有限公司 Increase the construction method of open-cut station newly on the basis of existing tunnel

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112095582A (en) * 2020-09-24 2020-12-18 叶倩文 Impervious concrete precast pile based on acid soil
CN112095582B (en) * 2020-09-24 2021-12-31 山东中能杆塔有限公司 Impervious concrete precast pile based on acid soil
CN112962578A (en) * 2021-02-03 2021-06-15 上海兴庚基础工程有限公司 Construction process of underground diaphragm wall
CN114718071A (en) * 2021-12-30 2022-07-08 中铁十四局集团有限公司 Plugging method suitable for junction of secant pile and continuous wall
CN114718071B (en) * 2021-12-30 2024-02-23 中铁十四局集团有限公司 Plugging method suitable for junction of occluding pile and continuous wall
CN115928737A (en) * 2022-11-30 2023-04-07 广西容梧高速公路有限公司 A construction method and system for eliminating the weakening effect of pile-wall joint mud skin
CN115928737B (en) * 2022-11-30 2025-02-11 广西容梧高速公路有限公司 A construction method and system for eliminating mud skin weakening effect at pile-wall joints
CN116624159A (en) * 2023-05-12 2023-08-22 中铁隧道局集团有限公司 The Method of Changing Tool of Shield Under Normal Pressure in Water-rich Sand and Pebble Stratum
CN116971364A (en) * 2023-07-27 2023-10-31 上海市基础工程集团有限公司 Construction method of joint connection between underground diaphragm wall and bite pile in deep foundation pit project

Also Published As

Publication number Publication date
CN110409511B (en) 2021-10-08

Similar Documents

Publication Publication Date Title
CN106284313B (en) Long spire based on circulating mud retaining wall is squeezed into rock filling pile construction method
CN110409511B (en) Water-stopping method at joint between occlusal pile and ground connecting wall
CN110409510B (en) Water stopping structure at joint of engagement pile and ground continuous wall
CN204000956U (en) A kind of basement bottom plate rear pouring tape structure
CN104711994A (en) Foundation pit deep well rainfall and plugging construction method
CN106545005A (en) A kind of reinforcing body and reinforcement means of subway tunnel shield termination
CN109113068A (en) A kind of inverse construction joint structure for building construction of deep basal pit
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
CN104846810A (en) Self-circulating posterior grouting bored pile construction method
CN104099946B (en) Inspection-pit between a kind of Novel top pipeline section
CN103321246A (en) Construction Method of Foundation Pit Using Underground Diaphragm Wall
CN110700280B (en) A diversion device and construction method for foundation pit support construction in narrow areas
CN202194149U (en) Waterproof curtain
CN211898541U (en) Guide wall structure for reinforced structure of air shaft initial end head
CN112176954A (en) Construction method for newly excavated channel
CN100387790C (en) Ground caisson construction technology and ground caisson
CN105178342B (en) Precipitation well casing and method for blocking reserved hole of foundation pit through precipitation well casing
CN105484277A (en) Component for tubular well precipitation construction in elevator foundation pit or sump and construction method
CN112176953A (en) Construction method for newly-built channel
CN205205844U (en) Member is used in construction of tubular well precipitation in elevator foundation ditch or sump pit
CN114575355B (en) Soil protection construction method
CN108035357A (en) Filling pile construction scheme and its funnel
CN118704502A (en) A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building
CN113175350B (en) A construction method for wastewater pumping station in water-rich sand layer
CN115977068A (en) Construction method of plastic concrete deep impervious wall of cross-strong-leakage easy-collapse backfill stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20210906

Address after: 266000 No.89 Donghai East Road, Laoshan District, Qingdao City, Shandong Province

Applicant after: NO.4 engineering corporation limited of cr20g

Applicant after: Qingdao University of Technology

Address before: 266000 No.89 Donghai East Road, Laoshan District, Qingdao City, Shandong Province

Applicant before: NO.4 engineering corporation limited of cr20g

GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211008