CN109930620A - The construction method of water-stop curtain pile foundation and pile foundation unit is built using waste mud - Google Patents

The construction method of water-stop curtain pile foundation and pile foundation unit is built using waste mud Download PDF

Info

Publication number
CN109930620A
CN109930620A CN201910138829.0A CN201910138829A CN109930620A CN 109930620 A CN109930620 A CN 109930620A CN 201910138829 A CN201910138829 A CN 201910138829A CN 109930620 A CN109930620 A CN 109930620A
Authority
CN
China
Prior art keywords
mud
stake holes
pile foundation
water
stop curtain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910138829.0A
Other languages
Chinese (zh)
Inventor
胡宝山
刘喜林
薛长江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Zhiping Foundation Engineering Co Ltd
Original Assignee
Shanghai Zhiping Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Zhiping Foundation Engineering Co Ltd filed Critical Shanghai Zhiping Foundation Engineering Co Ltd
Priority to CN201910138829.0A priority Critical patent/CN109930620A/en
Publication of CN109930620A publication Critical patent/CN109930620A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a kind of construction methods that water-stop curtain pile foundation and pile foundation unit are built using waste mud.Construction method using waste mud construction water-stop curtain pile foundation of the invention includes: to be drilled with the first stake holes using mud, mud in first stake holes is extracted to dirty mud sump, desanding processing is carried out to the waste mud in the dirty mud sump and obtains pure mud, pure mud is sent into stirring pool, cement is injected into the stirring pool, it stirs to obtain the mixed liquor of cement Yu pure mud, the cement slurry is extracted to first stake holes, stirring is to be uniformly mixed, to solidify to form the first pile foundation.Construction method using waste mud construction water-stop curtain pile foundation of the invention can reduce environmental pollution, and use manpower and material resources sparingly.

Description

The construction method of water-stop curtain pile foundation and pile foundation unit is built using waste mud
Technical field
The present invention relates to water-stop curtain field more particularly to a kind of utilization waste mud construction water-stop curtain pile foundations and pile foundation The construction method of unit.
Background technique
Water-stop curtain refers to a concept, is the general name of project subject periphery sealing series, project subject, which refers to, to be based on On foundation, receive, undertake and transmit all upper loads of construction project, maintains structural integrity, stability and safety The bearing structural system of property.Water-stop curtain is a kind of continuous water sealing structure, water-stop curtain is arranged around foundation pit, foundation pit is In the heatable adobe sleeping platform that the position of construction project main body is excavated, the underground water for preventing or reducing foundation pit side-wall and foundation pit bottom flows into base Hole.
The construction method of existing construction water-stop curtain pile foundation is that stake holes is first arranged, and the mud in stake holes is extracted, Then it will be transported to rivers,lakes and seas or disposal site outside these waste muds, the concrete of liquid then will be inserted in stake holes, from And form a pile foundation.But mud caused by the construction method of existing construction water-stop curtain pile foundation causes largely Useless sludge-polluted environment, while a large amount of manpower and material resources can be also expended during transporting outward.
Summary of the invention
The purpose of the present invention is to provide a kind of constructions that water-stop curtain pile foundation and pile foundation unit are built using waste mud Method can reduce pollution of the waste mud to environment, and avoid and all transport outward waste mud, to save manpower object Power, it is environmentally protective.
The present invention first aspect provide it is a kind of using waste mud construction water-stop curtain pile foundation construction method, including with Lower step:
S1, the first stake holes is drilled with using mud;
S2, mud in first stake holes is extracted to dirty mud sump;
S3, desanding processing is carried out to the waste mud in the dirty mud sump and obtains pure mud;
S4, pure mud is sent into stirring pool;
Cement is injected in S5, Xiang Suoshu stirring pool;
S6, it stirs to obtain the mixed liquor of cement Yu pure mud;
S7, the cement slurry is extracted to first stake holes, stirring is to be uniformly mixed, to solidify to form the first pile foundation.
In a kind of feasible scheme, in step sl, specifically includes the following steps:
The predeterminated position of S1001, selected first stake holes;
S1002, first stake holes is drilled in the predetermined position using pore-forming drill cooperation mud.
In a kind of feasible scheme, in step s 2, specifically includes the following steps:
S2001, mud is injected in first stake holes by borer drill rod using the first slush pump;
S2002, drilling tool is protruded into first stake holes, and controls the drilling tool rotation;
S2003, promotion and the drilling tool that sinks, clod and sediment for taking out of in first stake holes;
S2004, it proposes drilling tool and transfers conduit;
S2005, mud is injected into the pumping of the mud in first stake holes by the conduit using first slush pump To waste pulp pond.
It is further comprising the steps of after step S2005 in a kind of feasible scheme:
S2006, mud is injected into first stake holes by the aperture of first stake holes using first slush pump It is interior;
S2007, the drilling tool is protruded into first stake holes, and controls the drilling tool rotation;
S2008, promotion and the drilling tool that sinks, mud is taken out of out of drilling rod by high pressure slurry pump in first stake holes Clod and sediment in first stake holes;
S2009, after inner hole deposition slag is met the requirements, lift the drilling tool;
S2010, mud is injected in first stake holes using first slush pump, mud is logical in first stake holes It crosses first slush pump and takes clod and sediment out of out of described first stake holes.
In a kind of feasible scheme, in step s 2, specifically includes the following steps:
S221, wash away water filling to the first stake holes inner surface using the first water pump, water injection pressure is 0.3~ 0.6Mpa, and fill the water the water surface and be lower than first stake holes, to obtain dilution mud;
S222, the dilution mud in first stake holes is drawn in the dirty mud sump using the second slush pump, institute The driving power for stating the second slush pump is 15KW, and straw diameter 60mm~80mm, flow is 150L/min~250L/min.
Further include the following steps after step S222 in a kind of feasible scheme:
S223, the sucker of airlift suction dredger is protruded into first stake holes, and the sucker is apart from first stake holes bottom The distance in portion is greater than 10cm and is less than 1m;
S224, the starting airlift suction dredger, the sediment of first stake holes bottom and drilling cuttings are extracted out;
The airlift suction dredger is closed after S225,3min, and the sucker is extracted into first stake holes.
In a kind of feasible scheme, in step in S3, specifically includes the following steps:
S3001, the mud in the dirty mud sump is drawn in mud desander by third slush pump, the third The driving power of slush pump is 15KW, and straw diameter 60mm~80mm, flow is 150L/min~250L/min;
S3002, the mud in the dirty mud sump is subjected to desanding processing to obtain pure mud using mud desander It starches, vibrating screen is equipped in the mud desander, the sieve mesh number of the vibrating screen is 80~160 mesh, the vibration of the vibrating screen Dynamic frequency is 650~800 beats/min.
In a kind of feasible scheme, in the step s 7, specifically includes the following steps:
The specific gravity of addition yellow sand in S7001, Xiang Suoshu stirring pool, the mixed liquor and the yellow sand is 4:5;
The specific gravity of addition stone in S7002, Xiang Suoshu stirring pool, the mixed liquor and the stone is 4:7.
In a kind of feasible scheme, in the step s 7, specifically includes the following steps:
S701, the first backing plate is placed at first stake holes, first backing plate includes: fill orifice and two steel plugs Hole;
S702, two steel plugs are filled in into described two steel consents;
S703, it extracts the liquid concrete in stirring pool and is perfused to the fill orifice;
S704, after concrete reaches initial set, by described two steel plugs extract out, to form the first pile foundation.
The present invention provides a kind of construction method of water-stop curtain pile foundation unit in second aspect, specifically includes following step It is rapid:
S100, the construction as claimed in any of claims 1 to 9 using waste mud construction water-stop curtain pile foundation Method makes the first pile foundation;
S101, the second stake holes is drilled at the position apart from a stake diameter distance of first pile foundation;
S102, mud in second stake holes is extracted to the dirty mud sump;
S103, desanding processing is carried out to the waste mud in the dirty mud sump and obtains pure mud;
S104, pure mud is sent into stirring pool;
Cement is injected in S105, Xiang Suoshu stirring pool, and the specific gravity of cement and mud is 0.2~0.4;
S106, it stirs to obtain the mixed liquor of cement Yu pure mud;
S107, liquid concrete is prepared according to the mixed liquor in the stirring pool, until obtaining liquid concrete;
S108, the second backing plate identical with first backing plate is placed at second stake holes;
S109, steel plug is filled in into described two steel consents;
S110, it extracts the liquid concrete in the stirring pool and is perfused to the fill orifice;
S111, after concrete reaches initial set, steel plug is extracted out, to form the second pile foundation;
S112, third stake holes is drilled between first pile foundation and second pile foundation;
S113, mud in the third stake holes is extracted to the dirty mud sump;
S114, desanding processing is carried out to the waste mud in the dirty mud sump and obtains pure mud;
S115, pure mud is sent into the stirring pool;
Cement is injected in S116, Xiang Suoshu stirring pool, and the specific gravity of cement and mud is 0.2~0.4;
S117, it stirs to obtain the mixed liquor of cement Yu pure mud;
S118, liquid concrete is prepared according to the mixed liquor in the stirring pool, until obtaining liquid concrete;
S119, it extracts the liquid concrete in the stirring pool and is perfused to the third stake holes, to form the prism of third order Base, the third pile foundation are connected with first pile foundation and second pile foundation, to form water-stop curtain pile foundation unit.
Based on above scheme it is found that the construction method provided by the invention using waste mud construction water-stop curtain pile foundation, first The waste mud extracted out out of first stake holes progress desanding is largely utilized after desanding when making liquid concrete Waste mud, avoid and all transport outward waste mud, to save manpower and material resources, meanwhile, greatly reduce waste mud pair The pollution of environment, it is environmentally protective.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is this hair Bright some embodiments for those of ordinary skill in the art without any creative labor, can be with It obtains other drawings based on these drawings.
Fig. 1 is the flow chart of the construction method that water-stop curtain pile foundation is built using waste mud in the embodiment of the present invention one;
Fig. 2 is the plane structure chart of the first backing plate in the embodiment of the present invention one;
Fig. 3 is the first stake holes and the first pile foundation overlooking structure diagram in the embodiment of the present invention one;
Fig. 4 is the overlooking structure diagram of the water-stop curtain pile foundation unit in the embodiment of the present invention two;
Fig. 5 be multiple water-stop curtain pile foundation units in the embodiment of the present invention two be mutually twisted and the water-stop curtain that is formed;
Fig. 6 is the flow chart of the construction method of the construction water-stop curtain pile foundation unit in the embodiment of the present invention two.
Figure label:
First stake holes 1;
First pile foundation 11;
Second stake holes 2;
Second pile foundation 21;
Third stake holes 3;
Third pile foundation 31;
First backing plate 4;
Steel consent 41;
Fill orifice 42.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art Every other embodiment obtained without creative efforts, shall fall within the protection scope of the present invention.
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside", " axial direction ", " radial direction ", " circumferential direction " etc. The orientation or positional relationship of instruction is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of the description present invention and letter Change description, rather than the device or element of indication or suggestion meaning must have a particular orientation, with specific orientation construct and Operation, therefore be not considered as limiting the invention.
In the present invention unless specifically defined or limited otherwise, term " installation ", " connected ", " connection ", " fixation " etc. Term shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, and be also possible to integral;It can be Mechanical connection, is also possible to be electrically connected, is also possible to communication connection;It can be and be directly connected to, intermediary can also be passed through It is indirectly connected with, can be the connection inside two elements or the interaction relationship of two elements, unless otherwise restricted clearly. For the ordinary skill in the art, can understand as the case may be above-mentioned term in the present invention specifically contain Justice.
Technical solution of the present invention is described in detail with specifically embodiment below.These specific implementations below Example can be combined with each other, and the same or similar concept or process may be repeated no more in some embodiments.
Fig. 1 is the flow chart of the construction method that water-stop curtain pile foundation is built using waste mud in the embodiment of the present invention one, Fig. 3 is the first stake holes and the first pile foundation overlooking structure diagram in the embodiment of the present invention one.
Construction method provided in an embodiment of the present invention using waste mud construction water-stop curtain pile foundation.As shown in Figure 1, this reality The construction method for applying example includes:
S1, the first stake holes 1 is drilled with using mud.
For example, in step S1, the soil of the predetermined position of the first stake holes 1 is dredged using machinery equipment Pine, by a part of slurry prime in the predetermined position, carries out in the soil of loose predetermined position to the predeterminated position When boring stake holes, ordinatedly it is lower can Automatic-seepage water also be understood as waste mud so as to form moist mud, waste mud relative to Dry soil is easier that the first stake holes 1 is discharged, and is also beneficial to the subsequent borehole cleaning to the first stake holes 1 and operates.
S2, mud in the first stake holes 1 is extracted to dirty mud sump.
For example, in step S2, useless mud will be discharged into after the waste mud extraction in the first stake holes 1 using machinery equipment In stock tank, keep the first stake holes 1 vacant, to provide space for perfusion liquid concrete, wherein dirty mud sump is arranged in sealing Curtain areas adjacent, in order to the transport operation in subsequent step.
S3, desanding processing is carried out to the waste mud in dirty mud sump and obtains pure mud.
For example, in step S3, using machinery equipment by waste mud drilling cuttings and sand clear out of waste mud, from And pure mud is formed, when the amount of drilling cuttings and sand in waste mud, the drilling cuttings and sand that contain in mud is more, it can reduce The viscosity of concrete is prone to wear machinery equipment when utilizing slurry manufacture concrete using machinery equipment.
S4, pure mud is sent into stirring pool.
For example, in step S4, the pure mud after desanding step is sent into stirring using machinery equipment In pond, stirring pool is used to a variety of materials mixing stirring liquid concrete is made, and waste mud is fully utilized, is kept away Exempt from all to transport outward waste mud, can reduce environmental pollution, and has saved manpower and material resources spent by outward transport mud.
S5, cement is injected into stirring pool.
For example, in step S5, when making liquid concrete, can be in the quality of addition cement and the specific gravity of mud 0.2,0.25 or 0.4, the intensity and water-stagnating effect after manufactured liquid concrete solidification are good.
S6, it stirs to obtain the mixed liquor of cement Yu pure mud.
Specifically, in step S6, using machinery equipment to the mixed liquor of cement and pure mud in stirring pool It is stirred, is sufficiently mixed cement with pure mud, to be ready for subsequent production liquid concrete.
S7, cement slurry is extracted to the first stake holes 1, stirring is to be uniformly mixed, to solidify to form the first pile foundation 11.
Specifically, in step S7, after cement slurry to the first stake holes 1, cement slurry is in the first stake holes 1 with the time Passage, slurry have gradually lost plasticity, have become not flowable close state, hereafter the intensity of slurry gradually increases, directly It can become the stone shape solid with suitable intensity to the end, to form the first pile foundation 11.
Through the above it is not difficult to find that the construction party provided by the invention using waste mud construction water-stop curtain pile foundation First the mud extracted out out of first stake holes 1 progress desanding is largely utilized when making liquid concrete by removing for method Mud after sand avoids and all transports outward waste mud, so that manpower and material resources are saved, meanwhile, greatly reduce waste mud Pollution to environment, it is environmentally protective.
Optionally, in the present embodiment, in step sl, specifically includes the following steps:
The predeterminated position of S1001, selected first stake holes 1;
S1002, the first stake holes 1 is drilled in predetermined position using pore-forming drill cooperation mud.Specifically, single shaft is utilized Drilling machine is loose in the soil progress of predetermined position with the single-shaft-rotation speed of 40r/min~60r/min, to be drilled with first Stake holes 1, in the soil of loose predetermined position, the single-shaft-rotation speed of 40r/min~60r/min can prevent soil from splashing To around the first stake holes 1, due to underground meeting Automatic-seepage water, so as to form waste mud, waste mud is easier to arrange relative to soil First stake holes 1 out, to form the first stake holes 1, to the subsequent operation for emptying the first stake holes 1.
Optionally, in the present embodiment, in step s 2, specifically includes the following steps:
S2001, mud is injected in the first stake holes 1 by borer drill rod using the first slush pump;
S2002, drilling tool is protruded into the first stake holes 1, and controls drilling tool rotation;
S2003, promotion and sinking drilling tool, clod and sediment for taking out of in the first stake holes 1;
S2004, it proposes drilling tool and transfers conduit;
S2005, mud is evacuated in waste pulp pond by the mud that conduit injects in the first stake holes 1 using the first slush pump. When repeatedly being promoted with sinking drilling tool, clod and sediment can be made to mix more evenly, be conducive to clear up the first stake holes 1 more thorough Bottom.
Optionally, in the present embodiment, further comprising the steps of after step S2005:
S2006, mud is injected in the first stake holes 1 by the aperture of the first stake holes 1 using the first slush pump;
S2007, drilling tool is protruded into the first stake holes 1, and controls drilling tool rotation;
S2008, promotion and sinking drilling tool, mud takes first out of by high pressure slurry pump out of drilling rod in the first stake holes 1 Clod and sediment in hole 1;
S2009, after inner hole deposition slag is met the requirements, lift drilling tool;
S2010, mud is injected in the first stake holes 1 using the first slush pump, mud passes through the first mud in the first stake holes 1 Pump takes clod and sediment out of out of first stake holes 1.When repeatedly being promoted with sinking drilling tool, clod and sediment can be made to mix more equal It is even, be conducive to clear up the first stake holes 1 more thorough.
Optionally, in the present embodiment, in step s 2, specifically includes the following steps:
S221,1 inner surface of the first stake holes being carried out using the first water pump to wash away water filling, water injection pressure is 0.3~0.6Mpa, And the water filling water surface is lower than the first stake holes 1, to obtain dilution mud;
S222, the dilution mud in the first stake holes 1 is drawn in dirty mud sump using the first slush pump, the first slush pump Driving power be 15KW, straw diameter 60mm~80mm, flow be 150L/min~250L/min.
Optionally, in the present embodiment, further include the following steps after step S222:
S223, the sucker of airlift suction dredger is protruded into the first stake holes 1, and the distance of 1 bottom of the first stake holes of sucker distance is big In 10cm and it is less than 1m;
S224, starting airlift suction dredger, the sediment of 1 bottom of the first stake holes and drilling cuttings are extracted out;
Airlift suction dredger is closed after S225,3min, and sucker is extracted into the first stake holes 1.
Optionally, in the present embodiment, in step in S3, specifically includes the following steps:
S3001, the mud in dirty mud sump is drawn in mud desander by third slush pump, third slush pump Driving power is 15KW, and straw diameter 60mm~80mm, flow is 150L/min~250L/min;
S3002, the mud in dirty mud sump is subjected to desanding processing to obtain pure mud, mud using mud desander It starches and is equipped with vibrating screen in desander, the sieve mesh number of vibrating screen is 80~160 mesh, and the vibration frequency of vibrating screen is 650~800 Beat/min.Specifically, due to the drilling cuttings and sand in waste mud, the amount of the drilling cuttings and sand that contain in mud is more, can drop The viscosity of low concrete is prone to wear machinery equipment when utilizing slurry manufacture concrete using machinery equipment.Therefore, it utilizes Mud desander by waste mud drilling cuttings and sand clear out of waste mud, to form pure mud.
Optionally, in the present embodiment, in the step s 7, specifically includes the following steps:
S7001, yellow sand is added into stirring pool, the specific gravity of mixed liquor and yellow sand is 4:5;
S7002, stone is added into stirring pool, the specific gravity of mixed liquor and stone is 4:7.Specifically, it can use biography It send band that will make the materials such as other materials necessary to liquid concrete such as yellow sand, stone and is added to stirring pool according to above-mentioned specific gravity It is interior, so that produced liquid concrete is reached the requirement of production water-stop curtain.It should be understood that addition yellow sand and stone Sequentially without strict regulations, and it is different according to characteristic requirements of the various soil properties for the first pile foundation 11, and add different specific weight Yellow sand and stone.
Fig. 2 is the plane structure chart of the first backing plate in the embodiment of the present invention one.
Optionally, in the present embodiment, in the step s 7, specifically includes the following steps:
S701, the first backing plate 4 is placed at the first stake holes 1, the first backing plate 4 includes: fill orifice 42 and two steel consents 41;
S702, two steel plugs are filled in into two steel consents 41;
S703, it extracts the liquid concrete in stirring pool and is perfused to fill orifice 42;
S704, after concrete reaches initial set, two steel plugs are extracted out, to form the first pile foundation 11.
Fig. 4 is the overlooking structure diagram of the water-stop curtain pile foundation unit in the embodiment of the present invention two, and Fig. 6 is that the present invention is real Apply the flow chart of the construction method of the construction water-stop curtain pile foundation unit in example two.
The present invention provides a kind of construction method of water-stop curtain pile foundation unit in second aspect, specifically includes following step It is rapid:
S100, according to claim 1 to any one of 9 using waste mud construction water-stop curtain pile foundation construction method Make the first pile foundation;
S101, the second stake holes 2 is drilled at the position of a stake diameter distance of the first pile foundation of distance 11;
S102, mud in the second stake holes 2 is extracted to dirty mud sump;
S103, desanding processing is carried out to the waste mud in dirty mud sump and obtains pure mud;
S104, pure mud is sent into stirring pool;
S105, cement is injected into stirring pool, and the specific gravity of cement and mud is 0.2~0.4;
S106, it stirs to obtain the mixed liquor of cement Yu pure mud;
S107, liquid concrete is prepared according to the mixed liquor in stirring pool, until obtaining liquid concrete;
S108, the second backing plate identical with the first backing plate is placed at the second stake holes 2;
S109, steel plug is filled in two steel consents;
S110, it extracts the liquid concrete in stirring pool and is perfused to fill orifice;
S111, after concrete reaches initial set, steel plug is extracted out, to form the second pile foundation 21;
S112, third stake holes 3 is drilled between the first pile foundation and the second pile foundation 21;
S113, mud in third stake holes 3 is extracted to dirty mud sump;
S114, desanding processing is carried out to the waste mud in dirty mud sump and obtains pure mud;
S115, pure mud is sent into stirring pool;
S116, cement is injected into stirring pool, and the specific gravity of cement and mud is 0.2~0.4;
S117, it stirs to obtain the mixed liquor of cement Yu pure mud;
S118, liquid concrete is prepared according to the mixed liquor in stirring pool, until obtaining liquid concrete;
S119, it extracts the liquid concrete in stirring pool and is perfused to third stake holes 3, to form third pile foundation 31, the Three pile foundations 31 are connected with the first pile foundation 11 and the second pile foundation 21, to form water-stop curtain pile foundation unit.
The construction method of embodiment two includes the construction method of embodiment one, during building entire water-stop curtain Waste mud is utilized as far as possible, can reduce pollution of the waste mud to environment, and avoids and all transports outward waste mud, to save Manpower and material resources.
Through the above it is not difficult to find that it is provided by the invention construction water-stop curtain pile foundation unit construction method, be by Third pile foundation, which is connected with the first pile foundation and the second pile foundation, to be formed.The first pile foundation is built well according to one construction method of embodiment With the second pile foundation, third pile foundation is can be set just in the distance between the first pile foundation and the second pile foundation, and distinguishes third pile foundation It is mutually twisted with the first pile foundation and the second pile foundation, to be connected to form water-stop curtain pile foundation unit.It is worth noting that It can be placed respectively after being drilled with the first stake holes, the second stake holes and third stake holes, then by the first backing plate and the second backing plate At to the position of the first stake holes and the second stake holes, steel plug will be filled on four steel consents of the first backing plate and the second backing plate, i.e., Liquid concrete can be perfused separately or together from the fill orifice of the first backing plate and the fill orifice of the second backing plate, to form sealing Curtain pile foundation unit.
Fig. 5 be multiple water-stop curtain pile foundation units in the embodiment of the present invention two be mutually twisted and the water-stop curtain that is formed. As shown in figure 5, multiple water-stop curtain pile foundation units are mutually twisted, continuous water-stop curtain is formed, water-stop curtain two can be prevented The moisture of side circulates, to play the purpose of sealing.
Before step S119, can with the following steps are included:
Steel reinforcement cage is divided into third stake holes 3, steel reinforcement cage is that columned cage body is bundled by reinforcing bar, and the cross of its cage body Sectional area is less than the cross-sectional area of third stake holes 3, and third pile foundation 31 is the combination of armored concrete, and therefore, steel reinforcement cage makes third The intensity of pile foundation 31 is higher, and stability is also stronger, to keep the stability of water-stop curtain pile foundation unit stronger.
In the present invention unless specifically defined or limited otherwise, fisrt feature in the second feature " on " or " down " can be with It is that fisrt feature and second feature directly contact or fisrt feature and second feature pass through intermediary mediate contact.
Moreover, fisrt feature can be fisrt feature in second feature above the second feature " above ", " above " and " above " Directly above or obliquely above, or first feature horizontal height is merely representative of higher than second feature.Fisrt feature is in second feature " it Under ", " lower section " and " following " can be fisrt feature and be directly under or diagonally below the second feature, or be merely representative of fisrt feature water Flat height is lower than second feature.
In the description of this specification, reference term " one embodiment ", " some embodiments ", " example ", " specifically show The description of example " or " some examples " etc., it is intended that specific features, structure, material or spy described in conjunction with this embodiment or example Point is included at least one embodiment or example of the invention.In the present specification, schematic expression of the above terms are not It must be directed to identical embodiment or example.Moreover, particular features, structures, materials, or characteristics described can be in office It can be combined in any suitable manner in one or more embodiment or example of anticipating.In addition, without conflicting with each other, this field Technical staff can by the feature of different embodiments or examples described in this specification and different embodiments or examples into Row combination and combination.
Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention., rather than its limitations;To the greatest extent Pipe present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: its according to So be possible to modify the technical solutions described in the foregoing embodiments, or to some or all of the technical features into Row equivalent replacement;And these are modified or replaceed, various embodiments of the present invention technology that it does not separate the essence of the corresponding technical solution The range of scheme.

Claims (10)

1. a kind of construction method using waste mud construction water-stop curtain pile foundation, which comprises the following steps:
S1, the first stake holes is drilled with using mud;
S2, mud in first stake holes is extracted to dirty mud sump;
S3, desanding processing is carried out to the waste mud in the dirty mud sump and obtains pure mud;
S4, pure mud is sent into stirring pool;
Cement is injected in S5, Xiang Suoshu stirring pool;
S6, it stirs to obtain the mixed liquor of cement Yu pure mud;
S7, the cement slurry is extracted to first stake holes, stirring is to be uniformly mixed, to solidify to form the first pile foundation.
2. the construction method according to claim 1 using waste mud construction water-stop curtain pile foundation, which is characterized in that in step In rapid S1, specifically includes the following steps:
The predeterminated position of S1001, selected first stake holes;
S1002, first stake holes is drilled in the predetermined position using pore-forming drill cooperation mud.
3. the construction method according to claim 1 using waste mud construction water-stop curtain pile foundation, which is characterized in that in step In rapid S2, specifically includes the following steps:
S2001, mud is injected in first stake holes by borer drill rod using the first slush pump;
S2002, drilling tool is protruded into first stake holes, and controls the drilling tool rotation;
S2003, promotion and the drilling tool that sinks, clod and sediment for taking out of in first stake holes;
S2004, it proposes drilling tool and transfers conduit;
S2005, mud is evacuated to by the mud that the conduit injects in first stake holes using first slush pump it is useless In stock tank.
4. the construction method according to claim 3 using waste mud construction water-stop curtain pile foundation, which is characterized in that in step It is further comprising the steps of after rapid S2005:
S2006, mud is injected in first stake holes by the aperture of first stake holes using first slush pump;
S2007, the drilling tool is protruded into first stake holes, and controls the drilling tool rotation;
S2008, promotion and the drilling tool that sinks, mud is taken out of out of drilling rod described by high pressure slurry pump in first stake holes Clod and sediment in first stake holes;
S2009, after inner hole deposition slag is met the requirements, lift the drilling tool;
S2010, mud is injected in first stake holes using first slush pump, mud passes through institute in first stake holes It states the first slush pump and takes clod and sediment out of out of described first stake holes.
5. the construction method according to claim 1 using waste mud construction water-stop curtain pile foundation, which is characterized in that in step In rapid S2, specifically includes the following steps:
S221, the first stake holes inner surface being carried out using the first water pump to wash away water filling, water injection pressure is 0.3~0.6Mpa, And the water filling water surface is lower than first stake holes, to obtain dilution mud;
S222, the dilution mud in first stake holes is drawn in the dirty mud sump using the second slush pump, described The driving power of two slush pumps is 15KW, and straw diameter 60mm~80mm, flow is 150L/min~250L/min.
6. the construction method according to claim 5 using waste mud construction water-stop curtain pile foundation, which is characterized in that in step Further include the following steps after rapid S222:
S223, the sucker of airlift suction dredger is protruded into first stake holes, and the sucker is apart from first stake holes bottom Distance is greater than 10cm and is less than 1m;
S224, the starting airlift suction dredger, the sediment of first stake holes bottom and drilling cuttings are extracted out;
The airlift suction dredger is closed after S225,3min, and the sucker is extracted into first stake holes.
7. the construction method according to claim 1 using waste mud construction water-stop curtain pile foundation, which is characterized in that in step In rapid in S3, specifically includes the following steps:
S3001, the mud in the dirty mud sump is drawn in mud desander by third slush pump, the third mud The driving power of pump is 15KW, and straw diameter 60mm~80mm, flow is 150L/min~250L/min;
S3002, the mud in the dirty mud sump is subjected to desanding processing to obtain pure mud, institute using mud desander It states and is equipped with vibrating screen in mud desander, the sieve mesh number of the vibrating screen is 80~160 mesh, the vibration frequency of the vibrating screen It is 650~800 beats/min.
8. the construction method according to claim 1 using waste mud construction water-stop curtain pile foundation, which is characterized in that in step In rapid S7, specifically includes the following steps:
The specific gravity of addition yellow sand in S7001, Xiang Suoshu stirring pool, the mixed liquor and the yellow sand is 4:5;
The specific gravity of addition stone in S7002, Xiang Suoshu stirring pool, the mixed liquor and the stone is 4:7.
9. the construction method according to claim 1 using waste mud construction water-stop curtain pile foundation, which is characterized in that in step In rapid S7, specifically include:
S701, the first backing plate is placed at first stake holes, first backing plate includes: fill orifice and two steel consents;
S702, two steel plugs are filled in into described two steel consents;
S703, it extracts the liquid concrete in stirring pool and is perfused to the fill orifice;
S704, after concrete reaches initial set, by described two steel plugs extract out, to form the first pile foundation.
10. a kind of construction method of water-stop curtain pile foundation unit, which comprises the following steps:
S100, the construction method as claimed in any of claims 1 to 9 using waste mud construction water-stop curtain pile foundation Make the first pile foundation;
S101, the second stake holes is drilled at the position apart from a stake diameter distance of first pile foundation;
S102, mud in second stake holes is extracted to the dirty mud sump;
S103, desanding processing is carried out to the waste mud in the dirty mud sump and obtains pure mud;
S104, pure mud is sent into stirring pool;
Cement is injected in S105, Xiang Suoshu stirring pool, and the specific gravity of cement and mud is 0.2~0.4;
S106, it stirs to obtain the mixed liquor of cement Yu pure mud;
S107, liquid concrete is prepared according to the mixed liquor in the stirring pool, until obtaining liquid concrete;
S108, the second backing plate identical with first backing plate is placed at second stake holes;
S109, steel plug is filled in into described two steel consents;
S110, it extracts the liquid concrete in the stirring pool and is perfused to the fill orifice;
S111, after concrete reaches initial set, steel plug is extracted out, to form the second pile foundation;
S112, third stake holes is drilled between first pile foundation and second pile foundation;
S113, mud in the third stake holes is extracted to the dirty mud sump;
S114, desanding processing is carried out to the waste mud in the dirty mud sump and obtains pure mud;
S115, pure mud is sent into the stirring pool;
Cement is injected in S116, Xiang Suoshu stirring pool, and the specific gravity of cement and mud is 0.2~0.4;
S117, it stirs to obtain the mixed liquor of cement Yu pure mud;
S118, liquid concrete is prepared according to the mixed liquor in the stirring pool, until obtaining liquid concrete;
S119, it extracts the liquid concrete in the stirring pool and is perfused to the third stake holes, to form third pile foundation, institute It states third pile foundation to be connected with first pile foundation and second pile foundation, to form water-stop curtain pile foundation unit.
CN201910138829.0A 2019-02-25 2019-02-25 The construction method of water-stop curtain pile foundation and pile foundation unit is built using waste mud Pending CN109930620A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910138829.0A CN109930620A (en) 2019-02-25 2019-02-25 The construction method of water-stop curtain pile foundation and pile foundation unit is built using waste mud

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910138829.0A CN109930620A (en) 2019-02-25 2019-02-25 The construction method of water-stop curtain pile foundation and pile foundation unit is built using waste mud

Publications (1)

Publication Number Publication Date
CN109930620A true CN109930620A (en) 2019-06-25

Family

ID=66985898

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910138829.0A Pending CN109930620A (en) 2019-02-25 2019-02-25 The construction method of water-stop curtain pile foundation and pile foundation unit is built using waste mud

Country Status (1)

Country Link
CN (1) CN109930620A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114809910A (en) * 2022-05-31 2022-07-29 中国十九冶集团有限公司 Composite hole forming method for friction pile foundation hole forming

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202626978U (en) * 2012-04-10 2012-12-26 中冶建筑研究总院有限公司 Cemented soil secant pile group, diaphragm wall constituted by same and building foundation pit support system constituted by cemented soil secant pile group
CN203655190U (en) * 2013-09-29 2014-06-18 深圳市工勘岩土工程有限公司 Hole cleaning equipment for cast-in-place bored pile
JP2015218516A (en) * 2014-05-20 2015-12-07 三谷セキサン株式会社 Construction method of foundation pile whose pile head is reinforced, foundation pile structure whose pile head is reinforced
CN105887890A (en) * 2016-04-14 2016-08-24 广州市鲁班建筑集团股份有限公司 Plastic pile, construction method of plastic pile and foundation pit supporting watertight seal structure
CN107503349A (en) * 2017-08-17 2017-12-22 中铁隧道局集团有限公司 The heavy quarrel of rotary digging bottom hole and mud method for cleaning
CN207904990U (en) * 2018-02-09 2018-09-25 上海智平基础工程有限公司 A kind of groutable underground continuous wall connector

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202626978U (en) * 2012-04-10 2012-12-26 中冶建筑研究总院有限公司 Cemented soil secant pile group, diaphragm wall constituted by same and building foundation pit support system constituted by cemented soil secant pile group
CN203655190U (en) * 2013-09-29 2014-06-18 深圳市工勘岩土工程有限公司 Hole cleaning equipment for cast-in-place bored pile
JP2015218516A (en) * 2014-05-20 2015-12-07 三谷セキサン株式会社 Construction method of foundation pile whose pile head is reinforced, foundation pile structure whose pile head is reinforced
CN105887890A (en) * 2016-04-14 2016-08-24 广州市鲁班建筑集团股份有限公司 Plastic pile, construction method of plastic pile and foundation pit supporting watertight seal structure
CN107503349A (en) * 2017-08-17 2017-12-22 中铁隧道局集团有限公司 The heavy quarrel of rotary digging bottom hole and mud method for cleaning
CN207904990U (en) * 2018-02-09 2018-09-25 上海智平基础工程有限公司 A kind of groutable underground continuous wall connector

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114809910A (en) * 2022-05-31 2022-07-29 中国十九冶集团有限公司 Composite hole forming method for friction pile foundation hole forming

Similar Documents

Publication Publication Date Title
CN206917624U (en) A kind of mud circulating system for water Bridge bored pile construction
CN201212147Y (en) Combination drill tool for long screwy jet grouting and stirring pile
CN103114577B (en) Rotary excavating hole-forming construction method for building pile foundation
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN103882858A (en) Construction method of micro-piles with diameter of 300 mm
CN111197305A (en) Construction method of ultra-long large-diameter cast-in-situ bored pile
KR101527723B1 (en) Complex Ground Improving Devive and Ground Improving Method Using The Same
US5823276A (en) Diamond-tipped core barrel and method of using same
CN107869146A (en) A kind of method with clean-out machine Dewatering well
CN109930620A (en) The construction method of water-stop curtain pile foundation and pile foundation unit is built using waste mud
US6048137A (en) Drilled, cast-in-place shell pile and method of constructing same
CN105178333B (en) Construction method for removing anchor rod obstacles in grooving process of underground diaphragm wall
CN111893994A (en) Pile casing-free pore-forming method for foundation pile of aeolian dune steep slope
CN208379572U (en) A kind of anti-settling processing constructing device based on cutting edge formula propelling method
JP4011212B2 (en) Construction method of shaft
CN1024029C (en) Direct sink-and-insert method and equipment for constructing underground building with combined and interlocked prefabricated concrete components
JP4313070B2 (en) Sludge treatment method in ready-made pile construction and ground reinforcement structure obtained by the treatment method
CN114482107A (en) Construction method of impervious wall
CN204491577U (en) Device is stirred in a kind of spray carrying out consolidation process for specific soil layer
CN211037023U (en) Pipe well dewatering well arranged at bottom of underground diaphragm wall
CN210395451U (en) Connecting and guiding device for basement pile foundation construction
CN1342815A (en) Method for lowering water level in foundation pit of building engineering
CN104652404A (en) Method for carrying out resource utilization on caustic slag after physical dehydrating
CN104563887B (en) Combined screw thread soil compaction pore-forming sand drain drill bit
JP2977480B2 (en) Burying method of manhole pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190625