CN206917624U CN201720702021.7U CN201720702021U CN206917624U CN 206917624 U CN206917624 U CN 206917624U CN 201720702021 U CN201720702021 U CN 201720702021U CN 206917624 U CN206917624 U CN 206917624U
Authority
CN
China
Prior art keywords
mud
cofferdam
steel pile
slush pump
chute
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720702021.7U
Other languages
Chinese (zh)
Inventor
陈军
高云
余钦聪
杨宏
万贝海
张哲�
程华强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WUHAN BRIDGE ENGINEERING Co Ltd
Wuhan Municipal Construction Group Co Ltd
Original Assignee
WUHAN BRIDGE ENGINEERING Co Ltd
Wuhan Municipal Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHAN BRIDGE ENGINEERING Co Ltd, Wuhan Municipal Construction Group Co Ltd filed Critical WUHAN BRIDGE ENGINEERING Co Ltd
Priority to CN201720702021.7U priority Critical patent/CN206917624U/en
Application granted granted Critical
Publication of CN206917624U publication Critical patent/CN206917624U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a kind of mud circulating system for water Bridge bored pile construction, including the cofferdam in water, there are multiple Bored Pile of Bridge in cofferdam, a vertical steel pile casting is correspondingly configured with the datum hole of each Bored Pile of Bridge;The mud chute for connection is installed between two adjacent steel pile castings, mud chute is in tilted layout;The first slush pump is provided with cofferdam, is directly connected with the steel pile casting that mud chute upper end is connected by pipeline and the outlet of the first slush pump, the entrance of the first slush pump with the mud in cofferdam;The second slush pump is provided with the steel pile casting being connected with mud chute lower end, the steel pile casting being connected with mud chute upper end passes through pipeline and the outlet of the second slush pump.The beneficial effects of the utility model are:By the use of cofferdam as mud pit, without reconstruction mud pit in addition, construction cost is reduced;Meanwhile cofferdam volume is big, the cyclic space is big, mud sediment it is better.

Description

A kind of mud circulating system for water Bridge bored pile construction
Technical field
It the utility model is related to Bridge Construction field, and in particular to a kind of mud for water Bridge cast-in-situ bored pile Starch the circulatory system.
Background technology
With the fast development of social economy and traffic transport industry, Urban Bridge Construction just deploys on a large scale, across lake Pool, the bridge in river are also more and more.During Bridge Pile Foundation Construction, mud pit need to be largely used, it is more using soil at present Cubic meter of stone cofferdam forms mud pit or finished steel mud pit.However, mud pit or finished steel mud are formed using cubic metre of earth and stone cofferdam There is the defects of certain in stock tank, such as forming mud pit using cubic metre of earth and stone cofferdam expends substantial amounts of artificial, material and machinery expenses It is very high, and lake or river course are taken, polluted water and retardance current, particularly easily occur flood in flood season and pour in down a chimney cofferdam, enclose Weir such as caves at the accident, and potential safety hazard is big, pollutes environment;And finished steel mud pit is used, it will be cleared up first into slag bath before perfusion Totally, and evacuate internal mud, and ensure mud pit, mud pit, slurry transport truck have enough capacity and filled to store in place The mud discharged during note, and the Spatial General 6 R of finished steel mud pit is not very big, the buffer-precipitation that mud can not be good, Borehole cleaning is inefficient, and needs the sediment outward transport inside frequent cleaning, operationalizes very cumbersome, also takes up natively Limited over-water construction working face.Therefore, it is necessary to prior art is improved.
The content of the invention
The purpose of this utility model is, in view of the shortcomings of the prior art, there is provided a kind of cyclic space is big, mud sediment effect The good mud circulating system for water Bridge bored pile construction of fruit.
The technical solution adopted in the utility model is:A kind of mud cyclic system for water Bridge bored pile construction System, including the cofferdam in water, there are multiple Bored Pile of Bridge in cofferdam, be correspondingly configured with the datum hole of each Bored Pile of Bridge One vertical steel pile casting, the both ends open of steel pile casting;The mud for connection is installed between two adjacent steel pile castings Chute, mud chute are in tilted layout;The first slush pump is provided with cofferdam, the steel pile casting being connected with mud chute upper end passes through The outlet of pipeline and the first slush pump, the entrance of the first slush pump directly connect with the mud in cofferdam;With mud chute The second slush pump is provided with the connected steel pile casting in lower end, the steel pile casting being connected with mud chute upper end passes through pipeline and the second mud The outlet of pump.
By such scheme, dense mesh is installed in the lower end exit of mud chute.
By such scheme, the lower end of mud chute is provided with gravel outlet.
By such scheme, clay layer that the lower end of the steel pile casting is stretched into datum hole.
By such scheme, the top in the cofferdam is higher by 1m than highest water level on records.
Compared with prior art, the beneficial effects of the utility model are:
1st, by the use of needing the cofferdam of construction bearing platform, without reconstruction mud pit in addition, to reduce and apply as mud pit originally Work cost;Simultaneously as cofferdam volume is big, the cyclic space is big, mud sediment it is better, and adjacent steel pile casting plays tentatively Precipitation and buffered water stream percussion, mud in cofferdam can gentle quickly precipitation, can reach the purpose of rapid borehole cleaning.
2nd, will transport outward mud after the completion of all pile foundation constructions in a cushion cap again, mud be precipitated into dregs or Mud, it is not necessary to frequently transport outward mud, improve efficiency of construction, reduce construction cost;It it also avoid simultaneously to water body environment Pollution, protect environment.
Brief description of the drawings
Fig. 1 is the structural representation of one specific embodiment of the utility model.
Fig. 2 is the A-A sectional views in Fig. 1.
Wherein:1st, cofferdam;2nd, bridge pile foundation;3rd, the first steel pile casting;4th, the second steel pile casting;5th, mud chute;6th, the first mud Stock pump;7th, river surface highest water level on records;8th, the second slush pump.
Embodiment
In order to more fully understand the utility model, the utility model is made with specific embodiment below in conjunction with the accompanying drawings further Ground describes.
A kind of mud circulating system for water Bridge bored pile construction as shown in Figure 1, including as mud The cofferdam 1 being located in water of circulatory pool, there is multiple Bored Pile of Bridge 2 in cofferdam 1, corresponding in the datum hole of each Bored Pile of Bridge 2 It is configured with a vertical steel pile casting, the both ends open of steel pile casting, the clay layer that its lower end is stretched into datum hole;It is adjacent at two The mud chute 5 for connection is installed between steel pile casting, mud chute 5 is in tilted layout;The first mud is provided with cofferdam 1 Pump 6, with the steel pile casting that the upper end of mud chute 5 is connected by pipeline and the outlet of the first slush pump 6, the first slush pump 6 Entrance directly connects with the mud in cofferdam 1;The second slush pump 8 is provided with the steel pile casting being connected with the lower end of mud chute 5, with mud The connected steel pile casting in slurry chute 5 upper end passes through pipeline and the outlet of the second slush pump 8.
Preferably, dense mesh is installed in the lower end exit of mud chute 5, the sand in mud is flowed through with filtering Gravel;The lower end of mud chute 5 is provided with gravel outlet, and the gravel of filtering is discharged into cofferdam 1.
In the present embodiment, the cofferdam 1 can be Larsen steel sheet-pile cofferdam or other steel cofferdams;Wherein with mud chute 5 End be connected for the first steel pile casting 3, be connected with the lower end of mud chute 5 for the second steel pile casting 4.
The Specific construction process of the present embodiment comprises the following steps:
1st, the construction in cofferdam 1:Construction area injection Larsen steel sheet pile in river forms cofferdam 1, ensures that cofferdam 1 is not leaked Water;The top in cofferdam 1 is higher by 1m than highest water level on records 7 simultaneously, to ensure that flood season river will not pour in down a chimney into cofferdam 1.
2nd, steel pile casting is embedded:Bored Pile of Bridge is provided with cofferdam 1(The present embodiment includes the bridge that two rows are arranged symmetrically Pile foundation 2), and steel pile casting, the both ends open of steel pile casting are correspondingly arranged in the datum hole of each Bored Pile of Bridge 2, its lower end is inserted The mud entered in datum hole gos deep into clay layer.
3rd, the arrangement of mud chute 5:Install between the first steel pile casting 3 and the second steel pile casting 4 and slipped for the mud of connection Groove 5, and in the lower end of mud chute 5(Close on one end of the second steel pile casting 4)Dense mesh is installed, for filtering in mud Gravel.
4th, the arrangement of the first slush pump 6 and the second slush pump 8:The first slush pump 6 is provided with cofferdam 1, in the second steel The second slush pump 8 is installed in casing 4, the first steel pile casting 3 passes through pipeline and the outlet of the first slush pump 6, the first slush pump 6 Entrance directly connected with the mud in cofferdam 1;The entrance of second slush pump 8 directly connects with the mud in the second steel pile casting 4, The outlet of second slush pump 8 is connected by pipeline with the first steel pile casting 3.
Realize that the process that mud circulates is using the present embodiment:The pulping in cofferdam 1, with 3 corresponding bridge of the first steel pile casting When beam pile foundation 2 drills, mud is pumped into the first steel pile casting 3 through the first slush pump 6 from cofferdam 1;When rig is crept into, the first steel pile casting Mud in 3 is flowed into the second steel pile casting 4 after the dense mesh of mud chute 5 filters coarse gravel and clod(Slipped by mud The coarse gravel and soil block that groove 5 filters are discharged into cofferdam 1);Mud is in the second steel pile casting 4 through the second slush pump after buffer-precipitation 8 the first steel pile castings 3 of backflow, retaining wall is carried out to the bridge pile foundation 2 to drill, reaches the effect of mud circulation retaining wall.Treat cofferdam 1 After mud off reaches design strength requirement in the interior datum hole of all Bored Pile of Bridge 2, the steel shield in the datum hole of Bored Pile of Bridge 2 is taken out Cylinder(Namely first steel pile casting 3), and the mud cleared up in datum hole, mud now have become dregs or mud, with long-armed digging Machine, which is dug out, entrucks and carries away;The mud transported in cofferdam 1, for mud because putting time length, sedimentation effect is good, voluntarily air-dries in cofferdam 1 Consolidation;Water separates with mud, and transhipment is convenient, and volume is also smaller.
Finally it should be noted that these are only preferred embodiment of the present utility model, the utility model is not limited to, Although the utility model is described in detail with reference to embodiment, for those skilled in the art, it still may be used To be modified to the technical scheme described in foregoing embodiments, or equivalent substitution is carried out to which part technical characteristic, But it is all within the spirit and principles of the utility model, any modification, equivalent substitution and improvements made etc., it should be included in Within the scope of protection of the utility model.

Claims (4)

1. a kind of mud circulating system for water Bridge bored pile construction, it is characterised in that including in water Cofferdam, there are multiple Bored Pile of Bridge in cofferdam, a vertical steel pile casting be correspondingly configured with the datum hole of each Bored Pile of Bridge, The both ends open of steel pile casting;The mud chute for connection is installed between two adjacent steel pile castings, mud chute tilts Arrangement;The first slush pump is provided with cofferdam, the steel pile casting being connected with mud chute upper end passes through pipeline and the first slush pump Outlet, the entrance of the first slush pump directly connects with the mud in cofferdam;The steel pile casting being connected with mud chute lower end The second slush pump is inside provided with, the steel pile casting being connected with mud chute upper end passes through pipeline and the outlet of the second slush pump.
2. it is used for the mud circulating system of water Bridge bored pile construction as claimed in claim 1, it is characterised in that The lower end exit of mud chute is installed on dense mesh.
3. it is used for the mud circulating system of water Bridge bored pile construction as claimed in claim 2, it is characterised in that mud The lower end of slurry chute is provided with gravel outlet.
4. it is used for the mud circulating system of water Bridge bored pile construction as claimed in claim 1, it is characterised in that institute State the clay layer that the lower end of steel pile casting is stretched into datum hole.
CN201720702021.7U 2017-06-16 2017-06-16 A kind of mud circulating system for water Bridge bored pile construction Active CN206917624U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720702021.7U CN206917624U (en) 2017-06-16 2017-06-16 A kind of mud circulating system for water Bridge bored pile construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720702021.7U CN206917624U (en) 2017-06-16 2017-06-16 A kind of mud circulating system for water Bridge bored pile construction

Publications (1)

Publication Number Publication Date
CN206917624U true CN206917624U (en) 2018-01-23

Family

ID=61321631

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720702021.7U Active CN206917624U (en) 2017-06-16 2017-06-16 A kind of mud circulating system for water Bridge bored pile construction

Country Status (1)

Country Link
CN (1) CN206917624U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108301797A (en) * 2018-03-08 2018-07-20 中铁建大桥工程局集团第四工程有限公司 A kind of new-type mortar circulatory system for underwater platform drilled pile construction
CN108755665A (en) * 2018-05-31 2018-11-06 诚邦生态环境股份有限公司 Enclose the integrated platform construction method of brill
CN109441381A (en) * 2019-01-09 2019-03-08 中国建筑第四工程局有限公司 One kind recycling construction system for clump of piles mud in water
CN110258539A (en) * 2019-04-28 2019-09-20 安徽省公路桥梁工程有限公司 Cast-in-situ bored pile and its construction method in water
CN111706276A (en) * 2020-06-24 2020-09-25 中建四局土木工程有限公司 Gas lift slag-returning pore-forming construction method
CN113738275A (en) * 2021-09-02 2021-12-03 中铁二十三局集团第四工程有限公司 Anti-pollution construction method for cast-in-situ bored pile in pile foundation engineering
CN114458197A (en) * 2022-01-24 2022-05-10 中交二航局第四工程有限公司 Water-land cross-connection area pile group drilling mud circulation device and method
CN114753357A (en) * 2022-04-08 2022-07-15 中铁七局集团有限公司 Construction method of underwater drilled pile
CN114961600A (en) * 2022-05-13 2022-08-30 中国铁建大桥工程局集团有限公司 Deep-water large-diameter pile foundation mud recycling device and construction method

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108301797A (en) * 2018-03-08 2018-07-20 中铁建大桥工程局集团第四工程有限公司 A kind of new-type mortar circulatory system for underwater platform drilled pile construction
CN108755665A (en) * 2018-05-31 2018-11-06 诚邦生态环境股份有限公司 Enclose the integrated platform construction method of brill
CN109441381A (en) * 2019-01-09 2019-03-08 中国建筑第四工程局有限公司 One kind recycling construction system for clump of piles mud in water
CN110258539A (en) * 2019-04-28 2019-09-20 安徽省公路桥梁工程有限公司 Cast-in-situ bored pile and its construction method in water
CN110258539B (en) * 2019-04-28 2021-02-12 安徽省公路桥梁工程有限公司 Underwater cast-in-situ bored pile and construction method thereof
CN111706276A (en) * 2020-06-24 2020-09-25 中建四局土木工程有限公司 Gas lift slag-returning pore-forming construction method
CN113738275A (en) * 2021-09-02 2021-12-03 中铁二十三局集团第四工程有限公司 Anti-pollution construction method for cast-in-situ bored pile in pile foundation engineering
CN113738275B (en) * 2021-09-02 2024-02-27 中铁二十三局集团第四工程有限公司 Anti-pollution construction method for bored pile of pile foundation engineering
CN114458197A (en) * 2022-01-24 2022-05-10 中交二航局第四工程有限公司 Water-land cross-connection area pile group drilling mud circulation device and method
CN114753357A (en) * 2022-04-08 2022-07-15 中铁七局集团有限公司 Construction method of underwater drilled pile
CN114961600A (en) * 2022-05-13 2022-08-30 中国铁建大桥工程局集团有限公司 Deep-water large-diameter pile foundation mud recycling device and construction method

Similar Documents

Publication Publication Date Title
CN206917624U (en) A kind of mud circulating system for water Bridge bored pile construction
CN107119691B (en) Square deep foundation pit suitable for high bearing pressure of water-rich sand egg layer and excavation method thereof
CN104695879B (en) A kind of stake holes is rinsed and takes out sand hole method
CN107386195B (en) A kind of Dredging Construction method for the canal that drains off floodwaters
CN108193606A (en) A kind of means of defence of local scour near pier
CN104711968B (en) Negative-pressure three-dimensional flow-guiding disturbance impact solidification dredger filling method
CN110409420B (en) Underground continuous wall with pit facing surface and precipitation function
JP5213216B2 (en) Ground improvement method
CN112627212B (en) Water-faced cofferdam inner tube well dewatering dry excavation construction method
CN204959757U (en) Protect a mud circulating device
CN111827247A (en) Method for reinforcing soft foundation
JP4114944B2 (en) Ground improvement method
CN105155421B (en) Complete embedding circular construction method in a kind of single pile Single column pier river course shallow water
CN109024711B (en) Underground structure anti-floating system and construction method thereof
CN211037023U (en) Pipe well dewatering well arranged at bottom of underground diaphragm wall
CN214273568U (en) Sand gravel geology bored concrete pile pore-forming device
CN205954646U (en) Deep basal pit excavation precipitation device
CN114232622A (en) Pile foundation construction method adopting limiting steel box
CN211144529U (en) Rich water loess tunnel precipitation construction structures
CN110409474B (en) Pipe well dewatering well arranged at bottom of underground diaphragm wall
CN208023598U (en) A kind of base pit dewatering pipe well
CN204589985U (en) A kind of silt that uses backfills foundation pit construction water plug
CN109630192A (en) A kind of precipitation method suitable for the construction of half diagenesis bored tunnel
CN216664165U (en) Spacing steel case is used in pile foundation construction
CN218932867U (en) Construction structure of caisson with bottom at water collection pit and elevator shaft

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant