CN109919497A CN201910185047.2A CN201910185047A CN109919497A CN 109919497 A CN109919497 A CN 109919497A CN 201910185047 A CN201910185047 A CN 201910185047A CN 109919497 A CN109919497 A CN 109919497A
Authority
CN
China
Prior art keywords
collection system
data collection
shift
production
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910185047.2A
Other languages
Chinese (zh)
Other versions
CN109919497B (en
Inventor
高阳
李琳
黄其德
孙永
张莎莎
何心芹
方超
张娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tobacco Shandong Industrial Co Ltd
Original Assignee
China Tobacco Shandong Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tobacco Shandong Industrial Co Ltd filed Critical China Tobacco Shandong Industrial Co Ltd
Priority to CN201910185047.2A priority Critical patent/CN109919497B/en
Publication of CN109919497A publication Critical patent/CN109919497A/en
Application granted granted Critical
Publication of CN109919497B publication Critical patent/CN109919497B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

It changes shifts automatically method and device present disclose provides a kind of data collection system adaptability.Wherein, a kind of data collection system adaptability is changed shifts method automatically, and data collection system is connected with each production platform machine, and this method is completed in processor, comprising: receives plant calendar and Order Scheduling that production executive system MES in upper layer is issued;Day order plan is split as the quantity same day shift equal with shift and produces work order;Same day shift after the approval produces work order and is issued to each production board;Same day shift production work order issues the time and earlier than same day first opens a class time;According to shift alt time, starting and stopping for data collection system is automatically controlled.

Description

A kind of data collection system adaptability is changed shifts method and device automatically
Technical field
The disclosure belongs to data collection system field more particularly to a kind of data acquisition system between Cigarette manufacturing enterprises volume hired car System adaptability is changed shifts method and device automatically.
Background technique
Only there is provided background technical informations relevant to the disclosure for the statement of this part, it is not necessary to so constitute first skill Art.
Host device type is relatively uniform between Cigarette manufacturing enterprises volume hired car and production distribution is dispersed, each master between volume hired car Machine equipment carries out production and data collect statistics according to shift.Data collection system was built between Cigarette manufacturing enterprises volume hired car Cheng Zhong produces to adapt to break tour system between volume hired car, and same day production order is split as three according to shift information by data collection system Class's work order, the acquisition of data and summarizing summarize according to shift and being carried out in turn for work order.Accurate statistics of data acquisition requires work It is single to open and terminate to confirm that need of work is completed at the appointed time according to the equipment condition of production, and to retain certain adaptability Ensure the accuracy of shift delay situation data statistics.Inventors have found that consider the work characteristics of operation of host equipment personnel, behaviour Make personnel to need to do a large amount of preparations in shift replacement process, it is difficult to the operability for optimizing manual shift work, because of people Statistics of data acquisition error source is also increased to participate in changing shifts process, it is difficult to ensure the accuracy requirement of statistics of data acquisition.
Summary of the invention
To solve the above-mentioned problems, the first aspect of the disclosure provides a kind of data collection system adaptability from moving Class's method, wherein data collection system is connected with each production platform machine, and this method of the disclosure can be realized volume packet workshop data Acquisition system change shifts automatically function, reduce human intervention, promoted volume hired car between data collection system accuracy and adaptability.
A kind of data collection system adaptability of the first aspect of the disclosure is changed shifts the technical solution of method automatically are as follows:
A kind of data collection system adaptability is changed shifts method automatically, comprising:
Receive plant calendar and Order Scheduling that production executive system MES in upper layer is issued;
Day order plan is split as the quantity same day shift equal with shift and produces work order;
Same day shift after the approval produces work order and is issued to each production board;Same day shift production work order issues Time opens a class time earlier than same day first;
According to shift alt time, starting and stopping for data collection system is automatically controlled.
To solve the above-mentioned problems, the second aspect of the disclosure provides a kind of data collection system adaptability from moving Class device, can be realized volume hired car between data collection system change shifts automatically function, reduce human intervention, promoted volume hired car between number According to the accuracy and adaptability of acquisition system.
A kind of data collection system adaptability of the second aspect of the disclosure is changed shifts the technical solution of device automatically are as follows:
A kind of data collection system adaptability is changed shifts device automatically, comprising:
Order reception module is used to receive plant calendar and Order Scheduling that upper layer production executive system MES is issued;
Order division module is used to for day order plan being split as the quantity same day shift production work equal with shift It is single;
Production work order issues module, is used for same day shift production work order after the approval and is issued to each manufacturing machine Platform;Same day shift production work order issues the time and earlier than same day first opens a class time;
Data collection system start-up and shut-down control module is used to automatically control data collection system according to shift alt time Start and stop.
To solve the above-mentioned problems, in terms of the third of the disclosure, a kind of computer readable storage medium is provided, it can Realize between volume hired car data collection system automatically change shifts function, reduce human intervention, promote data collection system between volume hired car Accuracy and adaptability.
A kind of technical solution of computer readable storage medium in terms of the third of the disclosure are as follows:
A kind of computer readable storage medium, is stored thereon with computer program, realization when which is executed by processor Data collection system adaptability described above step in changing shifts method automatically.
To solve the above-mentioned problems, the 4th aspect of the disclosure, provides a kind of computer equipment, can be realized volume packet Workshop data acquisition system change shifts automatically function, reduce human intervention, promoted volume hired car between data collection system accuracy and Adaptability.
A kind of technical solution of computer equipment of 4th aspect of the disclosure are as follows:
A kind of computer equipment can be run on a memory and on a processor including memory, processor and storage Computer program, the processor realize the data collection system adaptability described above side of changing shifts automatically when executing described program Step in method.
The beneficial effect of the disclosure is:
The disclosure changes shifts more device data acquisition system production order production methods between Cigarette manufacturing enterprises volume hired car Process carries out in such a way that adaptability is changed shifts automatically, greatly improves the accuracy of data acquisition, reduces manual intervention and make At data acquisition errors, reduce labor intensity of operating staff.
Detailed description of the invention
The Figure of description for constituting a part of this disclosure is used to provide further understanding of the disclosure, and the disclosure is shown Meaning property embodiment and its explanation do not constitute the improper restriction to the disclosure for explaining the disclosure.
Fig. 1 is that a kind of data collection system adaptability that the embodiment of the present disclosure provides is changed shifts method flow diagram automatically.
Fig. 2 is a kind of data collection system adaptability system that the method for changing shifts is applicable in automatically that the embodiment of the present disclosure provides Structural schematic diagram.
Fig. 3 is that a kind of data collection system adaptability that the embodiment of the present disclosure provides is changed shifts logic chart automatically.
Fig. 4 is that a kind of data collection system adaptability that the embodiment of the present disclosure provides is changed shifts apparatus structure schematic diagram automatically.
Specific embodiment
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the disclosure.Unless another It indicates, all technical and scientific terms used herein has usual with disclosure person of an ordinary skill in the technical field The identical meanings of understanding.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root According to the illustrative embodiments of the disclosure.As used herein, unless the context clearly indicates otherwise, otherwise singular Also it is intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet Include " when, indicate existing characteristics, step, operation, device, component and/or their combination.
Term explains part:
(1) MES, Manufacturing Execution System, i.e. manufacturing enterprise's production process execute system, are one Cover the production information management system of Manufacture Enterprise workshop execution level.MES can be provided for enterprise including manufaturing data pipe Reason, plan scheduled production management, Production scheduling management, stock control, quality management, human resource management, work centre/equipment pipe Reason, tool tool management, purchasing management, cost management, project kanban system, production process control, bottom data integrated analysis, It is flat to make a sturdy, reliable, comprehensive, feasible manufacture coordinated management for enterprise for the management modules such as the integrated decomposition of upper layer data Platform.
(2) shift alt time is according to production scheduled production rule come the regular worker of each production board operator set Make the time.
A kind of data collection system adaptability of the present embodiment changes shifts method suitable for system as shown in Figure 2 automatically.? In Fig. 2, production executive system MES is connected with data collection system, and data collection system passes through redundant optical fiber looped network and each number It is connected according to acquisition station, wherein in Fig. 2, data collection station referred to as number adopts station.
Data collection system also passes through redundant optical fiber looped network and is connected with other control system or cigarette machine, such as:
Glyceride transportation system, filter stick conveying switching station, pipe tobacco conveying switching station, useless cigarette processor, power source two Grade metering, cut tobacco storing cabinet control system, volume packet centralized lighting system, conveying system of carton cigarette, volume packet dust pelletizing system and Pneumatic silk feeding system System etc..
In terms of time service calibration, the present embodiment passes through fiber redundant ring network data acquisition system using DAS Timer server System is connected to carry out time calibration, guarantees the time unification of each system or device.
Fig. 1 is that a kind of data collection system adaptability that the embodiment of the present disclosure provides is changed shifts method flow diagram automatically.
The method as shown in Figure 1, a kind of data collection system adaptability of the present embodiment is changed shifts automatically, comprising:
S101: plant calendar and Order Scheduling that production executive system MES in upper layer is issued are received.
Specifically, the plant calendar that production executive system MES in upper layer is issued includes date and the place that factory is in work In the date of inoperative.
It is corresponding that Order Scheduling with factory is in the date of work.Order Scheduling includes the type, quantity of cigarette in order And the deadline.
S102: day order plan is split as the quantity same day shift equal with shift and produces work order.
Such as: according to production scheduled production rule, the fixation working time of each production board operator of setting, three-shift system For T1, T2, T3.
In triple shift situation, day order plan is split as 3 corresponding same day shifts and produces work order, it is right respectively Answer T1, T2 and T3.
S103: same day shift after the approval produces work order and is issued to each production board;Same day shift produces work Singly issuing the time earlier than same day first opens a class time.
Specifically, production board is used to execute corresponding shift production work order task in corresponding shift.
Such as: setting same day shift production work order issues time t, and same day first opens a class time t0, then, same day shift is raw Produce work order issue time t (8:00) earlier than same day first open a class time t0 (such as: 8:30).
In specific implementation, production board includes molding machine, transmitter, cigarette machine, packing machine and case packer.
S104: according to shift alt time, starting and stopping for data collection system is automatically controlled.
In another embodiment, the data collection system adaptability is changed shifts method automatically, further includes:
If shift alt time point be changing shifts point, when each production board to change shifts put when, save current shift yield, Consumption, rejecting amount, shutdown/runing time, failure and number.
In another embodiment, when each production board is to when changing shifts, the yield of each production board of automatic clear disappears Consumption, rejecting amount, shutdown/runing time, failure and number restart to count the yield of each production board, consumption, pick Except amount, shutdown/runing time, failure and number.
Such as: reach the interval of service point T1, T2, T3, work order on duty, which has been audited, to be issued, and working work order is over, data Acquisition information has been saved, and current acquisition data are 0.
In specific implementation, according to shift alt time, the mistake of data collection system started and stopped is automatically controlled Cheng Zhong, if current time has reached interval of service point and current shift production work order is over, corresponding data has been saved, control Data collection system stops working.
In specific implementation, according to shift alt time, the mistake of data collection system started and stopped is automatically controlled Cheng Zhong does not receive shift delay information and receives next production work order if current time has reached interval of service point, will Current data acquisition value is reset, and control data collection system is started to work.
In specific implementation, according to shift alt time, the mistake of data collection system started and stopped is automatically controlled Cheng Zhong, if current time has reached interval of service point and received shift delay information, data collection system works on, until connecing It receives work order and terminates order and stop working.
Such as: reach the interval of service point T1, T2, T3, do not receive shift delay information, Current data acquisition value has obtained It saves, Current data acquisition value is reset.Shift delay information is received, work order is continued to run until manual operation terminates work order It completes.
In specific implementation, the numerical value of data collection system acquisition is divided into accumulated value data type, more new data type, note Record data type these three;Wherein, accumulated value data type is from production board acquisition data volume and accumulation calculating obtains finally Value;More new data type is to obtain data from production board directly to update storage to obtain end value;Recording data type is record Data type changes and is both saved.
Specifically, as shown in figure 3, the numerical value of data collection system acquisition is divided into accumulated value data type S, updates data class Type G, tri- kinds of data type M of record.
Accumulated value data type S: obtaining data volume from terminal device and accumulation calculating obtain end value, if last cumulative Save value SS, current cumulative process value DS, add up reception value JS.DS (update)=DS+JS.As DS > SS, DS value is assigned to SS.Condition DS < SS value need to be met when changing shifts, SS is reset after saving to database, DS is directly reset.Receive shift delay letter After breath, SS, DS lose count of zero in the interval of service, and until manual operation terminates work order, SS data are saved to database and clear at this time Zero.
More new data type C: obtaining data from terminal device and directly update storage to obtain end value, if last update is protected Value SC, current renewal process value DC are deposited, reception value JC is updated.DC (update)=JC.As DC > SC, DC value is assigned to SC.Occur Condition DC < SC need to be met when changing shifts, SC is reset after saving to database, DC is directly reset.After receiving shift delay information, SC is not It resets, JC clearing, at this point, SC=SC+DC, until manual operation terminates work order, SC data are saved to database and clearing at this time.
Record data type M: record data type M, which changes, both to be saved.
The present embodiment changes more device data acquisition system production order production methods between Cigarette manufacturing enterprises volume hired car Class's process carries out in such a way that adaptability is changed shifts automatically, greatly improves the accuracy of data acquisition, reduces manual intervention Caused by data acquisition errors, reduce labor intensity of operating staff.
Fig. 4 is that a kind of data collection system adaptability that the embodiment of the present disclosure provides is changed shifts apparatus structure schematic diagram automatically.
The device as shown in figure 4, a kind of data collection system adaptability of the present embodiment is changed shifts automatically, comprising:
Order reception module 101, by receiving based on the plant calendar and order that upper layer production executive system MES is issued It draws.
Specifically, the plant calendar that production executive system MES in upper layer is issued includes date and the place that factory is in work In the date of inoperative.
It is corresponding that Order Scheduling with factory is in the date of work.Order Scheduling includes the type, quantity of cigarette in order And the deadline.
It is raw to be used to for day order plan being split as the quantity same day shift equal with shift for order division module 102 Produce work order.
Such as: according to production scheduled production rule, the fixation working time of each production board operator of setting, three-shift system For T1, T2, T3.
In triple shift situation, day order plan is split as 3 corresponding same day shifts and produces work order, it is right respectively Answer T1, T2 and T3.
Production work order issues module 103, is used for same day shift production work order after the approval and is issued to each life Produce board;Same day shift production work order issues the time and earlier than same day first opens a class time.
Specifically, production board is used to execute corresponding shift production work order task in corresponding shift.
Such as: setting same day shift production work order issues time t, and same day first opens a class time t0, then, same day shift is raw Produce work order issue time t (8:00) earlier than same day first open a class time t0 (such as: 8:30).
In specific implementation, production board includes molding machine, transmitter, cigarette machine, packing machine and case packer.
Data collection system start-up and shut-down control module 104 is used to automatically control data acquisition system according to shift alt time System starts and stops.
In another embodiment, the data collection system adaptability is changed shifts device automatically, further includes:
Data recordin module, be used to set shift alt time point as change shifts point, when each production board to change shifts put when, Save yield, consumption, rejecting amount, shutdown/runing time, failure and the number of current shift.
Such as: reach the interval of service point T1, T2, T3, work order on duty, which has been audited, to be issued, and working work order is over, data Acquisition information has been saved, and current acquisition data are 0.
In specific implementation, in the data recordin module, when each production board is to when changing shifts, automatic clear is each Yield, consumption, rejecting amount, shutdown/runing time, failure and the number of a production board, restart to count each production Yield, consumption, rejecting amount, shutdown/runing time, failure and the number of board.
In specific implementation, in the data collection system start-up and shut-down control module, if current time has reached the interval of service Point and current shift produce work order and are over, and corresponding data has saved, and control data collection system stops working.
In specific implementation, in the data collection system start-up and shut-down control module, if current time has reached the interval of service Point does not receive shift delay information and receives next production work order, Current data acquisition value is reset, data are controlled Acquisition system is started to work.
In specific implementation, in the data collection system start-up and shut-down control module, if current time has reached the interval of service It puts and receives shift delay information, data collection system works on, and stops working until receiving work order and terminating order.
Such as: reach the interval of service point T1, T2, T3, do not receive shift delay information, Current data acquisition value has obtained It saves, Current data acquisition value is reset.Shift delay information is received, work order is continued to run until manual operation terminates work order It completes.
In specific implementation, the numerical value of data collection system acquisition is divided into accumulated value data type, more new data type, note Record data type these three;Wherein, accumulated value data type is from production board acquisition data volume and accumulation calculating obtains finally Value;More new data type is to obtain data from production board directly to update storage to obtain end value;Recording data type is record Data type changes and is both saved.
Specifically, as shown in figure 3, the numerical value of data collection system acquisition is divided into accumulated value data type S, updates data class Type G, tri- kinds of data type M of record.
Accumulated value data type S: obtaining data volume from terminal device and accumulation calculating obtain end value, if last cumulative Save value SS, current cumulative process value DS, add up reception value JS.DS (update)=DS+JS.As DS > SS, DS value is assigned to SS.Condition DS < SS value need to be met when changing shifts, SS is reset after saving to database, DS is directly reset.Receive shift delay letter After breath, SS, DS lose count of zero in the interval of service, and until manual operation terminates work order, SS data are saved to database and clear at this time Zero.
More new data type C: obtaining data from terminal device and directly update storage to obtain end value, if last update is protected Value SC, current renewal process value DC are deposited, reception value JC is updated.DC (update)=JC.As DC > SC, DC value is assigned to SC.Occur Condition DC < SC need to be met when changing shifts, SC is reset after saving to database, DC is directly reset.After receiving shift delay information, SC is not It resets, JC clearing, at this point, SC=SC+DC, until manual operation terminates work order, SC data are saved to database and clearing at this time.
Record data type M: record data type M, which changes, both to be saved.
The present embodiment changes more device data acquisition system production order production methods between Cigarette manufacturing enterprises volume hired car Class's process carries out in such a way that adaptability is changed shifts automatically, greatly improves the accuracy of data acquisition, reduces manual intervention Caused by data acquisition errors, reduce labor intensity of operating staff.
In another embodiment, a kind of this computer readable storage medium is additionally provided, computer program is stored thereon with, It is characterized in that, the program realizes that data collection system adaptability as shown in Figure 1 is changed shifts method automatically when being executed by processor In step.
In another embodiment, it additionally provides a kind of computer equipment, including memory, processor and is stored in memory Computer program that is upper and can running on a processor, which is characterized in that the processor realizes such as Fig. 1 when executing described program Shown in the data collection system adaptability step in changing shifts method automatically.
It should be understood by those skilled in the art that, embodiment of the disclosure can provide as method, system or computer program Product.Therefore, the shape of hardware embodiment, software implementation or embodiment combining software and hardware aspects can be used in the disclosure Formula.Moreover, the disclosure, which can be used, can use storage in the computer that one or more wherein includes computer usable program code The form for the computer program product implemented on medium (including but not limited to magnetic disk storage and optical memory etc.).
The disclosure be referring to according to the method for the embodiment of the present invention, the process of equipment (system) and computer program product Figure and/or block diagram describe.It should be understood that every one stream in flowchart and/or the block diagram can be realized by computer program instructions The combination of process and/or box in journey and/or box and flowchart and/or the block diagram.It can provide these computer programs Instruct the processor of general purpose computer, special purpose computer, Embedded Processor or other programmable data processing devices to produce A raw machine, so that being generated by the instruction that computer or the processor of other programmable data processing devices execute for real The device for the function of being specified in present one or more flows of the flowchart and/or one or more blocks of the block diagram.
These computer program instructions, which may also be stored in, is able to guide computer or other programmable data processing devices with spy Determine in the computer-readable memory that mode works, so that it includes referring to that instruction stored in the computer readable memory, which generates, Enable the manufacture of device, the command device realize in one box of one or more flows of the flowchart and/or block diagram or The function of being specified in multiple boxes.
These computer program instructions also can be loaded onto a computer or other programmable data processing device, so that counting Series of operation steps are executed on calculation machine or other programmable devices to generate computer implemented processing, thus in computer or The instruction executed on other programmable devices is provided for realizing in one or more flows of the flowchart and/or block diagram one The step of function of being specified in a box or multiple boxes.
Those of ordinary skill in the art will appreciate that realizing all or part of the process in above-described embodiment method, being can be with Relevant hardware is instructed to complete by computer program, the program can be stored in a computer-readable storage medium In, the program is when being executed, it may include such as the process of the embodiment of above-mentioned each method.Wherein, the storage medium can be magnetic Dish, CD, read-only memory (Read-Only Memory, ROM) or random access memory (Random AccessMemory, RAM) etc..
Although above-mentioned be described in conjunction with specific embodiment of the attached drawing to the disclosure, model not is protected to the disclosure The limitation enclosed, those skilled in the art should understand that, on the basis of the technical solution of the disclosure, those skilled in the art are not Need to make the creative labor the various modifications or changes that can be made still within the protection scope of the disclosure.

Claims (10)

  1. A kind of method 1. data collection system adaptability is changed shifts automatically, wherein data collection system is connected with each production platform machine, It is characterized in that, this method is completed in processor, comprising:
    Receive plant calendar and Order Scheduling that production executive system MES in upper layer is issued;
    Day order plan is split as the quantity same day shift equal with shift and produces work order;
    Same day shift after the approval produces work order and is issued to each production board;Same day shift production work order issues the time A class time is opened earlier than same day first;
    According to shift alt time, starting and stopping for data collection system is automatically controlled.
  2. The method 2. a kind of data collection system adaptability as described in claim 1 is changed shifts automatically, which is characterized in that the data Acquisition system adaptability is changed shifts method automatically, further includes:
    If shift alt time point is changing shifts point, when each production board to yield, the consumption for when changing shifts, saving current shift Amount, rejecting amount, shutdown/runing time, failure and number.
  3. The method 3. a kind of data collection system adaptability as claimed in claim 2 is changed shifts automatically, which is characterized in that when each life When production board is put to changing shifts, yield, consumption, the rejecting amount, shutdown/runing time, failure of each production board of automatic clear And number, restart the yield, consumption, rejecting amount, shutdown/runing time, failure and the number that count each production board.
  4. The method 4. a kind of data collection system adaptability as described in claim 1 is changed shifts automatically, which is characterized in that according to class Secondary alt time, during automatically controlling the starting and stopping of data collection system, if current time has reached interval of service point And current shift production work order is over, corresponding data has saved, and control data collection system stops working;
    Or/and
    During according to shift alt time, automatically controlling the starting and stopping of data collection system, if current time is Up to interval of service point, shift delay information is not received and receives next production work order, Current data acquisition value is clear Zero, control data collection system is started to work;
    Or/and
    During according to shift alt time, automatically controlling the starting and stopping of data collection system, if current time is Up to interval of service point and shift delay information is received, data collection system works on, until receiving work order terminates order It stops working;
    Or/and
    Data collection system acquisition numerical value be divided into accumulated value data type, more new data type, record data type these three; Wherein, accumulated value data type is from production board acquisition data volume and accumulation calculating obtains end value;More new data type is Data are obtained from production board directly to update storage to obtain end value;Record data type is that record data type changes both It is saved.
  5. The device 5. a kind of data collection system adaptability is changed shifts automatically characterized by comprising
    Order reception module is used to receive plant calendar and Order Scheduling that upper layer production executive system MES is issued;
    Order division module is used to for day order plan being split as the quantity same day shift production work order equal with shift;
    Production work order issues module, is used for same day shift production work order after the approval and is issued to each production board; Same day shift production work order issues the time and earlier than same day first opens a class time;
    Data collection system start-up and shut-down control module is used to automatically control opening for data collection system according to shift alt time Dynamic and stopping.
  6. The device 6. a kind of data collection system adaptability as claimed in claim 5 is changed shifts automatically, which is characterized in that the data Acquisition system adaptability is changed shifts device automatically, further includes:
    Data recordin module is used to set shift alt time point as point of changing shifts, when each production board is put to changing shifts, saves Yield, consumption, rejecting amount, shutdown/runing time, failure and the number of current shift.
  7. The device 7. a kind of data collection system adaptability as claimed in claim 6 is changed shifts automatically, which is characterized in that in the number According in logging modle, when each production board is to changing shifts point, the yield of each production board of automatic clear, consumption, rejecting Amount, shutdown/runing time, failure and number restart to count the yield of each production board, consumption, rejecting amount, stop Machine/runing time, failure and number.
  8. The device 8. a kind of data collection system adaptability as claimed in claim 5 is changed shifts automatically, which is characterized in that in the number According in acquisition system start-up and shut-down control module, if current time has reached interval of service point and current shift production work order has been tied Beam, corresponding data have saved, and control data collection system stops working;
    Or/and
    In the data collection system start-up and shut-down control module, if current time has reached interval of service point, shift is not received and is prolonged Slow information and next production work order is received, Current data acquisition value is reset, control data collection system is started to work;
    Or/and
    In the data collection system start-up and shut-down control module, if current time has reached interval of service point and has received shift delay Information, data collection system work on, and stop working until receiving work order and terminating order;
    Or/and
    Data collection system acquisition numerical value be divided into accumulated value data type, more new data type, record data type these three; Wherein, accumulated value data type is from production board acquisition data volume and accumulation calculating obtains end value;More new data type is Data are obtained from production board directly to update storage to obtain end value;Record data type is that record data type changes both It is saved.
  9. 9. a kind of computer readable storage medium, is stored thereon with computer program, which is characterized in that the program is held by processor It realizes when row with the step in data collection system adaptability such as of any of claims 1-4 automatically changing shifts method.
  10. 10. a kind of computer equipment including memory, processor and stores the meter that can be run on a memory and on a processor Calculation machine program, which is characterized in that the processor is realized when executing described program with such as of any of claims 1-4 The data collection system adaptability step in changing shifts method automatically.
CN201910185047.2A 2019-03-12 2019-03-12 Adaptive automatic shift changing method and device for data acquisition system Active CN109919497B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910185047.2A CN109919497B (en) 2019-03-12 2019-03-12 Adaptive automatic shift changing method and device for data acquisition system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910185047.2A CN109919497B (en) 2019-03-12 2019-03-12 Adaptive automatic shift changing method and device for data acquisition system

Publications (2)

Publication Number Publication Date
CN109919497A true CN109919497A (en) 2019-06-21
CN109919497B CN109919497B (en) 2021-06-18

Family

ID=66964317

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910185047.2A Active CN109919497B (en) 2019-03-12 2019-03-12 Adaptive automatic shift changing method and device for data acquisition system

Country Status (1)

Country Link
CN (1) CN109919497B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112330198A (en) * 2020-11-24 2021-02-05 苏州索尔智行新能源科技有限公司 Driver shift control method, device, computer equipment and storage medium

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120029971A1 (en) * 2010-07-30 2012-02-02 Lynn Lee Method and apparatus for risk identification and mitigation in shift work fatigue
CN103729740A (en) * 2013-12-30 2014-04-16 北京施达优技术有限公司 Data processing method and device for generating production plan
CN106779308A (en) * 2016-11-23 2017-05-31 智能云科信息科技有限公司 A kind of System and method for of the shop Planning scheduling towards discrete manufacture
CN108762211A (en) * 2018-04-13 2018-11-06 深圳市新天能科技开发有限公司 Industrial production line cloud monitoring system
CN109190944A (en) * 2018-08-20 2019-01-11 国药集团重庆医药设计院有限公司 Medicine enterprise manufactures execution system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120029971A1 (en) * 2010-07-30 2012-02-02 Lynn Lee Method and apparatus for risk identification and mitigation in shift work fatigue
CN103729740A (en) * 2013-12-30 2014-04-16 北京施达优技术有限公司 Data processing method and device for generating production plan
CN106779308A (en) * 2016-11-23 2017-05-31 智能云科信息科技有限公司 A kind of System and method for of the shop Planning scheduling towards discrete manufacture
CN108762211A (en) * 2018-04-13 2018-11-06 深圳市新天能科技开发有限公司 Industrial production line cloud monitoring system
CN109190944A (en) * 2018-08-20 2019-01-11 国药集团重庆医药设计院有限公司 Medicine enterprise manufactures execution system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
莫哲萌: "基于Modbus总线的产线数据采集管理系统及应用", 《中国优秀硕士学位论文全文数据库信息科技辑》 *
陈睿 等: "烟草制造行业中的数据采集系统", 《计算机应用》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112330198A (en) * 2020-11-24 2021-02-05 苏州索尔智行新能源科技有限公司 Driver shift control method, device, computer equipment and storage medium

Also Published As

Publication number Publication date
CN109919497B (en) 2021-06-18

Similar Documents

Publication Publication Date Title
CN108320069B (en) Production and manufacturing execution system
CN107767068B (en) Lean production advanced plan scheduling system and method
CN111880502B (en) Factory equipment preventive maintenance scheduling system and method based on delivery satisfaction
CN105160439B (en) A kind of production scheduling method and automatic arrangement program system
CN101639687B (en) Integrated technology quality control system and realization method thereof
CN108614526B (en) Reconfigurable production process management system
CN104951905A (en) Equipment dynamic ledger management system
CN105824300A (en) Heavy type intelligent factory system based on IoT (Internet of Things) technology and digital management technology
CN111047257A (en) Production order management system based on 5G network
CN103197634B (en) Generating system and generating method of on-line prediction and on-line processing plan for automatic manufacturing and processing system
CN110633839A (en) Kneading algorithm-based power failure maintenance plan analysis and optimization system
CN112465454B (en) Scheduling system and method applied to order production process
CN103336490B (en) A kind of cigarette flexible tobacco-strips producing dynamic dispatching method and system thereof
CN109615233B (en) Intelligent water affair management platform based on basic data acquisition
CN112462702A (en) Intelligent monitoring and intelligent scheduling system based on industrial internet
CN110516939A (en) Warehouse homework dispatches system
CN117010613A (en) Intelligent production planning and scheduling method, system, computer equipment and storage medium
CN108319638B (en) Dangerous goods production and manufacturing execution system applying handheld inspection equipment
CN111913943A (en) Data acquisition and processing method and system suitable for automatic factory scheduling
CN114742662A (en) Production management method, production management device, electronic device, and storage medium
CN109919497A (en) A kind of data collection system adaptability is changed shifts method and device automatically
CN105761008A (en) Intelligent production management method for signal equipment maintenance
CN116258337A (en) Industry chain collaborative management system based on enterprise manufacturing operation
CN109934425A (en) A kind of intelligent plant customization planning system and its method
CN107797856A (en) Plan target management-control method, device and storage medium based on windows services

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant