CN109914833A - 一种基坑土方开挖阶段防尘棚搭设方法 - Google Patents

一种基坑土方开挖阶段防尘棚搭设方法 Download PDF

Info

Publication number
CN109914833A
CN109914833A CN201910226212.4A CN201910226212A CN109914833A CN 109914833 A CN109914833 A CN 109914833A CN 201910226212 A CN201910226212 A CN 201910226212A CN 109914833 A CN109914833 A CN 109914833A
Authority
CN
China
Prior art keywords
steel
dust
proof shed
pit
erection method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910226212.4A
Other languages
English (en)
Inventor
范光云
梁广远
汪从
卢学建
赵叶辉
牛胜民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201910226212.4A priority Critical patent/CN109914833A/zh
Publication of CN109914833A publication Critical patent/CN109914833A/zh
Pending legal-status Critical Current

Links

Abstract

一种基坑土方开挖阶段防尘棚搭设方法,基坑周边支撑体系采用φ700mm钢筋混凝土灌注桩+止水帷幕,基坑的水平支撑体系采用一道钢筋混凝土梁板式临时支撑+格构柱竖向支撑体系,其特征在于包括以下步骤:a、工字钢预埋,b、支撑梁浇筑,c、设置支撑点,d、钢丝绳对拉,e、铺设防尘网。本发明的基坑土方开挖阶段防尘棚搭设方法具有挖土速度较快,防尘棚搭设在水平支撑养护阶段进行,不占用土方开挖时间,且在挖土过程中不考虑防尘网苫盖及揭开等工序,不影响土方开挖进度,工艺简单、施工方便,防尘棚搭设简单,使用时间长,此种防尘方法更易于推广使用和节约成本的优点。

Description

一种基坑土方开挖阶段防尘棚搭设方法
技术领域
本发明涉及一种建筑施工现场防尘棚搭设方法,具体地说,是一种基坑土方开挖阶段防尘棚搭设方法。
背景技术
目前国家高度重视环保治理工作,特别是在建筑行业如何治理扬尘已成为重中之重。土方开挖阶段扬尘控制措施一般有湿作业挖土及裸露土苫盖两种方式,采用人工苫盖土方存在苫盖不及时、防尘网易破损及苫盖不严密等问题,如何有效解决苫盖问题成为目前扬尘控制重点。
南开服装一厂地块定向安置经济适用房项目基坑面积13200㎡,基坑开挖深度10米左右,土方量13万m³。本工程地处天津市南开区城市中心,周边环境复杂,土方开挖持续时间长,如不能有效治理扬尘将给项目带来极大负面影响。
因此已知的建筑施工现场扬尘控制措施存在着上述种种不便和问题。
发明内容
本发明的目的,在于提出一种安全可靠的基坑土方开挖阶段防尘棚搭设方法。
为实现上述目的,本发明的技术解决方案是:
一种基坑土方开挖阶段防尘棚搭设方法,基坑周边支撑体系采用φ700mm钢筋混凝土灌注桩+止水帷幕,基坑的水平支撑体系采用一道钢筋混凝土梁板式临时支撑+格构柱竖向支撑体系,其特征在于包括以下步骤:
a、工字钢预埋
在基坑水平支撑体系上每隔4米预埋工字钢作支撑立柱,工字钢长6米,埋入帽梁0.7米,工字钢腹板垂直于帽梁长边设置;
b、支撑梁浇筑
预埋工字钢与支撑梁钢筋焊接固定,浇筑过程中避免工字钢扰动,并振捣密实;
c、设置支撑点
由于基坑环形支撑跨度≥80000mm,在中间位置设置两个支撑点,支撑点处下挖至标高-4.1米打入12米长钢板桩,并在钢板桩端部用角钢焊接为整体;钢板桩端部焊接7.6米长工字钢,工字钢中部设置4道揽风绳;开挖后在钢板桩外露部分设置4道斜撑,保证支撑点稳定;
d、钢丝绳对拉
用12#6*37钢丝绳在对应的立柱两端对拉固定;
e、铺设防尘网
在基坑侧面及顶面钢丝绳上铺1500目绿色防尘网,防尘网接口用扎丝绑扎连接。
本发明的基坑土方开挖阶段防尘棚搭设方法还可以采用以下的技术措施来进一步实现。
前述的方法,其中所述工字钢为12.6#工字钢。
前述的方法,其中所述立柱设置揽风绳。
前述的方法,其中所述钢板桩呈一顺一丁布置。
采用上述技术方案后,本发明的基坑土方开挖阶段防尘棚搭设方法具有以下优点:
1、挖土速度较快,防尘棚搭设在水平支撑养护阶段进行,不占用土方开挖时间,且在挖土过程中不考虑防尘网苫盖及揭开等工序,不影响土方开挖进度;
2、工艺简单、施工方便,防尘棚搭设简单,使用时间长,此种防尘方法更易于推广使用;
3、节约成本,采用此种方法大大节约了人工苫盖费用,防尘网只需一次购买,损耗基本为零。本项目节约人工费及材料费约20万左右。
附图说明
图1为本发明实施例的基坑水平支撑平面布置图;
图2为本发明实施例的防尘棚平面布置图;
图3为本发明实施例的钢板桩作一顺一丁布置的结构示意图。
图中:1防尘网,2中间支撑点,3立柱,4钢丝绳,5支撑梁,6出土大门。
具体实施方式
以下结合实施例及其附图对本发明作更进一步说明。
实施例1
现请参阅图1,图1为本发明实施例的基坑水平支撑平面布置图。本发明的基坑土方开挖阶段防尘棚搭设方法工艺流程及施工方法:工字钢预埋→支撑梁浇筑→设置支撑点→钢丝绳对拉→平面铺设防尘网→立面铺设防尘网。
本发明的基坑土方开挖阶段防尘棚搭设方法,包括以下步骤:
a、工字钢预埋
图2为本发明实施例的防尘棚平面布置图。如图所示,在基坑水平支撑体系上每隔4米预埋12.6#工字钢作支撑立柱,工字钢长6米,埋入帽梁0.7米,工字钢腹板垂直于帽梁长边设置,为保证其稳定性。每根工字钢设置揽风绳;
b、支撑梁浇筑
预埋工字钢与支撑梁钢筋焊接固定,浇筑过程中避免工字钢扰动,并振捣密实;
c、设置支撑点:由于环形支撑跨度较大,在中间位置设置两个支撑点,支撑点处下挖至标高-4.1米打入12米长钢板桩(一顺一丁),并在端部用角钢焊接为整体。端部焊接7.6米长12.6#工字钢,工字钢中部设置4道揽风绳;开挖后在钢板桩外露部分设置4道斜撑,保证支撑点稳定;图3为本发明实施例的钢板桩作一顺一丁布置的结构示意图。
d、钢丝绳对拉
用12#6*37钢丝绳两端对拉固定;
e、铺设防尘网
侧面及顶面铺1500目绿色防尘网,防尘网接口用扎丝绑扎连接。
本发明的基坑土方开挖阶段防尘棚搭设时注意:防尘棚安装高度宜结合挖土机械的作业面及防尘网下挠高度综合确定;防尘棚重量不宜超过基坑边堆载要求。
基坑土方开挖阶段防尘棚搭设本发明具有实质性特点和显著的技术进步,本发明的基坑土方开挖阶段防尘棚搭设方法中防尘网苫盖方法简单,既保证了土方开挖施工进度又大大地节约了扬尘治理措施费用,适用于各类基坑的土方开挖。
以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变化。因此,所有等同的技术方案也应该属于本发明的范畴,应由各权利要求限定。

Claims (4)

1.一种基坑土方开挖阶段防尘棚搭设方法,基坑周边支撑体系采用φ700mm钢筋混凝土灌注桩+止水帷幕,基坑的水平支撑体系采用一道钢筋混凝土梁板式临时支撑+格构柱竖向支撑体系,其特征在于包括以下步骤:
a、工字钢预埋
在基坑水平支撑体系上每隔4米预埋工字钢作支撑立柱,工字钢长6米,埋入帽梁0.7米,工字钢腹板垂直于帽梁长边设置;
b、支撑梁浇筑
预埋工字钢与支撑梁钢筋焊接固定,浇筑过程中避免工字钢扰动,并振捣密实;
c、设置支撑点
由于基坑环形支撑跨度≥80000mm,在中间位置设置两个支撑点,支撑点处下挖至标高-4.1米打入12米长钢板桩,并在钢板桩端部用角钢焊接为整体;钢板桩端部焊接7.6米长工字钢,工字钢中部设置4道揽风绳;开挖后在钢板桩外露部分设置4道斜撑,保证支撑点稳定;
d、钢丝绳对拉
用12#6*37mm钢丝绳在对应的立柱两端对拉固定;
e、铺设防尘网
在基坑侧面及顶面钢丝绳上铺1500目绿色防尘网,防尘网接口用扎丝绑扎连接。
2.如权利要求1所述的基坑土方开挖阶段防尘棚搭设方法,其特征在于,所述工字钢为12.6#工字钢。
3.如权利要求1所述的基坑土方开挖阶段防尘棚搭设方法,其特征在于,所述立柱设置揽风绳。
4.如权利要求1所述的基坑土方开挖阶段防尘棚搭设方法,其特征在于,所述钢板桩呈一顺一丁布置。
CN201910226212.4A 2019-03-25 2019-03-25 一种基坑土方开挖阶段防尘棚搭设方法 Pending CN109914833A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910226212.4A CN109914833A (zh) 2019-03-25 2019-03-25 一种基坑土方开挖阶段防尘棚搭设方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910226212.4A CN109914833A (zh) 2019-03-25 2019-03-25 一种基坑土方开挖阶段防尘棚搭设方法

Publications (1)

Publication Number Publication Date
CN109914833A true CN109914833A (zh) 2019-06-21

Family

ID=66966604

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910226212.4A Pending CN109914833A (zh) 2019-03-25 2019-03-25 一种基坑土方开挖阶段防尘棚搭设方法

Country Status (1)

Country Link
CN (1) CN109914833A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110552513A (zh) * 2019-08-01 2019-12-10 中国一冶集团有限公司 一种基槽土石方作业防尘棚及搭设方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05141090A (ja) * 1991-11-22 1993-06-08 Takenaka Komuten Co Ltd 工区分割方式による全天候型の建物構築法
JPH084007A (ja) * 1994-06-20 1996-01-09 Shuji Takase 仮設シャッター用ジョイント基礎
CN105155554A (zh) * 2015-09-25 2015-12-16 武汉高铁桩工科技有限公司 一种拱形支护体系的深基坑
CN105401585A (zh) * 2015-11-24 2016-03-16 中国建筑第八工程局有限公司 利用基坑支撑体系承托塔吊的结构及其施工方法
CN106049888A (zh) * 2016-07-18 2016-10-26 中铁隧道集团二处有限公司 明挖基坑内施工防雨棚
CN107366435A (zh) * 2017-05-25 2017-11-21 上海建工四建集团有限公司 全封闭式绿色施工围挡及其施工方法
CN108756262A (zh) * 2018-07-06 2018-11-06 上海宝冶集团有限公司 一种基坑大跨度自动覆盖系统

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05141090A (ja) * 1991-11-22 1993-06-08 Takenaka Komuten Co Ltd 工区分割方式による全天候型の建物構築法
JPH084007A (ja) * 1994-06-20 1996-01-09 Shuji Takase 仮設シャッター用ジョイント基礎
CN105155554A (zh) * 2015-09-25 2015-12-16 武汉高铁桩工科技有限公司 一种拱形支护体系的深基坑
CN105401585A (zh) * 2015-11-24 2016-03-16 中国建筑第八工程局有限公司 利用基坑支撑体系承托塔吊的结构及其施工方法
CN106049888A (zh) * 2016-07-18 2016-10-26 中铁隧道集团二处有限公司 明挖基坑内施工防雨棚
CN107366435A (zh) * 2017-05-25 2017-11-21 上海建工四建集团有限公司 全封闭式绿色施工围挡及其施工方法
CN108756262A (zh) * 2018-07-06 2018-11-06 上海宝冶集团有限公司 一种基坑大跨度自动覆盖系统

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110552513A (zh) * 2019-08-01 2019-12-10 中国一冶集团有限公司 一种基槽土石方作业防尘棚及搭设方法

Similar Documents

Publication Publication Date Title
CN102505695B (zh) 一种立体车库深基坑施工方法
CN102031784B (zh) 深基坑灌注护坡桩加锚索支护施工方法
CN105133627B (zh) 单壁钢板桩围堰流水状态下施工工法
CN104074199B (zh) 一种水下承台施工工法
CN106758841B (zh) 一种双塔双索面矮塔斜拉桥的整体施工工艺
CN204491626U (zh) 拉森钢板桩与预应力锚杆组合的基坑围护结构
CN205776347U (zh) 用于地铁车站的新型盖挖逆作结构体系
CN1948633A (zh) 盆式开挖逆作法施工方法
CN103938634B (zh) 一种深基坑支护结构及施工方法
CN107938692A (zh) 一种排水及回灌施工方法及结构
CN105756091B (zh) 一种控制邻近建筑物变形的地铁车站基坑施工方法
CN106320377A (zh) 一种富水软土地区深基坑盖挖逆作施工方法
CN100510281C (zh) 超大直径、超埋深度调蓄池的半逆作施工方法
CN105804089A (zh) 一种原深基坑施工后局部增深支护体系及其施工方法
CN106087746A (zh) 一种现浇箱梁膺架施工方法以及桥梁
CN105863042A (zh) 一种全钢结构建筑及其施工方法
CN104563146A (zh) 定直埋式雨污水泵站沉井工程施工方法
CN102758458A (zh) 地下连续墙修复方法
CN105133581A (zh) 支护结构中抗拔桩、格构柱及降水井三合一施工方法
CN109706952A (zh) 大型沉井施工方法
CN104652444B (zh) 超大型深基坑中心岛式交替土方开挖的整体逆作施工方法
CN101638898B (zh) 顶管竖井悬挂式施工方法
CN106065668B (zh) 一种建筑施工方法
CN111894023A (zh) 陡坡桥梁基础的施工方法
CN102235007B (zh) 上钉下桩组合的深基支护方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190621

RJ01 Rejection of invention patent application after publication