CN109914804A - A kind of assembled architecture top grouting process - Google Patents

A kind of assembled architecture top grouting process Download PDF

Info

Publication number
CN109914804A
CN109914804A CN201910150804.2A CN201910150804A CN109914804A CN 109914804 A CN109914804 A CN 109914804A CN 201910150804 A CN201910150804 A CN 201910150804A CN 109914804 A CN109914804 A CN 109914804A
Authority
CN
China
Prior art keywords
grouting
sleeve
assembled architecture
dry wall
air
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910150804.2A
Other languages
Chinese (zh)
Other versions
CN109914804B (en
Inventor
傅甜蓉
陆咏梅
黄可为
陆忠元
洪伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changshu Jian Gong Construction Group Co Ltd
Original Assignee
Changshu Jian Gong Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changshu Jian Gong Construction Group Co Ltd filed Critical Changshu Jian Gong Construction Group Co Ltd
Priority to CN201910150804.2A priority Critical patent/CN109914804B/en
Publication of CN109914804A publication Critical patent/CN109914804A/en
Application granted granted Critical
Publication of CN109914804B publication Critical patent/CN109914804B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses grouting process at the top of a kind of assembled architecture, the following steps are included: the production of dry wall, dry wall carrier pour, assemble and are in the milk, it is connected to using slip casting gun barrel and the sleeve top of grouting equipment, grouting material is injected sleeve, meanwhile pumping operation is carried out to sleeve bottom using air-extractor, additional air is discharged, so that grouting material quickly sinks, grouting is realized.Through the above way, grouting process at the top of assembled architecture of the present invention, the grouting of sleeve is carried out from top, the grouting material after drawing guns is avoided to flow out problem, without blocking, property swift to operate is improved, and pumping operation is carried out to sleeve bottom using air-extractor, it avoids the problem that lacking material, improves charging efficiency and quality.

Description

A kind of assembled architecture top grouting process
Technical field
The present invention relates to technical field of building construction, more particularly to grouting process at the top of a kind of assembled architecture.
Background technique
In recent years, the promotion with various regions to construction site environmental requirement, prefabrication and assembly construction, which is built, to be grown rapidly.Relatively For traditional cast-in-situ steel reinforced concrete and masonry building building, prefabrication and assembly construction building precasts building structure using in plant produced Part transports the mode constructed to in-site installation.
Prefabrication and assembly construction building has many advantages, such as that easy for construction, project progress is fast, small to surrounding environment influence, starts in recent years It is used in civil buildings.It when prefabrication and assembly construction construction, needs to be in the milk to sleeve, realizes the fixation of structure.Existing skill In art, thick liquid discharge mouth usually is set in upper cartridge, grout hole is arranged in bottom, the grouting of sleeve is carried out from bottom using grout hole, Then extra grouting material is discharged by the thick liquid discharge mouth on top, realizes the grouting of sleeve, still, since grout hole is in bottom, knot After beam grouting, needs slip casting gun barrel to extract, then block, inevitably can grouting material be flowed out in the process, waste is serious, also It may cause to lack material problem because blocking not in time, need to improve.
Summary of the invention
The invention mainly solves the technical problem of providing grouting process at the top of a kind of assembled architecture, avoid grouting stream Waste is led to the problem of out, it is ensured that grouting material tamps in sleeve.
In order to solve the above technical problems, one technical scheme adopted by the invention is that: a kind of assembled architecture top is provided Grouting process, comprising the following steps:
A, the production of dry wall: according to architectural design specification requirement, tying up for wall steel bar net is carried out in factory, and in wall steel Several downwardly directed sleeves are arranged in the bottom of muscle net, are then placed in wall mold, carry out pouring for concrete, obtain pre- Wall processed;
B, dry wall carrier pours: according to architectural design specification requirement, carrying out dry wall carrier steel mesh at the construction field (site) It ties up, and carries out the enclosing of dry wall carrier steel mesh using template, form dry wall carrier after casting concrete, it is ensured that prefabricated Reinforcing bar positioning column corresponding with sleeve is protruded on wall carrier;
C, it assembles: dry wall being transported to construction site, is lifted on dry wall carrier, and the insertion of reinforcing bar positioning column is corresponded to Sleeve;
D, it is in the milk: using being connected at the top of the slip casting gun barrel and sleeve of grouting equipment, grouting material being injected sleeve, meanwhile, utilize pumping Gas equipment carries out pumping operation to sleeve bottom, and additional air is discharged, so that grouting material quickly sinks, realizes grouting.
In a preferred embodiment of the present invention, the sleeve top side is connected with grouting bend pipe.
In a preferred embodiment of the present invention, first extended to above sleeve is connected on the outside of the sleeve bottom to take out Tracheae, the first exhaust tube top are provided with the first outwardly directed gas-tpe fitting, and the first gas-tpe fitting and air-extractor connect It connects and additional air is discharged.
In a preferred embodiment of the present invention, the grouting bend pipe is the L shape bend pipe pointed up, the L shape bend pipe Top is provided with outwardly directed grouting connector, when grouting, utilizes grouting connector and the mating connection of slip casting gun barrel.
In a preferred embodiment of the present invention, the reinforcing bar positioning column and the welding of dry wall carrier steel mesh or one Change structure.
In a preferred embodiment of the present invention, hub internal bore bottom indent is provided with annular groove, the sleeve top Portion is provided with the stomata for extending downwardly and being connected to annular groove, is provided with the second exhaust tube extended outward at the top of the stomata, The second pumping pipe end is provided with the second outwardly directed gas-tpe fitting, and second gas-tpe fitting is connect with air-extractor And additional air is discharged.
In a preferred embodiment of the present invention, the air-extractor include aspiration pump and connect with aspiration pump one section thoroughly Bright pipeline when pumping, carries out the observation in pipeline, when there is continuous grouting material, indicates that grouting is completed, first stops pumping, Then stop being in the milk again.
In a preferred embodiment of the present invention, the air-extractor further includes the grouting material caching being connected on pipeline Pot.
The beneficial effects of the present invention are: grouting process at the top of a kind of assembled architecture that the present invention points out, carries out from top The grouting of sleeve avoids the grouting material after drawing guns from flowing out problem, without blocking, improves property swift to operate, and set using pumping It is standby that pumping operation is carried out to sleeve bottom, it avoids the problem that lacking material, improves charging efficiency and quality.
Specific embodiment
The technical scheme in the embodiments of the invention will be clearly and completely described below, it is clear that described implementation Example is only a part of the embodiments of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is common Technical staff's all other embodiment obtained without making creative work belongs to the model that the present invention protects It encloses.
The embodiment of the present invention includes:
Embodiment 1:
A kind of assembled architecture top grouting process, comprising the following steps:
A, the production of dry wall: according to architectural design specification requirement, tying up for wall steel bar net is carried out in factory, and in wall steel Several downwardly directed sleeves are arranged in the bottom of muscle net, weld at the top of wall steel bar net and sleeve, are then placed within wall mold In, pouring for concrete is carried out, dry wall is obtained, is transported again after maintenance to construction site, lifting construction progress is conducive to;
B, dry wall carrier pours: according to architectural design specification requirement, carrying out dry wall carrier steel mesh at the construction field (site) It ties up, and carries out the enclosing of dry wall carrier steel mesh using template, form dry wall carrier after casting concrete, it is ensured that prefabricated Reinforcing bar positioning column corresponding with sleeve is protruded on wall carrier, reinforcing bar positioning column is weldingly connected with dry wall carrier steel mesh, knot Structure is secured;
C, it assembles: dry wall being transported to construction site, is lifted on dry wall carrier, and the insertion of reinforcing bar positioning column is corresponded to Sleeve, dimensional accuracy is high;
D, it is in the milk: using being connected at the top of the slip casting gun barrel and sleeve of grouting equipment, grouting material being injected sleeve, the sleeve top Side is connected with grouting bend pipe, and the grouting bend pipe is the L shape bend pipe pointed up, is provided with direction at the top of the L shape bend pipe The grouting connector in outside, when grouting, using grouting connector and the mating connection of slip casting gun barrel, meanwhile, using air-extractor to sleeve Bottom carries out pumping operation, specifically, the first exhaust tube extended to above sleeve is connected on the outside of sleeve bottom, described Be provided with the first outwardly directed gas-tpe fitting at the top of one exhaust tube, the first gas-tpe fitting connect with air-extractor and be discharged it is extra Air realizes grouting so that grouting material quickly sinks, and avoids lacking material problem.
Embodiment 2:
A kind of assembled architecture top grouting process, comprising the following steps:
A, the production of dry wall: according to architectural design specification requirement, tying up for wall steel bar net is carried out in factory, and in wall steel Several downwardly directed sleeves are arranged in the bottom of muscle net, and wall steel bar net is connect at the top of sleeve using engagement thread, sleeve top Threaded hole, installation and adjusting convenience is arranged in portion, is then placed in wall mold, carries out pouring for concrete, obtain dry wall, Here dry wall is also possible to cylinder or beam body, and only dry wall uses more;
B, dry wall carrier pours: according to architectural design specification requirement, carrying out dry wall carrier steel mesh at the construction field (site) It ties up, and carries out the enclosing of dry wall carrier steel mesh using template, form dry wall carrier after casting concrete, it is ensured that prefabricated Reinforcing bar positioning column corresponding with sleeve, reinforcing bar positioning column and dry wall carrier steel mesh integral structure are protruded on wall carrier, Reinforcing bar positioning column is that a part of reinforcing bar to extend out, sound construction are bent from dry wall carrier steel mesh;
C, it assembles: dry wall being transported to construction site, is lifted on dry wall carrier, and the insertion of reinforcing bar positioning column is corresponded to Sleeve, bulge loop can be set on hub internal bore and reinforcing bar positioning column outer circle, the vertical structural stability after promoting grouting;
D, it is in the milk: using being connected at the top of the slip casting gun barrel and sleeve of grouting equipment, grouting material being injected sleeve, the sleeve top Side is connected with grouting bend pipe, and the grouting bend pipe is the L shape bend pipe pointed up, is provided with direction at the top of the L shape bend pipe The grouting connector in outside, when grouting, using grouting connector and the mating connection of slip casting gun barrel, meanwhile, using air-extractor to sleeve Bottom carries out pumping operation, specifically, hub internal bore bottom indent is provided with annular groove, be provided at the top of the sleeve to Lower extension and the stomata that be connected to annular groove are provided with the second exhaust tube extended outward, second pumping at the top of the stomata Tracheae end is provided with the second outwardly directed gas-tpe fitting, second gas-tpe fitting connect with air-extractor and be discharged it is extra Air realizes grouting so that grouting material quickly sinks, without carrying out the blocking of grouting connector.
In addition, for the convenience of lifting construction, the air-extractor includes aspiration pump and connect with aspiration pump one section Transparent pipeline, when pumping, transparent pipeline, which facilitates, carries out grouting material observation in pipeline, when there is continuous grouting material, indicates Grouting is completed, and is first stopped pumping, is then stopped being in the milk again.The air-extractor further includes the grouting material caching being connected on pipeline Pot, the grouting material of extraction cache in grouting material caching pot, unload grouting material caching pot when will be full, and the grouting material of the inside can be with It recycles, avoids waste problem, pumping pump steam inlet position is arranged strainer, grouting material is avoided to enter in aspiration pump and influence pumping The work of pump, stability in use are high.
In conclusion grouting process at the top of a kind of assembled architecture that the present invention points out, realizes the top grouting of sleeve Operation avoids the missing of grouting material in sleeve the problem of avoiding traditional bottom grouting and flow slurry.
The above description is only an embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair Equivalent structure or equivalent flow shift made by bright description is applied directly or indirectly in other relevant technology necks Domain is included within the scope of the present invention.

Claims (8)

1. grouting process at the top of a kind of assembled architecture, which comprises the following steps:
A, the production of dry wall: according to architectural design specification requirement, tying up for wall steel bar net is carried out in factory, and in wall steel Several downwardly directed sleeves are arranged in the bottom of muscle net, are then placed in wall mold, carry out pouring for concrete, obtain pre- Wall processed;
B, dry wall carrier pours: according to architectural design specification requirement, carrying out dry wall carrier steel mesh at the construction field (site) It ties up, and carries out the enclosing of dry wall carrier steel mesh using template, form dry wall carrier after casting concrete, it is ensured that prefabricated Reinforcing bar positioning column corresponding with sleeve is protruded on wall carrier;
C, it assembles: dry wall being transported to construction site, is lifted on dry wall carrier, and the insertion of reinforcing bar positioning column is corresponded to Sleeve;
D, it is in the milk: using being connected at the top of the slip casting gun barrel and sleeve of grouting equipment, grouting material being injected sleeve, meanwhile, utilize pumping Gas equipment carries out pumping operation to sleeve bottom, and additional air is discharged, so that grouting material quickly sinks, realizes grouting.
2. grouting process at the top of assembled architecture according to claim 1, which is characterized in that the sleeve top side connects It is connected to grouting bend pipe.
3. grouting process at the top of assembled architecture according to claim 1, which is characterized in that connect on the outside of the sleeve bottom It is connected to the first exhaust tube extended to above sleeve, the first outwardly directed tracheae is provided at the top of first exhaust tube and connects Head, the first gas-tpe fitting connect with air-extractor and additional air are discharged.
4. grouting process at the top of assembled architecture according to claim 2, which is characterized in that the grouting bend pipe is to be directed toward The L shape bend pipe of top, is provided with outwardly directed grouting connector at the top of the L shape bend pipe, when grouting, utilizes grouting connector and note Starch the mating connection of gun barrel.
5. grouting process at the top of assembled architecture according to claim 1, which is characterized in that the reinforcing bar positioning column and pre- Wall carrier steel mesh welding processed or integral structure.
6. grouting process at the top of assembled architecture according to claim 1, which is characterized in that in the hub internal bore bottom It is recessed to be equipped with annular groove, it is provided with the stomata for extending downwardly and being connected to annular groove at the top of the sleeve, is set at the top of the stomata It is equipped with the second exhaust tube extended outward, the second pumping pipe end is provided with the second outwardly directed gas-tpe fitting, described Second gas-tpe fitting connect with air-extractor and additional air is discharged.
7. grouting process at the top of assembled architecture according to claim 1, which is characterized in that the air-extractor includes taking out Air pump and one section of transparent pipeline connecting with aspiration pump when pumping, carry out the observation in pipeline, when there is continuous grouting material When, it indicates that grouting is completed, first stops pumping, then stop being in the milk again.
8. grouting process at the top of assembled architecture according to claim 7, which is characterized in that the air-extractor further includes The grouting material caching pot being connected on pipeline.
CN201910150804.2A 2019-02-28 2019-02-28 Top grouting process for fabricated building Active CN109914804B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910150804.2A CN109914804B (en) 2019-02-28 2019-02-28 Top grouting process for fabricated building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910150804.2A CN109914804B (en) 2019-02-28 2019-02-28 Top grouting process for fabricated building

Publications (2)

Publication Number Publication Date
CN109914804A true CN109914804A (en) 2019-06-21
CN109914804B CN109914804B (en) 2021-06-29

Family

ID=66962712

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910150804.2A Active CN109914804B (en) 2019-02-28 2019-02-28 Top grouting process for fabricated building

Country Status (1)

Country Link
CN (1) CN109914804B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111270859A (en) * 2020-01-21 2020-06-12 中国建筑股份有限公司 Air exhaust system for assembled concrete grouting sleeve and construction method of air exhaust system
CN112025939A (en) * 2020-09-10 2020-12-04 倪立兵 Concrete wire pole shaping preparation mould

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000257173A (en) * 1999-03-10 2000-09-19 Tsutomu Haraguchi Grout holding cap
CN1508392A (en) * 2002-12-16 2004-06-30 柳州欧维姆机械有限责任公司 Vertical pipe vacuum pre pressing bidirectional slip casting method and sealed slip casting system thereof
CN106760059A (en) * 2017-03-10 2017-05-31 阜阳市兴华机械装备有限公司 A kind of assembled arthitecutral structure system
CN108252458A (en) * 2018-03-20 2018-07-06 浙江省建筑科学设计研究院有限公司 The cast-in-place connection of bean column node precast beam reinforced bar half grout sleeve component and its application
CN108252521A (en) * 2018-01-22 2018-07-06 中国建筑科学研究院建筑机械化研究分院 Vacuum negative pressure type grouting method and system
CN109208825A (en) * 2018-11-06 2019-01-15 沙洲职业工学院 A kind of assembled arthitecutral structure convenient for docking and being in the milk

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000257173A (en) * 1999-03-10 2000-09-19 Tsutomu Haraguchi Grout holding cap
CN1508392A (en) * 2002-12-16 2004-06-30 柳州欧维姆机械有限责任公司 Vertical pipe vacuum pre pressing bidirectional slip casting method and sealed slip casting system thereof
CN106760059A (en) * 2017-03-10 2017-05-31 阜阳市兴华机械装备有限公司 A kind of assembled arthitecutral structure system
CN108252521A (en) * 2018-01-22 2018-07-06 中国建筑科学研究院建筑机械化研究分院 Vacuum negative pressure type grouting method and system
CN108252458A (en) * 2018-03-20 2018-07-06 浙江省建筑科学设计研究院有限公司 The cast-in-place connection of bean column node precast beam reinforced bar half grout sleeve component and its application
CN109208825A (en) * 2018-11-06 2019-01-15 沙洲职业工学院 A kind of assembled arthitecutral structure convenient for docking and being in the milk

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111270859A (en) * 2020-01-21 2020-06-12 中国建筑股份有限公司 Air exhaust system for assembled concrete grouting sleeve and construction method of air exhaust system
CN112025939A (en) * 2020-09-10 2020-12-04 倪立兵 Concrete wire pole shaping preparation mould
CN112025939B (en) * 2020-09-10 2022-01-28 保山市瑞峰水泥制品有限公司 Concrete wire pole shaping preparation mould

Also Published As

Publication number Publication date
CN109914804B (en) 2021-06-29

Similar Documents

Publication Publication Date Title
CN204826426U (en) Grout sleeve for steel bar connection
CN102071776A (en) Precast grouted steel bar connecting sleeve and construction method thereof
CN109914804A (en) A kind of assembled architecture top grouting process
CN208981531U (en) A kind of prefabricated assembled parapet connection structure
CN206090861U (en) Portable built -in fitting is used in curtain installation
CN105064625A (en) Grout sleeve for reinforcement connection and reinforcement connecting method
CN208777149U (en) Packaged type bridges pier stud super high strength concrete connection structure
CN209468860U (en) A kind of assembled architecture node connecting structure
CN106438213A (en) Tower drum used for wind driven generator
CN206279628U (en) A kind of precast concrete reinforcing bar grouting connecting structure
CN105019606A (en) Precast concrete unit steel bar grouting connecting piece and connecting method
CN204826429U (en) Cast member reinforcing bar grout connecting piece
CN105014785B (en) Prefabricated assembled concrete component Bar Anchorage preformed hole hole-forming device and method
CN106182364A (en) A kind of detachable steel core and the method making pre-stressed concrete hollow beam
CN210458914U (en) Connecting structure of prefabricated bridge pier stud and capping beam
CN209163217U (en) Exposed Prefabricated concrete-filled steel tube column and foundation connection structure
CN208347790U (en) Assembled two serves as a contrast u-shaped tube chip architecture and its reinforcing bar mould
CN104805864B (en) The cementing Waterproof Construction Technique that closes of basement top-down method exterior wall tongue and groove and sealing
CN208803378U (en) A kind of UHPC component grouting connecting structure
CN108118834B (en) Prefabricated assembled concrete structure card key formula reinforcing bar connecting structure
CN208293744U (en) Precast concrete tubulose integral sewage treatment pool
CN110306737A (en) A kind of precast bridge concreting rain-proof constructing device
CN104911999A (en) Construction method for deeply burying anchor
CN207701096U (en) Pile foundation construction secondary pile hole cleaning sand filter under a kind of bridge water
CN201943071U (en) Implantable steel tube anchor rod with stabs

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant