CN109914441A - The big anti-skid system of ability and construction method - Google Patents
The big anti-skid system of ability and construction method Download PDFInfo
- Publication number
- CN109914441A CN109914441A CN201910195630.1A CN201910195630A CN109914441A CN 109914441 A CN109914441 A CN 109914441A CN 201910195630 A CN201910195630 A CN 201910195630A CN 109914441 A CN109914441 A CN 109914441A
- Authority
- CN
- China
- Prior art keywords
- construction
- chamber
- channel
- skid
- water collection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Abstract
The big anti-skid system of ability and construction method directly reinforce the slip band in landslide to change traditional friction pile fully against the branch gear pattern of sliding force, and the intracorporal underground water of cunning and lower infiltration can be automatically drained out, landslide form mechanism performance is significantly greatly increased, largely saves concrete amount, reduces engineering cost.The big anti-skid system of ability includes longitudinally, laterally being spaced rows of anti-skid body, and anti-skid body relies on construction chamber to construct, and construction chamber is located on slip band, or in the gliding mass of neighbouring slip band, and each anti-skid body passes through slip band by gliding mass and enters in slider bed.Construction chamber or anti-skid internal setting water collection chamber, construction chamber, water collection chamber are connected with the construction channel that setting extends to ground, the three-dimensional ejectment water system that building is connected with construction channel, water collection chamber in gliding mass collects in gliding mass underground water and lower seeps water and will be outside its ejectment to ground.
Description
Technical field
The present invention relates to landslide control engineering, in particular to the anti-skid system of a kind of big ability and construction method.
Background technique
Landslide structure is generally made of the slip band of top gliding mass and lower part slider bed and centre, between landslide and slider bed
Interface is known as sliding surface, and the crushed zone near sliding surface is known as slip band.In landslide engineering, mainly since slip band is by rainwater
Lower infiltration or influence on groundwater, the Thrust for the gliding mass that never can resist after mechanical index reduction, cause the phenomenon that comes down.Traditional landslide
Control measures are to arrange that 3~5 row's large size friction piles resist Thrust of Landslide on slip mass, since friction pile needs manually digging hole ten
Several meters of even tens of meters of depths, in some high altitudes and cold areas such as Sichuan-Tibet construction of railways, manual work is difficult and security risk compared with
Height, execution conditions are very poor, and traditional engineering measure urgently improves.
Current pertinent literature shows that domestic and international project personnel have conducted extensive research antiskid structure, but generally all also
It is angularly to be changed from structure stress, rigidity, cost and change functionally are little.
For example, a kind of friction pile arching combination is disclosed in the patent of invention specification of patent No. ZL201110318602.8
Structure and construction method, the composite structure include the friction pile that the tunnel two sides Jian Shen are arranged in a manner of flush type, and friction pile
Stable basement rock is protruded into, arching is connect with two sides friction pile, and the earthwork of tunnel arch is provided with the work space with two sides antiskid stake body
The connected shield arch of steel, protects on arch backfill rock layers after having stake.Suitable under ditch heart shape, earthing is thin on tunnel, two sides
The pre- supporting and retaining system reinforcing construction of tunnel portal when slope stability is poor or poor integrally combines friction pile and arching, shield arch
Mode, substantially increases the stress performance of friction pile, and ditch heart tunnel portal two sides side slope and upper overburden layer is made to form whole add
Gu reducing excavation and the reinforcing of ditch heart two sides side slope, it ensure that the stabilization and ecology of original slopes, saved two sides side slope
Reinforcement cost.
Prestressing force rubble uranium anchor and its landslide are disclosed in patent No. ZL201510038431.1 patent of invention specification
Administer construction method, rubble anchorage pile is column structure, including anchor head disk, rubble integrate draining section, chassis, blotter, porous
Floral tube and several prestressed anchors.Porous floral tube, which runs through, to be arranged between anchor head disk and rubble integrate draining section, and anchor is stretched out at top
Plane in cephalic disc, prestressed anchor passes through rubble integrate draining section and both ends are individually fixed on anchor head disk and chassis, sets on chassis
There is tapping pipe, rubble integrate draining section is connected by tapping pipe with blotter.The structure can effectively reduce ground water water in slip mass
Position reduces slip mass interior moisture content, the shear behavior of sliding surface is also added, to improve the stability on landslide.
In patent No. ZL201611028972.7 patent of invention specification, a kind of townhouse hollow section composite structure is disclosed
Antiskid pile group and its construction method, antiskid pile group are combined by multiple isolated friction piles and a series of binding-beams, friction pile
Centre be equipped with hollow structure, binding-beam includes a crossbeam, and there is a vertical beam at the both ends of crossbeam, and crossbeam and vertical beam are integrally formed, connection
The vertical beam of knot beam one end can closely form structure compatible with hollow structure, friction pile with the vertical beam of the neighboring bracing beams other end
It is inserted into hollow structure jointly by the vertical beam of binding-beam one end and the vertical beam of the neighboring bracing beams other end, by isolated friction pile
Form antiskid pile group.The structure is simple, safety, construction technology strong operability, can effectively reduce landslide control engineering investment.
Foregoing invention patent adjusts structure application process by improving in construction in pilework or integrating by composite structure
In force modes, improve structure entirety anti-slide performance.But friction pile still uses the branch gear pattern fully against sliding force, needs
More than ten meters of manually digging hole even tens of meters of depths, concrete amount is big.The high and cold high altitude localities such as line in Sichuan-Tibet, high gradient slope construction
Condition is excessively poor, by geology and weather conditionality, such as uses above-mentioned antiskid structure, then can be tired in face of cast-in-place concrete maintenance
It is difficult, manual operation amount is big, project cost is high and manually across hole workload is big and unsafe problem.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of big anti-skid systems of ability, complete to change traditional friction pile
The branch gear pattern of sliding force is resisted, directly reinforces the slip band in landslide, and can be automatic by the intracorporal underground water of cunning and lower infiltration
Discharge, is significantly greatly increased landslide form mechanism performance, largely saves concrete amount, reduces engineering cost.
It is as follows that the present invention solves technical solution used by above-mentioned technical problem:
The anti-skid system of big ability of the invention, including it is longitudinally, laterally spaced rows of anti-skid body, it is characterized in that: the resistance
Gliding mass relies on construction chamber to construct, and construction chamber is located on slip band, or in the gliding mass of neighbouring slip band, each anti-skid body
Slip band is passed through by gliding mass to enter in slider bed;The construction chamber or anti-skid internal setting water collection chamber, construct chamber, water collection chamber
It is connected with the construction channel for extending to ground is erect, the three-dimensional ejectment that building is connected with construction channel, water collection chamber in gliding mass
Water system, collects in gliding mass underground water and lower infiltration and will be outside its ejectment to ground.
The construction chamber is set on gliding mass in the gentle location of slide strips, and anti-skid body is in construction chamber casting concrete shape
At anti-slide mass, water collection chamber is set in anti-slide mass.
The construction chamber is set in gliding mass in the precipitous location of slide strips, and anti-skid body is by cushion cap and in the miniature of pile group placement
Stake is constituted, and cushion cap is formed in construction chamber lower portion space casting concrete, and the upper end of each mini pile and cushion cap consolidate, and its underpart is worn
Slip band is crossed to enter in slider bed;The water collection chamber is the upper space of construction chamber.
Another technical problem to be solved by this invention is to provide the construction method of the above-mentioned anti-skid system of big ability, this method
Include the following steps:
1. hand excavation constructs, channel is to slip band or adjacent to slip band, excavation construction chamber, and applies corresponding add
Fixing structure;
2. excavating diversion channel, drainage channel, the adjacent two rows of construction chambers of diversion channel connection by artificial or geological drilling rig
Room, drainage channel fill rubble or sandy gravel by most applying work chamber down to ground in diversion channel, drainage channel;
3. in the construction anti-skid body of chamber indoor construction and corresponding water collection chamber, each water collection chamber and construction channel, diversion channel or
Person's drainage channel is connected;
4. filling water collection chamber, rubble or sandy gravel in channel of constructing, construction channel was filled to the three-dimensional water collecting structure time-division
Layer and circumferentially spaced-apart be drilled with face upward inclined hole, respectively face upward insertion draining blind pipe in inclined hole, and it is blind to the draining of covering top layer to then proceed to filling
At pipe port position, then common soil is used to fill to ground.
The beneficial effects are mainly reflected as follows following aspects:
One, change traditional friction pile fully against the branch gear pattern of sliding force, anti-skid body directly adds directly at slip band
Gu the slip band in landslide, avoids anti-skid body from bearing excessive gliding mass thrust.Resistant function according to anti-skid body in slip band is sent out
Degree is waved, perpendicular to slip band direction, 2~3 anti-skid bodies can replace row's friction pile, in the resistance of 1~2, vertical section direction
Gliding mass can replace 3~5 row's friction piles, be greatly saved concrete amount, good antiskid effect;
Two, the three-dimensional ejectment water system that building is connected with construction channel, water collection chamber in gliding mass, collects underground water in gliding mass
With lower infiltration and by outside its ejectment to ground, perfect drainage system is formed in conjunction with earth's surface drainage measure, can effectively prevent to come down
It is formed;
Three, compared with traditional friction pile and composite structure, 50% or more concrete amount can be saved, is shortened the construction period
30% or more, significantly save project cost.
Detailed description of the invention
This specification includes following six width attached drawing:
Fig. 1 is the cross-section diagram of the anti-skid system implementation example 1 (reinforcing for the gentle location of slide strips) of big ability of the invention;
Fig. 2 is the work progress schematic diagram of the anti-skid system implementation example 1 of big ability of the invention;
Fig. 3 is the work progress schematic diagram of the anti-skid system implementation example 1 of big ability of the invention;
Fig. 4 is the cross-section diagram of the anti-skid system implementation example 2 (reinforcing for the precipitous location of slide strips) of big ability of the invention;
Fig. 5 is the work progress schematic diagram of the anti-skid system implementation example 2 of big ability of the invention;
Fig. 6 is the work progress schematic diagram of the anti-skid system implementation example 3 of big ability of the invention
Component and corresponding label be shown in figure: slider bed 10, gliding mass 11, slip band F, construction channel 21, construction chamber 22,
Face upward inclined hole 23, diversion channel 24, drainage channel 25, stake holes 26, anti-slide mass 30, water collection chamber 31, cushion cap 32, mini pile 33, draining
Blind pipe 34.
Specific embodiment
Present invention will be further explained below with reference to the attached drawings and examples.
Referring to Fig.1, Fig. 3 and Fig. 4, Fig. 6, the anti-skid system of big ability of the invention, including longitudinally, laterally it is spaced rows of resistance
Gliding mass, the anti-skid body rely on construction chamber 22 to construct, and construction chamber 22 is located on slip band F, or are located at neighbouring slip band F
Gliding mass 11 in, each anti-skid body by gliding mass 11 pass through slip band F enter in slider bed 10.Change traditional friction pile fully against downslide
The branch gear pattern of power, anti-skid body directly reinforce the slip band in landslide, anti-skid body are avoided to bear excessive gliding mass thrust.It presses
Resistant function according to anti-skid body in slip band plays degree, and perpendicular to slip band direction, 2~3 anti-skid bodies can replace one
Friction pile is arranged, anti-skid body can replace 3~5 row's friction piles 1~2, vertical section direction, be greatly saved concrete amount, prevent
Sliding effect is good.
It is formed referring to Fig.1 with Fig. 4, effectively prevention landslide, the construction chamber 22 or anti-skid internal setting water collection chamber 31,
Construction chamber 22, water collection chamber 31 are connected with the construction channel 21 for extending to ground is erect, building and construction channel in gliding mass 11
21, the three-dimensional ejectment water system that water collection chamber 31 is connected collects underground water in gliding mass 11 and lower infiltration and by its ejectment to ground
Outside face.
Referring to by the embodiment 1 shown in Fig. 1, Fig. 2 and Fig. 3, the construction chamber 22 is set to cunning in the gentle location of slide strips
On body 11, anti-skid body is the anti-slide mass 30 formed in construction 22 casting concrete of chamber, and water collection chamber 31 is set in anti-slide mass 30.
Referring to by the embodiment 2 shown in Fig. 4, Fig. 5 and Fig. 6, the construction chamber 22 is set to cunning in the precipitous location of slide strips
In body 11, anti-skid body is constituted by cushion cap 32 and in the mini pile 33 of pile group placement, and cushion cap 32 is poured in construction 22 lower space of chamber
It builds concrete to be formed, the upper end of each mini pile 33 and cushion cap 32 consolidate, and its underpart passes through slip band F and enters in slider bed 10.It is described
Water collection chamber 31 is the upper space of construction chamber 22.
Referring to Fig.1 and Fig. 4, the solid ejectment water system is by three-dimensional water collecting structure, water collection chamber 31, diversion channel 24 and row
Aquaporin 25 is constituted.Referring to Fig. 3 and Fig. 6, three-dimensional water collecting structure is along construction 21 longitudinal gap of channel, circumferentially spaced-apart setting draining
Blind pipe 34 is constituted, and is in dendritic distribution, and each lower end construction channel 21 for draining blind pipe 34 is connected, and oblique facing upward in gliding mass 11
Upper extension, facing upward oblique angle is 15~20 °.The diversion channel 24 is set between adjacent two rows of construction chambers 22, connection adjacent two
The water collection chamber 31 in work chamber 22 is applied, the drainage channel 25 is connected to ground and most applies the water collection chamber in work chamber 22 down
31.Filling rubble or sandy gravel in the construction channel 21, water collection chamber 31, diversion channel 24 and drainage channel 25;Construction is logical
In road 21 at filling to covering top layer draining 34 port position of blind pipe.
Referring to FIG. 1, FIG. 2 and FIG. 4, Fig. 5, the construction method of the anti-skid system of big ability of the invention, includes the following steps:
1. hand excavation constructs, channel 21 is to slip band F or adjacent to slip band F, excavation construction chamber 22, and applies phase
The ruggedized construction answered;
2. excavating diversion channel 24, drainage channel 25 by artificial or geological drilling rig, diversion channel 24 is connected to adjacent two rows
Construction chamber 22, drainage channel 25 are connected to ground, filling in diversion channel 24, drainage channel 25 by most applying work chamber 22 down
Rubble or sandy gravel;
3. constructing anti-skid body and corresponding water collection chamber 31 in construction chamber 22, each water collection chamber 31 and channel 21 of constructing are drawn
Aquaporin 24 or drainage channel 25 are connected;
4. filling water collection chamber 31, rubble or sandy gravel in construction channel 21, construction channel 21 filling to three-dimensional is catchmented knot
Structure layered and circumferentially spaced-apart be drilled with face upward inclined hole 23, respectively face upward insertion draining blind pipe 34 in inclined hole 23, then proceed to filling and extremely cover
Top layer drains at 34 port position of blind pipe, then is filled using common soil to ground.
In the gentle location of slide strips, the precipitous location of slide strips, anti-skid body uses different structure and form of construction work.Referring to figs. 1 to
Fig. 3, in the gentle location of slide strips, anti-skid body be anti-slide mass 30, the step 3. in, construction chamber 22 in formwork erection casting concrete
Form the water collection chamber 31 of anti-slide mass 30 and Qi Nei.Referring to fig. 4 to fig. 6, in the precipitous location of slide strips, anti-skid body is by cushion cap 32 and miniature
Stake 33 is constituted, the step 3. in, longitudinally, laterally interval is drilled with downwards and enters slider bed across slip band F in construction chamber 22
Stake holes 26 in 10, the interior mini pile 33 of constructing of stake holes 26.Then cushion cap is formed in construction 22 lower space casting concrete of chamber
32, the upper end of cushion cap 32 and each mini pile 33 consolidates, using 22 upper space of chamber of constructing as water collection chamber 31.
The above is the explain through diagrams anti-skid system of ability greatly and some principles of construction method of the invention, is not
By the present invention be confined to shown in and the specific structure and the scope of application in, therefore it is all it is all may be utilized accordingly repair
Change and equivalent, belongs to the applied the scope of the patents of the present invention.
Claims (9)
1. the big anti-skid system of ability, including it is longitudinally, laterally spaced rows of anti-skid body, it is characterized in that: the anti-skid body support is applied
Work chamber (22) is constructed, and construction chamber (22) is located on slip band (F), or is located in the gliding mass (11) of neighbouring slip band (F),
Each anti-skid body passes through slip band (F) by gliding mass (11) and enters in slider bed (10);The construction chamber (22) anti-skid sets in vivo
It sets water collection chamber (31), construction chamber (22), water collection chamber (31) are connected with the construction channel (21) for extending to ground is erect, gliding mass
(11) the three-dimensional ejectment water system that building is connected with construction channel (21), water collection chamber (31) in, collects the ground in gliding mass (11)
Be lauched and it is lower infiltration and will be outside its ejectment to ground.
2. the anti-skid system of big ability as described in claim 1, it is characterized in that: the construction chamber (22) is in the gentle location of slide strips
It is set on gliding mass (11), anti-skid body is the anti-slide mass (30) formed in construction chamber (22) casting concrete, water collection chamber (31)
It is set in anti-slide mass (30).
3. the anti-skid system of big ability as described in claim 1, it is characterized in that: the construction chamber (22) is in the precipitous location of slide strips
It is set in gliding mass (11), anti-skid body is constituted by cushion cap (32) and in the mini pile (33) of pile group placement, and cushion cap (32) is being constructed
Chamber (22) lower space casting concrete is formed, and the upper end and cushion cap (32) of each mini pile (33) consolidate, and its underpart, which passes through, to be slided
Dynamic band (F) enters in slider bed (10);The water collection chamber (31) is the upper space of construction chamber (22).
4. the anti-skid system of ability as claimed in claim 3 big, it is characterized in that: the solid ejectment water system is catchmented knot by three-dimensional
Structure, water collection chamber (31), diversion channel (24) and drainage channel (25) are constituted;The three-dimensional water collecting structure is along construction channel (21)
Longitudinal gap, circumferentially spaced-apart setting draining blind pipe (34) are constituted, and are in dendritic distribution, respectively drain the lower end construction channel of blind pipe (34)
(21) it is connected, and is extended obliquely upward being faced upward in gliding mass (11), facing upward oblique angle is 15~20 °.
5. the anti-skid system of big ability as claimed in claim 4, it is characterized in that: the diversion channel (24) is set to adjacent two rows
It constructs between chamber (22), the water collection chamber (31) being connected in adjacent two rows of constructions chamber (22), the drainage channel (25) is connected to
Ground and the water collection chamber (31) in work chamber (22) is most applied down.
6. the anti-skid system of ability as claimed in claim 5 big, it is characterized in that: the construction channel (21), water collection chamber (31), drawing
Filling rubble or sandy gravel in aquaporin (24) and drainage channel (25);Construct channel (21) interior filling extremely covering top layer row
At water blind pipe (34) port position.
7. the construction method of the anti-skid system of big ability, includes the following steps: as described in claim 1 to 6 any one
1. hand excavation constructs, channel (21) are to slip band (F) or adjacent to slip band (F), excavation construction chamber (22), and apply
Make corresponding ruggedized construction;
2. excavating diversion channel (24), drainage channel (25), diversion channel (24) connection adjacent two by artificial or geological drilling rig
It applies work chamber (22), drainage channel (25) is connected to ground by most applying work chamber (22) down, and diversion channel (24), draining are logical
Filling rubble or sandy gravel in road (25);
3. construct in construction chamber (22) anti-skid body and corresponding water collection chamber (31), each water collection chamber (31) and construction channel
(21), diversion channel (24) or drainage channel (25) are connected;
4. filling water collection chamber (31), the interior rubble of construction channel (21) or sandy gravel, construction channel (21) filling to three-dimensional is catchmented
Structure layered and circumferentially spaced-apart be drilled with face upward inclined hole (23), respectively face upward insertion draining blind pipe (34) in inclined hole (23), then proceed to fill out
It is charged at covering top layer draining blind pipe (34) port position, then filled using common soil to ground.
8. the construction method of the anti-skid system of ability as claimed in claim 7 big, it is characterized in that: the step 3. in, constructing
The interior formwork erection casting concrete of chamber (22) forms anti-slide mass (30) and the water collection chamber (31) in it.
9. the construction method of the anti-skid system of ability as claimed in claim 7 big, it is characterized in that: the step 3. in, constructing
Longitudinally, laterally interval is drilled with downwards the stake holes (26) entered in slider bed (10) across slip band (F), stake holes (26) in chamber (22)
Interior construction mini pile (33);Then construction chamber (22) lower space casting concrete formed cushion cap (32), cushion cap (32) with
The upper end of each mini pile (33) consolidates, using chamber of constructing (22) upper space as water collection chamber (31).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910195630.1A CN109914441B (en) | 2019-03-14 | 2019-03-14 | Construction method of high-capacity anti-skid system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910195630.1A CN109914441B (en) | 2019-03-14 | 2019-03-14 | Construction method of high-capacity anti-skid system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109914441A true CN109914441A (en) | 2019-06-21 |
CN109914441B CN109914441B (en) | 2023-09-22 |
Family
ID=66964990
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910195630.1A Active CN109914441B (en) | 2019-03-14 | 2019-03-14 | Construction method of high-capacity anti-skid system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109914441B (en) |
Citations (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2230156C2 (en) * | 2002-05-31 | 2004-06-10 | Кубанский государственный аграрный университет | Structure for protection against landslip |
JP2004190252A (en) * | 2002-12-09 | 2004-07-08 | Shin Gijutsu Koei Kk | Landslide prevention structure |
JP2004332357A (en) * | 2003-05-07 | 2004-11-25 | Shimizu Corp | Method for constructing elevated type traffic route and elevated type traffic route |
CN201148620Y (en) * | 2008-01-11 | 2008-11-12 | 肖世国 | Small-sized pile combined antiskid structure |
ITBO20080367A1 (en) * | 2008-06-10 | 2009-12-11 | Lega Rocciatori S R L | METHOD FOR THE CONSOLIDATION OF LAND IN DANGER OF FRANA AND PLANT TO IMPLEMENT THIS METHOD |
US20100239375A1 (en) * | 2009-03-20 | 2010-09-23 | Vitaly Boris Feygin | Diaphragm/ sea retaining wall system |
CN201908313U (en) * | 2010-11-26 | 2011-07-27 | 中国水电顾问集团成都勘测设计研究院 | Side slope reinforcement structure |
KR20110132910A (en) * | 2010-06-03 | 2011-12-09 | 김원근 | Underpass using precast concrete pile and bottom slab and method for constructing the same |
CN104674802A (en) * | 2015-01-26 | 2015-06-03 | 重庆大学 | Prestressed gravel anchoring pile and landslide control construction method thereof |
CN104727340A (en) * | 2015-03-11 | 2015-06-24 | 张江涛 | High cutting slope anchor rope space framework supporting and retaining structure |
CN205314116U (en) * | 2016-01-13 | 2016-06-15 | 重庆交通大学 | Continuous type of combined type drilling cling compound structure |
JP2016211363A (en) * | 2015-04-30 | 2016-12-15 | 鹿島建設株式会社 | Method and structure for flow inhibition of slope ground |
KR101816023B1 (en) * | 2017-03-20 | 2018-02-22 | 삼표레일웨이 주식회사 | Precast Concrete Slab Track and Constructing Method thereof |
KR101917813B1 (en) * | 2018-08-28 | 2018-11-12 | 이진경 | Railroad lower part no dig excavation construction sructure and construction method using it |
CN208309303U (en) * | 2018-06-13 | 2019-01-01 | 中铁二院工程集团有限责任公司 | A kind of landslide o earth slope consolidation roadbed of high-speed structure |
CN209891218U (en) * | 2019-03-14 | 2020-01-03 | 中铁二院工程集团有限责任公司 | High-capacity anti-slip system |
-
2019
- 2019-03-14 CN CN201910195630.1A patent/CN109914441B/en active Active
Patent Citations (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2230156C2 (en) * | 2002-05-31 | 2004-06-10 | Кубанский государственный аграрный университет | Structure for protection against landslip |
JP2004190252A (en) * | 2002-12-09 | 2004-07-08 | Shin Gijutsu Koei Kk | Landslide prevention structure |
JP2004332357A (en) * | 2003-05-07 | 2004-11-25 | Shimizu Corp | Method for constructing elevated type traffic route and elevated type traffic route |
CN201148620Y (en) * | 2008-01-11 | 2008-11-12 | 肖世国 | Small-sized pile combined antiskid structure |
ITBO20080367A1 (en) * | 2008-06-10 | 2009-12-11 | Lega Rocciatori S R L | METHOD FOR THE CONSOLIDATION OF LAND IN DANGER OF FRANA AND PLANT TO IMPLEMENT THIS METHOD |
US20100239375A1 (en) * | 2009-03-20 | 2010-09-23 | Vitaly Boris Feygin | Diaphragm/ sea retaining wall system |
KR20110132910A (en) * | 2010-06-03 | 2011-12-09 | 김원근 | Underpass using precast concrete pile and bottom slab and method for constructing the same |
CN201908313U (en) * | 2010-11-26 | 2011-07-27 | 中国水电顾问集团成都勘测设计研究院 | Side slope reinforcement structure |
CN104674802A (en) * | 2015-01-26 | 2015-06-03 | 重庆大学 | Prestressed gravel anchoring pile and landslide control construction method thereof |
CN104727340A (en) * | 2015-03-11 | 2015-06-24 | 张江涛 | High cutting slope anchor rope space framework supporting and retaining structure |
JP2016211363A (en) * | 2015-04-30 | 2016-12-15 | 鹿島建設株式会社 | Method and structure for flow inhibition of slope ground |
CN205314116U (en) * | 2016-01-13 | 2016-06-15 | 重庆交通大学 | Continuous type of combined type drilling cling compound structure |
KR101816023B1 (en) * | 2017-03-20 | 2018-02-22 | 삼표레일웨이 주식회사 | Precast Concrete Slab Track and Constructing Method thereof |
CN208309303U (en) * | 2018-06-13 | 2019-01-01 | 中铁二院工程集团有限责任公司 | A kind of landslide o earth slope consolidation roadbed of high-speed structure |
KR101917813B1 (en) * | 2018-08-28 | 2018-11-12 | 이진경 | Railroad lower part no dig excavation construction sructure and construction method using it |
CN209891218U (en) * | 2019-03-14 | 2020-01-03 | 中铁二院工程集团有限责任公司 | High-capacity anti-slip system |
Non-Patent Citations (2)
Title |
---|
卢应发;周盛沛;罗先启;吴延春;: "渗流对抗滑桩加固滑坡后的影响效果评价", 岩石力学与工程学报, no. 09 * |
钱同辉;陈芳;程周炳;丁红星;: "框架式双排抗滑桩结构性能研究", 长江科学院院报, no. 11 * |
Also Published As
Publication number | Publication date |
---|---|
CN109914441B (en) | 2023-09-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105927272B (en) | Bottom plate anchors restricted type tunnel lining structure | |
CN107503257B (en) | One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method | |
CN101476466B (en) | Giant heavy laver land slide pre-stress anchor cable antiskid tunnel construction method and novel prevention structure | |
CN207109475U (en) | It is close to mountain high-filled subgrade stabilization and Deformation control structure | |
CN109024458B (en) | Construction method for landscape revetment and underwater seepage prevention of coal mining subsidence land | |
CN205382507U (en) | Two -way anchored retaining wall by tie rods | |
CN108486976A (en) | Mountain highway, which is filled out, digs intersection road structure and its construction method | |
CN107740446A (en) | Combined construction method of the passive supplement in existing building basis with underpining system in hole | |
CN111173006B (en) | Ecological slope protection method for reinforcing hilly soil by combining permeable retaining wall and sounding type bar planting belt | |
CN113006097A (en) | Permeable water-intercepting anti-skid structure for treating giant landslide and construction method thereof | |
CN100513705C (en) | Underground beam-pile frame construction for reinforcing side slope | |
CN105804097A (en) | Cantilever structure way for treating landslides in cooperation with h-shaped anti-sliding piles and construction method of cantilever structure way | |
CN108385715A (en) | A kind of assembled stake arch combination retaining wall and its construction method | |
CN113186955A (en) | Compound side slope reinforced structure | |
CN110528540B (en) | Drainage slide-resistant pile structure with embedded pile columns and construction method thereof | |
CN102425179B (en) | Structure of reinforced soil sewer supported by bored concrete piles of mini steel tubes | |
CN208455387U (en) | Mountain highway, which is filled out, digs intersection road structure | |
CN216360618U (en) | Protection architecture suitable for ultra-shallow tunnel shield that buries wears existing highway subgrade down | |
CN113550336B (en) | Construction method of loose formation region railway deep cutting adjacent to existing building | |
CN109914441A (en) | The big anti-skid system of ability and construction method | |
CN209891218U (en) | High-capacity anti-slip system | |
CN209324377U (en) | Ledge method tunneling subway station arch springing ruggedized construction | |
Perzlmaier et al. | Foundation of the 140m high Kühtai Dam in the Längental valley | |
CN110130397A (en) | Tilt hexagon piping lane system and its construction method of the supporting in conjunction with main structure | |
CN215594063U (en) | Compound side slope reinforced structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |