CN208309303U - A kind of landslide o earth slope consolidation roadbed of high-speed structure - Google Patents
A kind of landslide o earth slope consolidation roadbed of high-speed structure Download PDFInfo
- Publication number
- CN208309303U CN208309303U CN201820909603.7U CN201820909603U CN208309303U CN 208309303 U CN208309303 U CN 208309303U CN 201820909603 U CN201820909603 U CN 201820909603U CN 208309303 U CN208309303 U CN 208309303U
- Authority
- CN
- China
- Prior art keywords
- landslide
- reinforcing
- pile
- slip mass
- earth slope
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
A kind of landslide o earth slope consolidation roadbed of high-speed structure meets the needs that high-speed railway subgrade engineering is built on slip mass effectively to control landslide o earth slope body stability and deformation.Longitudinally, laterally setting cement fly ash gravel pile in interval forms reinforcing body in the slip mass below road structure, and the lower part of each cement fly ash gravel pile passes through sliding surface and enters steady soil certain depth.On the upside of reinforcing body, longitudinally spaced setting reinforcing pile in the slip mass of downside, the lower part of reinforcing pile is passed into sliding surface and enters steady soil certain depth.The top of reinforcing body is laid with bed course, and road structure is constructed on bed course.
Description
Technical field
The utility model relates to geotechnical engineerings, in particular to landslide o earth slope consolidation roadbed of high-speed structure.
Background technique
Landslide is largely distributed in Southwestern China mountain area, when the good ground of certain depth under slip mass and sliding surface is soil property
When, high-speed railway subgrade engineering how is built on slip mass and has easy for construction, economical, while meeting high-speed railway to steady
Qualitative and deformation requirement, therefore need to propose a kind of landslide o earth slope consolidation roadbed of high-speed structure, and should have safe and environment-friendly
The features such as.
Utility model content
The technical problem to be solved by the utility model is to provide a kind of landslide o earth slope consolidation roadbed of high-speed structure, with
Effectively control landslide o earth slope body stability and deformation meet the needs that high-speed railway subgrade engineering is built on slip mass.
It is as follows that the utility model solves the technical solution that above-mentioned technical problem is taken:
A kind of landslide o earth slope consolidation roadbed of high-speed structure, including road structure, it is characterized in that: under the road structure
Longitudinally, laterally setting cement fly ash gravel pile in interval forms reinforcing body in the slip mass of side, each cement fly ash gravel pile
Lower part passes through sliding surface and enters steady soil certain depth;On the upside of the reinforcing body, longitudinally spaced setting in the slip mass of downside
Reinforcing pile, the lower part of reinforcing pile are passed into sliding surface and enter steady soil certain depth;The top of the reinforcing body is laid with bed course,
Road structure is constructed on bed course.
The utility model has the beneficial effects that effectively control landslide o earth slope body stability and deformation, is able to satisfy in slip mass
On build the needs of high-speed railway subgrade engineering;Construction is simple, construction investment is low, and meets the requirement of environmental protection, has to promote and answer
Use prospect.
Detailed description of the invention
This specification includes following two width attached drawing:
Fig. 1 is a kind of sectional schematic diagram of landslide o earth slope consolidation roadbed of high-speed structure of the utility model.
Fig. 2 is the structural schematic diagram of bed course in a kind of landslide o earth slope consolidation roadbed of high-speed structure of the utility model.
Component name and corresponding label: cement fly ash gravel pile 1, reinforcing pile 2, bed course 3, lower rubble are shown in figure
Layer 31, upper metalling 33, lower TGXG 34, upper TGXG 35, road structure 4, slip mass A, stablizes soil at medium stone layer 32
Layer B, sliding surface C.
Specific embodiment
The present invention will be further described with reference to the accompanying drawings and examples.
Referring to Fig.1, a kind of landslide o earth slope consolidation roadbed of high-speed structure of the utility model includes road structure 4.Institute
It states and is longitudinally, laterally spaced the setting formation reinforcing body of cement fly ash gravel pile 1, each cement in the slip mass A of 4 lower section of road structure
The lower part of flyash gravel pile 1 crosses into sliding surface C and enters steady soil B certain depth.The cunning of the reinforcing body upside, downside
Longitudinally spaced setting reinforcing pile 2 in slopes A, the lower part of reinforcing pile 2 cross sliding surface C and enter steady soil B certain depth.It is described
The top of reinforcing body is laid with bed course 3, and road structure 4 is constructed on bed course 3.It is described to be set on the upside of reinforcing body in slip mass A
Reinforcing pile 2 is set to the reinforcing pile 2 on the downside of reinforcing body in slip mass A and is used small bore stake using big section stake.
Referring to Fig.1, the utility model using (CFG) the reinforcing slip mass A of cement fly ash gravel pile 1 and enters stabilization
Soil layer B certain depth solves the problems, such as that the landslide soil body generates Vertical Settlement, CFG technology maturations, warp under upper load effect
Ji property is good, and CFG pass through sliding surface C and can increase skid resistance;Using be arranged on the upside of reinforcing body, the reinforcing pile 2 of downside stablize slide
Slopes A, so that the high-speed railway built on slip mass A has enough stability, upside reinforcing pile 2 uses big section stake,
Size, which is subject to, meets resistance sliding force size at stake position, and lower side uses small bore stake, migrates shadow to avoid downside slip mass
It rings.Using bed course 3 as the buffer layer between reinforcing body and top road structure 4, make cement fly ash gravel pile 1 and top
Uniformly, road structure 4 is basic as the carrying of high-speed railway for structure stress deformation.It is steady that the structure efficiently solves landslide o earth slope body
The problem of qualitative and strict control deformation, be able to satisfy and build high-speed railway subgrade engineering on slip mass, and have construction is simple,
The features such as construction investment is low has popularization and application foreground, and meets the requirement of environmental protection.
Referring to Fig.1, the depth that the cement fly ash gravel pile 1 enters steady soil B is typically no less than 1.0m.Referring to figure
2, the bed course 3 is by the lower metalling 31, lower TGXG 34, medium stone layer 32, the upper soil that successively fill and be laid with from below to up
Work grid 35 and the compound composition of upper metalling 33, thickness are generally 0.6m.
The above only explains through diagrams the one of a kind of landslide o earth slope consolidation roadbed of high-speed structure of the utility model
A little principles, be not intended to for the utility model to be confined to shown in and the specific structure scope of application in, therefore it is all it is all can
The corresponding modification that can be utilized and equivalent, belong to the applied the scope of the patents of the utility model.
Claims (4)
1. a kind of landslide o earth slope consolidation roadbed of high-speed structure, including road structure (4), it is characterized in that: the road structure
(4) longitudinally, laterally interval setting cement fly ash gravel pile (1) forms reinforcing body, each cement fine coal in the slip mass (A) below
The lower part of ash broken stones stake (1) crosses into sliding surface (C) into steady soil (B) certain depth;On the upside of the reinforcing body, downside
Sliding surface (C) is crossed into steady soil (B) in longitudinally spaced setting reinforcing pile (2) in slip mass (A), the lower part of reinforcing pile (2)
Certain depth;The top of the reinforcing body is laid with bed course (3), and road structure (4) is constructed on bed course (3).
2. a kind of landslide o earth slope consolidation roadbed of high-speed structure as described in claim 1, it is characterized in that: the cement fine coal
The depth of ash broken stones stake (1) into steady soil (B) are not less than 1.0m.
3. a kind of landslide o earth slope consolidation roadbed of high-speed structure as described in claim 1, it is characterized in that: described be set to adds
Reinforcing pile (2) on the upside of solid in slip mass (A) is set to the reinforcing on the downside of reinforcing body in slip mass (A) using big section stake
Stake (2) uses small bore stake.
4. a kind of landslide o earth slope consolidation roadbed of high-speed structure as described in claim 1, it is characterized in that: the bed course (3)
By lower metalling (31), lower TGXG (34), the medium stone layer (32), upper TGXG for successively filling and being laid with from below to up
(35) and upper metalling (33) compound composition, with a thickness of 0.6m.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820909603.7U CN208309303U (en) | 2018-06-13 | 2018-06-13 | A kind of landslide o earth slope consolidation roadbed of high-speed structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820909603.7U CN208309303U (en) | 2018-06-13 | 2018-06-13 | A kind of landslide o earth slope consolidation roadbed of high-speed structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208309303U true CN208309303U (en) | 2019-01-01 |
Family
ID=64708075
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820909603.7U Active CN208309303U (en) | 2018-06-13 | 2018-06-13 | A kind of landslide o earth slope consolidation roadbed of high-speed structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208309303U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109914440A (en) * | 2019-03-14 | 2019-06-21 | 中铁二院工程集团有限责任公司 | The anti-skid structure of the big ability of w type and construction method |
CN109914441A (en) * | 2019-03-14 | 2019-06-21 | 中铁二院工程集团有限责任公司 | The big anti-skid system of ability and construction method |
-
2018
- 2018-06-13 CN CN201820909603.7U patent/CN208309303U/en active Active
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109914440A (en) * | 2019-03-14 | 2019-06-21 | 中铁二院工程集团有限责任公司 | The anti-skid structure of the big ability of w type and construction method |
CN109914441A (en) * | 2019-03-14 | 2019-06-21 | 中铁二院工程集团有限责任公司 | The big anti-skid system of ability and construction method |
CN109914440B (en) * | 2019-03-14 | 2023-09-22 | 中铁二院工程集团有限责任公司 | Construction method of w-type high-capacity anti-slip structure |
CN109914441B (en) * | 2019-03-14 | 2023-09-22 | 中铁二院工程集团有限责任公司 | Construction method of high-capacity anti-skid system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103498696B (en) | A kind of method from roadway in the roof grouting filling compacting goaf filling body | |
CN101654899A (en) | Liquified soil foundation-bed shock-resistant strengthening structure of high-speed railway | |
CN208309303U (en) | A kind of landslide o earth slope consolidation roadbed of high-speed structure | |
CN201343730Y (en) | Ecological protection structure for high rock slope | |
CN106759390A (en) | A kind of rubble non-uniform pile composite construction and its construction method with draining and AsA -GSH cycle | |
CN101403209B (en) | Fast water-permeable brick for stopping pad and laying method | |
CN107447597A (en) | A kind of non-fragment orbit railway expensive soil cutting structure and construction method | |
CN201530968U (en) | High-speed railway liquefying soil foundation-roadbed seismic strengthening structure | |
CN207672343U (en) | A kind of curb construction reducing railway subgrade surface width | |
CN105839659A (en) | Debris flow retaining dam base reinforcing method based on composite micro-piles | |
CN101200888A (en) | Construction method of composite foundation | |
Aljanabi et al. | Construction of a new highway embankment on the soft clay soil treatment by stone columns in Malaysia | |
CN102518136A (en) | Flexible reinforcement combination protection structure for controlling humidification and damage for soft rock strong weathering zone | |
CN107151960A (en) | The soft interim sidewalk laying structure in base and laying method | |
CN202830675U (en) | Deep and thick soft soil composite floating pile foundation damage reinforcement structure | |
CN102031743A (en) | Construction method of mudstone-filled embankment | |
CN105569055B (en) | A kind of structure for preventing landslide | |
CN203866814U (en) | Medium-compressibility soil foundation reinforcing structure for high speed railway | |
CN108049438B (en) | The anchor force measuring method of Resistant heave pile foundation in a kind of ballastless track roadbed substrate swelled ground | |
CN103821164B (en) | Mountain area cheuch backfill tunnel construction | |
CN207130545U (en) | High-speed railway active breaking belt region road structure | |
CN108130826A (en) | A kind of karst railway bed substrate antidumping foundation reinforcing structure | |
CN205223764U (en) | Embankment structure between existing bridge pier | |
CN205088528U (en) | Cause of a quarrel height piece of smooth land concrete roadbed structure that fills is abandoned to soft ground | |
CN207295346U (en) | A kind of non-fragment orbit railway expensive soil cutting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |