CN109914423A - Pattern foundation pit supporting structure processing method in number library Fang Yudi narrow space - Google Patents

Pattern foundation pit supporting structure processing method in number library Fang Yudi narrow space Download PDF

Info

Publication number
CN109914423A
CN109914423A CN201910167398.0A CN201910167398A CN109914423A CN 109914423 A CN109914423 A CN 109914423A CN 201910167398 A CN201910167398 A CN 201910167398A CN 109914423 A CN109914423 A CN 109914423A
Authority
CN
China
Prior art keywords
room
bottom plate
steel sheet
sheet pile
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910167398.0A
Other languages
Chinese (zh)
Other versions
CN109914423B (en
Inventor
李伟强
蒋宜翔
李耀良
张云海
吴斌
张龙
钱丹凤
陈辉
顾欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jianxi Civil Engineering Consulting Co Ltd
Shanghai Foundation Engineering Group Co Ltd
Original Assignee
Shanghai Jianxi Civil Engineering Consulting Co Ltd
Shanghai Foundation Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jianxi Civil Engineering Consulting Co Ltd, Shanghai Foundation Engineering Group Co Ltd filed Critical Shanghai Jianxi Civil Engineering Consulting Co Ltd
Priority to CN201910167398.0A priority Critical patent/CN109914423B/en
Publication of CN109914423A publication Critical patent/CN109914423A/en
Application granted granted Critical
Publication of CN109914423B publication Critical patent/CN109914423B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to the pattern foundation pit supporting structure processing methods in the narrow space of the library one kind Fang Yudi, the steps include: 1) construction room pile foundation;2) small seam allowance steel sheet pile is set in ground library and a number room boundary position;3) number of pouring room bed course, distance room and garage difference of height juncture area 5m inner cushion layer configuration reinforcement mesh sheet;4) Two bors d's oeuveres channel steel purlin is arranged in steel sheet pile side, pull rod is passed through reserved opening in the middle part of steel sheet pile and purlin, end setting anchor head is fixed, and the other end is connected and fixed with the reinforcing steel bar of pull rod connector being arranged in bed course;5) construction room bottom plate;6) the low garage foundation pit of colon room bottom plate is excavated, bottom plate and external wall structure construction are carried out;After the completion of garage basement construction, steel sheet pile recycling is pulled out.Using difference of height foundation pit that can well between the number of processing room bottom plate and ground library in narrow space of the invention, pile foundation is intensive and lead to the problem of support system construction space deficiency under the number of avoiding room bottom plate, also avoids displacement, the destruction of number room bottom plate and pile foundation caused by ground library is excavated.

Description

Pattern foundation pit supporting structure processing method in number library Fang Yudi narrow space
Technical field
The present invention relates to the pattern foundation pit supporting structure in the narrow space of the library one kind Fang Yudi, the especially library one kind Fang Yudi is narrow Pattern foundation pit supporting structure processing method in space.
Background technique
Currently, in building engineering, developed and required due to basement, generally requires to carry out pattern foundation pit supporting structure, but root According to architectural composition, number room basement bottom board generally greater than library basement bottom board, under not supporting state library excavation often The displacement of the number of will lead to room pile foundation and bottom plate, damages.Under normal circumstances, it will do it in ground library and a number room height boundary position Supporting, the often self-supporting support system such as Soil-cement Wall gravity dam of use, but in most cases under number premises Distance is narrow between room bottom plate and ground library exterior wall, and the Influence of Pile Foundation in number room, can not supporting to the construction of self-supporting support system.
Summary of the invention
The present invention is to provide for the pattern foundation pit supporting structure processing method in the narrow space of the library one kind Fang Yudi, in narrow space Depth intersection foundation pit carries out supporting, and this method can avoid the insufficient disadvantage of traditional handicraft construction space, and the solution duration is limited, work The shortcomings that journey cost secondary waste.
To achieve the above object, the technical scheme is that pattern foundation pit supporting structure in the narrow space of the library one kind Fang Yudi Processing method, which is characterized in that comprise the concrete steps that:
1) construction room pile foundation, pile foundation set small seam allowance steel sheet pile in ground library and a number room boundary position after the completion;
2) number of pouring room bed course, distance room and garage difference of height juncture area 5m inner cushion layer configuration reinforcement mesh sheet, and set Set horizontal direction rod head;
3) Two bors d's oeuveres channel steel purlin is arranged in steel sheet pile side, and pull rod is passed through reserved opening in the middle part of steel sheet pile and purlin, end Setting anchor head is fixed, and the other end is connected and fixed with the reinforcing steel bar of pull rod connector being arranged in bed course;
4) construction room bottom plate;
5) the low garage foundation pit of colon room bottom plate is excavated, bottom plate and external wall structure construction are carried out;To garage basement construction After the completion, steel sheet pile recycling is pulled out.
Further, the library described Fang Yudi difference of height position carries out supporting using the steel sheet pile to occupy little space.
Further, the steel sheet pile is connect using steel bar rod with a number room bed course.
The beneficial effects of the present invention are:
Using the present invention, difference of height foundation pit that can well between the number of processing room bottom plate and ground library in narrow space is avoided Pile foundation is intensive and lead to the problem of support system construction space deficiency under number room bottom plate, also avoids ground library and excavates caused number The displacement of room bottom plate and pile foundation destroys.In addition, steel sheet pile due to that can lease, without maintenance, substantially reduces the work of engineering Phase, it can carry out pulling out recycling after engineering, it is also greatly considerable in economy, in technical feasibility, working efficiency, implementation Traditional approach is all much stronger than in effect.
Detailed description of the invention
Fig. 1 is the pattern foundation pit supporting structure processing schematic in number library Fang Yudi narrow space of the invention.
Specific embodiment
Below with reference to specific example, the embodiment that the present invention is further explained.It should be understood that these examples are merely to illustrate The range of the present invention rather than limitation the invention patent.In addition, it should also be understood that, after reading the content taught by the present invention, this Field technical staff can make various changes or modifications the present invention, and such equivalent forms equally fall within right appended by the application and want Seek book limited range.
As shown in Figure 1, the pattern foundation pit supporting structure processing method in the narrow space of the library one kind Fang Yudi, comprises the concrete steps that:
1) construction room pile foundation 1, pile foundation set small seam allowance steel sheet pile 7 in ground library and a number room boundary position after the completion;
2) number of pouring room bed course 2, distance room and garage difference of height juncture area 5m inner cushion layer configuration reinforcement mesh sheet 3, steel Muscle specification is Φ 10@150 (bar diameter 10mm, spacing 150mm) single-layer bidirectional, while 20@of horizontal direction pull rod Φ is arranged 1000 (5 diameter of pull rod is 10mm, spacing 1000mm) connectors;
3) Two bors d's oeuveres channel steel purlin 8 is arranged in 7 side of steel sheet pile, and pull rod is passed through reserved opening in the middle part of steel sheet pile and purlin, is enclosed Purlin end is arranged anchor head 6 and fixes, and the reinforcing steel bar of pull rod connector being arranged in the other end and bed course 2 is connected and fixed to form anchor-pull brace body The earthwork of system, check mark room pile foundation and difference of height region carries out supporting and retaining system protection;
4) after the completion of a number room bottom plate 4 pours, the low garage foundation pit of colon room bottom plate is excavated, bottom plate and external wall structure are carried out Construction;After the completion of garage basement construction, steel sheet pile recycling is pulled out.

Claims (3)

1. the pattern foundation pit supporting structure processing method in the narrow space of the library one kind Fang Yudi, which is characterized in that comprise the concrete steps that:
1) construction room pile foundation, pile foundation set small seam allowance steel sheet pile in ground library and a number room boundary position after the completion;
2) number of pouring room bed course, distance room and garage difference of height juncture area 5m inner cushion layer configuration reinforcement mesh sheet, and water is set It puts down to rod head;
3) Two bors d's oeuveres channel steel purlin is arranged in steel sheet pile side, and pull rod is passed through reserved opening in the middle part of steel sheet pile and purlin, end setting Anchor head is fixed, and the other end is connected and fixed with the reinforcing steel bar of pull rod connector being arranged in bed course;
4) construction room bottom plate;
5) the low garage foundation pit of colon room bottom plate is excavated, bottom plate and external wall structure construction are carried out;It is completed to garage basement construction Afterwards, steel sheet pile recycling is pulled out.
2. the pattern foundation pit supporting structure processing method in the narrow space of the library according to claim 1 Fang Yudi, it is characterised in that: institute The library the number of stating Fang Yudi difference of height position carries out supporting using the steel sheet pile to occupy little space.
3. the pattern foundation pit supporting structure processing method in the narrow space of the library according to claim 1 Fang Yudi, it is characterised in that: institute Steel sheet pile is stated to connect using steel bar rod with a number room bed course.
CN201910167398.0A 2019-03-06 2019-03-06 Foundation pit support treatment method in narrow space of house and ground warehouse Active CN109914423B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910167398.0A CN109914423B (en) 2019-03-06 2019-03-06 Foundation pit support treatment method in narrow space of house and ground warehouse

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910167398.0A CN109914423B (en) 2019-03-06 2019-03-06 Foundation pit support treatment method in narrow space of house and ground warehouse

Publications (2)

Publication Number Publication Date
CN109914423A true CN109914423A (en) 2019-06-21
CN109914423B CN109914423B (en) 2021-03-26

Family

ID=66963531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910167398.0A Active CN109914423B (en) 2019-03-06 2019-03-06 Foundation pit support treatment method in narrow space of house and ground warehouse

Country Status (1)

Country Link
CN (1) CN109914423B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501777A (en) * 2020-04-20 2020-08-07 中铁隧道集团二处有限公司 Construction method for treating bias voltage of open cut foundation pit

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003268770A (en) * 2002-03-18 2003-09-25 Rita Sogo Kikaku:Kk Earth retaining construction method and reinforcing structure of sheet pile used for this construction method
CN102493459A (en) * 2011-11-24 2012-06-13 天津二十冶建设有限公司 Building isolation support construction method for constructing deep foundation in narrow environment
CN202745063U (en) * 2012-08-22 2013-02-20 中国建筑第六工程局有限公司 Deep foundation pit steel plate pile and anchor cable shoring system construction structure
CN206385548U (en) * 2016-12-16 2017-08-08 浙江省交通规划设计研究院 A kind of tandem anchor slab foundation pit support system with Recyclable anchor rope
CN107653886A (en) * 2017-08-15 2018-02-02 广东工业大学 A kind of building supporting construction and its implementation applied to foundation ditch landform
CN109235421A (en) * 2018-10-16 2019-01-18 中铁第四勘察设计院集团有限公司 A kind of double steel sheet pile fabricated structure of steel purlin also serving as interim sidewalk

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003268770A (en) * 2002-03-18 2003-09-25 Rita Sogo Kikaku:Kk Earth retaining construction method and reinforcing structure of sheet pile used for this construction method
CN102493459A (en) * 2011-11-24 2012-06-13 天津二十冶建设有限公司 Building isolation support construction method for constructing deep foundation in narrow environment
CN202745063U (en) * 2012-08-22 2013-02-20 中国建筑第六工程局有限公司 Deep foundation pit steel plate pile and anchor cable shoring system construction structure
CN206385548U (en) * 2016-12-16 2017-08-08 浙江省交通规划设计研究院 A kind of tandem anchor slab foundation pit support system with Recyclable anchor rope
CN107653886A (en) * 2017-08-15 2018-02-02 广东工业大学 A kind of building supporting construction and its implementation applied to foundation ditch landform
CN109235421A (en) * 2018-10-16 2019-01-18 中铁第四勘察设计院集团有限公司 A kind of double steel sheet pile fabricated structure of steel purlin also serving as interim sidewalk

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501777A (en) * 2020-04-20 2020-08-07 中铁隧道集团二处有限公司 Construction method for treating bias voltage of open cut foundation pit
CN111501777B (en) * 2020-04-20 2021-07-16 中铁隧道集团二处有限公司 Construction method for treating bias voltage of open cut foundation pit

Also Published As

Publication number Publication date
CN109914423B (en) 2021-03-26

Similar Documents

Publication Publication Date Title
CN205742213U (en) Foundation pit supporting construction
CN101509263A (en) Digging method foundation pit structure of steel cover and plate cover, and construction method
CN105089061A (en) Ultra-deep foundation pit supporting method
CN104060615B (en) Newly-built foundation pit supporting construction is utilized to remove the construction method of underground obstacle
CN103806464B (en) Large-scale high ferro station and subway cross top-down construction method up and down
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN104452812A (en) Construction method of basement outer wall
CN101736757A (en) Two-way synchronous construction method of tube structure of high-rise building
CN100510281C (en) Semi-inverse construction method of super large diameter, ultra-burial depth storage pond
CN109797755B (en) Steel pipe Larsen steel sheet pile enclosure structure supported by steel mesh frame and construction method thereof
CN106245678A (en) Outer wall of basement single side formwork construction method based on steel pipe truss
CN107642252A (en) Old building free removal is double to increase rebuilding construction technique
CN108385693B (en) Equal-generation anchor bolt supporting method and system for staged basement supporting
CN107326932B (en) Quasi-semi-reverse construction method for underground garage
CN106120804A (en) A kind of two grades of support systems of super-giant foundation pit double-row pile and construction method thereof
CN109914423A (en) Pattern foundation pit supporting structure processing method in number library Fang Yudi narrow space
CN204898684U (en) Super dark excavation supporting system
CN107816359A (en) A kind of construction method of the artificial pillar of underground engineering
CN209066508U (en) Cross the existing electric power piping lane protection structure of tunnel foundation pit
CN204715364U (en) A kind of foundation pit support device
CN106193120A (en) Basement is encorbelmented, and base plate is inverse makees structure and construction method
CN215406119U (en) Tall and big side slope plain noodles supporting construction
CN205688448U (en) A kind of foundation pit support device utilizing karst fragmented rock body to reinforce bearing
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
CN212248256U (en) Beam type connecting structure of front wall and rear pile combined support

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant