CN109898664A - A kind of jack-up construction method and its assembled arthitecutral structure for multi-story structure - Google Patents
A kind of jack-up construction method and its assembled arthitecutral structure for multi-story structure Download PDFInfo
- Publication number
- CN109898664A CN109898664A CN201910106247.4A CN201910106247A CN109898664A CN 109898664 A CN109898664 A CN 109898664A CN 201910106247 A CN201910106247 A CN 201910106247A CN 109898664 A CN109898664 A CN 109898664A
- Authority
- CN
- China
- Prior art keywords
- column
- layering
- jack
- layers
- girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 35
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 45
- 239000010959 steel Substances 0.000 claims abstract description 45
- 239000000725 suspension Substances 0.000 claims abstract description 41
- 238000009434 installation Methods 0.000 claims abstract description 15
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 4
- 238000000034 method Methods 0.000 claims description 11
- 238000003466 welding Methods 0.000 claims description 4
- 238000004519 manufacturing process Methods 0.000 claims description 3
- 238000002156 mixing Methods 0.000 claims 2
- 238000009432 framing Methods 0.000 claims 1
- 230000003252 repetitive effect Effects 0.000 claims 1
- 239000000428 dust Substances 0.000 abstract 1
- 239000010410 layer Substances 0.000 description 67
- 238000010586 diagram Methods 0.000 description 8
- 230000000694 effects Effects 0.000 description 2
- RYGMFSIKBFXOCR-UHFFFAOYSA-N Copper Chemical compound [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 description 1
- 229910052802 copper Inorganic materials 0.000 description 1
- 239000010949 copper Substances 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000004064 recycling Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000002356 single layer Substances 0.000 description 1
Abstract
The invention patent creates a kind of building jacking construction method, and implementation initial stage is initially applied to assembling type steel structure system.The system includes 1, reinforced concrete foundation, and suspension column and steel cylinder are embedded in basis, jack is installed in steel cylinder;2, layer Steel Structure engineering and various building blocks of function are installed;3, roofworks is jacked to N layers (top layer) of layer height with jack;4, jack piston is replaced with layering column (top layer column);5, it withdraws jack piston and returns to original position;6, N layers of (top layer) entire infrastructure and various building blocks of function are installed;7, roofworks and N layers of (top layer) engineering are jacked into the height to N-1 layers of layering column with jack;8, jack piston is replaced with N-1 layers of layering column;9, it withdraws jack piston and returns to original position;10, the structure of N-1 layers of installation and various building blocks of function, and so on, continue to complete all-work.The operation side of jack-up construction method is mainly in one layer of ground or basement construction.Be easy to use small-sized machine installation, the transport of no high-altitude, without high altitude operation, without dust, it is pollution-free, noiseless, without tower crane, saving of labor, material-saving, save duration, investment-saving, create conditions for automated construction.
Description
Technical field
The invention belongs to architectural engineering construction technique fields, inhabitation, office, business, specifically for multilayer or high level
The building of school, hospital, hotel ... etc. purposes, initial stage of implementing apply assembling type steel structure building system, and the present invention is upper
It states various buildings and more one kind, block, good, province construction method is provided.
Background technique
Existing various architecture constructions, are constructed by bottom, and up superposition in layer is finally constructed
Roofworks, the work surface of this sequence of construction are layer-by-layer raised, one layer or a several layers of work surfaces, it is therefore necessary to tower be arranged
It hangs to transport member and material, it is necessary to elevator be set and be used to transport construction personnel and construction tool, it is clear that this construction method
There are long construction period, construction efficiency is low, it is at high cost, take up a large area, pollute environment, noise ... etc. shortcoming.
Summary of the invention
The present invention provides a kind of anti-convention construction method by roofing to bottom, when reinforced concrete foundation engineering complete with
Afterwards, it constructs first roofworks, top layer (referred to as " N " layer) engineering of secondly constructing, -1 layer of engineering of constructing N numbered again, until completing N-N
Until layer engineering.The operation working face of this construction method always in one layer of ground or basement construction, without tower crane, elevator,
Scaffold, material-saving, saves fund, also safety at noiseless, pollution-free, time saving, saving of labor.
To achieve the above object, the present invention provides following technical scheme;The integral reinforced concrete of construction building object first
Basic (hereinafter referred to as " basis "), needs to be embedded in basis " suspension column " of all load-bearing pillars, a part of buried foundation of suspension column
In, another part exposes surface of base, around suspension column, in the underface of building frame girder embedment steel cylinder, steel cylinder
In a part of buried foundation, a part exposes surface of base.
The main body frame of the embodiment of the present invention selects assembling type steel structure system, and frame column is by roofing column to layering column to column
Foot all selects same steel clock, same quality, the square shaped pipe production of same model.Roofing column is layered between column, suspension column three
Connection all use the form of connecting plate, wherein roofing column, referred to as " column column is temporarily connect for layering column and the connecting plate of " suspension column "
Plate " (except basecoat), roofing column and layering column, layering column and the connecting plate for being layered column are referred to as " the permanently connected plate of column column " forever
It can add when connection long with welding.
Main beam in frame includes " roof girder " and " layering girder " all same steel grades of selection, same quality, same model
It is in roofing that the connector of I-steel production, roof girder and layering girder and level column and layering column, which is " column beam connecting plate " this plate,
Column and giving for layering column are installed to above level column and layering column in system.At the both ends of roof girder and layering girder, " beam is set
Column link slot ", this slot are mounted on above the supporting plate above jack piston, this slot plays the role of beam-to-column joint together,
Also there is the function as auxiliary jack supporting plate.
Jack be lifted monolithic architecture object power, be arranged around " suspension column ", roof girder and be layered girder two
It holds, be mounted in steel cylinder described in [0004].The effect of steel cylinder is: installation, adjustment, replacement, recycling and the appearance for fixing jack
Device, the top periphery setting of steel cylinder is several " adjustment and fixing bolt ", jack is adjusted and fixed with bolt, the lower part of steel cylinder is given
Steel ring is first installed, to the very heavy top/bottom part of fixation.
When the building number of plies of jacking is more, intercolumniation span is larger, load excessively wherein when, in the surface of jack,
Needed between upper layer and lower layer girder install " wall center pillar ", this column is mounted within wallboard, may be selected with I-shaped steel make, both ends with
It is connect, can also be welded together with beam or two kinds of connection method dual-purposes with beam with styletable plate and bolt between upper underbeam.In order to
The stress of Liang Yuzhu is tightened and improved, " small shear wall " can be set between layering column and wall center pillar between upper and lower two beam
It is made of reinforcing pull rod and horizontal support bar.
The work progress of the embodiment of the present invention is as follows:
Roofing column is installed first above " suspension column ", with " the temporary connecting plate of column column " (hereinafter referred to as " temporary connecting plate ") and
Bolt temporarily links together roofing column and suspension column;
" supporting plate " is installed on jack piston;
" beam-to-column joint slot " (hereinafter referred to as: link slot) is installed above " supporting plate ";
The end plate of " link slot " and " the column beam connecting plate " and roofing column of roofing column are linked together with bolt.
Roof girder is installed between beam-to-column joint slot (hereinafter referred to as link slot) facing each other, with bolt by roof girder with
Link slot links together, and can be welded.
It checks quality of connection between Liang Yuzhu, after passed examination, removes the temporary connecting plate of column column for the first time, start for the first time
Roofing capital is raised to top layer (hereinafter referred to as " N " layer) with jack piston, is layered the height of column by jack, and pico- is more than point
The length of layer column.
It jacked range request to travel at the uniform speed, a step one checks, a step one measurement, a step one leveling.
The layering column for installing " N " layer between suspension column and roofing column for the first time, to replace jack piston and supporting plate.N
The upper end of layer layering column is securely connect with roofing column lower end with the permanently connected plate of column column (hereinafter referred to as permanently connected plate) and bolt
Together, it can be welded.The lower end temporary connecting plate of column column (hereinafter referred to as temporary connecting plate) and bolt for being layered column will divide
Layer column links together with suspension column.
Jack piston and supporting plate are withdrawn for the first time, and piston and supporting plate are retracted into original position.
Link slot is installed on supporting plate for the second time.Link slot and N layers of column beam connecting plate and N layers of layering column are used simultaneously
It is bolted together, can be welded.
Second of installation layering girder between link slot facing each other (being installation roof girder for the first time).
For the first time between roof girder and N layers of layering girder, wall center pillar is installed in the surface of jack.
Small shear wall is installed between wall center pillar and layering column and between two beams (roof girder and layering girder) for the first time.
Second of dismounting temporary connecting plate of column column, starts jack for the second time, and roof structure and N layers of structure are jacked N-1
The layering pillar height degree of layer.
For the second time with N-1 layers of layering columns replacement jack piston and supporting plate.The upper end and roofing column lower end of N layers of layering column are used
The permanently connected plate of column column (hereinafter referred to as permanently connected plate) and bolt are securely joined together, and can be welded.It is layered under column
The end temporary connecting plate of column column (hereinafter referred to as temporary connecting plate) and bolt will be layered column and link together with suspension column.
Second of withdrawal jack piston and supporting plate, are removed to original position.
Each layer of operating process repeats the operating process of [0019] to [0025] below.Different links be N-N layers
Layering column and suspension column between no longer with " temporary connecting plate " but be connected with " permanently connected plate ".
Above operation sequence is only only completed the beam column skeleton of major project, roof boarding and its more than roofworks and every
Floor plate, wallboard (inner-outer wall, shear wall), door and window, stair, elevator ... etc. successive projects, construction of making separate arrangements.
Certainly there are also another modes of operation, that is, in [0014] after roof girder installation, can also continue to install
Every engineering more than roof boarding and roof boarding removes temporary connecting plate after roofworks is completed by design requirement again,
Jack is started again, will be complete, qualified, the integral roofing by examination jacks the height of N layers (top layer).
After the completion of wall center pillar and small shear wall in [0022], jack wouldn't be started, and equally with [0028], installation
N layers of floor, wallboard (inside and outside wall board and shear wall slab), door and window, stair and various pipe engineerings and various utensils and finishing
Engineering etc., after substantially meeting every construction content of design requirement, temporary connecting plate of dismantling starts jack again will
N layers of (top layer) engineering of whole roofworkss and whole of completion jack the height of N-1 layers of layering column.The operating process of following layers
The operating process for repeating [0028] and [0029], until completing N-N layers of all-work.
[0028] and the operation scheme of [0029] is feasible and optimal, because each layer of all-work is all
It can be completed in one layer of ground or basement,.This is only optimal jack-up construction method, can realize automatically to be final, nobody
The target of construction lays the foundation.The beam column skeleton that selection completes every layer actually jacks in advance, or completes every layer of all-work
Jack again, or complete a certain engineering between the two in advance, such as complete floor project and start to jack, or complete floor project and
Start to jack after wallboard engineering, according to the actual situation, is studied and determined jointly by Party A, design side and construction party.
In special circumstances, 2 or 2 or more jack can be respectively arranged in each layering girder both ends.Wall center pillar can also be with
Increased according to the increase of jack quantity.If two jack are respectively installed at layering girder both ends, main jack can be divided into
With secondary jack.
Detailed description of the invention
In order to illustrate the technical solution of the embodiments of the present invention more clearly, below letter will be made to attached drawing used in embodiment
It is single to introduce.It should be understood that the following drawings only shows certain embodiments of the present invention, therefore attached drawing is not construed as to this hair
The restriction of bright the scope of the patents.
In the accompanying drawings:
Fig. 1 is roofworks, foundation engineering and Lifting Equipment scheme of installation;
Fig. 2 is to start jack for the high-level schematic of roofworks jacking first floor;
Fig. 3 is with single layer column replacement jack and to withdraw jack piston schematic diagram;
Fig. 4 is to indicate to have completed roofing, N layers, N-1 layers, jacking and installing engineering schematic diagram;
Fig. 5 is roofing column schematic diagram;
Fig. 6 is layering column schematic diagram;
Fig. 7 is layering girder schematic diagram;
Fig. 8 is layering column, link slot and layering girder assembling schematic diagram;
Fig. 9 is steel cylinder and suspension column schematic diagram;
Figure 10 is steel cylinder and suspension column E-E diagrammatic cross-section;
Figure 11 is copper cylinder and F-F diagrammatic cross-section;
Figure 12 is supporting plate plane and diagrammatic cross-section;
Figure 13 is wall center pillar schematic diagram;
1. roofing column;2. roof girder;3. being layered girder;4. beam-to-column joint slot;5. supporting plate;6. steel cylinder;7. suspension column;8. layering
Column;9. the permanently connected plate of column column;10. the temporary connecting plate of column column;11. column beam connecting plate;12. bolt;13. screw hole;14. layering master
Beam end plate;15. fixed and centering bolt;16. beam-to-column joint slot end plate;17. beam-to-column joint trough floor;18. wall center pillar;19. point
Layer girder end plate;20. jack;21. steel ring;A. roofworks;B.N layers of (top layer) engineering;C.N-1 layers of (lower 1 layer of top) engineering;
D. foundation engineering.
Specific implementation method:
Below with reference to attached drawing, in conjunction with the embodiments, the invention will be further described.
As shown in Figure 1, Figure 2, Figure 3, Figure 4, A is the roofworks in full building, and roofing column 1 is the most upper of full building vertical support
Section, the lower half mounting post beam connecting plate 11 of roofing column 1, there are screw holes 13 to pass through the temporary connecting plate of column column for the bottom of roofing column 1
10 are connected with suspension column 7.Roof girder 2 is the horizontally-supported main part of roofing frame.Roofing column 1 passes through " column beam connecting plate " 11 and beam column
Link slot 4 is connected with roof girder 2.Roofing column 1 and roof girder 2 form roofing main body frame.It is laid with roof boarding and various above
Facility collectively constitutes roofing integrated engineering A.
As shown in Figure 1, Figure 2, Figure 3, Figure 4, layering column 8 is the interlude of each floor vertical support in full building, the upper end and roofing
Column 1 is connected with the permanently connected plate 9 of column column and bolt 13, and lower end and suspension column 7 are temporary with the temporary connecting plate 10 of column column and bolt 12
When be connected.Layering column 8 is connected by column beam connecting plate 11 and beam-to-column joint slot 4 with layering girder 3, and N layers of (top are collectively constituted
Layer) beam column frame, be then laid with floor, inside and outside wall board and shear wall slab on the top of layering girder and various other set
It applies, completes N layers of all-work B in this way.N-1 layers of all-work C can also be completed according to procedure above.
As shown in Figure 1, Figure 2, Figure 3, Figure 4, D is the foundation engineering in full building, and suspension column 7 and steel cylinder 6, steel are embedded in basic D
A part of length of cylinder 6 and suspension column 7 exposes the basis surface D.The upper end of suspension column 7 prepares and the roofing above it there are screw hole 13
Column 1 or layering column 8 are connected with the temporary connecting plate 10 of column column." fixed and tune is provided below in the suitable for reading of steel cylinder 6 as shown in figure 11
Whole bolt 15, the bottom of steel cylinder 6 are equipped with steel ring 21, install jack 20 inside steel cylinder, 20 bottom of jack is fixed on steel ring 21
In, " fixed and centering bolt 15 is aligned and fixed " is used on the top of jack 20.
As shown in Figure 1, Figure 2, shown in the basic D in Fig. 3, Fig. 4, the top land of jack 20 installs supporting plate 5, above supporting plate 5
Beam column connecting slot 4 is installed, beam-to-column joint slot 4 is also connected with layering girder 3 and layering column 8 simultaneously.
As shown in Figure 5 and Figure 6,1 lower end of roofing column passes through the temporary connecting plate of column column there are screw hole 13 and is connected with suspension column 7.
8 upper and lower side of column is layered all there are screw hole 13, upper end is connected with roofing column 1, and lower end is layered 8 phase of column with suspension column 7 or with another
Connection.Mounting post beam connecting plate 11 when prefabricated on roofing column 1 and the layering lower part of column 8, end screw hole 13, when installation and beam column
The end plate 16 of link slot 4 is connected.
Roof girder 2 as shown in Figure 5, Figure 6 is equipped with end plate with layering (two beams the are identical) both ends of girder 3, can be with beam column
The end plate 16 of link slot 4 is connected, and there are screw holes for the lower wing plate of roof girder 2 and layering girder 3, can be with the bottom of beam-to-column joint slot 4
Plate 17 is connected.The end plate 16 and bottom plate 17 of beam-to-column joint slot 4 have screw hole and roof girder 1 and layering 3 end plate of girder and bottom plate
It can connect, according to the actual situation optionally.Beam-to-column joint slot 4 and column beam connecting plate 11 are less when floor, building load compared with
When low, it can decide what to use according to the actual situation.
As shown in Fig. 9, Figure 10, Figure 11, illustrate the correlation of jack and steel cylinder, particularly shows bottom steel ring 21 and upper
The fixed effect with adjustment bolt 15 in portion.
The plane and section of supporting plate 5 as shown in figure 12.
As shown in figure 13, it when building floor is very high, when intercolumniation span is very big, is excessively concentrated to reduce load, in column
Around foot, the surface of jack two is layered setting wall center pillar 18 between beams up and down.
As shown in Figure 1, supporting plate 5 is mounted on 20 piston of jack first installing engineering is by 20 piston of jack,
Beam-to-column joint slot 4 is mounted on supporting plate 5 again, then the end plate 16 of beam-to-column joint slot 4 and column beam connecting plate 11 and roofing column 1 are connected
It is connected together, then roof girder 2 is mounted on beam-to-column joint slot 4, roof girder 2 and the bottom plate 17 of beam-to-column joint slot 4 are connected to
Together, then the engineering of roof boarding and roof boarding or more can be installed.
As shown in Figure 1, after quality examination is qualified, it is temporary to remove column column for the first time when roofworks is all installed
Connecting plate 10.Jack 20 is started for the first time, it is pico- to be layered more than N layers by the height of roofworks A jacking " N " layer (top layer)
The height of column 8, as shown in Figure 2.
As shown in figure 3, jack 20 is replaced with N layers of layering column 8 for the first time, then by the upper end and room of N layers of layering column 8
The permanently connected plate 9 of lower end column column of face column 1 is securely joined together, and column column is used between the lower end and suspension column 7 of N layers of layering column 8
After temporary connecting plate 10 links together, withdraw 20 piston of jack for the first time, make 20 piston of jack return to it is in situ (including
Supporting plate 5) so far, lifting finishes for the first time.
Second of lifting and first time are essentially identical, beam column link slot 4 are successively installed on supporting plate 4, by beam-to-column joint slot 4
End plate 16 and column beam connecting plate 11 and layering column 8 link together, installation layering girder 3, layering girder 3 and beam-to-column joint slot
4 bottom plate 17 links together, and the end plate 19 for being layered girder 3 can also be connect with the end plate 16 of beam-to-column joint slot 4 and column beam
Plate 11 and layering column 8 link together.Then N floor plate, inside and outside wall board, shear wall slab and N layers of all-work can be installed.
Such as [0060], after the completion of N layers of all-work, second of dismounting temporary connecting plate 10 of column column starts for the second time
Jack 20.Roofworks and N layers of engineering are raised to N-1 layers of height, then replaced with N-1 layers of layering column 8 for second
20 piston of jack, then withdraw 20 piston of jack second, it is returned to original position.N-1 layers of installing engineering are carried out again.Work as N-1
After the completion of layer installing engineering, third time removes the temporary connecting plate 10 of column column, starts jack 20 for the third time, by roofworks, N layers
Engineering and N-1 layers of engineering jack the height of N-2 layers of layering column, and so on, N-3 layers N-4 layers are completed until the completion of N-N engineering is
Only.
Claims (7)
1. building jacking construction method of the invention, first the reinforced concrete foundation engineering D of construction building object are (hereinafter referred to as
Basic D).By in the load-bearing pillar lowermost buried foundation D for needing to combine with basis D in building entirety beam column frame, claim
For suspension column 7.
A part of suspension column 7 is embedded in basic D, and another part exposes the basis surface D.
The prefabricated screw hole 13 in the top of suspension column 7.
2. building jacking construction method requires the pre-buried steel cylinder 6 in basic D, in a part of buried foundation of steel cylinder 6, another portion
Divide and exposes the basis surface D.The roof girder 2 in building general frame and the underface at layering 3 both ends of girder is arranged in steel cylinder 6,
Close to 7 place of suspension column.Hydraulic jack 20 (abbreviation jack 20) is installed in steel cylinder 6, is pacified in the piston upper of jack 20
Supporting plate 5 is filled, beam column link slot 4 is installed on supporting plate 5.
In the bottom of steel cylinder 6 setting positioning steel ring 21, suitable for reading in steel cylinder 6 is installed below several fixations and centering bolt 15, uses
To align and fix jack 20.
1 steel cylinder 6 is arranged in every end ordinary circumstance of roof girder and layering girder 3, two or more steel cylinders are arranged in special circumstances
6。
One hydraulic jack 20 (hereinafter referred to as jack 20) is installed, steel ring 21 is inserted into 20 lower end of jack in each steel cylinder 6
In, the fixation of the upper end steel cylinder 6 of jack 20 and centering bolt 15 are fixed and are aligned to jack 20.Jack 20 is living
It the center of plug must be to the center of roof girder 2 and layering girder 3 just above it.
3. building jacking construction method of the invention, for implementing initial stage temporary assembling type steel structure frame system.The structure
The vertical support column system of frame system is successively from bottom to top that suspension column 7, several layering columns 8 and roofing column 1 form.The frame
Horizontal shore system by roof girder 2 and layering girder 3 and several secondary beams form.
It is connected between suspension column 7 and layering column 8 with the temporary connecting plate 10 of column column and bolt 12 between suspension column 7 and roofing column 1.Roofing
It connects, can also increase between column 1 and layering column 8 and with the permanently connected plate 9 of column column and bolt 12 between layering column 8 and layering column 8
Welding.
Column beam connecting plate 11 and beam-to-column joint slot 4 are all used between roof girder 2 and roofing column 1, between layering column 8 and layering girder 3
And bolt 12 connects, and can also increase welding.
For convenient for construction, the present embodiment roof girder 2, layering girder 3, roofing column 1, layering column 8, suspension column 7 all select same steel grade,
The section steel manufacture of same quality, same model.
4. the building jacking construction method operation sequence that the present invention is created is:
Suspension column 7 and roofing column 1 are temporarily linked together with the temporary connecting plate 10 of column column and bolt 12.
Supporting plate 5 is installed on 20 piston of jack.
Beam column link slot 4 is installed on supporting plate 5 for the first time.
The end plate 16 of beam-to-column joint slot 4 is bolted together by column beam connecting plate 11 with roofing column 1 for the first time, can be added
With welding.
For the first time between every two roofing column 1, the upper surface of two opposite beam-to-column joint slots 4 install roof girder 2.By roof girder
2 link together with the bolt 12 of bottom plate 17 of beam-to-column joint slot 4, also can weld.The end plate 16 of beam-to-column joint slot 4 is led to simultaneously
It crosses column beam connecting plate 11 to be connected with the bolt 12 of roofing column 1, can also be welded.So far the beam column frame of first time roofing has been
Through being formed, and this frame is already installed on the piston and supporting plate 5 of multiple jack 20.For the first time remove roofing column 1 with
The temporary connecting plate 10 of column column between suspension column 7.
Jack 20 is started for the first time, it is pico- super by roofing beam column frame jacking to the height of top layer (N layers of abbreviation) layering column 8
Cross the length of layering column 8.
It uses the lower end of the layering column 8 for installing N layers between roofing column 1 and suspension column 7 for the first time, the upper end and roofing column 1 that are layered column 8
The permanently connected plate 9 of column column and bolt 12 link together both ends, can be welded, and the lower end of column 8 and the upper end of suspension column 7 are layered
With the temporary connecting plate 10 of column column and bolt 12, both ends are linked together.
The piston and supporting plate 5 of jack 20 are recalled for the first time.So far the construction space of N layers (top layers) has been formed.
Second of installation beam column link slot 4 on supporting plate 5.
The end plate 16 of beam-to-column joint slot 4 is linked together by column beam connecting plate 11 and the layering bolt 12 of column 8 for the second time, it can
It is welded.
For the second time between every two layering column 8, the installation layering girder 3 between two opposite beam-to-column joint slots 4, (first
Secondary is installation roof girder), and the both ends for being layered girder 3 are linked together with the bolt 12 of beam-to-column joint slot 4, it can be welded
It connects.So far the beam column frame of N layers (top layers) has been formed.
Second of temporary connecting plate 10 of column column removed between layering column 8 and suspension column 7.
Jack 20 is started for the second time, and roofing beam column frame and N layers of beam column frame are jacked to the height of N-1 layers of layering column 8.
Second of N-1 layers of layering column 8 of installation between N layers of layering column 8 and suspension column 7.The upper end of N-1 layers of layering column 8 and N layers of layering
The lower end of column 8 is linked together with permanently connected 9 blending bolt 12 of plate of column column, can be welded.The lower end of N-1 layers of layering column 8
Temporarily it is connected with suspension column 7 with the temporary connecting plate 10 of column column and bolt 12.So far N-1 layers of construction space has been formed.
Third time installs beam column link slot 4 on supporting plate 5, and the end plate 16 of beam-to-column joint slot 4 is passed through column Liang Lian by blending bolt 12
Fishplate bar 11 links together with layering column 8, can be welded.
Third time is between layering column 1 and layering column 1, installation layering girder 3, layering between two opposite beam-to-column joint slots 4
The both ends of girder 3 are connect with the bolt 12 of beam-to-column joint slot 4 respectively, can be welded.So far N-1 layers of beam column frame shape
At.
Third time removes the temporary connecting plate 10 of studding column of N-1 layers of layering column 8 and suspension column 7.
Third time starts jack 20, and by roofing beam column frame, N layers of beam column frame and N-1 layers of beam column frame jack N-2 layers of layering
The height of column 8.And the piston of jack 20 is replaced with N-2 layers of layering column.So far N-2 layers of construction space has been formed.
And so on, according to above procedure repetitive operation, until completing N-N layers of frame engineering.
The roof boarding of for example each layer of successive projects, wallboard (inside and outside wall board, shear wall slab etc.), door and window, stair, elevator, various pipelines,
Various utensils and fitting-out work etc., successive projects are separately constructed.
5. there are also better sequences of construction, it is installed in roof girder 2, after roofing beam column frame has been formed, does not start temporarily
Jack does not jack temporarily, continues to install roof boarding engineering, and by whole roofworkss of design requirement and then dismounting
The temporary connecting plate 10 of column column between room room column 1 and suspension column 7, then jack is started, by complete by examination, whole room
Face engineering jacks N layer of height, other each layers such as N-1 layers, N-2 layers ... until the top N-N, all as roofworks,
Each layer wouldn't start thousand tops after the completion of beam column frame, wouldn't jack, but continue to complete this layer of floor project, various walls
Plate engineering, door and window work, stair engineering, various pipelines and the installing engineering ... of various utensils etc., after the completion of above-mentioned engineering
The temporary connecting plate 10 of column column is removed again, then starts jack, and the engineering completed is jacked to the height of this layer of layering column.This
Kind operational procedure is optimal, can be that automated construction from now on lay the foundation.
6. being installed between the surface of jack 20, upper and lower two layerings girder 3 to improve structural framing stress equalization degree
Between the both ends of wall center pillar 18 and upper lower leaf girder 3 with bolt 12 or connection is welded and fixed in wall center pillar 18, and wall center pillar 18 is arranged
Indoor finishing is not influenced among wallboard.
7. small shear wall is arranged, to reinforce building between upper lower leaf girder 3 between wall center pillar 18 and layering column 8
Stability.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910106247.4A CN109898664A (en) | 2019-02-02 | 2019-02-02 | A kind of jack-up construction method and its assembled arthitecutral structure for multi-story structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910106247.4A CN109898664A (en) | 2019-02-02 | 2019-02-02 | A kind of jack-up construction method and its assembled arthitecutral structure for multi-story structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109898664A true CN109898664A (en) | 2019-06-18 |
Family
ID=66944738
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910106247.4A Pending CN109898664A (en) | 2019-02-02 | 2019-02-02 | A kind of jack-up construction method and its assembled arthitecutral structure for multi-story structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109898664A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112112283A (en) * | 2019-06-19 | 2020-12-22 | 高继良 | Layered flow structure installation method matched with fabricated building jacking construction method |
CN114893022A (en) * | 2022-06-17 | 2022-08-12 | 上海建工四建集团有限公司 | Floor descending device for reverse building demolition and construction method |
Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06200626A (en) * | 1993-01-08 | 1994-07-19 | Kajima Corp | Jacking-up method for building |
JPH0988185A (en) * | 1995-09-22 | 1997-03-31 | Kajima Corp | Building construction method of building structure body and lifter of building structure body |
CN1155029A (en) * | 1996-10-07 | 1997-07-23 | 邓庚厚 | Top-lifting building method of building from upper to lower |
JP2000199278A (en) * | 1999-01-05 | 2000-07-18 | Kawasaki Heavy Ind Ltd | Building method for structural body of building |
CN1262365A (en) * | 1999-01-22 | 2000-08-09 | 高继良 | Method and apparatus for raising up building |
JP2004003155A (en) * | 2002-05-31 | 2004-01-08 | East Japan Railway Co | Jack-down method available for construction of steel frame building |
KR20090116099A (en) * | 2008-05-06 | 2009-11-11 | 김태유 | Column supporting beam structure and iron frame construction using it |
JP2016102298A (en) * | 2014-11-27 | 2016-06-02 | 株式会社竹中工務店 | Building raising structure |
CN105839784A (en) * | 2016-03-17 | 2016-08-10 | 杨春 | Assemble-jacking type building construction method |
CN105863287A (en) * | 2016-03-31 | 2016-08-17 | 山东建筑大学 | Method for jacking storey-addition and shock insulation of framework-structure building |
CN106638975A (en) * | 2016-12-29 | 2017-05-10 | 河北省建筑科学研究院 | Building jacking overturn-preventing construction method |
CN107013046A (en) * | 2017-06-19 | 2017-08-04 | 中冶建工集团有限公司 | A kind of antidote of heavy in section concrete filled steel tube coupled column |
CN211143319U (en) * | 2019-02-02 | 2020-07-31 | 高继良 | Building structure composed of beam column framework for multi-layer steel structure building |
-
2019
- 2019-02-02 CN CN201910106247.4A patent/CN109898664A/en active Pending
Patent Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06200626A (en) * | 1993-01-08 | 1994-07-19 | Kajima Corp | Jacking-up method for building |
JPH0988185A (en) * | 1995-09-22 | 1997-03-31 | Kajima Corp | Building construction method of building structure body and lifter of building structure body |
CN1155029A (en) * | 1996-10-07 | 1997-07-23 | 邓庚厚 | Top-lifting building method of building from upper to lower |
JP2000199278A (en) * | 1999-01-05 | 2000-07-18 | Kawasaki Heavy Ind Ltd | Building method for structural body of building |
CN1262365A (en) * | 1999-01-22 | 2000-08-09 | 高继良 | Method and apparatus for raising up building |
JP2004003155A (en) * | 2002-05-31 | 2004-01-08 | East Japan Railway Co | Jack-down method available for construction of steel frame building |
KR20090116099A (en) * | 2008-05-06 | 2009-11-11 | 김태유 | Column supporting beam structure and iron frame construction using it |
JP2016102298A (en) * | 2014-11-27 | 2016-06-02 | 株式会社竹中工務店 | Building raising structure |
CN105839784A (en) * | 2016-03-17 | 2016-08-10 | 杨春 | Assemble-jacking type building construction method |
CN105863287A (en) * | 2016-03-31 | 2016-08-17 | 山东建筑大学 | Method for jacking storey-addition and shock insulation of framework-structure building |
CN106638975A (en) * | 2016-12-29 | 2017-05-10 | 河北省建筑科学研究院 | Building jacking overturn-preventing construction method |
CN107013046A (en) * | 2017-06-19 | 2017-08-04 | 中冶建工集团有限公司 | A kind of antidote of heavy in section concrete filled steel tube coupled column |
CN211143319U (en) * | 2019-02-02 | 2020-07-31 | 高继良 | Building structure composed of beam column framework for multi-layer steel structure building |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112112283A (en) * | 2019-06-19 | 2020-12-22 | 高继良 | Layered flow structure installation method matched with fabricated building jacking construction method |
CN114893022A (en) * | 2022-06-17 | 2022-08-12 | 上海建工四建集团有限公司 | Floor descending device for reverse building demolition and construction method |
CN114893022B (en) * | 2022-06-17 | 2023-09-22 | 上海建工四建集团有限公司 | Floor lowering device for reversely dismantling building and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111254796B (en) | Single-side integral hoisting long-span overbridge for multiple railway business lines and construction method | |
US6082058A (en) | Lifting method of building construction from top to bottom | |
CN211774523U (en) | Prefabricated building that can build temporarily | |
CN105569358A (en) | Construction method of special-shaped curved surface roof with large span and multiple curvatures | |
CN204826308U (en) | Structure assembly type structure is pieced together in advance to prefabricated shaped steel concrete shear force wall | |
CN110042867B (en) | Full-composite assembled subway station prefabricated part mechanized transportation system and method | |
CN105089178A (en) | Fabricated building of pre-assembling structure of prefabricated section steel concrete shear wall | |
CN109898664A (en) | A kind of jack-up construction method and its assembled arthitecutral structure for multi-story structure | |
CN110700103A (en) | Construction method of continuous composite beam | |
CN210685444U (en) | Quick leveling, mounting and supporting device for prefabricated external wall panel | |
CN110042861B (en) | Assembled rail top air duct of subway station and connecting node of assembled rail top air duct and prefabricated middle plate | |
CN113389304A (en) | Assembled double-blade cavity superposed wall system and construction method thereof | |
CN111088846A (en) | Recyclable prefabricated house and installation method | |
CN205875520U (en) | Precast beam steel reinforcement cage component and reinforced concrete roof beam | |
CN109267578B (en) | Inclined plane plain concrete structure and construction method thereof | |
CN211143319U (en) | Building structure composed of beam column framework for multi-layer steel structure building | |
CN106939642A (en) | Under hanging packway davit structure and its installation forming method | |
CN111236416A (en) | Prefabricated reinforced concrete structure house and installation method thereof | |
CN111101645A (en) | Self-in-place reinforced precast concrete wallboard, connecting structure and construction method | |
CN216042835U (en) | Layer adding device with light wall board for raising frame structure | |
CN212667017U (en) | Rockery special-shaped steel structure jig frame | |
CN211081037U (en) | Above-ground building and underground structure integrated assembly type building structure | |
CN211172365U (en) | Assembled low-rise residential structure system | |
CN216108617U (en) | Structure system of prefabricated reinforced concrete beam of underground station | |
CN218814375U (en) | Assembled wallboard-column joint structure and assembled house |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |