JP2000199278A - Building method for structural body of building - Google Patents

Building method for structural body of building

Info

Publication number
JP2000199278A
JP2000199278A JP11000329A JP32999A JP2000199278A JP 2000199278 A JP2000199278 A JP 2000199278A JP 11000329 A JP11000329 A JP 11000329A JP 32999 A JP32999 A JP 32999A JP 2000199278 A JP2000199278 A JP 2000199278A
Authority
JP
Japan
Prior art keywords
floor
lifting
main
building
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11000329A
Other languages
Japanese (ja)
Other versions
JP3398839B2 (en
Inventor
Tsutomu Tomita
勉 冨田
Tomoaki Matsuda
友秋 松田
Kiminari Ishida
公成 石田
Takashi Takahashi
敬 高橋
Akira Mizutani
亮 水谷
Akitoshi Yoshii
昭捷 喜井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Kawasaki Heavy Industries Ltd
Original Assignee
Kajima Corp
Kawasaki Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Kawasaki Heavy Industries Ltd filed Critical Kajima Corp
Priority to JP00032999A priority Critical patent/JP3398839B2/en
Publication of JP2000199278A publication Critical patent/JP2000199278A/en
Application granted granted Critical
Publication of JP3398839B2 publication Critical patent/JP3398839B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide load lifting equipment and a building method capable of efficiently obtaining a building of a stable quality. SOLUTION: This method comprises a first process in which a load lifting equipment D' is arranged at an inground middle main column 33 and, on the other hand, the penthouse floor and the highest floor are assembled, and a lifting beam 44 of a weight lifting equipment D' is arranged to the bottom surface of both the beams of the middle main column 32, a second process in which the highest floor layer is lifted to a height corresponding to one layer story and the whole load is transferred to a temporary receiving column 32b and the lifting beam 44 is made free, a third process in which the lifting beam 44 is further lowered and a beam-receiving base 47 is interposed to the lower surface of the lifting beam 44, a fourth process in which the structural body of building is lifted more than one story layer by weight lifting bodies A, D', the lifting beam 44 is transferred to a foundation pipe and the beam of the next story layer is assembled between the main columns, and a fifth process in which the lifting beam 44 is lowered to the lowest level and then the lifting beam 44 is reset again to the initial position. Then, the processes 2 to 5 are repeatedly performed and the building construction work for first floor layer is completed by the sixth process in which the lower end of the middle main column 32 is coupled to the foundation pile.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】 本発明は、ビル、マンショ
ンなど建物構造体の全天候型建築工法に係る技術的分野
に属する。
TECHNICAL FIELD [0001] The present invention belongs to a technical field related to an all-weather construction method for a building structure such as a building or an apartment.

【0002】[0002]

【従来の技術】 従来、全天候型の建物構造体の基礎工
法としては、特開平3−107037号公報、又は特開
平3−107038号公報に開示されているように、コ
ア部1を、仮設支柱、型枠部、ジャッキ及びブラケット
からなる自動上昇型枠により構築するとともに、建築物
の柱13が立設される個所にもジャッキ12を設置す
る。次に2層分のコア部1を先行構築した後、建築物の
最上部から3層分の梁14,柱13を同時構築し、柱用
底型枠、柱用型枠を配設し、柱13及びスラブ24のコ
ンクリートを打設する。そして柱13が自立可能な状態
まで降下した段階で、ジャッキ12などを伸長して躯体
を1層分上方に押し上げ、順次下階の構築作業を継続
し、これを繰り返す建築工法などが知られている。又、
他の工法として特開平5−25864号公報に示すよう
に、建造物の柱10を施工した後、この柱10に沿って
床スラブSを上昇させるという操作を逐次繰り返し実施
して、各床スラブSをそれぞれ各階の床部に配設する。
このような建築躯体の構築方法において、床スラブSを
上昇させる工程を、最上階の床スラブSから次層階側の
床スラブ1Sへ順次に実施する。そして床スラブSの下
面に配置された上昇装置2によって床スラブSを支持し
ながら上昇させる建築工法などが知られている。また、
他の工法として特公平7−33689号公報に示すよう
に、地上レベルで1階分の躯体を集中的に施工し、1階
分の躯体工事完了後に階高分だけ上方に躯体の柱をプッ
シュアップすることを繰り返すことにより建物を施工
し、その場合において、プッシュアップ用ピン穴と固定
用ピン穴を有するフランジを柱に取付けるとともに、当
該プッシュアップ用ピン穴と係合可能なピンを備えるセ
ンターホールジャッキと当該固定用ピン穴と係合可能な
ピンを備える躯体保持装置とを前記柱の周囲に配し、こ
れをもって躯体の柱をプッシュアップする建築工法など
が知られている。
2. Description of the Related Art Conventionally, as a foundation construction method for an all-weather building structure, as disclosed in JP-A-3-103737 or JP-A-3-107038, a core 1 is provided with a temporary support. , And a jack 12 is installed at the place where the pillar 13 of the building is erected. Next, after preliminarily constructing the core portion 1 for two layers, the beams 14 and columns 13 for three layers are simultaneously constructed from the top of the building, and a bottom formwork for columns and a formwork for columns are provided. The concrete of the pillar 13 and the slab 24 is cast. At the stage when the pillar 13 is lowered to a state where the pillar 13 can be self-supported, the jack 12 and the like are extended to push up the frame by one layer, and the construction work on the lower floor is sequentially continued. I have. or,
As another construction method, as shown in Japanese Patent Application Laid-Open No. Hei 5-25864, after constructing a pillar 10 of a building, an operation of raising a floor slab S along the pillar 10 is sequentially and repeatedly performed. S is placed on the floor of each floor.
In such a construction method of the building frame, the step of raising the floor slab S is sequentially performed from the floor slab S on the top floor to the floor slab 1S on the next floor. A construction method of raising the floor slab S while supporting the floor slab S by a lifting device 2 arranged on the lower surface of the floor slab S is known. Also,
As another construction method, as shown in Japanese Patent Publication No. 7-33689, one frame of the skeleton is intensively constructed at the ground level, and after completing the framing of the first floor, the pillar of the skeleton is pushed upward by the height of the floor. A building having a push-up pin hole and a flange having a fixing pin hole attached to a pillar, and a center having a pin engageable with the push-up pin hole. There is a known construction method in which a hole jack and a skeleton holding device having a pin that can be engaged with the fixing pin hole are arranged around the pillar, and the pillar of the skeleton is pushed up with this.

【0003】上述した従来の建物構造体の建築工法に
は、次のような特質が認められている。 (a)全天候下での作業がなし得られ、天候に左右され
ない。 (b)高所作業が少ないため安全な施工ができ、而も近
隣に資材落下、飛散などの不安を与えない。 (c)建物の上部にタワークレーンなどの仮設設備を設
けないため、電波などに影響を与えない。
The following characteristics are recognized in the above-mentioned conventional construction method for building structures. (A) Work can be performed in all weather conditions and is not affected by weather conditions. (B) Since there is little work at high altitudes, safe construction can be performed, and there is no fear of falling or scattering materials nearby. (C) No temporary equipment such as a tower crane is installed above the building, so there is no effect on radio waves.

【0004】しかしながら、この種従来例のうちの2件
は建物構造体の全天候型建築工法は、最上階から未完の
骨組躯体を順次押し上げてゆく方式であるため、次に示
すような課題が依然として残されている。 (a)各階層における未完躯体の高所建築作業がそのま
ま残されており、資材の落下や飛散などの不安がある。 (b)地層毎に躯体構築用の資材を搬送する設備を要
し、建築作業量の平準化が望めない。また、従来例の他
の1件は、地上レベルで1階分の躯体を施工し、これを
順次プッシュアップする方式であるため、上記の課題は
ないものの次のような課題が残されている。 (c)プッシュアップ用の専用仮設フランジを柱に取り
付けるなど、躯体に取り付ける特別の仮設が必要であ
る。 (d)躯体の柱のプッシュアップ時に、フレームが柱を
囲むためプッシュアップ以前に躯体の梁を柱に取付ける
ことができず、従って梁取付けを中空位置で行わざるを
得ない。
[0004] However, two of the conventional examples of this kind are all-weather construction methods for building structures, in which an unfinished frame structure is sequentially pushed up from the top floor, and the following problems still remain. Is left. (A) Unfinished high-level building work at each level is left as it is, and there is concern about falling or scattering of materials. (B) Equipment for transporting building construction materials is required for each stratum, making it impossible to equalize the amount of construction work. Another example of the conventional example is a method in which a frame of one floor is constructed at the ground level and sequentially pushed up, so the following problems are left though the above problems are not present. . (C) It is necessary to provide a special temporary mounting to the frame, such as mounting a dedicated temporary flange for push-up on the pillar. (D) At the time of pushing up the pillar of the skeleton, the frame surrounds the pillar, so that the beam of the skeleton cannot be attached to the pillar before the push-up. Therefore, the beam must be attached in the hollow position.

【0005】上記技術的課題を解決するため、本件発明
者等は、特開平9−88185号公報に示すような、建
物構造体の建築工法及び建物構造体の扛重構造体の扛重
装置を提案している。この公開された先行技術は、地上
近傍で最上階の建物躯体を略完成させ、最上階から完成
した建物躯体を順次扛重し、所要階数の中高層階の建物
構造体を構築せしめ、高所作業のない安全な施工がなし
うるとともに、安定した品質の建物が効能的に得られる
建築工法と扛重装置を提供することにある。
In order to solve the above technical problems, the present inventors have proposed a construction method for a building structure and a lifting device for a lifting structure of a building structure as disclosed in Japanese Patent Application Laid-Open No. 9-88185. is suggesting. This published prior art is to complete the building structure on the top floor near the ground, lift the completed building structure from the top floor in order, and build the required number of mezzanine and high-rise building structures. It is an object of the present invention to provide a construction method and a lifting device capable of performing safe construction without any trouble and efficiently obtaining a building of stable quality.

【0006】本発明の目的は、上記特開平9−8818
5号公報に示された建築工法及び扛重装置の技術的事項
をそのまま利用するとともに、この技術に更に建物構造
体を構成する中間主柱の建柱に別個の扛重手段を用い、
更に安定した品質の建物が高能率的に得られる建築工法
と扛重装置を提供することにある。
An object of the present invention is to solve the above-mentioned problem described in Japanese Patent Application Laid-Open No. 9-8818.
In addition to utilizing the technical matters of the construction method and the lifting device shown in Japanese Patent Publication No. 5 as it is, a separate lifting device is used for the pillars of the intermediate main pillars constituting the building structure.
Another object of the present invention is to provide a construction method and a lifting device capable of efficiently obtaining a building of stable quality.

【0007】[0007]

【課題を解決するための手段】 上記課題を解決する手
段として本発明は、次のょうな建物構造体の建築工法を
採用する。
Means for Solving the Problems As means for solving the above problems, the present invention employs the following construction method for a building structure.

【0008】上記目的は、基礎上において中高層階建物
構造物の屋上階及び最上階を組立てたのち、建物構造体
を構成する外周主柱近傍の両側梁下面を扛重手段(A)
の閂にて支持して扛上し、この扛上により生ずる作業空
間部に下層階を順次組み立てて構築するようにした建物
構造体の建築工法において、建築構造体を構成する中間
主柱を建柱する基礎杭両側の地中梁上または地層階の主
柱両側の梁上に、中間主柱位置を挟むように2個一組の
扛重装置(D’)を配設せしめ、一方、1層階分高さの
外周主柱の搬入組立てと前後して基礎杭上または地層階
の主柱上に略1.5層階分の高さを有する中間主柱を搬
入乗載し、この中間主柱および外周主柱相互間の梁の組
立て、天井部材、小梁などを取付けて建築構造体の屋上
階及び最上階を組立てるとともに、この組立て作業と前
後して中間主柱の両側梁下面に扛重装置(D’)の昇降
ビーム(閂)を配設する第1工程、扛重手段(A)と同
調して、扛重手段(D’)により最上階層を一層階分高
さに満たない高さ分だけ扛上したのち、基礎杭または地
層階の中間主柱上に短尺の仮受け柱を乗載するととも
に、最上層階を若干降下させ、全荷重を仮受け柱に預
け、昇降ビーム(閂)をフリーにする第2工程、フリー
となった扛重手段(D’)の昇降ビーム(閂)と扛重手
段(A)の閂を更に降下させ、扛重手段(D’)の昇降ビ
ームと梁下面との間に梁受け台を介装する第3工程、扛
重手段(A)、(D’)により建築構造体を扛上し、フ
リーとなった仮受け柱を退避させるとともに、建築構造
体を第1工程時点より1層階分より若干高く扛上したの
ち、1層階分の高さをもつ次層階の外周主柱を扛重手段
(A)における施工用ブロック上に、また次層階の中間
主柱を基礎杭または地層階の中間主柱上に搬入設置し、
扛重手段(A)、(D’)の閂、昇降ビーム(閂)を若
干降下して全荷重を各基礎杭または地層階の中間主柱に
預け、前後して次層階の梁を各主柱間に組立てる第4工
程、フリーとなった扛重手段(A)、(D’)の閂、昇
降ビーム(閂)を移動して新たに設置された次層階の梁
との干渉を避けながら最下位まで降下させたのち、昇降
ビーム(閂)を再び原位置に復帰し、次いで若干量上昇
させて各主柱両側の梁下面部に臨ませる第5工程、前記
2〜5工程を繰り返し行い、所定階層の建築構造体を構
築して2階以上の扛上ののちに、1,2階間の高さに調
整した所定長さの外周志柱および中間主柱を基礎杭上ま
たは地層階の主柱上に組立て、各主柱の上部を2階の各
主柱の下端を結合し、中間主柱の下端を基礎杭または地
層階の主柱と結合する第6工程、そののちに、扛重装置
(A)、(D’)を解体撤去し、前後して一階層の建築
作業を完了させることにより達成される。
[0008] The above object is to assemble the top floor and the top floor of a middle- and high-rise building structure on a foundation, and then lift the lower surfaces of both side beams near the outer peripheral main pillars constituting the building structure by lifting means (A).
In the construction method of a building structure, which is constructed by assembling and constructing lower floors sequentially in the work space generated by this lifting, the intermediate main pillars constituting the building structure are constructed. On the underground beams on both sides of the foundation pile to be pillared or on the beams on both sides of the main column on the stratum, two sets of lifting devices (D ') are arranged so as to sandwich the position of the intermediate main column. Before and after the loading and assembling of the outer main pillars at the height of the floor, an intermediate main pillar having a height of about 1.5 floors is loaded and mounted on the foundation pile or the main pillar of the formation floor. Assemble the beams between the main and outer main columns, attach ceiling members, small beams, etc. to assemble the rooftop and top floors of the building structure. The first step of arranging the lifting beam (bar) of the lifting device (D '), in synchronization with the lifting device (A), '), The uppermost floor is lifted by a height less than the floor height, and a temporary short support column is mounted on the foundation pile or the middle main pillar of the formation floor, and the top floor is slightly lifted. The second step of lowering, depositing the entire load on the temporary receiving column, and freeing the lifting beam (bar), the lifting beam (bar) of the lifting means (D ') and the lifting means (A) of the free lifting means (D') The bar is further lowered, and the third step in which a beam support is interposed between the lifting beam of the lifting means (D ') and the lower surface of the beam, the building structure is lifted by the lifting means (A) and (D'). After lifting and freeing the temporary pillars that have become free, the building structure was lifted slightly higher than the first floor from the time of the first process, and then the next floor with the height of one floor was lifted. Carry out and install the outer main pillar on the construction block in the lifting means (A), and the intermediate main pillar on the next floor on the foundation pile or on the intermediate main pillar on the ground floor. And
The bar of the lifting means (A), (D ') and the lifting beam (bar) are slightly lowered to deposit the entire load on each foundation pile or intermediate main pillar of the stratum, and before and after the beam of the next story The 4th process of assembling between the main pillars, the free lifting means (A), (D ') bar and lifting beam (bar) are moved to interfere with the newly installed beam on the next floor. After lowering to the lowest position while avoiding, return the elevating beam (bar) to the original position again, and then raise it slightly by a small amount to face the beam lower surface on both sides of each main column. Repeatedly, after constructing the building structure of the predetermined level and lifting on the second floor or more, the outer peripheral pillars and intermediate main pillars of the predetermined length adjusted to the height between the first and second floors on the foundation pile or Assemble on the main pillar on the basement floor, connect the upper part of each main pillar with the lower end of each main pillar on the second floor, and connect the lower end of the middle main pillar with the foundation pile or main pillar on the ground floor. 6 process, after the, 扛重 device (A), (D ') was dismantled and is achieved by completing the construction work of one level back and forth.

【0009】上記目的は、基礎上において中高層階建物
構造物の屋上階及び最上階を組立てたのち、建物構造体
を構成する外周主柱近傍の両側梁下面を扛重手段の
(A)の閂にて支持して扛上し、この扛上により生ずる
作業空間部に下層階を順次組み立てて構築するようにし
た建物構造体の建築工法において、建築構造体を構成す
る中間主柱を建柱する基礎杭両側の地中梁上または、地
層階の主柱両側の梁上に、中間主柱位置を挟むように2
個一組の扛重装置(D’)を配設せしめ、一方、1層階
分高さの外周主柱の搬入組立てと前後して基礎杭上また
は地層階の主柱に略1.5層階分の高さを有する中間主
柱を搬入乗載し、この中間主柱および外周主柱相互間の
梁の組立て、天井部材、小梁などを取付けて建築構造体
の屋上階及び最上階を組立てるとともに、この組立て作
業と前後して中間主柱の両側梁下面に扛重装置(D’)
の昇降ビーム(閂)を配設する第1工程、扛上手段
(A)と同調して扛重手段(D’)により最上階層を一
層階分高さを越す高さだけ扛上したのち、基礎杭上また
は地層階の中間主柱上に一層階分の高さをもつ次層階の
外周主柱と中間主柱を搬入設置し、扛重装置(A)、
(D’)を若干降下して全荷重を基礎杭または地層階の
中間主柱に預ける第2工程、フリーとなった扛重手段
(D’)の昇降ビーム(閂)と扛重手段(A)の閂を最
下位まで降下させたのち、中間主柱と外周主柱相互間の
梁の組立てを行い、扛重手段(D’)の昇降ビーム
(閂)を中間主柱両側の梁下面部に臨ませる第3工程、
前記2、3工程を繰り返し行い、所要階層の建築構造体
を構築して2階以上の扛上ののち、1,2階間の高さに
調整した所定長さの外周主柱および中間主柱を基礎杭上
または地層階の中間主柱上に組立て、中間主柱の上端を
2階の中間主柱の下端と結合し、中間主柱の下端を基礎
杭または地層階の主柱と結合する第4工程、そののち
に、扛重装置(A)、(D’)を解体撤去し、前後して
一階層の建築作業を完了させることによわり達成され
る。
The above object is to assemble the roof top floor and the top floor of the middle and high-rise building structure on the foundation and then to lower the lower surfaces of both side beams near the outer peripheral main pillars constituting the building structure by using the bar of lifting means (A). In the construction method of a building structure that is constructed by assembling and constructing lower floors sequentially in the work space generated by the lifting, the intermediate main pillars that constitute the building structure are built. On the underground beam on both sides of the foundation pile or on the beam on both sides of the main column on the stratum,
A set of lifting equipment (D ') will be installed. On the other hand, approximately 1.5 layers will be placed on the foundation pile or on the main pillar on the ground floor before and after the loading and assembling of the outer main pillar with a height of one floor. The intermediate main pillar having the height of the floor is loaded and loaded, and the beams between the intermediate main pillar and the outer peripheral main pillar are assembled, ceiling members, small beams, etc. are attached, and the rooftop floor and the top floor of the building structure are formed. At the time of assembling, before and after this assembling work, lifting devices (D ')
In the first step of arranging the lifting beam (bar), in synchronization with the lifting means (A), the lifting means (D ') lifts the uppermost level by a height that exceeds the floor height by one level, The outer main column and the intermediate main column of the next floor with the height of one layer are loaded and installed on the foundation pile or the intermediate main column of the formation floor, and the lifting device (A),
(D ') is slightly lowered and the entire load is deposited on a foundation pile or an intermediate main pillar on a stratum floor. The lifting beam (bar) and lifting means (A) of the lifting means (D') are free. ) After lowering the bar to the lowest position, assemble the beam between the intermediate main column and the outer main column, and raise and lower the beam (bar) of the lifting means (D ') with the lower side of the beam on both sides of the intermediate main column. The third step to face
The above-mentioned steps 2 and 3 are repeated to construct a building structure of a required level, and after lifting on two or more floors, an outer main pillar and an intermediate main pillar of a predetermined length adjusted to the height between the first and second floors. Is assembled on the foundation pile or on the middle main pillar of the formation floor, the upper end of the middle main pillar is connected with the lower end of the middle main pillar on the second floor, and the lower end of the middle main pillar is connected with the foundation pile or the main pillar of the formation floor. The fourth step is achieved by dismantling and removing the lifting devices (A) and (D ') after that, and completing one-story building work before and after.

【0010】[0010]

【発明の実施の形態】 次に、図面について本発明の建
築工法の詳細を説明する。
Next, details of the construction method of the present invention will be described with reference to the drawings.

【0011】先ず、特開平9−88185号公報に開示
され、本発明の建築工法に併用するとともに、一層階分
より若干高く建物躯体を一挙に扛上する機能をもつ扛重
装置Aの構成を、図2、図10〜図14について説明す
る。
First, the construction of a lifting device A disclosed in Japanese Patent Application Laid-Open No. 9-88185 and having a function of lifting the building frame at a time slightly higher than the floor, which is used together with the construction method of the present invention, is described. 2 and FIGS. 10 to 14 will be described.

【0012】1は、建物構造体Bの外周に配設建柱され
る外周主柱2の外側左右に配設される1層階分の高さよ
り背高とした架台であって、該架台1は外周主柱2およ
び梁または梁仕口3と干渉しないよう配置されている。
前記架台1には、外周主柱2側鉛直面に沿うように上下
動する昇降梁5が介設されており、この昇降梁5には前
記架台1に対して脱抜可能に垂設装架したスクリューロ
ッド6を貫通するとともに、このスクリューロッド6は
昇降梁5の左右下部に固定したナット部材7に脱抜可能
に挿入螺合されている。又、前記スクリューロッド6の
上端にはスプロケット8と、両架台1の外側上方に夫々
配設した駆動モータ9の軸に設けたスプロケットとがチ
ェンによって接続されており、駆動モータ9の駆動によ
り回転するスクリューロッド6と、前記昇降梁5に固定
したナット部材7の相関関係により、昇降梁5が架台1
の外側1Aを案内として上下動するように構成されてい
る。図中13はベアリングである。
Reference numeral 1 denotes a gantry having a height higher than the height of a single story provided on the left and right sides of an outer main column 2 provided on the outer periphery of the building structure B. Are arranged so as not to interfere with the outer main column 2 and the beam or beam connection 3.
The gantry 1 is provided with an elevating beam 5 that moves up and down along the vertical plane on the outer peripheral main column 2 side, and the elevating beam 5 is vertically mounted detachably with respect to the gantry 1. The screw rod 6 penetrates the screw rod 6, and the screw rod 6 is detachably inserted and screwed into a nut member 7 fixed to the lower left and right portions of the lifting beam 5. A sprocket 8 is connected to the upper end of the screw rod 6 and a sprocket provided on a shaft of a drive motor 9 disposed outside and above the gantry 1 by a chain. The sprocket 8 is rotated by the drive of the drive motor 9. Due to the correlation between the screw rod 6 and the nut member 7 fixed to the elevating beam 5, the elevating beam 5
It is configured to move up and down with the outer side 1A as a guide. In the figure, reference numeral 13 denotes a bearing.

【0013】次に前記昇降梁5の構成について説明す
る。昇降梁5の上面左右側、詳しくは、昇降梁5に挿貫
した前記両スクリューロッド6の夫々内側部位に、昇降
梁5の左右軸線方向と直行する前後軸線方向にそって進
退移動可能で、かつ、閂構造からなる2個の荷重受け梁
14を平行に乗載せしめる。この両荷重受け梁14は昇
降梁5の上面に立設された2枚一組の案内板15間にス
ライド自在に挿嵌することとともに、夫々の荷重受け梁
14の先端上部に、梁の歪調整用の円筒座16を上面に
もつ調整ブロック17を設ける。なお、調整ブロック1
7は場合により省略できる。18は、前記昇降梁5の後
部に設けた正面形状が門構形をした前記荷重受け梁14
の反力を支受する連絡梁で、昇降梁5の上面と連結梁1
8の下面間に荷重受け梁14をスライド可能に挟持し、
荷重受け梁14の先端に掛かる荷重の反力を連結梁18
で支承するようにしたものである。図中19は連結梁1
8補助梁18の補強用の支持梁である。
Next, the structure of the lifting beam 5 will be described. The upper and lower sides of the elevating beam 5, specifically, the inside portions of the two screw rods 6 inserted into the elevating beam 5, can move forward and backward along the front-rear axis direction perpendicular to the left-right axis direction of the elevating beam 5, At the same time, two load receiving beams 14 having a bar structure are mounted in parallel. The load receiving beams 14 are slidably inserted between a pair of guide plates 15 erected on the upper surface of the elevating beam 5, and a distortion of the beam is placed on the upper end of each load receiving beam 14. An adjustment block 17 having a cylindrical seat 16 for adjustment on the upper surface is provided. Adjustment block 1
7 can be omitted in some cases. Reference numeral 18 denotes the load receiving beam 14 provided at the rear of the lifting beam 5 and having a frontal gate shape.
A connecting beam that receives the reaction force of
8, the load receiving beam 14 is slidably held between the lower surfaces,
The reaction force of the load applied to the tip of the load receiving beam 14 is
It is intended to be supported by. 19 in the figure is connecting beam 1
8 is a support beam for reinforcing the auxiliary beam 18.

【0014】前記昇降梁5の両側端面に比較的広巾の凹
所20を形成するとともに、この凹所20に嵌合介入す
る凸部ガイド(図示略)を前記架台1の外側壁の内面上
下方向に形成したものである。そして、凸部ガイドの前
後面又は前記凹所20を構成する前部壁面及び前記連結
梁18の前面上部に、両者の摺動を円滑にするためのテ
フロン樹脂板などの摺動部材22を張設せしめる。尚、
このテフロン樹脂板に代え、凹所20又は凸部ガイドの
何れかの前後面にローラ(図示略)を設けるものであ
る。そして、図2、図11から明らかなように、前記2
本の荷重受け梁14が外周主柱2を挟むようにして架台
1が配置され、該外周主柱2間に取り合う両側の梁の基
部、詳しくは、外周主柱2に設けた梁または梁仕口3の
下面を両荷重受け梁14によって支持し、建築作業が略
完了した建物躯体Cを一層階分余扛上するようにしたも
のである。図中3cは、コーナー部主柱2に梁仕口3が
片側にしかないため、この梁仕口3と対称位置に設ける
仮仕口である。扛重装置Aは上述のように構成されてい
る。
A relatively wide recess 20 is formed in both end surfaces of the lifting beam 5 and a convex guide (not shown) which fits into the recess 20 is provided in the vertical direction of the inner surface of the outer wall of the gantry 1. It is formed in. Then, a sliding member 22 such as a Teflon resin plate for facilitating sliding between the two is provided on the front and rear surfaces of the convex guide or on the front wall surface forming the recess 20 and the upper front surface of the connecting beam 18. I will set it up. still,
Instead of the Teflon resin plate, rollers (not shown) are provided on the front and rear surfaces of either the concave portion 20 or the convex portion guide. Then, as is apparent from FIGS.
The gantry 1 is arranged so that the load receiving beams 14 sandwich the outer peripheral main column 2, and the bases of the beams on both sides that are interposed between the outer peripheral main columns 2, more specifically, the beam or beam connection 3 provided on the outer main column 2. Is supported by both load receiving beams 14, so that the building skeleton C, for which the construction work has been substantially completed, is further lifted by a floor. In the figure, reference numeral 3c denotes a temporary connection provided at a position symmetrical to the beam connection 3 because the beam connection 3 is only on one side of the corner main pillar 2. The lifting device A is configured as described above.

【0015】次に、前述した扛重装置Aを使用する建物
構造体Bの建築工法を図14について説明する。図14
aに示すように、施工レベルを調整した施工用ブロック
23の外方に扛重装置Aを配設し、前記扛重装置Aを構
成する平行2条の荷重受け梁14の中間に施工用ブロッ
ク23を位置させる。該施工用ブロック23は建物構造
体Bの基礎上に設け、建物本来の主柱1の一部を転用し
てもよい。該施工用ブロック23上に最上階の外周主柱
2を立設し、この外周主柱2に最上階の屋上構成用の柱
間梁53、梁仕口3を取り付けるとともに、最上階床面
構成用の柱間梁53を夫々とりつけ、最上階の建物躯体
Cの建築作業を完成させる。(図2参照)
Next, a construction method of a building structure B using the above-described lifting device A will be described with reference to FIG. FIG.
As shown in a, the lifting device A is disposed outside the construction block 23 whose construction level has been adjusted, and the construction block is provided between the two parallel load receiving beams 14 constituting the lifting device A. Position 23. The construction block 23 may be provided on the foundation of the building structure B, and a part of the main pillar 1 of the building may be diverted. The outermost main pillar 2 of the top floor is erected on the construction block 23, and the inter-column beam 53 and the beam connection 3 for the rooftop construction of the top floor are attached to the outermost main pillar 2, and the top floor floor structure Attach the beam 53 between the columns to complete the construction work of the building skeleton C on the top floor. (See Fig. 2)

【0016】最上階の建物躯体Cが完成したら図14b
に示すように、両荷重受け梁14を前進させ、これの先
端に設けた調整ブロック17を梁仕口3,仮仕口3cの
下側に夫々臨ませたのち、前記駆動モータ9の駆動にス
クリューロッド6を回転させ、ナット部材を介して昇降
梁5を梁仕口3,仮仕口3cの下面に当接せしめ、図1
4cに示すように全ての外周主柱2を若干扛重して全荷
重受け梁14への載荷を確認するようにして、全ての扛
重装置Aの零点調整制御を行う。(図11参照)
When the building structure C on the top floor is completed, FIG.
As shown in (2), the load receiving beams 14 are advanced, and the adjustment blocks 17 provided at the ends thereof are made to face under the beam ports 3 and the temporary ports 3c, respectively. By rotating the screw rod 6, the lifting beam 5 is brought into contact with the lower surface of the beam connection 3 and the temporary connection 3c via the nut member, and FIG.
As shown in FIG. 4c, zero lifting adjustment of all the lifting devices A is performed by slightly lifting all the outer main pillars 2 and confirming the load on all the load receiving beams 14. (See Fig. 11)

【0017】このように扛重装置Aの零点調整制御が完
了したら、図14dのように、例えば約20mm/min
の上昇スピードで約3時間で最上階建物躯体Cを一層階
分余扛重し、最上階の建物躯体Cの下方に次層階の作業
空間24を形成する。
When the zero-point adjustment control of the lifting device A is completed as described above, for example, as shown in FIG.
In about 3 hours at the rising speed, the top-floor building frame C is lifted by one more floor, and a work space 24 of the next floor is formed below the top-layer building frame C.

【0018】次いで、図14eに示すように、作業空間
24を利用して前記全てのブロック23上に一層階分の
長さを有する外周主柱2を搬入して最上階外周主柱2の
下部に取付け、最上階の建物躯体Cの扛重姿勢を保持し
たまま、この立設された外周主柱2に次層階床面構成用
の梁仕口3を取り付け、最上階建物期待Cを構成する外
周主柱2の下端と、次層階構成用の外周主柱2の上端と
を溶接又はガセットを用いた結合手段にて連結連合して
次層階の建築作業を管理用させて、次層階建物躯体Cを
構成したのち、図14fに示すように、駆動モータ9を
逆転させてスクリューボルト6の作用で昇降梁5を若干
下降させて、建物躯体Cの全荷重を施工用ブロック23
に載せ替え、次いで荷重受け梁14による最上階建物躯
体C、梁仕口3,仮仕口3c下面の支持を解除する。そ
して、図14g〜図14iに示すように、前記荷重受け
梁14を梁仕口3,仮仕口3cと無関係な後方に退避さ
せることにより、昇降梁5を次層階の梁仕口3に干渉し
ない状態で最下位まで下降させた上で、荷重受け梁14
を前進させて調整ブロック17を次層階建物躯体Cを構
成する梁仕口3,仮仕口3cの下方に臨ませる。
Next, as shown in FIG. 14e, the outer peripheral main pillar 2 having a length corresponding to one floor is loaded onto all the blocks 23 using the work space 24, and the lower part of the outermost main pillar 2 on the uppermost floor is provided. , While maintaining the lifting posture of the building frame C on the top floor, a beam connection 3 for the floor of the next floor is attached to the standing outer pillar 2 to form the expected building C on the top floor. The lower end of the outer main column 2 to be connected to the upper end of the outer main column 2 for the next floor is welded or connected by connecting means using gussets to manage the construction work of the next floor, and After constructing the multi-story building frame C, as shown in FIG. 14f, the drive motor 9 is reversed and the lifting beam 5 is slightly lowered by the action of the screw bolt 6, so that the entire load of the building frame C is applied to the construction block 23.
Then, the support of the uppermost building frame C, the beam connection 3, and the temporary connection 3c under the load receiving beam 14 is released. Then, as shown in FIGS. 14g to 14i, the load receiving beam 14 is retracted to the rear irrespective of the beam connection 3 and the temporary connection 3c, so that the lifting beam 5 is moved to the beam connection 3 on the next floor. After lowering to the lowest position without interference, the load receiving beam 14
To make the adjustment block 17 face below the beam connection 3 and the temporary connection 3c constituting the next-story building frame C.

【0019】次に図14jのように、前記と同様な手段
で昇降梁5を上昇させて調整ブロック17を梁仕口3,
仮仕口3cの下面に当接せしめ、次層階を含む最上階の
建物躯体Cを若干上昇させ、円筒座16で梁仕口3をも
つ梁の歪調整と全ての扛重装置Aの零点調整制御を行っ
たのち、図14kで示すように、建物躯体Cを一層階分
余扛上し、これの下方に次々層階の作業空間を構成し、
以下所要階層n−2層〜2階まで上層から下層に向かっ
て図14e、図14kの工法を繰り返し行う。
Next, as shown in FIG. 14j, the lifting beam 5 is raised by means similar to the above, and the adjustment block 17 is moved to the beam connection 3,
Abut the lower surface of the temporary connection 3c, slightly raise the building frame C on the top floor including the next floor, adjust the distortion of the beam having the beam connection 3 with the cylindrical seat 16, and set the zero point of all lifting devices A. After performing the adjustment control, as shown in FIG. 14k, the building skeleton C is lifted up by one floor, and a work space of the next floor is formed below this, and
14e and 14k are repeatedly performed from the upper layer to the lower layer from the (n-2) th layer to the second floor.

【0020】図14lに示すように、2階までの建物躯
体Cが完了したら、施工用ブロック23を撤去するか、
あるいは、施工用ブロック23を本来の1階外周主柱2
の一部として埋め殺し、1階高さを補足する短柱25を
2階外周主柱2の下部に結合するか、あるいは1階の構
築に必要な高さまで扛重し、2階建物躯体を構成する外
周主柱2との間に1階の外周主柱2を乗載結合したの
ち、2階を含む建物躯体Cを図14mに示すように下降
させ、2階構成用の外周主柱2の下端と短柱25の上端
とを結合してから荷重受け梁14を下降し、2階構成用
の外周主柱2の梁仕口3B、仮仕口3cに対する下面支
持を解除したのち、全ての扛重装置Aを外側方に退去さ
せ、1階の建築作業を完了させ、所要階層の建物構造体
Bを得る。
As shown in FIG. 14L, when the building skeleton C up to the second floor is completed, the construction block 23 is removed or
Alternatively, the construction block 23 may be replaced with the main pillar 2 on the first floor.
Buried as a part of the building, and the short columns 25 that supplement the height of the first floor are connected to the lower part of the main pillar 2 on the second floor, or they are lifted to the height required for the construction of the first floor, and After the first-floor outer main pillar 2 is mounted on and coupled to the outer main pillar 2 to be configured, the building skeleton C including the second floor is lowered as shown in FIG. After the lower end of the lower column and the upper end of the short column 25 are joined, the load receiving beam 14 is lowered, and the lower surface support for the beam connection 3B and the temporary connection 3c of the outer main column 2 for the second floor is released. The lifting apparatus A of the first floor is retreated to the outside to complete the construction work on the first floor, and the building structure B of the required level is obtained.

【0021】次に、図2〜図6について、建物内部の主
柱である中間主柱32に関し、本発明の建築工法を実施
するための扛重装置D’に係る実施の形態を説明する。
Next, referring to FIGS. 2 to 6, an embodiment of a lifting device D 'for carrying out the construction method of the present invention will be described with respect to an intermediate main column 32 which is a main column inside a building.

【0022】31は、建物構造体Bの外周に配設建柱せ
しめられる前記外周主柱2を除いた内部の所要部位に、
建柱される一層階分の高さをもつ中間仕口32の梁仕口
32aに取り合うべく基礎、例えば、地中の杭、あるい
は、地層階の中間主柱33に設けた地中梁33a上にセ
ットされたライナー33b上に配設される架台である。
この架台31は、中間主柱32を挟むように、これの両
側に近接して配設される2個一組で、而も上下方向に複
数に分割可能な架台構成体31a、31bからなる。
Reference numeral 31 denotes a necessary portion inside the building structure B excluding the outer main pillar 2 which is provided on the outer periphery of the building structure B.
On a foundation, for example, an underground pile or an underground beam 33a provided on an intermediate main pillar 33 on a stratum, to fit a beam connection 32a of an intermediate connection 32 having a height of one layer to be built. This is a pedestal provided on the liner 33b set in the frame.
The gantry 31 is a pair of gantry components 31a and 31b that can be divided into a plurality of pieces in the vertical direction.

【0023】図2、図3から明らかなように、各架台構
成体31a、31bの両側下部は、分解可能な継ぎ部材3
4によって結合されるとともに、両架台構成体31a、
31bの両側下部には、スプロケット35をもつ回転伝
達体36が夫々設けられており、この回転伝達体36の
上部に架台31よりやや背低のスクリュー軸37がキー
構造を介して回動可能に、かつ、嵌脱自在に垂設されて
いる。又、両架台構成体31a、31bの両外側部には駆
動モータ38を夫々設け、この駆動モータ38の駆動軸
に設けたスプロケット39と、前記スプロケット35と
がチェン又は別途トルク伝達系40によって連結されて
おり、各駆動も38の正逆、逆転駆動が回転伝達体36
を介して各別にスクリュー軸37に伝達される。
As is apparent from FIGS. 2 and 3, the lower portions on both sides of each of the gantry members 31a and 31b are provided with disassemblable joint members 3.
4, and both gantry structures 31a,
Rotation transmission bodies 36 each having a sprocket 35 are provided at the lower portion on both sides of 31b, and a screw shaft 37 slightly shorter than the gantry 31 is rotatable above the rotation transmission body 36 via a key structure. And it is vertically installed so that it can be freely inserted and removed. Driving motors 38 are provided on both outer sides of both gantry structures 31a and 31b, respectively. A sprocket 39 provided on a driving shaft of the driving motor 38 and the sprocket 35 are connected by a chain or a separate torque transmission system 40. Each drive is also performed by the forward / reverse and reverse rotation drive of the rotation transmission body 36.
And transmitted to the screw shaft 37 separately.

【0024】スクリュー軸37は、閂構造とした昇降ブ
ロック41に固定したナット部材42に対して脱抜可能
に夫々挿入螺合されている。一方、各昇降ブロック41
の両側には対称的に案内凸部41aを設け、この案内凸
部41aは架台31の両側縦方向に形成した案内凹溝3
1cに嵌合してあり、ナット部材42、詳しくは、スク
リュー軸37の回動作用が昇降ブロック41の昇降作用
に変換せさめられ、全ての昇降ブロック41が均等に而
も同期昇降しうるように構成されている。又、案内凹溝
31cの内面または、案内凸部41aの周面に、テフロン
樹脂板などの摺動部材43を設け、両者の摺動を円滑に
する。又、この摺動部材43に代え、何れかにローラ
(図示略)を転動可能に付設してもよい。また、図示は
してないがスクリュー軸37を架台31a、31bに対
して回転しないよう固定し、ナット部材42を回転させ
るように構成してもよい。
The screw shaft 37 is detachably inserted and screwed into a nut member 42 fixed to a lifting block 41 having a bar structure. On the other hand, each lifting block 41
Are provided symmetrically on both sides of the base 31. The guide protrusions 41a are formed in the guide grooves 3 formed in the longitudinal direction on both sides of the gantry 31.
1c, the rotation of the nut member 42, more specifically, the screw shaft 37 is converted into the lifting and lowering of the lifting block 41, so that all the lifting blocks 41 can be raised and lowered equally and synchronously. Is configured. Further, a sliding member 43 such as a Teflon resin plate is provided on the inner surface of the guide groove 31c or on the peripheral surface of the guide convex portion 41a to make the sliding of both members smooth. Instead of the sliding member 43, a roller (not shown) may be rotatably attached to any of the members. Further, although not shown, the screw shaft 37 may be fixed to the frames 31a and 31b so as not to rotate, and the nut member 42 may be rotated.

【0025】一方の架台構成体31aの両昇降ブロック
41が他方の架台構成体31bに対面する側に、昇降ビ
ーム44のいったんを旋回可能に夫々軸支するととも
に、昇降ビーム44の遊動他端に連結用の孔44aを垂
設する。又、他方の架台構成体31bに設けた両昇降ブ
ロック41が、一方の架台構成体31aに対面するする
側に、前記連結用の孔44aに適用する孔44bを設け、
両孔44a、44bが適合したときに、この両孔44a、
44bに上方よりノックピン45を共通的に挿入し、両
昇降ブロック41間に昇降ビーム44が橋架的に連結固
定される。両昇降ブロック41間に橋架された昇降ビー
ム44は、図から明らかなように、中間主柱32の側面
に固装されている梁仕口32aの下面に対応するように
構成してある。又、両架台構成体31a、31bのスクリ
ュー軸37及びこれの三方を囲うようにした案内凹溝3
1cを設けた架台部分を除いた基部は、比較的平面部分
が広く構成されているので、この平面部分を口述する盛
り替え用の仮受け柱32bの退避場所として利用しう
る。
The two lifting / lowering blocks 41 of one of the pedestal structures 31a support the vertically movable beam 44 on the side facing the other pedestal structure 31b. A connecting hole 44a is vertically provided. Further, the two lifting blocks 41 provided on the other gantry structure 31b are provided with holes 44b to be applied to the connection holes 44a on the side facing one gantry structure 31a,
When the two holes 44a, 44b are fitted, the two holes 44a, 44b,
A knock pin 45 is commonly inserted from above into 44b, and the lifting beam 44 is fixedly connected between the lifting blocks 41 in a bridge manner. The lifting beam 44 bridged between the lifting blocks 41 is configured to correspond to the lower surface of the beam connection 32a fixed to the side surface of the intermediate main column 32, as is apparent from the drawing. Further, the screw shaft 37 of each of the gantry constituting bodies 31a and 31b and the guide groove 3 surrounding the three sides thereof are provided.
Since the base portion excluding the pedestal portion provided with 1c has a relatively wide flat portion, the flat portion can be used as a retreat place for the temporary receiving pillars 32b for dictation.

【0026】図から明らかなように、昇降ビーム44に
はこれの軸線にそってスライド移動可能なスライド筒4
6が被嵌されており、該スライド筒46上には梁仕口3
2aの下部に臨み、かつ、中間主柱32の盛り替え用と
して用いる梁受け台47が付設してある。扛重装置D’
は、上述のように構成されている。
As is apparent from the figure, the lifting cylinder 44 has a sliding cylinder 4 slidable along its axis.
6 are fitted, and the beam connection 3 is placed on the slide cylinder 46.
A beam support 47 which faces the lower portion of 2a and is used for refilling the intermediate main pillar 32 is additionally provided. Lifting device D '
Is configured as described above.

【0027】図7は、前述した実施の形態の昇降ビーム
44の遊動端部の内側面に、係合ロック凹部48を形成
したものを示し、この係合ロック凹部48が、他方の昇
降ブロック41に形成した係合ロック凸部49に係合離
脱しうるように構成する。その他の構成は実施の形態で
説明したものと同様であることから、同一構成部分には
同一符号を付すことにより詳細な説明は省略する。
FIG. 7 shows an embodiment in which an engaging lock recess 48 is formed on the inner surface of the floating end of the lifting beam 44 of the above-described embodiment. Is configured to be able to be disengaged from and engaged with the engagement lock convex portion 49 formed in the above. Since other configurations are the same as those described in the embodiment, the same components are denoted by the same reference numerals, and detailed description is omitted.

【0028】図8は、前述した実施の形態の梁受け台4
7の別形態を示している。この形態は、中間主柱32の
梁仕口32aの下部から外れた位置の使用校ビーム44
の上面に、梁受け台50を反転可能、詳しくは、この梁
受け台50の梁仕口32a側の下端角隅部を昇降ビーム
44に軸支せしめ、この状態の梁受け台50を反転させ
ることにより梁仕口32aの直下部に梁受け台50が隣
設されるようにしたものである。
FIG. 8 shows the beam support 4 of the above-described embodiment.
7 shows another embodiment. In this embodiment, the used school beam 44 is located at a position off the lower part of the beam connection 32a of the intermediate main column 32.
The beam receiver 50 can be turned over on the upper surface of the beam receiver. More specifically, the lower corner of the beam receiver 32 on the side of the beam connection 32a is pivotally supported by the elevating beam 44, and the beam receiver 50 in this state is turned over. Thus, the beam receiving base 50 is provided immediately below the beam connection 32a.

【0029】図9は、前述した実施の形態の梁受け台4
7の更に別形態を示している。この形態は、中間主柱3
2の梁仕口32aの下方に対応する昇降ビーム44の側
面に、この昇降ビーム44の上面と同一平面となる梁受
け台51の上端角隅部を軸支せしめ、この状態の梁受け
台51を反転して昇降ビーム44の上面に乗載支持して
梁仕口32aの直下32aの直下に梁受け台51を臨ま
せ、中間主柱32の盛り替えとして使用しうるように構
成したものである。
FIG. 9 shows a beam support 4 of the above-described embodiment.
7 shows still another embodiment. This form is an intermediate main pillar 3
The upper end corner of a beam receiving base 51 coplanar with the upper surface of the lifting / lowering beam 44 is axially supported on the side surface of the lifting / lowering beam 44 below the second beam connection 32a. And the beam supporting base 51 is mounted on the upper surface of the elevating beam 44 and supported so as to face the beam receiving base 51 directly below the beam connection 32a, so that the intermediate main column 32 can be used as a rearrangement. is there.

【0030】昇降ビーム(44)に対する梁受け台の装着
手段としては特に図示してないが、前述した実施の形態
以外多々想定しうることから、図示のものに特定される
ことはない。
Although the means for mounting the beam support to the lifting beam (44) is not specifically shown, it is not limited to the one shown in the drawings since it can be supposed in many ways other than the embodiment described above.

【0031】次に、前述した扛重装置D’を使用する建
物構造体Bの建築工法を、図1a〜eについて説明す
る。尚、この建築工法については、前述した扛重装置A
を扛重装置D’と同調した挙動で使用することは勿論で
ある。
Next, a construction method of a building structure B using the above-described lifting device D 'will be described with reference to FIGS. In this construction method, the lifting device A described above is used.
Of course is used in synchronism with the lifting device D '.

【0032】図1aは、扛重装置D’、詳しくは、架台
31を構成する架台構成体31a、31bを全ての中間主
柱32の両側に設置し、両架台構成体31a、31b間に
橋架した昇降ビーム44を中間主柱32の両側に設けた
梁仕口32aの下部に臨ませた姿勢を示している。この
図1aは昇降開始準備完了後の姿勢を示しており、主柱
2の梁仕口32aと、これに対応する中間主柱32の梁
仕口32a間には柱間梁53が接続されている。
FIG. 1a shows a lifting device D ', more specifically, gantry structures 31a and 31b constituting a gantry 31 are installed on both sides of all intermediate main columns 32, and a bridge is provided between the gantry structures 31a and 31b. This shows a posture in which the lift beam 44 facing the lower part of the beam connection 32a provided on both sides of the intermediate main column 32 is shown. FIG. 1a shows the posture after completion of the preparation for starting the elevating operation. An inter-column beam 53 is connected between the beam connection 32a of the main column 2 and the corresponding beam connection 32a of the intermediate main column 32. I have.

【0033】図1aの状態において、全てのスクリュー
軸37を同期駆動して昇降ビーム44を上昇させ、梁仕
口32aを介して中間主柱32を定められたストロー
ク、詳しくは、仮受け柱32bの高さより若干高い位置
まで上昇させる。次いで、架台31の基部上に待機させ
ていた仮受け柱32bを地中の中間主柱(33)上に搬
送乗載したのち、スクリュー軸37を逆回転させて昇降
ビーム44を下降せしめて中間主柱32の下端を仮受け
柱46上に乗せ全ての荷重を預ける。(図1b参照)
In the state shown in FIG. 1A, all the screw shafts 37 are driven synchronously to raise and lower the elevating beam 44, and the intermediate main column 32 is set to a predetermined stroke through the beam connection 32a. To a position slightly higher than the height of Next, the temporary receiving column 32b, which has been waiting on the base of the gantry 31, is transported and mounted on the underground intermediate main column (33), and then the screw shaft 37 is rotated in the reverse direction to lower the elevating beam 44 so that the intermediate beam is lowered. The lower end of the main column 32 is placed on the temporary receiving column 46 and all loads are deposited. (See Fig. 1b)

【0034】この状態で、更に昇降ビーム44を下降さ
せ、これに設けた梁受け台47の上面が梁仕口32aの
下面より若干下方となるように下降させた時点で、梁受
け台47を昇降ビーム44に沿って横移動(紙面右方
向)して梁受け台47を梁仕口32aの下方にセットす
る。(図1c参照)
In this state, the elevating beam 44 is further lowered, and when the upper surface of the beam support 47 provided on the lower beam is lowered slightly below the lower surface of the beam connection 32a, the beam support 47 is lowered. The beam receiver 47 is moved laterally (rightward on the paper) along the elevating beam 44 to set the beam receiver 47 below the beam connection 32a. (See Fig. 1c)

【0035】次いで、スクリュー軸37を駆動して中間
主柱32を大きく、詳しくは、一層階より若干高く上昇
させ、この中間主柱32の下面と中間主柱(33)の上面
との開きが、一層階分高さの中間主柱32の高さより若
干高く扛上した時点で昇降ビーム44の上昇を止め、上
層階の中間主柱32の下部空間に新たな中間主柱32を
搬入介装する。(図1d参照)
Next, the screw shaft 37 is driven to make the intermediate main column 32 larger, specifically, slightly higher than the floor, so that the lower surface of the intermediate main column 32 and the upper surface of the intermediate main column (33) are opened. The lift beam 44 is stopped when the vehicle is lifted slightly higher than the height of the intermediate main pillar 32 at the height of one floor, and a new intermediate main pillar 32 is inserted into the lower space of the intermediate main pillar 32 on the upper floor. I do. (See Fig. 1d)

【0036】この状態て昇降ビーム44を下降させ、そ
の下降途中で上層階の中間主柱32の下端を、新たに搬
入された中間主柱32の上端に乗載支持せしめるととも
に、荷重を預け、更に下降する昇降ビーム44により梁
仕口32a から解放された状態にある昇降ビーム44の
遊動端と、昇降ブロック41を連結しているノックピン
45を外し、フリーとなった昇降ビーム44を外方向に
約90°旋回させる。旋回された昇降ビーム44は、新
たに搬入された中間主柱32の梁仕口32aの領域から
外側方にあるため、昇降ビーム44は最下位の上昇移動
開始準備位置まで降下する。(図1e参照)
In this state, the elevating beam 44 is lowered, and the lower end of the intermediate main column 32 of the upper floor is supported on the upper end of the newly introduced intermediate main column 32 during the descent, and the load is deposited. Further, the floating end of the lifting beam 44 released from the beam connection 32a by the lowering lifting beam 44 and the knock pin 45 connecting the lifting block 41 are removed, and the free lifting beam 44 is moved outward. Turn about 90 °. Since the swiveled elevating beam 44 is located outside the region of the beam connection 32a of the newly-loaded intermediate main column 32, the elevating beam 44 descends to the lowest elevating movement start preparation position. (See Fig. 1e)

【0037】そして昇降ビーム44を逆方向に約90°
旋回してに戻し、これの遊動端をノックピン45で昇降
ブロック41に結合す。(図1a参照)
Then, the elevating beam 44 is turned by about 90 ° in the reverse direction.
It is turned back and its free end is connected to the lifting block 41 with the knock pin 45. (See Fig. 1a)

【0038】図1a〜図1eの作業を扛重装置D’と、
これの挙動に同期する扛重装置Aを用いて繰り返し行う
ことにより、所望階層の建物を構築することができる。
そして全ての扛重装置A、D’を外側方に分解し撤去し
たのち、1階の建築作業を完了させて所要階層の建物構
造体Bが完了する。
The operation shown in FIGS. 1A to 1E is referred to as a lifting device D ′.
By repeatedly using the lifting device A synchronized with this behavior, a building of a desired level can be constructed.
Then, after all the lifting devices A and D 'are disassembled outward and removed, the construction work on the first floor is completed to complete the building structure B on the required level.

【0039】[0039]

【発明の効果】 上述のように本発明の構成によれば、
次のような効果が得られ。
According to the configuration of the present invention as described above,
The following effects are obtained.

【0040】全天候下での作業がなし得られ、天候に左
右されずに工期の大巾 短縮が図れ、高所作業がないた
め安全な施工ができ、資材の落下、飛散などによる不安
がなく、最上階から所要階層に至る角隅層の建物躯体を
順次完了させる工法であるため、作業は全て地上階での
施工となり安定した品質の建物が得られ、更に、略完成
された建物躯体の扛重作用点が、全ての外周、中間主柱
近傍の両側梁下面支持によって行われるため、階層が進
むにつれて増加される荷重に充分耐えることができると
ともに、各階層の建物躯体の完了毎に支持梁の歪取り調
整と全ての扛重装置の零点調整制御が行われるため、す
でに完成された建物躯体の扛重による損傷のない中高層
建物の構築が効率よく行えることは勿論のこと。
Work can be performed under all weather conditions, the construction period can be shortened without being affected by the weather, and safe work can be performed because there is no work at high places. Since this is a construction method that sequentially completes the corner framing from the top floor to the required floor, all work is done on the ground floor and a stable quality building is obtained.Furthermore, the almost completed building framing is lifted. Since the point of heavy action is provided by the support on both sides of the beam near the outer periphery and the middle main column, it is possible to withstand the load that increases as the story progresses, and to support the beam every time the building frame of each story is completed. Of course, it is possible to efficiently construct a mid-to-high-rise building without damage due to the lifting of the already completed building frame because the straightening adjustment and the zero point control of all lifting devices are performed.

【0041】扛重装置Aと扛重装置D’を同調させて扛
上することにより、夫々の扛重装置が分担する扛重荷重
が軽減され、扛重装置の小型化が図れるとともに、扛重
装置D’が盛り替え工法可能であることから、扛重装置
D’の高さを建築される1階層分より背低に構成でき
る。
By lifting the lifting device A and the lifting device D 'in synchronism, the lifting load shared by each lifting device is reduced, and the lifting device can be downsized. Since the device D 'can be refilled, the height of the lifting device D' can be configured to be shorter than the height of one level to be built.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 扛重装置D’による本発明工法を示す流れ図
である。
FIG. 1 is a flowchart showing a construction method of the present invention using a lifting device D ′.

【図2】 扛重装置A、D’の配置と主柱、梁の取合関
係を示す平面図である。
FIG. 2 is a plan view showing the arrangement of the lifting devices A and D ′ and the relationship between the main columns and beams.

【図3】 扛重装置D’の平面図である。FIG. 3 is a plan view of a lifting device D ′.

【図4】 図1の一部切欠正面図である。FIG. 4 is a partially cutaway front view of FIG. 1;

【図5】 図1の正面図である。FIG. 5 is a front view of FIG. 1;

【図6】 図1の側面図である。FIG. 6 is a side view of FIG. 1;

【図7】 昇降ビームの別形態を示す扛重装置D’の平
面図である。
FIG. 7 is a plan view of a lifting device D ′ showing another form of the lifting beam.

【図8】 梁受け台の別形態を示す要部の正面図であ
る。
FIG. 8 is a front view of a main part showing another form of the beam support.

【図9】 梁受け台の更に別形態を示す要部の側面図で
ある。
FIG. 9 is a side view of a main part showing still another form of the beam support.

【図10】 扛重装置Aによる建物躯体の構築状態を示
す建物構造体の斜視図である。
FIG. 10 is a perspective view of a building structure showing a building state of the building frame by the lifting device A.

【図11】 扛重装置Aと主柱、梁の取合関係を示す斜
視図である。
FIG. 11 is a perspective view showing an assembling relationship between the lifting device A, the main pillar, and the beam.

【図12】 扛重装置Aの斜視図である。FIG. 12 is a perspective view of a lifting device A.

【図13】 扛重装置Aの内部構造を示す斜視図であ
る。
FIG. 13 is a perspective view showing the internal structure of the lifting device A.

【図14】 扛重装置Aによる建築工法を示す流れ図で
ある。
FIG. 14 is a flowchart showing a construction method using the lifting device A.

【符号の説明】[Explanation of symbols]

A 扛重装置 D’ 扛重装置 31 基礎 31a 架台構成体 31c 案内凹溝 32 中間主柱 32a 梁仕口 32b 仮受け柱 33 地中中間主柱 33b ライナー 34 継ぎ部材 35 スプロケット 36 回転伝達体 37 スクリュー軸 38 駆動モータ 39 スプロケット 40 チェン 41 昇降ブロック 41a 案内凸部 42 ナット部材 43 摺動部材 44 昇降ビーム 44a 孔 44b 孔 45 ノックピン 46 カラー 47 梁受け台 48 係合ロック凹部 49 係合ロック凸部 50 梁受け台 51 梁受け台 53 柱間梁 A Lifting device D 'Lifting device 31 Foundation 31a Frame structure 31c Guide groove 32 Intermediate main column 32a Beam connection 32b Temporary receiving column 33 Underground intermediate main column 33b Liner 34 Splicing member 35 Sprocket 36 Rotating transmission body 37 Screw Shaft 38 Drive motor 39 Sprocket 40 Chain 41 Elevating block 41a Guide convex part 42 Nut member 43 Sliding member 44 Elevating beam 44a Hole 44b Hole 45 Dowel pin 46 Collar 47 Beam cradle 48 Engagement lock concave part 49 Engagement lock convex part 50 Beam Cradle 51 Beam support 53 Beam between columns

─────────────────────────────────────────────────────
────────────────────────────────────────────────── ───

【手続補正書】[Procedure amendment]

【提出日】平成11年2月25日(1999.2.2
5)
[Submission date] February 25, 1999 (1999.2.2
5)

【手続補正1】[Procedure amendment 1]

【補正対象書類名】図面[Document name to be amended] Drawing

【補正対象項目名】全図[Correction target item name] All figures

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【図1】 FIG.

【図3】 FIG. 3

【図2】 FIG. 2

【図4】 FIG. 4

【図5】 FIG. 5

【図8】 FIG. 8

【図6】 FIG. 6

【図7】 FIG. 7

【図9】 FIG. 9

【図11】 FIG. 11

【図10】 FIG. 10

【図12】 FIG.

【図13】 FIG. 13

【図14】 ─────────────────────────────────────────────────────
FIG. 14 ────────────────────────────────────────────────── ───

【手続補正書】[Procedure amendment]

【提出日】平成12年1月24日(2000.1.2
4)
[Submission date] January 24, 2000 (2000.1.2
4)

【手続補正1】[Procedure amendment 1]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】全文[Correction target item name] Full text

【補正方法】変更[Correction method] Change

【補正内容】[Correction contents]

【書類名】 明細書[Document Name] Statement

【発明の名称】 建物構造体の建築工法[Title of the Invention] Building construction method of building structure

【特許請求の範囲】[Claims]

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】 本発明は、ビル、マンショ
ンなど建物構造体の全天候型建築工法に係る技術的分野
に属する。
TECHNICAL FIELD [0001] The present invention belongs to a technical field related to an all-weather construction method for a building structure such as a building or an apartment.

【0002】[0002]

【従来の技術】 従来、全天候型の建物構造体の基礎工
法としては、特開平3−107037号公報、又は特開
平3−107038号公報に開示されているように、コ
ア部1を、仮設支柱、型枠部、ジャッキ及びブラケット
からなる自動上昇型枠により構築するとともに、建築物
の柱13が立設される個所にもジャッキ12を設置す
る。次に2層分のコア部1を先行構築した後、建築物の
最上部から3層分の梁14,柱13を同時構築し、柱用
底型枠、柱用型枠を配設し、柱13及びスラブ24のコ
ンクリートを打設する。そして柱13が自立可能な状態
まで降下した段階で、ジャッキ12などを伸長して躯体
を1層分上方に押し上げ、順次下階の構築作業を継続
し、これを繰り返す建築工法などが知られている。又、
他の工法として特開平5−25864号公報に示すよう
に、建造物の柱10を施工した後、この柱10に沿って
床スラブSを上昇させるという操作を逐次繰り返し実施
して、各床スラブSをそれぞれ各階の床部に配設する。
このような建築躯体の構築方法において、床スラブSを
上昇させる工程を、最上階の床スラブSから次層階側の
床スラブ1Sへ順次に実施する。そして床スラブSの下
面に配置された上昇装置2によって床スラブSを支持し
ながら上昇させる建築工法などが知られている。また、
他の工法として特公平7−33689号公報に示すよう
に、地上レベルで1階分の躯体を集中的に施工し、1階
分の躯体工事完了後に階高分だけ上方に躯体の柱をプッ
シュアップすることを繰り返すことにより建物を施工
し、その場合において、プッシュアップ用ピン穴と固定
用ピン穴を有するフランジを柱に取付けるとともに、当
該プッシュアップ用ピン穴と係合可能なピンを備えるセ
ンターホールジャッキと当該固定用ピン穴と係合可能な
ピンを備える躯体保持装置とを前記柱の周囲に配し、こ
れをもって躯体の柱をプッシュアップする建築工法など
が知られている。
2. Description of the Related Art Conventionally, as a foundation construction method for an all-weather building structure, as disclosed in JP-A-3-103737 or JP-A-3-107038, a core 1 is provided with a temporary support. , And a jack 12 is installed at the place where the pillar 13 of the building is erected. Next, after preliminarily constructing the core portion 1 for two layers, the beams 14 and columns 13 for three layers are simultaneously constructed from the top of the building, and a bottom formwork for columns and a formwork for columns are provided. The concrete of the pillar 13 and the slab 24 is cast. At the stage when the pillar 13 is lowered to a state where the pillar 13 can be self-supported, the jack 12 and the like are extended to push up the frame by one layer, and the construction work on the lower floor is sequentially continued. I have. or,
As another construction method, as shown in Japanese Patent Application Laid-Open No. Hei 5-25864, after constructing a pillar 10 of a building, an operation of raising a floor slab S along the pillar 10 is sequentially and repeatedly performed. S is placed on the floor of each floor.
In such a construction method of the building frame, the step of raising the floor slab S is sequentially performed from the floor slab S on the top floor to the floor slab 1S on the next floor. A construction method of raising the floor slab S while supporting the floor slab S by a lifting device 2 arranged on the lower surface of the floor slab S is known. Also,
As another construction method, as shown in Japanese Patent Publication No. 7-33689, one frame of the skeleton is intensively constructed at the ground level, and after completing the framing of the first floor, the pillar of the skeleton is pushed upward by the height of the floor. A building having a push-up pin hole and a flange having a fixing pin hole attached to a pillar, and a center having a pin engageable with the push-up pin hole. There is a known construction method in which a hole jack and a skeleton holding device having a pin that can be engaged with the fixing pin hole are arranged around the pillar, and the pillar of the skeleton is pushed up with this.

【0003】上述した従来の建物構造体の建築工法に
は、次のような特質が認められている。 (a)全天候下での作業がなし得られ、天候に左右され
ない。 (b)高所作業が少ないため安全な施工ができ、而も近
隣に資材落下、飛散などの不安を与えない。 (c)建物の上部にタワークレーンなどの仮設設備を設
けないため、電波などに影響を与えない。
The following characteristics are recognized in the above-mentioned conventional construction method for building structures. (A) Work can be performed in all weather conditions and is not affected by weather conditions. (B) Since there is little work at high altitudes, safe construction can be performed, and there is no fear of falling or scattering materials nearby. (C) No temporary equipment such as a tower crane is installed above the building, so there is no effect on radio waves.

【0004】しかしながら、この種従来例のうちの2件
は建物構造体の全天候型建築工法は、最上階から未完の
骨組躯体を順次押し上げてゆく方式であるため、次に示
すような課題が依然として残されている。 (a)各階層における未完躯体の高所建築作業がそのま
ま残されており、資材の落下や飛散などの不安がある。 (b)地層毎に躯体構築用の資材を搬送する設備を要
し、建築作業量の平準化が望めない。また、従来例の他
の1件は、地上レベルで1階分の躯体を施工し、これを
順次プッシュアップする方式であるため、上記の課題は
ないものの次のような課題が残されている。 (c)プッシュアップ用の専用仮設フランジを柱に取り
付けるなど、躯体に取り付ける特別の仮設が必要であ
る。 (d)躯体の柱のプッシュアップ時に、フレームが柱を
囲むためプッシュアップ以前に躯体の梁を柱に取付ける
ことができず、従って梁取付けを中空位置で行わざるを
得ない。
[0004] However, two of the conventional examples of this kind are all-weather construction methods for building structures, in which an unfinished frame structure is sequentially pushed up from the top floor, and the following problems still remain. Is left. (A) Unfinished high-level building work at each level is left as it is, and there is concern about falling or scattering of materials. (B) Equipment for transporting building construction materials is required for each stratum, making it impossible to equalize the amount of construction work. Another example of the conventional example is a method in which a frame of one floor is constructed at the ground level and sequentially pushed up, so the following problems are left though the above problems are not present. . (C) It is necessary to provide a special temporary mounting to the frame, such as mounting a dedicated temporary flange for push-up on the pillar. (D) At the time of pushing up the pillar of the skeleton, the frame surrounds the pillar, so that the beam of the skeleton cannot be attached to the pillar before the push-up. Therefore, the beam must be attached in the hollow position.

【0005】上記技術的課題を解決するため、本件発明
者等は、特開平9−88185号公報に示すような、建
物構造体の建築工法及び建物構造体の扛重構造体の扛重
装置を提案している。この公開された先行技術は、地上
近傍で最上階の建物躯体を略完成させ、最上階から完成
した建物躯体を順次扛重し、所要階数の中高層階の建物
構造体を構築せしめ、高所作業のない安全な施工がなし
うるとともに、安定した品質の建物が効能的に得られる
建築工法と扛重装置を提供することにある。
In order to solve the above technical problems, the present inventors have proposed a construction method for a building structure and a lifting device for a lifting structure of a building structure as disclosed in Japanese Patent Application Laid-Open No. 9-88185. is suggesting. This published prior art is to complete the building structure on the top floor near the ground, lift the completed building structure from the top floor in order, and build the required number of mezzanine and high-rise building structures. It is an object of the present invention to provide a construction method and a lifting device capable of performing safe construction without any trouble and efficiently obtaining a building of stable quality.

【0006】本発明の目的は、上記特開平9−8818
5号公報に示された建築工法及び扛重装置の技術的事項
をそのまま利用するとともに、この技術に更に建物構造
体を構成する中間主柱の建柱に別個の扛重手段を用い、
更に安定した品質の建物が高能率的に得られる建築工法
と扛重装置を提供することにある。
An object of the present invention is to solve the above-mentioned problem described in Japanese Patent Application Laid-Open No. 9-8818.
In addition to utilizing the technical matters of the construction method and the lifting device shown in Japanese Patent Publication No. 5 as it is, a separate lifting device is used for the pillars of the intermediate main pillars constituting the building structure.
Another object of the present invention is to provide a construction method and a lifting device capable of efficiently obtaining a building of stable quality.

【0007】[0007]

【課題を解決するための手段】 上記課題を解決する手
段として本発明は、次のうな建物構造体の建築工法を
採用する。
In order to achieve the object of the present invention as a means for solving the above-mentioned problems, to adopt the construction methods of the next good UNA building structure.

【0008】上記目的は、基礎上において中高層階建物
構造物の屋上階及び最上階を組立てたのち、建物構造体
を構成する外周主柱近傍の両側梁下面を扛重手段(A)
の閂にて支持して扛上し、この扛上により生ずる作業空
間部に下層階を順次組み立てて構築するようにした建物
構造体の建築工法において、建築構造体を構成する中間
主柱を建柱する基礎杭両側の地中梁上または地層階の主
柱両側の梁上に、中間主柱位置を挟むように2個一組の
扛重装置(D’)を配設せしめ、一方、1層階分高さの
外周主柱の搬入組立てと前後して基礎杭上または地層階
の主柱上に最上階階高プラス次層階の一部の高さを有す
る中間主柱を搬入乗載し、この中間主柱および外周主柱
相互間の梁の組立て、天井部材、小梁などを取付けて建
築構造体の屋上階及び最上階を組立てるとともに、この
組立て作業と前後して中間主柱の両側梁下面に扛重装置
(D’)の昇降ビーム(閂)を配設する第1工程、扛重
手段(A)と同調して、扛重手段(D’)により最上階
層を一層階分高さに満たない高さ分だけ扛上したのち、
基礎杭または地層階の中間主柱上に短尺の仮受け柱を乗
載するとともに、最上層階を若干降下させ、全荷重を仮
受け柱に預け、昇降ビーム(閂)をフリーにする第2工
程、フリーとなった扛重手段(D’)の昇降ビーム
(閂)と扛重手段(A)の閂を更に降下させ、扛重手段
(D’)の昇降ビームと梁下面との間に梁受け台を介装
する第3工程、扛重手段(A)、(D’)により建築構
造体を扛上し、フリーとなった仮受け柱を退避させると
ともに、建築構造体を第1工程時点より1層階分より若
干高く扛上したのち、1層階分の高さをもつ次層階の外
周主柱を扛重手段(A)における施工用ブロック上に、
また次層階の中間主柱を基礎杭または地層階の中間主柱
上に搬入設置し、扛重手段(A)、(D’)の閂、昇降
ビーム(閂)を若干降下して全荷重を各基礎杭または地
層階の中間主柱に預け、前後して次層階の梁を各主柱間
に組立てる第4工程、フリーとなった扛重手段(A)、
(D’)の閂、昇降ビーム新たに設置された次層階の
と干渉しないよう水平方向に移動した状態で、閂、
降ビームを最下位まで下降させたのち、閂、昇降ビーム
を再び原位置に復帰し、次いで若干量上昇させて各主柱
両側の梁下面部に臨ませる第5工程、前記2〜5工程を
繰り返し行い、所定階層の建築構造体を構築して2階以
上の扛上ののちに、1,2階間の高さに調整した所定長
さの外周柱および中間主柱を基礎杭上または地層階の
主柱上に組立て、各主柱の上部を2階の各主柱の下端を
結合し、中間主柱の下端を基礎杭または地層階の主柱と
結合する第6工程、そののちに、扛重装置(A)、
(D’)を解体撤去し、前後して一階層の建築作業を完
了させることにより達成される。
[0008] The above object is to assemble the top floor and the top floor of a middle- and high-rise building structure on a foundation, and then lift the lower surfaces of both side beams near the outer peripheral main pillars constituting the building structure by lifting means (A).
In the construction method of a building structure, which is constructed by assembling and constructing lower floors sequentially in the work space generated by this lifting, the intermediate main pillars constituting the building structure are constructed. On the underground beams on both sides of the foundation pile to be pillared or on the beams on both sides of the main column on the stratum, two sets of lifting devices (D ') are arranged so as to sandwich the position of the intermediate main column. Before and after the loading and assembling of the outer main pillars at the height of the floor, the intermediate main pillar with the height of the top floor plus a part of the height of the next floor is loaded on the foundation pile or the main pillar of the formation floor. Then, assembling beams between the intermediate main column and the outer main column, attaching ceiling members, small beams, etc. to assemble the rooftop floor and the top floor of the building structure, and before and after this assembling work, The first step in which the lifting beam (bar) of the lifting device (D ') is provided on the lower surface of both beams, in synchronization with the lifting means (A) , After the top level was jacked by more Kaibun height of less than the height by 扛重 means (D '),
A short temporary support pillar is mounted on the foundation main pillar or the middle main pillar of the formation floor, and the top floor is slightly lowered, all the load is deposited on the temporary support pillar, and the lifting beam (bar) is freed. In the process, the lifting beam (bar) of the lifting means (D ') and the bar of the lifting means (A) are further lowered, and between the lifting beam (D') and the lower surface of the beam. The third step in which a beam support is interposed, the building structure is lifted by the lifting means (A) and (D '), the free temporary receiving pillars are evacuated, and the building structure is moved in the first step. After lifting a little higher than the first floor from the time, the outer main pillar of the next floor having the height of the first floor is placed on the construction block in the lifting means (A).
In addition, the intermediate main pillar of the next floor is loaded and installed on the foundation pile or the intermediate main pillar of the geological floor, and the bar of lifting means (A), (D ') and the bar (elevator) are slightly lowered to fully load. 4th step of assembling the beam of the next floor between each main pillar before and after depositing the foundation pile or the intermediate main pillar of the formation floor, the lifting means (A) which became free,
Obex of (D '), the lifting beam is in a state of being moved in the horizontal direction so as not to interfere with the newly installed next layer floor beams, obex, after lowering the lifting beams to the lowest, obex, lifting beams < The fifth step of returning to the original position again, and then slightly rising and facing the lower surface of the beam on both sides of each main pillar, and repeating the above-described 2 to 5 steps, to construct a building structure of a predetermined level. After ascending two or more floors, assemble the outer main pillars and intermediate main pillars of the specified length adjusted to the height between the first and second floors on the foundation piles or the main pillars on the stratum floor. The sixth step in which the lower part of each main pillar on the second floor is connected to the upper part of the second floor, and the lower end of the intermediate main pillar is connected to the foundation pillar or the main pillar of the stratum floor, after which the lifting device (A)
This is achieved by dismantling and removing (D ') and completing one-story building work before and after.

【0009】上記目的は、基礎上において中高層階建物
構造物の屋上階及び最上階を組立てたのち、建物構造体
を構成する外周主柱近傍の両側梁下面を扛重手段の
(A)の閂にて支持して扛上し、この扛上により生ずる
作業空間部に下層階を順次組み立てて構築するようにし
た建物構造体の建築工法において、建築構造体を構成す
る中間主柱を建柱する基礎杭両側の地中梁上または、地
層階の主柱両側の梁上に、中間主柱位置を挟むように2
個一組の扛重装置(D’)を配設せしめ、一方、1層階
分高さの外周主柱の搬入組立てと前後して基礎杭上また
は地層階の主柱最上階階高プラス次層階の一部の高
を有する中間主柱を搬入乗載し、この中間主柱および
外周主柱相互間の梁の組立て、天井部材、小梁などを取
付けて建築構造体の屋上階及び最上階を組立てるととも
に、この組立て作業と前後して中間主柱の両側梁下面に
扛重装置(D’)の昇降ビーム(閂)を配設する第1工
程、扛手段(A)と同調して扛重手段(D’)により
最上階層を一層階分高さを越す高さだけ扛上したのち、
基礎杭上または地層階の中間主柱上に一層階分の高さを
もつ次層階の外周主柱と中間主柱を搬入設置し、扛重装
置(A)、(D’)を若干降下して全荷重を基礎杭また
は地層階の中間主柱に預ける第2工程、フリーとなった
扛重手段(A),(D’)の閂、昇降ビームが新たに設
置された次層階の梁と干渉しないよう水平方向に移動し
た状態で、閂、昇降ビームを最下位まで下降させたの
ち、閂、昇降ビームを再び原位置に復帰し、前後して、
中間主柱相互間および中間主柱と外周主柱の間の梁の組
立てを行う第3工程、前記2、3工程を繰り返し行い、
所要階層の建築構造体を構築して2階以上の扛上のの
ち、1,2階間の高さに調整した所定長さの外周主柱お
よび中間主柱を基礎杭上または地層階の中間主柱上に組
立て、中間主柱の上端を2階の中間主柱の下端と結合
し、中間主柱の下端を基礎杭または地層階の主柱と結合
する第4工程、そののちに、扛重装置(A)、(D’)
を解体撤去し、前後して一階層の建築作業を完了させる
ことにより達成される。
The above object is to assemble the roof top floor and the top floor of the middle and high-rise building structure on the foundation and then to lower the lower surfaces of both side beams near the outer peripheral main pillars constituting the building structure by using the bar of lifting means (A). In the construction method of a building structure that is constructed by assembling and constructing lower floors sequentially in the work space generated by the lifting, the intermediate main pillars that constitute the building structure are built. On the underground beam on both sides of the foundation pile or on the beam on both sides of the main column on the stratum,
Allowed disposed pieces set of扛重device (D '), whereas, 1 Sokaibun top floor to the height of the outer main pillars of the loading assembly and the foundation pile and before, after, or strata floor main pole story height Plus some heights on the next floor
The intermediate main pillar having the height is carried in and mounted, the beams between the intermediate main pillar and the outer peripheral main pillar are assembled, ceiling members, small beams are attached, and the rooftop floor and the top floor of the building structure are assembled. the first step,扛重means in phase with扛load means (a) disposing the lifting beam (obex) assembly operations and扛重device on either side beams lower surface of the intermediate main pillar and longitudinal (D ') (D '), The top level was lifted to a height that exceeds the height of the next floor, and then lifted.
The outer main column and the intermediate main column of the next floor with a height of one layer are loaded and installed on the foundation pile or the intermediate main column of the formation floor, and the lifting devices (A) and (D ') are slightly lowered. In the second step, the entire load is deposited on the foundation pile or the middle main column of the stratum floor, and the free lifting means (A), (D ') and the lifting beam are newly installed.
Move horizontally so as not to interfere with the beam on the next floor
The bar and the lifting beam were lowered to the bottom.
The bar, the lifting beam returns to its original position again,
Beam sets between the intermediate main columns and between the intermediate main column and the outer main column
A third step of erecting, repeating the steps 2 and 3,
After constructing the building structure of the required level and lifting on the second floor or higher, the outer main pillars and intermediate main pillars of a predetermined length adjusted to the height between the first and second floors are placed on the foundation pile or in the middle of the stratum floor. The fourth step of assembling on the main pillar, connecting the upper end of the intermediate main pillar to the lower end of the intermediate main pillar on the second floor, and connecting the lower end of the intermediate main pillar to the main pillar on the foundation pile or stratum floor, and then lifting Heavy equipment (A), (D ')
And dismantling the, it is more accomplished in that to complete the construction work of one level back and forth.

【0010】[0010]

【発明の実施の形態】 次に、図面について本発明の建
築工法の詳細を説明する。
Next, details of the construction method of the present invention will be described with reference to the drawings.

【0011】先ず、特開平9−88185号公報に開示
され、本発明の建築工法に併用するとともに、一層階分
より若干高く建物躯体を一挙に扛上する機能をもつ扛重
装置Aの構成を、図2、図10〜図14について説明す
る。
First, the construction of a lifting device A disclosed in Japanese Patent Application Laid-Open No. 9-88185 and having a function of lifting the building frame at a time slightly higher than the floor, which is used together with the construction method of the present invention, is described. 2 and FIGS. 10 to 14 will be described.

【0012】1は、建物構造体Bの外周に配設建柱され
る外周主柱2の外側左右に配設される1層階分の高さよ
り背高とした架台であって、該架台1は外周主柱2およ
び梁または梁仕口3と干渉しないよう配置されている。
前記架台1には、外周主柱2側鉛直面に沿うように上下
動する昇降梁5が介設されており、この昇降梁5には前
記架台1に対して脱抜可能に垂設装架したスクリューロ
ッド6を貫通するとともに、このスクリューロッド6は
昇降梁5の左右下部に固定したナット部材7に脱抜可能
に挿入螺合されている。又、前記スクリューロッド6の
上端にはスプロケット8と、両架台1の外側上方に夫々
配設した駆動モータ9の軸に設けたスプロケットとがチ
ェンによって接続されており、駆動モータ9の駆動によ
り回転するスクリューロッド6と、前記昇降梁5に固定
したナット部材7の相関関係により、昇降梁5が架台1
の外側1Aを案内として上下動するように構成されてい
る。図中13はベアリングである。
Reference numeral 1 denotes a gantry having a height higher than the height of a single story provided on the left and right sides of an outer main column 2 provided on the outer periphery of the building structure B. Are arranged so as not to interfere with the outer main column 2 and the beam or beam connection 3.
The gantry 1 is provided with an elevating beam 5 that moves up and down along the vertical plane on the outer peripheral main column 2 side, and the elevating beam 5 is vertically mounted detachably with respect to the gantry 1. The screw rod 6 penetrates the screw rod 6, and the screw rod 6 is detachably inserted and screwed into a nut member 7 fixed to the lower left and right portions of the lifting beam 5. A sprocket 8 is connected to the upper end of the screw rod 6 and a sprocket provided on a shaft of a drive motor 9 disposed outside and above the gantry 1 by a chain. The sprocket 8 is rotated by the drive of the drive motor 9. Due to the correlation between the screw rod 6 and the nut member 7 fixed to the elevating beam 5, the elevating beam 5
It is configured to move up and down with the outer side 1A as a guide. In the figure, reference numeral 13 denotes a bearing.

【0013】次に前記昇降梁5の構成について説明す
る。昇降梁5の上面左右側、詳しくは、昇降梁5に挿貫
した前記両スクリューロッド6の夫々内側部位に、昇降
梁5の左右軸線方向と直行する前後軸線方向にそって進
退移動可能で、かつ、閂構造からなる2個の荷重受け梁
14を平行に乗載せしめる。この両荷重受け梁14は昇
降梁5の上面に立設された2枚一組の案内板15間にス
ライド自在に挿嵌するとともに、夫々の荷重受け梁14
の先端上部に、梁の歪調整用の円筒座16を上面にもつ
調整ブロック17を設ける。なお、調整ブロック17は
場合により省略できる。18は、前記昇降梁5の後部に
設けた正面形状が門構形をした前記荷重受け梁14の反
力を支受する連絡梁で、昇降梁5の上面と連結梁18の
下面間に荷重受け梁14をスライド可能に挟持し、荷重
受け梁14の先端に掛かる荷重の反力を連結梁18で支
承するようにしたものである。図中19は連結梁18補
助梁18の補強用の支持梁である。
Next, the structure of the lifting beam 5 will be described. The upper and lower sides of the elevating beam 5, specifically, the inside portions of the two screw rods 6 inserted into the elevating beam 5, can move forward and backward along the front-rear axis direction perpendicular to the left-right axis direction of the elevating beam 5, At the same time, two load receiving beams 14 having a bar structure are mounted in parallel. Both this two load receiving beams 14 you fitted slidably between a set of two sheets of the guide plate 15 provided upright on the upper surface of the lifting beam 5, a load of each received beam 14
An adjustment block 17 having a cylindrical seat 16 for adjusting the distortion of the beam on the upper surface is provided at the top of the tip. Note that the adjustment block 17 can be omitted in some cases. Reference numeral 18 denotes a connecting beam provided at a rear portion of the elevating beam 5 and receiving a reaction force of the load receiving beam 14 having a frontal gate shape, and a load between the upper surface of the elevating beam 5 and the lower surface of the connecting beam 18. The receiving beam 14 is slidably held, and the reaction force of the load applied to the tip of the load receiving beam 14 is supported by the connecting beam 18. In the figure, reference numeral 19 denotes a support beam for reinforcing the connecting beam 18 and the auxiliary beam 18.

【0014】前記昇降梁5の両側端面に比較的広巾の凹
所20を形成するとともに、この凹所20に嵌合介入す
る凸部ガイド(図示略)を前記架台1の外側壁の内面上
下方向に形成したものである。そして、凸部ガイドの前
後面又は前記凹所20を構成する前部壁面及び前記連結
梁18の前面上部に、両者の摺動を円滑にするためのテ
フロン樹脂板などの摺動部材22を張設せしめる。尚、
このテフロン樹脂板に代え、凹所20又は凸部ガイドの
何れかの前後面にローラ(図示略)を設けるものであ
る。そして、図2、図11から明らかなように、前記2
本の荷重受け梁14が外周主柱2を挟むようにして架台
1が配置され、該外周主柱2間に取り合う両側の梁の基
部、詳しくは、外周主柱2に設けた梁または梁仕口3の
下面を両荷重受け梁14によって支持し、建築作業が略
完了した建物躯体Cを一層階分余扛上するようにしたも
のである。図中3cは、コーナー部主柱2に梁仕口3が
片側にしかないため、この梁仕口3と対称位置に設ける
仮仕口である。扛重装置Aは上述のように構成されてい
る。
A relatively wide recess 20 is formed in both end surfaces of the lifting beam 5 and a convex guide (not shown) which fits into the recess 20 is provided in the vertical direction of the inner surface of the outer wall of the gantry 1. It is formed in. Then, a sliding member 22 such as a Teflon resin plate for facilitating sliding between the two is provided on the front and rear surfaces of the convex guide or on the front wall surface forming the recess 20 and the upper front surface of the connecting beam 18. I will set it up. still,
Instead of the Teflon resin plate, rollers (not shown) are provided on the front and rear surfaces of either the concave portion 20 or the convex portion guide. Then, as is apparent from FIGS.
The gantry 1 is arranged so that the load receiving beams 14 sandwich the outer peripheral main column 2, and the bases of the beams on both sides that are interposed between the outer peripheral main columns 2, more specifically, the beam or beam connection 3 provided on the outer main column 2. Is supported by both load receiving beams 14, so that the building skeleton C, for which the construction work has been substantially completed, is further lifted by a floor. In the figure, reference numeral 3c denotes a temporary connection provided at a position symmetrical to the beam connection 3 because the beam connection 3 is only on one side of the corner main pillar 2. The lifting device A is configured as described above.

【0015】次に、前述した扛重装置Aを使用する建物
構造体Bの建築工法を図14について説明する。図14
aに示すように、施工レベルを調整した施工用ブロック
23の外方に扛重装置Aを配設し、前記扛重装置Aを構
成する平行2条の荷重受け梁14の中間に施工用ブロッ
ク23を位置させる。該施工用ブロック23は建物構造
体Bの基礎上に設け、建物本来の主柱1の一部を転用し
てもよい。該施工用ブロック23上に最上階の外周主柱
2を立設し、この外周主柱2に最上階の屋上構成用の柱
間梁53、梁仕口3を取り付けるとともに、最上階床面
構成用の柱間梁53を夫々とりつけ、最上階の建物躯体
Cの建築作業を完成させる。(図2参照)
Next, a construction method of a building structure B using the above-described lifting device A will be described with reference to FIG. FIG.
As shown in a, the lifting device A is disposed outside the construction block 23 whose construction level has been adjusted, and the construction block is provided between the two parallel load receiving beams 14 constituting the lifting device A. Position 23. The construction block 23 may be provided on the foundation of the building structure B, and a part of the main pillar 1 of the building may be diverted. The outermost main pillar 2 of the top floor is erected on the construction block 23, and the inter-column beam 53 and the beam connection 3 for the rooftop construction of the top floor are attached to the outermost main pillar 2, and the top floor floor structure Attach the beam 53 between the columns to complete the construction work of the building skeleton C on the top floor. (See Fig. 2)

【0016】最上階の建物躯体Cが完成したら図14b
に示すように、両荷重受け梁14を前進させ、これの先
端に設けた調整ブロック17を梁仕口3,仮仕口3cの
下側に夫々臨ませたのち、前記駆動モータ9の駆動にス
クリューロッド6を回転させ、ナット部材を介して昇降
梁5を梁仕口3,仮仕口3cの下面に当接せしめ、図1
4cに示すように全ての外周主柱2を若干扛重して全荷
重受け梁14への載荷を確認するようにして、全ての扛
重装置Aの零点調整制御を行う。(図11参照)
When the building structure C on the top floor is completed, FIG.
As shown in (2), the load receiving beams 14 are advanced, and the adjustment blocks 17 provided at the ends thereof are made to face under the beam ports 3 and the temporary ports 3c, respectively. By rotating the screw rod 6, the lifting beam 5 is brought into contact with the lower surface of the beam connection 3 and the temporary connection 3c via the nut member, and FIG.
As shown in FIG. 4c, zero lifting adjustment of all the lifting devices A is performed by slightly lifting all the outer main pillars 2 and confirming the load on all the load receiving beams 14. (See Fig. 11)

【0017】このように扛重装置Aの零点調整制御が完
了したら、図14dのように、例えば約20mm/min
の上昇スピードで約3時間で最上階建物躯体Cを一層階
分余扛重し、最上階の建物躯体Cの下方に次層階の作業
空間24を形成する。
When the zero-point adjustment control of the lifting device A is completed as described above, for example, as shown in FIG.
In about 3 hours at the rising speed, the top-floor building frame C is lifted by one more floor, and a work space 24 of the next floor is formed below the top-layer building frame C.

【0018】次いで、図14eに示すように、作業空間
24を利用して前記全てのブロック23上に一層階分の
長さを有する外周主柱2を搬入して最上階外周主柱2の
下部に取付け、最上階の建物躯体Cの扛重姿勢を保持し
たまま、この立設された外周主柱2に次層階床面構成用
の梁仕口3を取り付け、最上階建物駆体Cを構成する外
周主柱2の下端と、次層階構成用の外周主柱2の上端と
を溶接又はガセットを用いた結合手段にて連結連合して
次層階の建築作業を管理用させて、次層階建物躯体Cを
構成したのち、図14fに示すように、駆動モータ9を
逆転させてスクリューボルト6の作用で昇降梁5を若干
下降させて、建物躯体Cの全荷重を施工用ブロック23
に載せ替え、次いで荷重受け梁14による最上階建物躯
体C、梁仕口3,仮仕口3c下面の支持を解除する。そ
して、図14g〜図14iに示すように、前記荷重受け
梁14を梁仕口3,仮仕口3cと無関係な後方に退避さ
せることにより、昇降梁5を次層階の梁仕口3に干渉し
ない状態で最下位まで下降させた上で、荷重受け梁14
を前進させて調整ブロック17を次層階建物躯体Cを構
成する梁仕口3,仮仕口3cの下方に臨ませる。
Next, as shown in FIG. 14e, the outer peripheral main pillar 2 having a length corresponding to one floor is loaded onto all the blocks 23 using the work space 24, and the lower part of the outermost main pillar 2 on the uppermost floor is provided. the mounting, while maintaining the扛重posture of the top floor of the building structures C, the mounting beam Joint 3 for Tsugiso floor surface configured to the erected outer peripheral main pole 2, the top floor building precursor C The lower end of the outer peripheral main pillar 2 to be configured and the upper end of the outer peripheral main pillar 2 for the next floor are connected and connected by a connecting means using welding or a gusset to manage the construction work of the next floor, After constructing the next-floor building skeleton C, as shown in FIG. 14f, the drive motor 9 is reversed and the lifting beam 5 is slightly lowered by the action of the screw bolt 6, so that the entire load of the building skeleton C is applied to the construction block. 23
Then, the support of the uppermost building frame C, the beam connection 3, and the temporary connection 3c under the load receiving beam 14 is released. Then, as shown in FIGS. 14g to 14i, the load receiving beam 14 is retracted to the rear irrespective of the beam connection 3 and the temporary connection 3c, so that the lifting beam 5 is moved to the beam connection 3 on the next floor. After lowering to the lowest position without interference, the load receiving beam 14
To make the adjustment block 17 face below the beam connection 3 and the temporary connection 3c constituting the next-story building frame C.

【0019】次に図14jのように、前記と同様な手段
で昇降梁5を上昇させて調整ブロック17を梁仕口3,
仮仕口3cの下面に当接せしめ、次層階を含む最上階の
建物躯体Cを若干上昇させ、円筒座16で梁仕口3をも
つ梁の歪調整と全ての扛重装置Aの零点調整制御を行っ
たのち、図14kで示すように、建物躯体Cを一層階分
余扛上し、これの下方に次々層階の作業空間を構成し、
以下所要階層n−2層〜2階まで上層から下層に向かっ
て図14e、図14kの工法を繰り返し行う。
Next, as shown in FIG. 14j, the lifting beam 5 is raised by means similar to the above, and the adjustment block 17 is moved to the beam connection 3,
Abut the lower surface of the temporary connection 3c, slightly raise the building frame C on the top floor including the next floor, adjust the distortion of the beam having the beam connection 3 with the cylindrical seat 16, and set the zero point of all lifting devices A. After performing the adjustment control, as shown in FIG. 14k, the building skeleton C is lifted up by one floor, and a work space of the next floor is formed below this, and
14e and 14k are repeatedly performed from the upper layer to the lower layer from the (n-2) th layer to the second floor.

【0020】図14lに示すように、2階までの建物躯
体Cが完了したら、施工用ブロック23を撤去するか、
あるいは、施工用ブロック23を本来の1階外周主柱2
の一部として埋め殺し、1階高さを補足する短柱25を
2階外周主柱2の下部に結合するか、あるいは1階の構
築に必要な高さまで扛重し、2階建物躯体を構成する外
周主柱2との間に1階の外周主柱2を乗載結合したの
ち、2階を含む建物躯体Cを図14mに示すように下降
させ、2階構成用の外周主柱2の下端と短柱25の上端
とを結合してから荷重受け梁14を下降し、2階構成用
の外周主柱2の梁仕口3B、仮仕口3cに対する下面支
持を解除したのち、全ての扛重装置Aを外側方に退去さ
せ、1階の建築作業を完了させ、所要階層の建物構造体
Bを得る。
As shown in FIG. 14L, when the building skeleton C up to the second floor is completed, the construction block 23 is removed or
Alternatively, the construction block 23 may be replaced with the main pillar 2 on the first floor.
Buried as a part of the building, and the short columns 25 that supplement the height of the first floor are connected to the lower part of the main pillar 2 on the second floor, or they are lifted to the height required for the construction of the first floor, and After the first-floor outer main pillar 2 is mounted on and coupled to the outer main pillar 2 to be configured, the building skeleton C including the second floor is lowered as shown in FIG. After the lower end of the lower column and the upper end of the short column 25 are joined, the load receiving beam 14 is lowered, and the lower surface support for the beam connection 3B and the temporary connection 3c of the outer main column 2 for the second floor is released. The lifting apparatus A of the first floor is retreated to the outside to complete the construction work on the first floor, and the building structure B of the required level is obtained.

【0021】次に、図2〜図6について、建物内部の主
柱である中間主柱32に関し、本発明の建築工法を実施
するための扛重装置D’に係る実施の形態を説明する。
Next, referring to FIGS. 2 to 6, an embodiment of a lifting device D 'for carrying out the construction method of the present invention will be described with respect to an intermediate main column 32 which is a main column inside a building.

【0022】31は、建物構造体Bの外周に配設建柱せ
しめられる前記外周主柱2を除いた内部の所要部位に、
建柱される一層階分の高さをもつ中間仕口32の梁仕口
32aに取り合うべく基礎、例えば、地中の杭、あるい
は、地層階の中間主柱33に設けた地中梁33a上にセ
ットされたライナー33b上に配設される架台である。
この架台31は、中間主柱32を挟むように、これの両
側に近接して配設される2個一組で、而も上下方向に複
数に分割可能な架台構成体31a、31bからなる。
Reference numeral 31 denotes a necessary portion inside the building structure B excluding the outer main pillar 2 which is provided on the outer periphery of the building structure B.
On a foundation, for example, an underground pile or an underground beam 33a provided on an intermediate main pillar 33 on a stratum, to fit a beam connection 32a of an intermediate connection 32 having a height of one layer to be built. This is a pedestal provided on the liner 33b set in the frame.
The gantry 31 is a pair of gantry components 31a and 31b that can be divided into a plurality of pieces in the vertical direction.

【0023】図2、図3から明らかなように、各架台構
成体31a、31bの両側下部は、分解可能な継ぎ部材3
4によって結合されるとともに、両架台構成体31a、
31bの両側下部には、スプロケット35をもつ回転伝
達体36が夫々設けられており、この回転伝達体36の
上部に架台31よりやや背低のスクリュー軸37がキー
構造を介して回動可能に、かつ、嵌脱自在に垂設されて
いる。又、両架台構成体31a、31bの両外側部には駆
動モータ38を夫々設け、この駆動モータ38の駆動軸
に設けたスプロケット39と、前記スプロケット35と
がチェン又は別途トルク伝達系40によって連結されて
おり、各駆動も38の正逆、逆転駆動が回転伝達体36
を介して各別にスクリュー軸37に伝達される。
As is apparent from FIGS. 2 and 3, the lower portions on both sides of each of the gantry members 31a and 31b are provided with disassemblable joint members 3.
4, and both gantry structures 31a,
Rotation transmission bodies 36 each having a sprocket 35 are provided at the lower portion on both sides of 31b, and a screw shaft 37 slightly shorter than the gantry 31 is rotatable above the rotation transmission body 36 via a key structure. And it is vertically installed so that it can be freely inserted and removed. Driving motors 38 are provided on both outer sides of both gantry structures 31a and 31b, respectively. A sprocket 39 provided on a driving shaft of the driving motor 38 and the sprocket 35 are connected by a chain or a separate torque transmission system 40. Each drive is also performed by the forward / reverse and reverse rotation drive of the rotation transmission body 36.
And transmitted to the screw shaft 37 separately.

【0024】スクリュー軸37は、閂構造とした昇降ブ
ロック41に固定したナット部材42に対して脱抜可能
に夫々挿入螺合されている。一方、各昇降ブロック41
の両側には対称的に案内凸部41aを設け、この案内凸
部41aは架台31の両側縦方向に形成した案内凹溝3
1cに嵌合してあり、ナット部材42、詳しくは、スク
リュー軸37の回動作用が昇降ブロック41の昇降作用
に変換せめられ、全ての昇降ブロック41が均等に而
も同期昇降しうるように構成されている。又、案内凹溝
31cの内面または、案内凸部41aの周面に、テフロン
樹脂板などの摺動部材43を設け、両者の摺動を円滑に
する。又、この摺動部材43に代え、何れかにローラ
(図示略)を転動可能に付設してもよい。また、図示は
してないがスクリュー軸37を架台31a、31bに対
して回転しないよう固定し、ナット部材42を回転させ
るように構成してもよい。
The screw shaft 37 is detachably inserted and screwed into a nut member 42 fixed to a lifting block 41 having a bar structure. On the other hand, each lifting block 41
Are provided symmetrically on both sides of the base 31. The guide protrusions 41a are formed in the guide grooves 3 formed in the longitudinal direction on both sides of the gantry 31.
Yes fitted to 1c, the nut member 42, specifically, Shi allowed conversion times operation of the screw shaft 37 to the lifting action of the lifting block 41 Merare all the lifting block 41 can evenly Thus also synchronized lifting It is configured as follows. Further, a sliding member 43 such as a Teflon resin plate is provided on the inner surface of the guide groove 31c or on the peripheral surface of the guide convex portion 41a to make the sliding of both members smooth. Instead of the sliding member 43, a roller (not shown) may be rotatably attached to any of the members. Further, although not shown, the screw shaft 37 may be fixed to the frames 31a and 31b so as not to rotate, and the nut member 42 may be rotated.

【0025】一方の架台構成体31aの両昇降ブロック
41が他方の架台構成体31bに対面する側に、昇降ビ
ーム44のいったんを旋回可能に夫々軸支するととも
に、昇降ビーム44の遊動他端に連結用の孔44aを垂
設する。又、他方の架台構成体31bに設けた両昇降ブ
ロック41が、一方の架台構成体31aに対面する側
に、前記連結用の孔44aに適用する孔44bを設け、両
孔44a、44bが適合したときに、この両孔44a、4
4bに上方よりノックピン45を共通的に挿入し、両昇
降ブロック41間に昇降ビーム44が橋架的に連結固定
される。両昇降ブロック41間に橋架された昇降ビーム
44は、図から明らかなように、中間主柱32の側面に
固装されている梁仕口32aの下面に対応するように構
成してある。又、両架台構成体31a、31bのスクリュ
ー軸37及びこれの三方を囲うようにした案内凹溝31
cを設けた架台部分を除いた基部は、比較的平面部分が
広く構成されているので、この平面部分を口述する盛り
替え用の仮受け柱32bの退避場所として利用しうる。
Both raising and lowering blocks of one pedestal constituting body 31a
The elevator 41 is located on the side facing the other gantry structure 31b.
Once the arm 44 is pivotally supported,
At the same time, a connection hole 44a is suspended from the other end of the floating beam 44.
Set up. Also, the two lifting and lowering brackets provided on the other gantry constituting body 31b are provided.
The lock 41 faces one of the pedestal components 31a.Side
A hole 44b to be applied to the connection hole 44a,
When the holes 44a, 44b are fitted, the holes 44a, 44b
4b, insert the knock pin 45 in common from above,
Elevating beam 44 is connected and fixed between bridges 41 in a bridge.
Is done. Elevating beam bridged between both elevating blocks 41
44 is on the side surface of the intermediate main pillar 32 as is apparent from the drawing.
It is configured to correspond to the lower surface of the beam connection 32a that is fixed.
It has been done. Also, the screws of the two gantry components 31a, 31b
-Shaft 37 and guide groove 31 surrounding three sides thereof
The base, excluding the cradle part provided with c, has a relatively flat
Because it is widely constructed, a prime to dictate this flat part
It can be used as a refuge place for the temporary receiving pillar 32b for replacement.

【0026】図から明らかなように、昇降ビーム44に
はこれの軸線にそってスライド移動可能なスライド筒4
6が被嵌されており、該スライド筒46上には梁仕口3
2aの下部に臨み、かつ、中間主柱32の盛り替え用と
して用いる梁受け台47が付設してある。扛重装置D’
は、上述のように構成されている。
As is apparent from the figure, the lifting cylinder 44 has a sliding cylinder 4 slidable along its axis.
6 are fitted, and the beam connection 3 is placed on the slide cylinder 46.
A beam support 47 which faces the lower portion of 2a and is used for refilling the intermediate main pillar 32 is additionally provided. Lifting device D '
Is configured as described above.

【0027】図7は、前述した実施の形態の昇降ビーム
44の遊動端部の内側面に、係合ロック凹部48を形成
したものを示し、この係合ロック凹部48が、他方の昇
降ブロック41に形成した係合ロック凸部49に係合離
脱しうるように構成する。その他の構成は実施の形態で
説明したものと同様であることから、同一構成部分には
同一符号を付すことにより詳細な説明は省略する。
FIG. 7 shows an embodiment in which an engaging lock recess 48 is formed on the inner surface of the floating end of the lifting beam 44 of the above-described embodiment. Is configured to be able to be disengaged from and engaged with the engagement lock convex portion 49 formed in the above. Since other configurations are the same as those described in the embodiment, the same components are denoted by the same reference numerals, and detailed description is omitted.

【0028】図8は、前述した実施の形態の梁受け台4
7の別形態を示している。この形態は、中間主柱32の
梁仕口32aの下部から外れた位置の使用校ビーム44
の上面に、梁受け台50を反転可能、詳しくは、この梁
受け台50の梁仕口32a側の下端角隅部を昇降ビーム
44に軸支せしめ、この状態の梁受け台50を反転させ
ることにより梁仕口32aの直下部に梁受け台50が隣
設されるようにしたものである。
FIG. 8 shows the beam support 4 of the above-described embodiment.
7 shows another embodiment. In this embodiment, the used school beam 44 is located at a position off the lower part of the beam connection 32a of the intermediate main column 32.
The beam receiver 50 can be turned over on the upper surface of the beam receiver. More specifically, the lower corner of the beam receiver 32 on the side of the beam connection 32a is pivotally supported by the elevating beam 44, and the beam receiver 50 in this state is turned over. Thus, the beam receiving base 50 is provided immediately below the beam connection 32a.

【0029】図9は、前述した実施の形態の梁受け台4
7の更に別形態を示している。この形態は、中間主柱3
2の梁仕口32aの下方に対応する昇降ビーム44の側
面に、この昇降ビーム44の上面と同一平面となる梁受
け台51の上端角隅部を軸支せしめ、この状態の梁受け
台51を反転して昇降ビーム44の上面に乗載支持して
梁仕口32aの直下32aの直下に梁受け台51を臨ま
せ、中間主柱32の盛り替えとして使用しうるように構
成したものである。
FIG. 9 shows a beam support 4 of the above-described embodiment.
7 shows still another embodiment. This form is an intermediate main pillar 3
The upper end corner of a beam receiving base 51 coplanar with the upper surface of the lifting / lowering beam 44 is axially supported on the side surface of the lifting / lowering beam 44 below the second beam connection 32a. And the beam supporting base 51 is mounted on the upper surface of the elevating beam 44 and supported so as to face the beam receiving base 51 directly below the beam connection 32a, so that the intermediate main column 32 can be used as a rearrangement. is there.

【0030】昇降ビーム(44)に対する梁受け台の装着
手段としては特に図示してないが、前述した実施の形態
以外多々想定しうることから、図示のものに特定される
ことはない。
Although the means for mounting the beam support to the lifting beam (44) is not specifically shown, it is not limited to the one shown in the drawings since it can be supposed in many ways other than the embodiment described above.

【0031】次に、前述した扛重装置D’を使用する建
物構造体Bの建築工法を、図1a〜eについて説明す
る。尚、この建築工法については、前述した扛重装置A
を扛重装置D’と同調した挙動で使用することは勿論で
ある。
Next, a construction method of a building structure B using the above-described lifting device D 'will be described with reference to FIGS. In this construction method, the lifting device A described above is used.
Of course is used in synchronism with the lifting device D '.

【0032】図1aは、扛重装置D’、詳しくは、架台
31を構成する架台構成体31a、31bを全ての中間主
柱32の両側に設置し、両架台構成体31a、31b間に
橋架した昇降ビーム44を中間主柱32の両側に設けた
梁仕口32aの下部に臨ませた姿勢を示している。この
図1aは昇降開始準備完了後の姿勢を示しており、主柱
2の梁仕口32aと、これに対応する中間主柱32の梁
仕口32a間には柱間梁53が接続されている。
FIG. 1a shows a lifting device D ', more specifically, gantry structures 31a and 31b constituting a gantry 31 are installed on both sides of all intermediate main columns 32, and a bridge is provided between the gantry structures 31a and 31b. This shows a posture in which the lift beam 44 facing the lower part of the beam connection 32a provided on both sides of the intermediate main column 32 is shown. FIG. 1a shows the posture after completion of the preparation for starting the elevating operation. An inter-column beam 53 is connected between the beam connection 32a of the main column 2 and the corresponding beam connection 32a of the intermediate main column 32. I have.

【0033】図1aの状態において、全てのスクリュー
軸37を同期駆動して昇降ビーム44を上昇させ、梁仕
口32aを介して中間主柱32を定められたストロー
ク、詳しくは、仮受け柱32bの高さより若干高い位置
まで上昇させる。次いで、架台31の基部上に待機させ
ていた仮受け柱32bを地中の中間主柱(33)上に搬
送乗載したのち、スクリュー軸37を逆回転させて昇降
ビーム44を下降せしめて中間主柱32の下端を仮受け
柱46上に乗せ全ての荷重を預ける。(図1b参照)
In the state shown in FIG. 1A, all the screw shafts 37 are driven synchronously to raise and lower the elevating beam 44, and the intermediate main column 32 is set to a predetermined stroke through the beam connection 32a. To a position slightly higher than the height of Next, the temporary receiving column 32b, which has been waiting on the base of the gantry 31, is transported and mounted on the underground intermediate main column (33), and then the screw shaft 37 is rotated in the reverse direction to lower the elevating beam 44 so that the intermediate beam is lowered. The lower end of the main column 32 is placed on the temporary receiving column 46 and all loads are deposited. (See Fig. 1b)

【0034】この状態で、更に昇降ビーム44を下降さ
せ、これに設けた梁受け台47の上面が梁仕口32aの
下面より若干下方となるように下降させた時点で、梁受
け台47を昇降ビーム44に沿って横移動(紙面右方
向)して梁受け台47を梁仕口32aの下方にセットす
る。(図1c参照)
In this state, the elevating beam 44 is further lowered, and when the upper surface of the beam support 47 provided on the lower beam is lowered slightly below the lower surface of the beam connection 32a, the beam support 47 is lowered. The beam receiver 47 is moved laterally (rightward on the paper) along the elevating beam 44 to set the beam receiver 47 below the beam connection 32a. (See Fig. 1c)

【0035】次いで、スクリュー軸37を駆動して中間
主柱32を大きく、詳しくは、一層階より若干高く上昇
させ、この中間主柱32の下面と中間主柱(33)の上面
との開きが、一層階分高さの中間主柱32の高さより若
干高く扛上した時点で昇降ビーム44の上昇を止め、上
層階の中間主柱32の下部空間に新たな中間主柱32を
搬入介装する。(図1d参照)
Next, the screw shaft 37 is driven to make the intermediate main column 32 larger, specifically, slightly higher than the floor, so that the lower surface of the intermediate main column 32 and the upper surface of the intermediate main column (33) are opened. The lift beam 44 is stopped when the vehicle is lifted slightly higher than the height of the intermediate main pillar 32 at the height of one floor, and a new intermediate main pillar 32 is inserted into the lower space of the intermediate main pillar 32 on the upper floor. I do. (See Fig. 1d)

【0036】この状態て昇降ビーム44を下降させ、そ
の下降途中で上層階の中間主柱32の下端を、新たに搬
入された中間主柱32の上端に乗載支持せしめるととも
に、荷重を預け、更に下降する昇降ビーム44により梁
仕口32a から解放された状態にある昇降ビーム44の
遊動端と、昇降ブロック41を連結しているノックピン
45を外し、フリーとなった昇降ビーム44を外方向に
約90旋回させる。旋回された昇降ビーム44は、新
たに搬入された中間主柱32の梁仕口32aの領域から
外側方にあるため、昇降ビーム44は最下位の上昇移動
開始準備位置まで降下する。(図1e参照)
In this state, the elevating beam 44 is lowered, and the lower end of the intermediate main column 32 of the upper floor is supported on the upper end of the newly introduced intermediate main column 32 during the descent, and the load is deposited. Further, the floating end of the lifting beam 44 released from the beam connection 32a by the lowering lifting beam 44 and the knock pin 45 connecting the lifting block 41 are removed, and the free lifting beam 44 is moved outward. Turn about 90 degrees . Since the swiveled elevating beam 44 is located outside the region of the beam connection 32a of the newly-loaded intermediate main column 32, the elevating beam 44 descends to the lowest elevating movement start preparation position. (See Fig. 1e)

【0037】そして昇降ビーム44を逆方向に約90
旋回してに戻し、これの遊動端をノックピン45で昇降
ブロック41に結合す。(図1a参照)
Then, the lifting beam 44 is turned back by about 90 degrees in the reverse direction, and its free end is connected to the lifting block 41 by the knock pin 45. (See Fig. 1a)

【0038】図1a〜図1eの作業を扛重装置D’と、
これの挙動に同期する扛重装置Aを用いて繰り返し行う
ことにより、所望階層の建物を構築することができる。
そして全ての扛重装置A、D’を外側方に分解し撤去し
たのち、1階の建築作業を完了させて所要階層の建物構
造体Bが完了する。
The operation shown in FIGS. 1A to 1E is referred to as a lifting device D ′.
By repeatedly using the lifting device A synchronized with this behavior, a building of a desired level can be constructed.
Then, after all the lifting devices A and D 'are disassembled outward and removed, the construction work on the first floor is completed to complete the building structure B on the required level.

【0039】[0039]

【発明の効果】 上述のように本発明の構成によれば、
次のような効果が得られ。
According to the configuration of the present invention as described above,
The following effects are obtained.

【0040】全天候下での作業がなし得られ、天候に左
右されずに工期の大巾 短縮が図れ、高所作業がないた
め安全な施工ができ、資材の落下、飛散などによる不安
がなく、最上階から所要階層に至る各階層の建物躯体を
順次完了させる工法であるため、作業は全て地上階での
施工となり安定した品質の建物が得られ、更に、略完成
された建物躯体の扛重作用点が、全ての外周、中間主柱
近傍の両側梁下面支持によって行われるため、階層が進
むにつれて増加される荷重に充分耐えることができると
ともに、各階層の建物躯体の完了毎に支持梁の歪取り調
整と全ての扛重装置の零点調整制御が行われるため、す
でに完成された建物躯体の扛重による損傷のない中高層
建物の構築が効率よく行えることは勿論のこと。
Work can be performed under all weather conditions, the construction period can be shortened without being affected by the weather, and safe work can be performed because there is no work at high places. for a method to complete the building structures each floor layer extending from the top floor to the required hierarchical order, the work is construction and becomes a stable quality building with all ground floor obtained, further,扛重of building structures which are substantially completed Since the point of action is provided by the support on both sides of the beam on all sides and near the middle main column, it can fully withstand the load that increases as the story progresses, and the support beam is completed each time the building frame of each story is completed. Since the straightening adjustment and zero point adjustment control of all lifting devices are performed, it is of course possible to efficiently construct a mid-to-high-rise building without damage due to the lifting of the already completed building frame.

【0041】扛重装置Aと扛重装置D’を同調させて扛
上することにより、夫々の扛重装置が分担する扛重荷重
が軽減され、扛重装置の小型化が図れるとともに、扛重
装置D’が盛り替え工法可能であることから、扛重装置
D’の高さを建築される1階層分より背低に構成でき
る。
By lifting the lifting device A and the lifting device D 'in synchronism, the lifting load shared by each lifting device is reduced, and the lifting device can be downsized. Since the device D 'can be refilled, the height of the lifting device D' can be configured to be shorter than the height of one level to be built.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 扛重装置D’による本発明工法を示す流れ図
である。
FIG. 1 is a flowchart showing a construction method of the present invention using a lifting device D ′.

【図2】 扛重装置A、D’の配置と主柱、梁の取合関
係を示す平面図である。
FIG. 2 is a plan view showing the arrangement of the lifting devices A and D ′ and the relationship between the main columns and beams.

【図3】 扛重装置D’の平面図である。FIG. 3 is a plan view of a lifting device D ′.

【図4】 図1の一部切欠正面図である。FIG. 4 is a partially cutaway front view of FIG. 1;

【図5】 図1の正面図である。FIG. 5 is a front view of FIG. 1;

【図6】 図1の側面図である。FIG. 6 is a side view of FIG. 1;

【図7】 昇降ビームの別形態を示す扛重装置D’の平
面図である。
FIG. 7 is a plan view of a lifting device D ′ showing another form of the lifting beam.

【図8】 梁受け台の別形態を示す要部の正面図であ
る。
FIG. 8 is a front view of a main part showing another form of the beam support.

【図9】 梁受け台の更に別形態を示す要部の側面図で
ある。
FIG. 9 is a side view of a main part showing still another form of the beam support.

【図10】 扛重装置Aによる建物躯体の構築状態を示
す建物構造体の斜視図である。
FIG. 10 is a perspective view of a building structure showing a building state of the building frame by the lifting device A.

【図11】 扛重装置Aと主柱、梁の取合関係を示す斜
視図である。
FIG. 11 is a perspective view showing an assembling relationship between the lifting device A, the main pillar, and the beam.

【図12】 扛重装置Aの斜視図である。FIG. 12 is a perspective view of a lifting device A.

【図13】 扛重装置Aの内部構造を示す斜視図であ
る。
FIG. 13 is a perspective view showing the internal structure of the lifting device A.

【図14】 扛重装置Aによる建築工法を示す流れ図で
ある。
FIG. 14 is a flowchart showing a construction method using the lifting device A.

【符号の説明】 A 扛重装置 D’ 扛重装置 31 基礎 31a 架台構成体 31c 案内凹溝 32 中間主柱 32a 梁仕口 32b 仮受け柱 33 地中中間主柱 33b ライナー 34 継ぎ部材 35 スプロケット 36 回転伝達体 37 スクリュー軸 38 駆動モータ 39 スプロケット 40 チェン 41 昇降ブロック 41a 案内凸部 42 ナット部材 43 摺動部材 44 昇降ビーム 44a 孔 44b 孔 45 ノックピン 46 カラー 47 梁受け台 48 係合ロック凹部 49 係合ロック凸部 50 梁受け台 51 梁受け台 53 柱間梁[Description of Signs] A Lifting Device D 'Lifting Device 31 Foundation 31a Mount Structure 31c Guide Groove 32 Intermediate Main Column 32a Beam Connection 32b Temporary Receiving Column 33 Underground Intermediate Main Column 33b Liner 34 Splicing Member 35 Sprocket 36 Rotation transmitting body 37 Screw shaft 38 Drive motor 39 Sprocket 40 Chain 41 Elevating block 41a Guide convex part 42 Nut member 43 Sliding member 44 Elevating beam 44a Hole 44b hole 45 Knock pin 46 Collar 47 Beam support 48 Engagement lock concave part 49 Engagement Lock projection 50 Beam support 51 Beam support 53 Beam between columns

───────────────────────────────────────────────────── フロントページの続き (72)発明者 松田 友秋 東京都江東区南砂二丁目6番5号 川崎重 工業株式会社東京事務所内 (72)発明者 石田 公成 東京都江東区南砂二丁目6番5号 川崎重 工業株式会社東京事務所内 (72)発明者 高橋 敬 東京都港区元赤坂一丁目2番7号 鹿島建 設株式会社内 (72)発明者 水谷 亮 東京都港区元赤坂一丁目2番7号 鹿島建 設株式会社内 (72)発明者 喜井 昭捷 東京都港区元赤坂一丁目2番7号 鹿島建 設株式会社内 Fターム(参考) 2E174 CA04 CA17 CA34 CA43 DA02 DA12 DA13 DA51 DA58 DA62 DA63 DA67 EA02  ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Tomoaki Matsuda 2-6-5 Minamisuna, Koto-ku, Tokyo Inside Kawasaki Heavy Industries, Ltd. Tokyo Office (72) Inventor Kosei Ishida 2-6-Minamisuna, Koto-ku, Tokyo No. 5 Kawasaki Shige Kogyo Co., Ltd. Tokyo Office (72) Inventor Takashi Takahashi 1-7-7 Moto Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Ryo Mizutani Ryo Moto Akasaka, Minato-ku, Tokyo 2-7-7 Kashima Construction Co., Ltd. (72) Inventor Akiyoshi Kii 1-2-7 Moto-Akasaka, Minato-ku, Tokyo F-term in Kashima Construction Co., Ltd. 2E174 CA04 CA17 CA34 CA43 DA02 DA12 DA13 DA51 DA58 DA62 DA63 DA67 EA02

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 基礎上において中高層階建物構造物の屋
上階及び最上階を組立てたのち、建物構造体を構成する
外周主柱近傍の両側梁下面を扛重手段(A)の閂にて支
持して扛上し、この扛上により生ずる作業空間部に下層
階を順次組み立てて構築するようにした建物構造体の建
築工法において、 建築構造体を構成する中間主柱を建柱する基礎杭両側の
地中梁上または地層階の主柱両側の梁上に、中間主柱位
置を挟むように2個一組の扛重装置(D’)を配設せし
め、一方、1層階分高さの外周主柱の搬入組立と前後し
て基礎杭上または地層階の主柱上に略1.5層階分の高
さを有する中間主柱を搬入乗載し、この中間主柱および
外周主柱相互間の梁の組立て、天井部材、小梁などを取
付けて建築構造体の屋上階及び最上階を組立てるととも
に、この組立て作業と前後して中間主柱の両側梁下面に
扛重装置(D’)の昇降ビーム(閂)を配設する第1工
程、 扛重手段(A)と同調して、扛重手段(D’)により最
上階層を一層階分高さに満たない高さ分だけ扛上したの
ち、基礎杭または地層階の中間主柱上に短尺の仮受け柱
を乗載するとともに、最上層階を若干降下させ、全荷重
を仮受け柱に預け、昇降ビーム(閂)をフリーにする第
2工程、 フリーとなった扛重手段(D’)の昇降ビーム(閂)と
扛重手段(A)の閂を更に降下させ、扛重手段(D’)の
昇降ビームと梁下面との間に梁受け台を介装する第3工
程、 扛重手段(A)、(D’)により建築構造体を扛上し、
フリーとなった仮受け柱を退避させるとともに、建築構
造体を第1工程時点より1層階分より若干高く扛上した
のち、1層階分の高さをもつ次層階の外周主柱を扛重手
段(A)における施工用ブロック上に、また次層階の中
間主柱を基礎杭または地層階の中間主柱上に搬入設置
し、扛重手段(A)、(D’)の閂、昇降ビーム(閂)
を若干降下して全荷重を各基礎杭または地層階の中間主
柱に預け、前後して次層階の梁を各主柱間に組立てる第
4工程、 フリーとなった扛重手段(A)、(D’)の閂、昇降ビ
ーム(閂)を移動して新たに設置された次層階の梁との
干渉を避けながら最下位まで降下させたのち、昇降ビー
ム(閂)を再び原位置に復帰し、次いで若干量上昇させ
て各主柱両側の梁下面部に臨ませる第5工程、 前記2〜5工程を繰り返し行い、所定階層の建築構造体
を構築して2階以上の扛上ののちに、1,2階間の高さ
に調整した所定長さの外周主柱および中間主柱を基礎杭
上または地層階の主柱上に組立て、各主柱の上部を2階
の各主柱の下端に結合し、中間主柱の下端を基礎杭また
は地層階の主柱と結合する第6工程、 そののちに、扛重装置(A)、(D’)を解体撤去し、
前後して一階層の建築作業を完了させることを特徴とす
る建物構造体の建築工法。
After assembling the top floor and the top floor of a middle- and high-rise building structure on a foundation, the lower surfaces of both side beams near the outer peripheral main pillars constituting the building structure are supported by a bar of lifting means (A). In the construction method of a building structure which is constructed by assembling and constructing lower floors sequentially in the work space generated by the lifting, the foundation piles on which the intermediate main pillars constituting the building structure are built are constructed. A set of two lifting devices (D ') is placed on the underground beam of the building or on the beams on both sides of the main column on the stratum, so as to sandwich the position of the intermediate main column. Before and after the loading and assembling of the outer main column, the intermediate main column having a height of about 1.5 floors is loaded and loaded on the foundation pile or the main column on the formation floor, and the intermediate main column and the outer main column are loaded. While assembling beams between columns, attaching ceiling members, small beams, etc., assembling the rooftop and top floors of the building structure Before and after this assembling work, the first step of arranging the lifting beam (bar) of the lifting device (D ') on the lower surface of the beams on both sides of the intermediate main pillar, in synchronization with the lifting device (A), the lifting device (D ') After lifting the top floor by a height less than the floor height by (D'), a short temporary receiving column is mounted on the foundation pile or the middle main pillar of the formation floor, and the top floor is lifted. The second step of lowering the load slightly, depositing the entire load on the temporary receiving column, and freeing the lifting beam (bar), the lifting beam (bar) and lifting means (A) of the lifting means (D ') that has become free ) Is further lowered, and the third step of interposing a beam support between the lifting beam of the lifting means (D ') and the lower surface of the beam, the lifting means (A) and (D') are used to construct the building structure. Lift your body,
Evacuate the temporary pillars that have become free, lift the building structure slightly higher than the first floor from the first stage, and then move the outer main pillars of the next floor with the height of the first floor. On the construction block in the lifting means (A), the intermediate main pillar of the next floor is loaded and installed on the foundation pile or the intermediate main pillar of the formation floor, and the bar of the lifting means (A) and (D ') is installed. , Lifting beam (bar)
4th process of assembling the beam of the next floor between each main pillar before and after depositing the entire load on each foundation pile or the middle main column of the stratum, and freeing the lifting means (A) , (D '), move the up / down beam (bar) and lower it to the lowest position while avoiding interference with the newly installed beam on the next floor, and then move the up / down beam (bar) to its original position 5th step of raising the floor slightly and facing the lower surface of the beam on both sides of each main column. Repeating the above 2 to 5 steps, constructing a building structure of a predetermined level and lifting the second floor or more After that, an outer main pillar and an intermediate main pillar of a predetermined length adjusted to the height between the first and second floors are assembled on the foundation pile or the main pillar on the stratum floor, and the upper part of each main pillar is placed on each of the second floor. A sixth step in which the lower end of the main main column is connected to the lower end of the main main column and the lower end of the intermediate main column is connected to the main post on the foundation pile or stratum, and then the lifting device (A), (D ') Demolition and removal,
A building construction method for a building structure characterized by completing one-level building work before and after.
【請求項2】 基礎上において中高層階建物構造物の屋
上階及び最上階を組立てたのち、建物構造体を構成する
外周主柱近傍の両側梁下面を扛重手段の(A)の閂にて
支持して扛上し、この扛上により生ずる作業空間部に下
層階を順次組み立てて構築するようにした建物構造体の
建築工法において、 建築構造体を構成する中間主柱を建柱する基礎杭両側の
地中梁上または、地層階の主柱両側の梁上に、中間主柱
位置を挟むように2個一組の扛重装置(D’)を配設せ
しめ、一方、1層階分高さの外周主柱の搬入組立てと前
後して基礎杭上または地層階の主柱に略1.5層階分の
高さを有する中間主柱を搬入乗載し、この中間主柱およ
び外周主柱相互間の梁の組立て、天井部材、小梁などを
取付けて建築構造体の屋上階及び最上階を組立てるとと
もに、この組立て作業と前後して中間主柱の両側梁下面
に扛重装置(D’)の昇降ビーム(閂)を配設する第1
工程、 扛上手段(A)と同調して扛重手段(D’)により最上
階層を一層階分高さを越す高さだけ扛上したのち、基礎
杭上または地層階の中間主柱上に一層階分の高さをもつ
次層階の外周主柱と中間主柱を搬入設置し、扛重装置
(A)、(D’)を若干降下して全荷重を基礎杭または
地層階の中間主柱に預ける第2工程、 フリーとなった扛重手段(D’)の昇降ビーム(閂)と
扛重手段(A)の閂を最下位まで降下させたのち、中間
主柱と外周主柱相互間の梁の組立てを行い、扛重手段
(D’)の昇降ビーム(閂)を中間主柱両側の梁下面部
に臨ませる第3工程、 前記2、3工程を繰り返し行い、所要階層の建築構造体
を構築して2階以上の扛上ののち、1,2階間の高さに
調整した所定長さの外周主柱および中間主柱を基礎杭上
または地層階の中間主柱上に組立て、中間主柱の上端を
2階の中間主柱の下端と結合し、中間主柱の下端を基礎
杭または地層階の主柱と結合する第4工程、 そののちに、扛重装置(A)、(D’)を解体撤去し、
前後して一階層の建築作業を完了させることを特徴とす
る建物構造体の建築工法。
2. After assembling the rooftop floor and the top floor of a middle- and high-rise building structure on a foundation, the lower surfaces of both side beams near the outer peripheral main pillars constituting the building structure are fixed with a bar of lifting means (A). In the construction method of a building structure, which is constructed by assembling and constructing lower floors sequentially in a work space generated by the lifting by supporting and lifting, a foundation pile for constructing an intermediate main pillar constituting the building structure. Two sets of lifting equipment (D ') are placed on the underground beams on both sides or on the beams on both sides of the main column on the stratum, so as to sandwich the position of the intermediate main column. Before and after the loading and assembling of the outer peripheral main pillar having a height, an intermediate main pillar having a height of about 1.5 floors is loaded and loaded on the main pillar on the foundation pile or the stratum floor, and the intermediate main pillar and the outer periphery are loaded. Assembling the beams between the main pillars, attaching ceiling members, small beams, etc., and assembling the rooftop and top floors of the building structure The first to arrange the lifting beam of the assembly operation and 扛重 device on either side beams lower surface of the intermediate main pillar and longitudinal (D ') (obex)
Process: After lifting the uppermost layer by a height exceeding the height of one story by the lifting means (D ') in synchronization with the lifting means (A), place it on the foundation pile or on the middle main pillar of the stratum floor. Load and install the outer main pillars and intermediate main pillars of the next floor with the height of one floor, and lower the lifting devices (A) and (D ') slightly to reduce the total load to the middle of the foundation pile or the middle floor. The second step of depositing on the main column, after lowering the lifting beam (bar) of the lifting device (D ') and the bar of the lifting device (A) to the lowest position, the intermediate main column and the outer main column The third step of assembling the beams between each other and the lifting beams (bars) of the lifting means (D ') facing the lower surfaces of the beams on both sides of the intermediate main column is repeated, and the above-mentioned steps (2) and (3) are repeated. After constructing the building structure and lifting on the second floor or higher, the outer main pillars and intermediate main pillars of the specified length adjusted to the height between the first and second floors are placed on the foundation pile or on the stratum floor. A fourth process of assembling on the intermediate main pillar, connecting the upper end of the intermediate main pillar to the lower end of the intermediate main pillar on the second floor, and connecting the lower end of the intermediate main pillar to the main pillar on the foundation pile or the geological floor, Demolition and removal of lifting equipment (A), (D ')
A building construction method for a building structure characterized by completing one-level building work before and after.
JP00032999A 1999-01-05 1999-01-05 Building construction method Expired - Fee Related JP3398839B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP00032999A JP3398839B2 (en) 1999-01-05 1999-01-05 Building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP00032999A JP3398839B2 (en) 1999-01-05 1999-01-05 Building construction method

Publications (2)

Publication Number Publication Date
JP2000199278A true JP2000199278A (en) 2000-07-18
JP3398839B2 JP3398839B2 (en) 2003-04-21

Family

ID=11470875

Family Applications (1)

Application Number Title Priority Date Filing Date
JP00032999A Expired - Fee Related JP3398839B2 (en) 1999-01-05 1999-01-05 Building construction method

Country Status (1)

Country Link
JP (1) JP3398839B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243926A (en) * 2013-05-13 2013-08-14 中建五局第三建设有限公司 Construction method for hoisting engineering tube well stand pipe of high-rise building
CN109898664A (en) * 2019-02-02 2019-06-18 高继良 A kind of jack-up construction method and its assembled arthitecutral structure for multi-story structure
JP2019210750A (en) * 2018-06-07 2019-12-12 鹿島建設株式会社 Jack-up device, construction method and demolition method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535865B (en) * 2011-12-19 2014-08-20 悉地(北京)国际建筑设计顾问有限公司 Construction method of hexagon screen drum structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243926A (en) * 2013-05-13 2013-08-14 中建五局第三建设有限公司 Construction method for hoisting engineering tube well stand pipe of high-rise building
CN103243926B (en) * 2013-05-13 2015-07-15 中建五局第三建设有限公司 Construction method for hoisting engineering tube well stand pipe of high-rise building
JP2019210750A (en) * 2018-06-07 2019-12-12 鹿島建設株式会社 Jack-up device, construction method and demolition method
JP7072448B2 (en) 2018-06-07 2022-05-20 鹿島建設株式会社 Jack-up device, construction method and dismantling method
CN109898664A (en) * 2019-02-02 2019-06-18 高继良 A kind of jack-up construction method and its assembled arthitecutral structure for multi-story structure

Also Published As

Publication number Publication date
JP3398839B2 (en) 2003-04-21

Similar Documents

Publication Publication Date Title
WO2020185587A1 (en) Vertical slip form construction system with multi-function platform, and method of constructing a building therewith
JP2000199278A (en) Building method for structural body of building
CN108661329A (en) The mounting bracket of prefabricated components, precast wall body and its installation method containing the holder
JP3263782B2 (en) Construction method of building structure and lifting device of building structure
JPH102108A (en) Method for constructing tower-shaped rc structure
JP2884397B2 (en) Construction method of building structure and lifting device of building structure
JPH04161566A (en) Constructing apparatus for large space building
JP2884396B2 (en) Construction method of building structure and lifting device of building structure
JP2754196B2 (en) Lifting equipment for building structures
JP2003119806A (en) Device and method for constructing sidewall of underground tank
JPH0733688B2 (en) Push-up method
JPH0932121A (en) Constructing method of structure and push-up system using constructing method thereof
JP2884398B2 (en) Construction method of building structure and lifting device of building structure
JP2903006B2 (en) Push-up method for large roof
JPH08218628A (en) Construction of roof for cylindrical structure
JP2946372B2 (en) Construction method of structure
CN117364914A (en) Combined structure of steel frame at lower part of upper steel truss and construction method of combined structure
CN116517299A (en) Steel structure modularization construction technology
JPH0733689B2 (en) Push-up method and apparatus
JPH0781323B2 (en) Building construction method
JPH06200626A (en) Jacking-up method for building
JPH03197734A (en) Lift up method by replacement of scaffold body
CN116624660A (en) Temporary fixing and supporting device for large pipeline and temporary supporting method for pipeline
JP2956554B2 (en) Support structure of support and method of changing support
CN115637996A (en) Movable and rotatable large-scale steel formwork device

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees