CN109898429A - A kind of structure and its construction technology reinforced for Bridge Crack - Google Patents

A kind of structure and its construction technology reinforced for Bridge Crack Download PDF

Info

Publication number
CN109898429A
CN109898429A CN201910291668.9A CN201910291668A CN109898429A CN 109898429 A CN109898429 A CN 109898429A CN 201910291668 A CN201910291668 A CN 201910291668A CN 109898429 A CN109898429 A CN 109898429A
Authority
CN
China
Prior art keywords
crack
bridge
steel slab
strengthening
strengthening steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910291668.9A
Other languages
Chinese (zh)
Other versions
CN109898429B (en
Inventor
陈红军
余黎明
李辉
李永荃
冉明
杨建松
吉庆锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Beixin Technology Innovation Consulting Co ltd
Xinjiang Beixin Road and Bridge Group Co Ltd
Original Assignee
Xinjiang Beixin Sifang Engineering Testing And Consulting Co Ltd
Xinjiang Beixin Road and Bridge Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Beixin Sifang Engineering Testing And Consulting Co Ltd, Xinjiang Beixin Road and Bridge Group Co Ltd filed Critical Xinjiang Beixin Sifang Engineering Testing And Consulting Co Ltd
Priority to CN201910291668.9A priority Critical patent/CN109898429B/en
Publication of CN109898429A publication Critical patent/CN109898429A/en
Application granted granted Critical
Publication of CN109898429B publication Critical patent/CN109898429B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The present invention provides a kind of structures and its construction technology reinforced for Bridge Crack, a plurality of step is modified out on the inner wall in crack, it opens up reinforced hole and sets up support frame, filler is poured again, so that having stable support construction in crack, ruggedized construction can combine together with bridge ontology, it can be subjected to various transverse directions, longitudinal stress and do not fall off, so that the internal structure in crack is more firm, sealant is equipped between filler and strengthening steel slab, corrosive substance can be obstructed enter fracture in the ruggedized construction of crack and cause secondary destruction, it is conducive to extend the service life of ruggedized construction, the outer edge of strengthening steel slab mounting groove is opened up apart from crack mouthful > 100mm, it can guarantee that crack sealing part structure is more firm, secondary destruction is not easily caused to be arranged, strengthening steel slab mounting groove outer edge is 3 at a distance from fixed point simultaneously 0~50mm, while fixed reinforce, but also stress more evenly, is able to bear bigger pressure between ruggedized construction and crack.

Description

A kind of structure and its construction technology reinforced for Bridge Crack
Technical field
The present invention relates to bridge maintenance fields, more particularly to a kind of structure reinforced for Bridge Crack and its construction work Skill.
Background technique
Bridge refers generally to be erected in rivers,lakes and seas, the structures for making traffic etc. that can smoothly pass through.It is modern to adapt to The transportation industry of high speed development, bridge be also extended to across mountain stream, unfavorable geology or meet other traffic need and set up make Current more convenient and fast building.
Current existing bridge is largely reinforced concrete structure, since bridge can be subjected to the wind day that drenches with rain for a long time Shine, in addition the weight in use process, hit and naturally expand with heat and contract with cold, can all cause breakage to bridge, and then generation is opened It splits, form crack, this can seriously reduce the load-bearing capacity of bridge, if repaired not in time, crack the more will be expanded the more big, very To the collapsing that will lead to bridge, great security risk and economic loss are caused.
The structures and methods in current existing reinforcement bridge crack simple built reinforcing bar and are poured typically in crack Concrete can not be integrated although this reinforcing mode can temporarily repair the crack on bridge with former bridge structure, The phenomenon that ruggedized construction and the disengaging of bridge ontology will be generated after a period of use, not only it cannot be guaranteed that reinforcing axle casing just It is often used, it can also further expansion crack.
Therefore, a kind of structure and its construction technology reinforced for Bridge Crack is needed, existing highway bridge crack is able to solve Reinforcement means and structure are ineffective for Bridge Crack punishment, and ruggedized construction is easy to fall off, the problem that cannot be fixed for a long time.
Summary of the invention
It is above-mentioned existing to solve the object of the present invention is to provide a kind of structure and its construction technology reinforced for Bridge Crack There are Bridge Crack reinforcement means and structure to punish Bridge Crack ineffective, ruggedized construction is easy to fall off, cannot consolidate for a long time Fixed problem.
To achieve the above object, the present invention provides following schemes:
The present invention provides a kind of structure reinforced for Bridge Crack, including with crannied bridge ontology, the bridge The covering of the crack of ontology mouthful place is fixed with strengthening steel slab, equipped with support frame in the crack of the bridge ontology, support frame as described above and Gap filling between the crack of the bridge ontology has a filler, and the filler covers support frame as described above completely, the filler with Sealant is additionally provided between the strengthening steel slab;
Wherein, it is equipped with strengthening steel slab mounting groove at the crack mouthful of the bridge ontology, the strengthening steel slab installs and fixes In in the strengthening steel slab mounting groove, the crack inner wall finishing of the bridge ontology has several steps, and every step is equal Top is extended to by the crack mouthful bottom of the crack bridge ontology, the bottommost of every step offers corresponding master and adds Solid hole, the side of every layer of step are equipped with transversely strengthening hole, and the plane of every layer of step is equipped with longitudinal reinforcement hole;
Support frame as described above includes main support rod, and the main support rod is plugged in the main reinforced hole, the transversely strengthening Kong Jun is inserted with transversely strengthening bar, and the transversely strengthening bar fixed company of the main support rod corresponding with step where it It connects, the longitudinal reinforcement hole is inserted with longitudinal reinforcement bar, and the transverse direction of the longitudinal reinforcement bar with step where it adds Solid rod is fixedly connected, and is fixedly connected to connecting rod between every two main support rods.
Preferably, the minimum range at the strengthening steel slab mounting groove outer edge crack apart from the bridge ontology mouthful edge ≥100mm。
Preferably, the fixed point of the strengthening steel slab mounting groove and the bridge ontology is apart from the strengthening steel slab mounting groove Outer peripheral distance is 30~50mm.
Preferably, item number >=2 of the step.
Preferably, each layer height of the step is 60~120mm.
Preferably, the depth of the main reinforced hole is 40~100mm.
Preferably, the depth in the transversely strengthening hole and the longitudinal reinforcement hole is 20~40mm.
It is a kind of for Bridge Crack reinforce structure construction technology, the construction technology the following steps are included:
(1) modify crack: by the crack on bridge be trimmed to long and width be all larger than 15cm can working size, in crack Step is modified out on wall, and strengthening steel slab mounting groove is opened up out according to the size in crack mouthful;
(2) fixing support rack: main reinforced hole, transversely strengthening hole and longitudinal reinforcement hole are opened up at the step in crack, will be split Seam is cleaned out, and main support rod, transversely strengthening bar, longitudinal reinforcement bar and connecting rod are connected and fixed by corresponding position;
(3) pour filler: filler is poured in gap in crack, and constantly vibrates, filler pour to strengthening steel slab The bottom surface of mounting groove is concordant;
(4) it is laid with sealant: being laid with sealant in the bottom surface of filler surface and strengthening steel slab mounting groove;
(5) strengthening steel slab is installed: strengthening steel slab is mounted on strengthening steel slab mounting groove and fixation.
Preferably, the filler uses cement concrete, health is needed after molding 4~7 days.
Preferably, the sealant uses epoxy resin glue material, and laying depth is 2~6mm.
The present invention achieves following advantageous effects compared with the existing technology:
1, a kind of structure and its construction technology reinforced for Bridge Crack provided by the invention, is repaired on the inner wall in crack Whole a plurality of step out opens up the reinforced hole of certain depth, the corresponding main support rod of every step, step on every layer of step On reinforced hole in plug reinforcing bar, reinforcing bar stress in reinforced hole is more stable, between reinforcing bar and corresponding reinforcing bar, It is fixedly connected with, is connected and fixed between main support rod bar by connecting rod, then pour and fill out between reinforcing bar and corresponding main support rod Material, so that having stable support construction in crack, ruggedized construction can combine together with bridge ontology, can be subjected to various cross It is not fallen off to, longitudinal stress, so that the internal structure in crack is more firm.
2, a kind of structure and its construction technology reinforced for Bridge Crack provided by the invention, in filler and strengthening steel slab Between be equipped with sealant, corrosive substance can be obstructed enter fracture in the ruggedized construction of crack and cause secondary destruction, favorably In the service life for extending ruggedized construction.
3, a kind of structure and its construction technology reinforced for Bridge Crack provided by the invention, strengthening steel slab mounting groove Outer edge is opened up apart from crack mouthful > 100mm, can guarantee that crack sealing part structure is more firm, and secondary destruction is not easily caused to set Set, at the same the fixed point of strengthening steel slab mounting groove and bridge ontology apart from the outer peripheral distance of strengthening steel slab mounting groove be 30~ 50mm, while fixed reinforce, but also stress more evenly, is able to bear bigger pressure between ruggedized construction and crack.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without any creative labor, can also be according to these attached drawings Obtain other attached drawings.
Fig. 1 is that ruggedized construction is longitudinal in a kind of structure and its construction technology reinforced for Bridge Crack provided by the invention Cross-sectional view;
Fig. 2 is that supporting frame part is bowed in a kind of structure and its construction technology reinforced for Bridge Crack provided by the invention View;
Fig. 3 is construction technology process in a kind of structure and its construction technology reinforced for Bridge Crack provided by the invention Figure;
In figure: 1: bridge ontology, 11: step, 111: transversely strengthening hole, 112: longitudinal reinforcement hole, 12: strengthening steel slab installation Slot, 13: main reinforced hole, 2: support frame, 21: main support rod, 22: transversely strengthening bar, 23: longitudinal reinforcement bar, 24: connecting rod, 3: Strengthening steel slab, 4: filler, 5: sealant.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
The object of the present invention is to provide a kind of structures and its construction technology reinforced for Bridge Crack, by crack Setting support frame simultaneously pour filler, covering strengthening steel slab, Bridge Crack is reinforced it is firmer, to solve existing highway bridge crack Reinforcement means and structure are ineffective for Bridge Crack punishment, and ruggedized construction is easy to fall off, the problem that cannot be fixed for a long time.
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing and specific real Applying mode, the present invention is described in further detail.
Embodiment 1:
The present embodiment provides a kind of structures reinforced for Bridge Crack, and as depicted in figs. 1 and 2, ruggedized construction includes band Crannied bridge ontology 1, the crack of bridge ontology 1 mouthful place, which covers, is fixed with strengthening steel slab 3, sets in the crack of bridge ontology 1 There is support frame 2, the gap filling between support frame 2 and the crack of bridge ontology 1 has filler 4, and filler 4 covers support frame 2 completely, Sealant 5 is additionally provided between filler 4 and strengthening steel slab 3.
Specifically, the crack mouthful of bridge ontology 1 offers strengthening steel slab mounting groove 12,12 outer edge of strengthening steel slab mounting groove The minimum range at the crack mouthful edge apart from bridge ontology 1 is 120mm, and strengthening steel slab 3 is mounted and fixed to reinforce by screw In steel plate mounting groove 12, screw is 40mm, the crack inner wall of bridge ontology 1 apart from the outer peripheral distance of strengthening steel slab mounting groove 12 Finishing has 5 steps 11, and every step 11 extends to top by the crack mouthful bottom of crack bridge ontology 1, step 11 it is every One layer height is controlled in 60mm, and the bottommost of every step 11 offers corresponding main reinforced hole 13, the depth of main reinforced hole 13 For 50mm, diameter 12mm, the side of every layer of step 11 is equipped with transversely strengthening hole 111, and the plane of every layer of step 11 is equipped with The depth in longitudinal reinforcement hole 112, transversely strengthening hole 111 and longitudinal reinforcement hole 112 is 30mm, diameter 8mm.
Further, support frame 2 includes main support rod 21, and main support rod 21 selects 10mm reinforcing bar, and is plugged in main reinforcing In hole 13, transversely strengthening hole 111 is inserted with transversely strengthening bar 22, and transversely strengthening bar 22 selects 6mm reinforcing bar, and transversely strengthening bar 22 are fixedly connected with the corresponding main support rod 21 of step where it by tying up silk, and longitudinal reinforcement hole 112 is inserted with longitudinal direction Reinforcing bar 23, longitudinal reinforcement bar 23 select 6mm reinforcing bar, and transversely strengthening bar 22 of the longitudinal reinforcement bar 23 with step where it passes through It ties up silk to be fixedly connected, is fixedly connected with connecting rod 24 by tying up silk between every two main support rods 21.
The construction technology of the above-mentioned structure reinforced for Bridge Crack uses electric pick counterincision as shown in Figure 1,2 and 3 first Seam is modified, and the size for work is modified out in crack, 5 steps 11, every layer of height of step 11 are modified out in crack Degree control opens up strengthening steel slab mounting groove 12,12 outer edge of strengthening steel slab mounting groove and crack around crack mouthful in 60mm The minimum range at mouth edge is 120mm, connecting hole is opened up on strengthening steel slab mounting groove 12 using drill, connecting hole distance adds It Gu 12 outer edge of steel plate mounting groove is 40mm, can guarantee that crack sealing part structure is more firm in this way, not easily cause secondary broken Bad setting, while fixed reinforce, but also stress more evenly, is able to bear bigger pressure between ruggedized construction and crack Power.
Further, main reinforced hole 13, transversely strengthening hole 111 and longitudinal reinforcement hole 112 are bored in crack using drill, Each main reinforced hole 13 is in the bottommost of every step 11, diameter 12mm, depth 50mm, each transversely strengthening hole 111 In the center of every layer of step side, diameter 8mm, depth 30mm, reinforced hole 112 is in every layer of step plane longitudinally in each Center, support that diameter 8mm, depth 30mm, in this way drilling enable support frame 2 to consolidate crack and solid It is fixed, and will not fracture destroy again, cleared up using hair dryer fracture, blowout dust, residue etc. avoid subsequent reinforcement It is the entrance for having sundries, material needed for ready for reinforcing crack selects 10mm reinforcing bar as main support rod 21,6mm reinforcing bar conduct Transversely strengthening bar 22 and longitudinal reinforcement bar 23, and reinforcing bar is cut into suitable length according to the size in crack, by main support rod 21 It is inserted into main reinforced hole 13, transversely strengthening bar 22 is inserted into transversely strengthening hole 111 and is fixed on main support by tying up silk On bar 21, longitudinal reinforcement bar 23 is inserted into longitudinal reinforcement hole 112 and is fixed on every transversely strengthening bar 22 by tying up silk, The connecting rod 24 that appropriate length is chosen further according to the position of 5 main support rods 21, is fixed on every two by tying up silk for connecting rod 24 Between root main support rod 21, such support frame 2 just sets up completion, sets up support frame in this way and makes have stable support in crack Structure.
Further, it is poured onto cement concrete as filler 4 in the crack for having set up support frame 2, during which with vibration It smashes device constantly to vibrate, the air being discharged in concrete simultaneously makes concrete enter the every nook and cranny in crack, more steps up in crack It is close, until concrete is concordant with the bottom surface of strengthening steel slab mounting groove 12, watering health 4 days is carried out after concrete forms completely, So that concrete and support frame are more firm in crack, ruggedized construction can combine together with bridge ontology, can be subjected to each It plants stress laterally, longitudinal and does not fall off, so that the internal structure in crack is more firm.
Finally, being laid with one layer of sealant 5 on the bottom surface of molding concrete surface and strengthening steel slab mounting groove 12, select Epoxide-resin glue avoids foreign object from corroding crack and damages, will reinforce steel after glue is dry as sealing material, laying depth 3mm Plate 3 is mounted in strengthening steel slab mounting groove 12, is inserted into expansion bolt in the connecting hole of strengthening steel slab mounting groove 12, will reinforce steel Plate 3 is fixed on bridge ontology 1, completes the reinforcing of Bridge Crack.
Invention applies a specific example illustrates the principle and implementation of the invention, above embodiments are said It is bright to be merely used to help understand method and its core concept of the invention;At the same time, for those skilled in the art, foundation Thought of the invention, there will be changes in the specific implementation manner and application range.To sum up, the content of the present specification should not manage Solution is limitation of the present invention.

Claims (10)

1. a kind of structure reinforced for Bridge Crack, including with crannied bridge ontology (1), it is characterised in that: the bridge It covers and is fixed with strengthening steel slab (3) at the crack mouthful of beam ontology (1), support frame is equipped in the crack of the bridge ontology (1) (2), the gap filling between support frame as described above (2) and the crack of the bridge ontology (1) has filler (4), and the filler (4) is complete It is complete to cover support frame as described above (2), sealant (5) are additionally provided between the filler (4) and the strengthening steel slab (3);
Wherein, strengthening steel slab mounting groove (12) are equipped at the crack mouthful of the bridge ontology (1), strengthening steel slab (3) installation And be fixed in the strengthening steel slab mounting groove (12), the crack inner wall finishing of the bridge ontology (1) has several steps (11), every step (11) extends to top by the crack mouthful bottom of the crack bridge ontology (1), and every described The bottommost of rank (11) offers corresponding main reinforced hole (13), and the side of every layer of step (11) is equipped with transversely strengthening hole (111), the plane of every layer of step (11) is equipped with longitudinal reinforcement hole (112);
Support frame as described above (2) includes main support rod (21), and the main support rod (21) is plugged in the main reinforced hole (13), institute Transversely strengthening hole (111) is stated to be inserted with transversely strengthening bar (22), and the transversely strengthening bar (22) with it where step The corresponding main support rod (21) is fixedly connected, and the longitudinal reinforcement hole (112) is inserted with longitudinal reinforcement bar (23), described Longitudinal reinforcement bar (23) is fixedly connected with the transversely strengthening bar (22) of step where it, every two main support rods (21) connecting rod (24) are fixedly connected between.
2. a kind of structure reinforced for Bridge Crack according to claim 1, it is characterised in that: the strengthening steel slab peace Minimum range >=the 100mm at tankage (12) the outer edge crack apart from the bridge ontology (1) mouthful edge.
3. a kind of structure reinforced for Bridge Crack according to claim 2, it is characterised in that: the strengthening steel slab peace The fixed point of tankage (12) and the bridge ontology (1) apart from the outer peripheral distance of the strengthening steel slab mounting groove (12) be 30~ 50mm。
4. a kind of structure reinforced for Bridge Crack according to claim 1, it is characterised in that: the step (11) Item number >=2.
5. a kind of structure reinforced for Bridge Crack according to claim 1, it is characterised in that: the step (11) Each layer height is 60~120mm.
6. a kind of structure reinforced for Bridge Crack according to claim 1, it is characterised in that: the main reinforced hole (13) depth is 40~100mm.
7. a kind of structure reinforced for Bridge Crack according to claim 1, it is characterised in that: the transversely strengthening hole (111) and the depth in the longitudinal reinforcement hole (112) is 20~40mm.
8. a kind of construction technology of the structure reinforced for Bridge Crack as described in claim 1~7 is any, feature exist In: the construction technology the following steps are included:
(1) modify crack: by the crack on bridge be trimmed to long and width be all larger than 15cm can working size, on the inner wall of crack Step is modified out, and strengthening steel slab mounting groove is opened up out according to the size in crack mouthful;
(2) fixing support rack: opening up main reinforced hole, transversely strengthening hole and longitudinal reinforcement hole at the step in crack, and crack is clear Reason is clean, and main support rod, transversely strengthening bar, longitudinal reinforcement bar and connecting rod are connected and fixed by corresponding position;
(3) pour filler: filler is poured in the gap in crack, and constantly vibrates, and filler is poured to strengthening steel slab and installed The bottom surface of slot is concordant;
(4) it is laid with sealant: being laid with sealant in the bottom surface of filler surface and strengthening steel slab mounting groove;
(5) strengthening steel slab is installed: strengthening steel slab is mounted on strengthening steel slab mounting groove and fixation.
9. a kind of construction technology of structure reinforced for Bridge Crack according to claim 8, it is characterised in that: described Filler uses cement concrete, health is needed after molding 4~7 days.
10. a kind of construction technology of structure reinforced for Bridge Crack according to claim 8, it is characterised in that: institute Sealant is stated using epoxy resin glue material, laying depth is 2~6mm.
CN201910291668.9A 2019-04-12 2019-04-12 Structure for reinforcing bridge cracks and construction process thereof Active CN109898429B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910291668.9A CN109898429B (en) 2019-04-12 2019-04-12 Structure for reinforcing bridge cracks and construction process thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910291668.9A CN109898429B (en) 2019-04-12 2019-04-12 Structure for reinforcing bridge cracks and construction process thereof

Publications (2)

Publication Number Publication Date
CN109898429A true CN109898429A (en) 2019-06-18
CN109898429B CN109898429B (en) 2021-06-08

Family

ID=66955700

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910291668.9A Active CN109898429B (en) 2019-04-12 2019-04-12 Structure for reinforcing bridge cracks and construction process thereof

Country Status (1)

Country Link
CN (1) CN109898429B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110735403A (en) * 2019-10-09 2020-01-31 北京夏都水利工程有限公司 Repair structure for bridge pier cracks and reinforcing method thereof
CN113356087A (en) * 2021-06-01 2021-09-07 中铁十九局集团有限公司 Bridge crack repairing method
CN113882213A (en) * 2021-10-09 2022-01-04 宁波市天马生态建设有限公司 Highway damage repairing method
CN114892466A (en) * 2022-05-24 2022-08-12 新疆北新科技创新咨询有限公司 Road gap filling and repairing structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101258180B1 (en) * 2011-01-28 2013-05-02 한국도로공사 Bridge expansion joint repairing method
CN206173821U (en) * 2016-11-09 2017-05-17 牛洪全 Road and bridge crack reinforced structure
CN206553864U (en) * 2017-01-19 2017-10-13 徐其亮 A kind of road and bridge crack bracing means
CN207295506U (en) * 2017-09-19 2018-05-01 南京明阳建筑工程有限公司 A kind of road and bridge crack bracing means
CN207295508U (en) * 2017-10-12 2018-05-01 樊新波 Road and bridge crack ruggedized construction
CN208266618U (en) * 2018-06-08 2018-12-21 中建八局第二建设有限公司 A kind of road and bridge crack construction reinforcing connection structure
CN208649865U (en) * 2018-07-03 2019-03-26 杨凌职业技术学院 A kind of road and bridge crack ruggedized construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101258180B1 (en) * 2011-01-28 2013-05-02 한국도로공사 Bridge expansion joint repairing method
CN206173821U (en) * 2016-11-09 2017-05-17 牛洪全 Road and bridge crack reinforced structure
CN206553864U (en) * 2017-01-19 2017-10-13 徐其亮 A kind of road and bridge crack bracing means
CN207295506U (en) * 2017-09-19 2018-05-01 南京明阳建筑工程有限公司 A kind of road and bridge crack bracing means
CN207295508U (en) * 2017-10-12 2018-05-01 樊新波 Road and bridge crack ruggedized construction
CN208266618U (en) * 2018-06-08 2018-12-21 中建八局第二建设有限公司 A kind of road and bridge crack construction reinforcing connection structure
CN208649865U (en) * 2018-07-03 2019-03-26 杨凌职业技术学院 A kind of road and bridge crack ruggedized construction

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110735403A (en) * 2019-10-09 2020-01-31 北京夏都水利工程有限公司 Repair structure for bridge pier cracks and reinforcing method thereof
CN110735403B (en) * 2019-10-09 2021-03-02 北京夏都水利工程有限公司 Bridge pier crack repairing structure and reinforcing method thereof
CN113356087A (en) * 2021-06-01 2021-09-07 中铁十九局集团有限公司 Bridge crack repairing method
CN113882213A (en) * 2021-10-09 2022-01-04 宁波市天马生态建设有限公司 Highway damage repairing method
CN114892466A (en) * 2022-05-24 2022-08-12 新疆北新科技创新咨询有限公司 Road gap filling and repairing structure
CN114892466B (en) * 2022-05-24 2023-10-31 新疆北新科技创新咨询有限公司 Road gap filling and repairing structure

Also Published As

Publication number Publication date
CN109898429B (en) 2021-06-08

Similar Documents

Publication Publication Date Title
CN109898429A (en) A kind of structure and its construction technology reinforced for Bridge Crack
CN106801517B (en) External reinforcing and reinforcing method for school shed with prefabricated porous plate brick mixed structure
CN101949135B (en) Transverse anchorage system outside hollow slab bridge body and construction process thereof
CN105484151B (en) The construction and its construction method connected between a kind of enhancing precast concrete segment
CN104675141A (en) FRP (Fiber Reinforced Plastic) pipe confined cement based composite material reinforced pier column structure
CN101294423A (en) Construction method for embedding thermal insulation in concrete structure exterior wall surface
CN207512622U (en) A kind of road and bridge crack ruggedized construction
CN102839601A (en) Fixed connection structure for steel pier column and cushion cap of portal rigid frame overbridge and construction method of fixed connection structure
CN110821156A (en) Sinking type toilet hanging die structure and construction method thereof
CN109972538B (en) Steel plate inner filling material combined reinforced concrete bridge structure and construction technology
CN108517793A (en) A kind of combination T beam bridges assembled lateral connection ruggedized construction and its reinforcement means
CN108086081A (en) A kind of road maintenance construction method
CN110080454A (en) LPM light filling body Construction of Cast-in-situ Concrete Hollow
CN103291082A (en) Wood beam reinforcing body external pre-stress construction method
CN110905074A (en) Independent node assembly type frame structure and construction method
CN107237492A (en) The installation method of sizing cylindrical form
CN105507109A (en) Damaged concrete pavement panel reinforcing structure and method
CN206706844U (en) A kind of alter-pouring strips mould plate installs construction
CN110878641B (en) Reinforcing structure adopting superimposed hollow floor slab grid system and new construction method
CN111593888A (en) Installation control system and installation construction method for cast-in-situ concrete hollow floor system combined plastic mold box
CN105064160B (en) A kind of concrete prepackage road of High anti bending strength
CN208122041U (en) A kind of IPS Cast-in-place concrete shear wall structure of self-heat preservation system system
CN105507110A (en) Reinforcing structure and method for damaged concrete pavement panel
CN206279441U (en) A kind of high speed railway box beam bridge floor pre-fabricated electric cables groove
CN212336719U (en) Sinking type toilet hanging mould structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: Floor 16-17, block a, Yingke Plaza, 217 Gaoxin street, Gaoxin District, Urumqi, Xinjiang Uygur Autonomous Region 830011

Patentee after: XINJIANG BEIXIN ROAD & BRIDGE GROUP Co.,Ltd.

Patentee after: Xinjiang Beixin technology innovation Consulting Co.,Ltd.

Address before: Floor 16-17, block a, Yingke Plaza, 217 Gaoxin street, Gaoxin District, Urumqi, Xinjiang Uygur Autonomous Region 830011

Patentee before: XINJIANG BEIXIN ROAD & BRIDGE GROUP Co.,Ltd.

Patentee before: XINJIANG BEIXIN SIFANG ENGINEERING TESTING CONSULTING Co.,Ltd.

CP01 Change in the name or title of a patent holder