CN109868785A - A kind of mixing dam body permeable ecology makes beach engineering - Google Patents

A kind of mixing dam body permeable ecology makes beach engineering Download PDF

Info

Publication number
CN109868785A
CN109868785A CN201910266356.2A CN201910266356A CN109868785A CN 109868785 A CN109868785 A CN 109868785A CN 201910266356 A CN201910266356 A CN 201910266356A CN 109868785 A CN109868785 A CN 109868785A
Authority
CN
China
Prior art keywords
groynes
beach
dike
longitudinal dike
longitudinal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910266356.2A
Other languages
Chinese (zh)
Inventor
刘万利
刘晓菲
张华庆
张明进
刘鹏飞
李华国
朱玉德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Research Institute for Water Transport Engineering MOT
Original Assignee
Tianjin Research Institute for Water Transport Engineering MOT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Research Institute for Water Transport Engineering MOT filed Critical Tianjin Research Institute for Water Transport Engineering MOT
Priority to CN201910266356.2A priority Critical patent/CN109868785A/en
Publication of CN109868785A publication Critical patent/CN109868785A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins

Landscapes

  • Revetment (AREA)

Abstract

The invention discloses a kind of mixing dam body permeable ecologies to make beach engineering, the engineering installation is in channel bar and secondary channel upstream, fourth longitudinal dike including fair current setting and the groynes of fourth longitudinal dike upstream is set, the length of the groynes is less than the length of the vertical embankment section of the fourth longitudinal dike, flowing hole is designed on the fourth longitudinal dike and the groynes, it is equipped with area II of back-silting between the fourth longitudinal dike and the groynes, area I of back-silting is equipped with after the dam body of the fourth longitudinal dike.The present invention uses combined type permeable dike group structure, both can also slow down flow rate of water flow with overcurrent, and be conducive to the siltation of silt around the body of beach, makes beach effect with good;Using combined type permeable dike group structure, so that the velocity field on point bar periphery becomes rich and varied, existence is provided for water plant, aquatic meiofauna and the microorganism around the body of beach, inhabites, lay eggs, the suitable space of forage.During making beach, the aquatic ecological environment around the body of beach can be more further enriched.

Description

A kind of mixing dam body permeable ecology makes beach engineering
Technical field
The present invention relates to one kind to make beach engineering, and especially a kind of mixing dam body permeable ecology makes beach engineering.
Background technique
According to the correlation of beach body and riverbank, beach body can be summarized as three types: point bar, channel bar and the continent beach Tou Di. Point bar is to depend on a bank, the beach body substantially in the same direction or little the angle of cut with water flow.The essential characteristic of point bar are as follows: beach body is usually located at slow Area is flowed, straight relax in river is distributed in.Beach body is connected with close, to have semi-detached (there are string ditches) with riverbank.Channel bar is Relatively independent underwater siltation body.The essential characteristic of channel bar are as follows: be normally at and relax in river, what is had is more stable, and some is not Stablize.Stablize channel bar and is normally at non-mainstream area, it is short gentle, it is more complete;Unstable channel bar be normally at the variation of big vast low water compared with Big main stream line fluctuation zone.The continent beach Tou Di is the underwater extension of middle bar continent head.The essential characteristic on the continent beach Tou Di are as follows: be located at Diffusion region is shunted, end slope is relatively slow, and tail portion is steeper, is in front-low-rear-high shape.Beach body is connected with close, some half points with continent body From (string ditch), the continent beach Tou Di form is related to the differentiation of two branchs of a river, and in general, which branch of a river the low beachhead portion in continent is biased to, which branch of a river It tends to fail.Making beach is to take certain measure, promotes sediment siltation around the body of beach, and then mould good beach volume morphing.
Silt rush silt is referred to and makes to be transported in the form of bed load and suspended load by boundary condition, the dynamic condition etc. for changing water flow Dynamic silt is converted to the bed material load stationary in bed surface.For engineering viewpoint, promote silt erosion control refer to by build groynes, The entities building such as longitudinal dike, or build pile, set up wire netting, the permeable structures such as flexible floating curtain of jettisoninging, and planted on beach face Water plant is planted, to change the dynamic condition of water flow, sediment movement, makes the reduced velocity flow of water flow or forms reflux, silt is made to exist Bottom falls silt with aggradation bed surface, to protect the basis of beach face and various hydraulic structures from current scour.
Interior korneforos promotees silt erosion control technology and is broadly divided into 3 major class by the pattern of works: the impermeable water type of entity, the ecotype and its His novel structural shape.The impermeable water type of entity, which promotees silt erosion control technology, mainly dykes and dams (including groynes, longitudinal dike, dam group, cofferdam) And thin plate, application of this kind of technology in China is relatively early and very extensive, and construction experience is mature, and it is obvious to promote silt erosion control effect.It is raw State type promotees silt erosion control technology and refers in seashore or shallow water bottom planting aquatic plants, stops water flow and mud with its flourishing rhizome Sand, the technology utilize ecological organization's function, water flow are made to slow down naturally, and silt falls silt and stablizes, persistently.In recent years, although in life State, which promotees to become silted up, to be made in beach and possesses some special knowledge, but the technology that can promote and apply or very limited, as country is to inland river ecological, environmental protective Demand is more and more, and urgent need develops ecology that is novel and being rapidly and effectively applied to cruiseway and makes beach engineering.
Summary of the invention
The present invention is to solve technical problem present in well-known technique and provide in one kind can be rapidly and effectively applied to The mixing dam body permeable ecology in river navigation channel makes beach engineering.
The technical scheme adopted by the present invention to solve the technical problems existing in the known art is that a kind of mixing dam body is saturating Water type ecology makes beach engineering, and the engineering installation is in channel bar and secondary channel upstream, and fourth longitudinal dike and setting including fair current setting are in institute The groynes of fourth longitudinal dike upstream is stated, the length of the groynes is less than the length of the vertical embankment section of the fourth longitudinal dike, in the fourth longitudinal dike It is designed with flowing hole on the groynes, area II of back-silting is equipped between the fourth longitudinal dike and the groynes, in the fourth longitudinal dike Dam body after be equipped with and back-silt area I.
The groynes at least 2, all groynes are spaced apart, and are equipped with and are back-silted between two adjacent groynes Area III.
The groynes has 2~5 groups, and every group includes at least two, the equal length of every group of groynes, and two adjacent groups groynes is close The fourth longitudinal dike it is longer, be equipped with area of back-silting between the two neighboring groynes between two adjacent groups groynes and in every group of groynes Ⅳ。
The length of the groynes is 80~100m, and the diameter of the flowing hole is 8~10m.
The advantages and positive effects of the present invention are: one) use combined type permeable dike group structure, both can with overcurrent, Flow rate of water flow can be slowed down, be conducive to the siltation of silt around the body of beach, make beach effect with good;Two) saturating using combined type Dam group structure, so that the velocity field on point bar periphery becomes rich and varied, for the water plant around the body of beach, aquatic meiofauna It is provided with microorganism and survives, inhabites, laying eggs, the suitable space of forage.During making beach, can more further it enrich Aquatic ecological environment around the body of beach.Therefore the present invention can be rapidly and effectively applied to cruiseway.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the embodiment of the present invention 1;
Fig. 2 is the structural schematic diagram of the embodiment of the present invention 2.
In figure: 1, groynes;2, fourth longitudinal dike;3-1, area I of back-silting;3-2, area II of back-silting;3-3, area III of back-silting;3-4, area of back-silting Ⅳ;4, flowing hole;5, channel bar;6, secondary channel.
Specific embodiment
In order to further understand the content, features and effects of the present invention, the following examples are hereby given, and cooperate attached drawing Detailed description are as follows:
Fig. 1 and Fig. 2 are please referred to, in order to form low beach in the upstream of channel bar 5, inventive concept of the invention is: in 5 He of channel bar The upstream of secondary channel 6, which promotees to become silted up using permeable mixed dam group, makes beach, and concrete scheme includes fourth longitudinal dike 2 and the setting of fair current setting Groynes 1 in 2 upstream of fourth longitudinal dike, the length of the groynes 2 is less than the length of the vertical embankment section of the fourth longitudinal dike 2, in institute It states and is designed with flowing hole 4 on fourth longitudinal dike 2 and the groynes 1, area II of back-silting is equipped between the fourth longitudinal dike 2 and the groynes 1 3-2 is equipped with I 3-1 of area that back-silts after the dam body of the fourth longitudinal dike 2.
The length of above-mentioned groynes 1 and fourth longitudinal dike 2 determines that the spacing between dam body is big according to beach body according to the river width in river Small determination.It is 80~100m that the present invention, which recommends the length of the groynes 1, and the diameter of the flowing hole 4 is 8~10m.
Embodiment 1:
Referring to Fig. 1, above-mentioned groynes 1 at least 2, all groynes 1 are spaced apart, two adjacent groynes III 3-3 of area that back-silts is equipped between 1.
Embodiment 2:
Referring to Fig. 2, the groynes 1 has 2~5 groups, every group includes at least two, the equal length of every group of groynes, adjacent two The two neighboring groynes 1 of the group groynes close to the longer of the fourth longitudinal dike 2, between two adjacent groups groynes and in every group of groynes Between be equipped with IV 3-4 of area that back-silts.
Although the preferred embodiment of the present invention is described above in conjunction with attached drawing, the invention is not limited to upper The specific embodiment stated, the above mentioned embodiment is only schematical, be not it is restrictive, this field it is common Technical staff under the inspiration of the present invention, in the case where not departing from present inventive concept and scope of the claimed protection, goes back Many forms can be made, within these are all belonged to the scope of protection of the present invention.

Claims (4)

1. a kind of mixing dam body permeable ecology makes beach engineering, which is characterized in that the engineering installation is in channel bar and secondary channel upstream, packet It includes the fourth longitudinal dike of fair current setting and the groynes of fourth longitudinal dike upstream is set, the length of the groynes is less than the fourth longitudinal dike The length of vertical embankment section, is designed with flowing hole on the fourth longitudinal dike and the groynes, in the fourth longitudinal dike and the groynes Between be equipped with and back-silt area II, area I of back-silting is equipped with after the dam body of the fourth longitudinal dike.
2. mixing dam body permeable ecology according to claim 1 makes beach engineering, which is characterized in that the groynes is at least 2, all groynes are spaced apart, and area III of back-silting is equipped between two adjacent groynes.
3. mixing dam body permeable ecology according to claim 1 makes beach engineering, which is characterized in that the groynes has 2~5 Group, every group includes at least two, and the equal length of every group of groynes, two adjacent groups groynes is longer close to the fourth longitudinal dike, and adjacent two Area IV of back-silting is equipped between two neighboring groynes between group groynes and in every group of groynes.
4. mixing dam body permeable ecology according to claim 1 makes beach engineering, which is characterized in that the length of the groynes For 80~100m, the diameter of the flowing hole is 8~10m.
CN201910266356.2A 2019-04-03 2019-04-03 A kind of mixing dam body permeable ecology makes beach engineering Pending CN109868785A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910266356.2A CN109868785A (en) 2019-04-03 2019-04-03 A kind of mixing dam body permeable ecology makes beach engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910266356.2A CN109868785A (en) 2019-04-03 2019-04-03 A kind of mixing dam body permeable ecology makes beach engineering

Publications (1)

Publication Number Publication Date
CN109868785A true CN109868785A (en) 2019-06-11

Family

ID=66921915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910266356.2A Pending CN109868785A (en) 2019-04-03 2019-04-03 A kind of mixing dam body permeable ecology makes beach engineering

Country Status (1)

Country Link
CN (1) CN109868785A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111996994A (en) * 2020-08-31 2020-11-27 交通运输部天津水运工程科学研究所 Ecological beach building engineering
CN114718007A (en) * 2022-05-07 2022-07-08 交通运输部天津水运工程科学研究所 Ecological beach construction method for low beach

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1103846A (en) * 1954-07-06 1955-11-07 Improvement of the groynes to protect the coast against erosion
SU1717704A1 (en) * 1989-09-22 1992-03-07 Kozhin Yurij P Spur dike block
CN102220747A (en) * 2011-02-23 2011-10-19 河海大学 Combined type water-purifying spur dike group system for heavily polluted rivers
CN104153320A (en) * 2014-07-24 2014-11-19 重庆交通大学 Method for regulating pebble shoal in intensified low-flow branching layout
CN206289584U (en) * 2016-11-25 2017-06-30 陆永明 A kind of sandy riverbed Fen Chaduan shoals waterway regulation groynes structures of alluvial stream
CN107119626A (en) * 2017-04-12 2017-09-01 重庆交通大学 A kind of ecological, environmental protective permeable spur structure
CN108374385A (en) * 2018-03-30 2018-08-07 上海交通大学 A kind of water conservancy diversion of board plug type with holes, sediment trapping promote silt hydraulic structure and building method
CN108612041A (en) * 2018-07-05 2018-10-02 交通运输部天津水运工程科学研究所 Anti-impact ecotype groynes
CN209873699U (en) * 2019-04-03 2019-12-31 交通运输部天津水运工程科学研究所 Water-permeable ecological beach building engineering for mixed dam body

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1103846A (en) * 1954-07-06 1955-11-07 Improvement of the groynes to protect the coast against erosion
SU1717704A1 (en) * 1989-09-22 1992-03-07 Kozhin Yurij P Spur dike block
CN102220747A (en) * 2011-02-23 2011-10-19 河海大学 Combined type water-purifying spur dike group system for heavily polluted rivers
CN104153320A (en) * 2014-07-24 2014-11-19 重庆交通大学 Method for regulating pebble shoal in intensified low-flow branching layout
CN206289584U (en) * 2016-11-25 2017-06-30 陆永明 A kind of sandy riverbed Fen Chaduan shoals waterway regulation groynes structures of alluvial stream
CN107119626A (en) * 2017-04-12 2017-09-01 重庆交通大学 A kind of ecological, environmental protective permeable spur structure
CN108374385A (en) * 2018-03-30 2018-08-07 上海交通大学 A kind of water conservancy diversion of board plug type with holes, sediment trapping promote silt hydraulic structure and building method
CN108612041A (en) * 2018-07-05 2018-10-02 交通运输部天津水运工程科学研究所 Anti-impact ecotype groynes
CN209873699U (en) * 2019-04-03 2019-12-31 交通运输部天津水运工程科学研究所 Water-permeable ecological beach building engineering for mixed dam body

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈晓云: "浅谈川江过渡段浅滩整治中丁坝、顺坝的作用与布置", 水运工程, no. 2, pages 21 - 25 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111996994A (en) * 2020-08-31 2020-11-27 交通运输部天津水运工程科学研究所 Ecological beach building engineering
CN114718007A (en) * 2022-05-07 2022-07-08 交通运输部天津水运工程科学研究所 Ecological beach construction method for low beach

Similar Documents

Publication Publication Date Title
CN104695377A (en) Winding form construction method for small-and-medium-sized linear riverways
CN111285470A (en) Riverway bypass water purification wetland system
CN1318702C (en) Installation for trapping sediment from riverbed and seabed promoting siltation and erosion protection
CN109868785A (en) A kind of mixing dam body permeable ecology makes beach engineering
CN110258437A (en) The construction method of cruiseway engineering Mesichthyes habitat
CN209873699U (en) Water-permeable ecological beach building engineering for mixed dam body
CN102561260A (en) Water-permeable waterway improvement spur dike
CN109338987A (en) Inland river eco-river control groynes group
CN109797704A (en) A kind of mixed type ecology makes beach engineering
CN103306241B (en) Watercourse and rubber dam water storage system
CN109295915A (en) The riverbed naturalization remodeling method in a set of wide shallow river
CN209307945U (en) Inland river eco-river control groynes group
CN109778774A (en) A kind of permeable spur structure
CN212200277U (en) Ecological bank protection for hydraulic engineering
CN215715111U (en) Be suitable for and found bottom hole type fishway view weir structure that falls
CN208055980U (en) A kind of permeable erosion control wall construction of hydraulic engineering
CN212026132U (en) Hydraulic engineering protection buffering slope
CN209429047U (en) The water discharge tunnel makeup of the imports for ditch water process
CN209873700U (en) Mixed type ecological beach building engineering
CN209619938U (en) Ecological revetment structure
CN100383343C (en) Environment protection type multipurpose flood-discharging and water-discharging riverbed
CN208933906U (en) It is a kind of to be able to satisfy the current ecological bank protection structure of amphibian animal
CN113235531A (en) Fish migration channel
CN113463582A (en) Be suitable for and found bottom hole type fishway view weir structure that falls
CN201962646U (en) Ecological sandy soil dike structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190611