CN109838012A - A kind of flexible connecting device and its construction method of the assembled building block wall with aluminium set - Google Patents

A kind of flexible connecting device and its construction method of the assembled building block wall with aluminium set Download PDF

Info

Publication number
CN109838012A
CN109838012A CN201910247043.2A CN201910247043A CN109838012A CN 109838012 A CN109838012 A CN 109838012A CN 201910247043 A CN201910247043 A CN 201910247043A CN 109838012 A CN109838012 A CN 109838012A
Authority
CN
China
Prior art keywords
connector
wall
assembled
assembled wall
aluminium set
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910247043.2A
Other languages
Chinese (zh)
Inventor
邓兴贵
蔡安谷
左金涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Quick Construction Technology Co., Ltd
Original Assignee
Guizhou Xinggui Hengyuan New Building Materials Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Xinggui Hengyuan New Building Materials Co Ltd filed Critical Guizhou Xinggui Hengyuan New Building Materials Co Ltd
Priority to CN201910247043.2A priority Critical patent/CN109838012A/en
Publication of CN109838012A publication Critical patent/CN109838012A/en
Pending legal-status Critical Current

Links

Abstract

Flexible connecting device and its construction method the invention discloses a kind of assembled building block wall with aluminium set, it include first assembled wall and second assembled wall, there are gaps between first assembled wall and second assembled wall, the attachment device includes the first connector, second connector, aluminium set and tie up silk, first connector can be embedded in the side of first assembled wall, second connector can be embedded in the side of second assembled wall, the both ends of the aluminium set are connected with second connector of the first connector respectively by tying up silk.Using flexible connecting device of the present invention and its construction method, solves the connection type between traditional architecture wall, not only make the gap between wall smaller, construction is more convenient when filling wall pours, material is saved, and but also the production of assembled building block wall and installation process are more convenient, has structure simple, the advantages that construction is simple is quick, safe and practical.

Description

A kind of flexible connecting device and its construction method of the assembled building block wall with aluminium set
Technical field
The present invention relates to building structure technology field, specifically a kind of flexibility of the assembled building block wall with aluminium set Attachment device and its construction method.
Background technique
With the development of modern industrial technology, building house can be manufactured in batch completely as machine production.As long as Prefabricated house component, transport to assemble in site get up just at.Since the construction speed of assembled architecture is fast, and produce Cost is relatively low, promotes come all over the world rapidly.In China, sent out according to propulsion supply side structural reform and novel urbanization The assembled architectures such as steel construction, concrete are greatly developed in the requirement of exhibition, are to have to develop energy conservation and environmental protection NPD projects and improve to build One important content of safety.Had using the major advantage of assembled architecture: a large amount of building subassembly is processed by Workshop Production At, and only need to carry out a large amount of assembling work at the scene, greatly reduce than original cast-in-place operation;Using building, finishing one Change design, construction, component gets over standard, and production efficiency is higher, and corresponding component cost will decline, and cooperates the digitlization pipe of factory Reason, the cost performance of entire assembled architecture can be higher and higher, while also being compliant with the requirement of green building.Therefore, develop assembled Building has the larger advantage and market prospects for saving resource.
Filling wall is a kind of building structure, and wall is different according to structure stress situation, there is load bearing wall, non-load bearing wall. Using building block in house building course, gap can be generated between blocks, so that filling wall construction is formed, it is main at present to use It disengages the connection type not disengaged either to be attached, when using the method disengaged, fills and reserved between the building block of wall both ends Gap not less than 20mm, the Out-Plane Stability Problems of filling wall are more prominent when using disengagement mode in this way.And use does not take off There is also certain problems for the connection method opened, and at present mainly based on bar planting method, bar planting method is problem appear to is that the steel being implanted into Muscle is insecure, and stability is poor.These problems seriously affect structure safety, so that the whole shock resistance of structure can be reduced Can, security-hidden trouble is left to engineering.The drawbacks of to overcome rigid connection, " the masonry filler wall detail of construction " 10SG64-2 In propose flexible connection scheme between filling wall and main structure, " seismic design provision in building code " (GB50011-2011) the 13.2.1 item provides: to the building element of flexible connection, can be not counted in rigidity, masonry filler wall can not be considered to main structure Stiffness contribution.Therefore, reduction coefficient natural vibration period for considering main structure can not be had in main structure seismic resistance calculation, it is convenient The design application of concrete structure.However, effective flexible connection forms there is no to can solve masonry filler wall pair at present The problems such as influence to tension rib of the stiffness contribution of main structure, masonry filler wall sedimentation and deformation.
Summary of the invention
The technical problem to be solved by the present invention is to be directed to background technique, it is simple to provide a kind of structure, applies The convenient flexible connecting device of work, breaks the connection type between traditional architecture wall, and filling wall is cast-in-situ concrete member, two sides It is flexibly connected with assembled building block wall, filling wall can construct after the completion of assembled building block, so that the life of assembled building block wall It produces and installation process is more convenient, specifically a kind of flexible connecting device and its construction party of the assembled building block wall with aluminium set Method.
In order to solve the above technical problems, the technical scheme adopted by the invention is as follows: a kind of assembled building block wall is with aluminium set Flexible connecting device, includes first assembled wall and second assembled wall, first assembled wall and There are gap between second assembled wall, the attachment device includes the first connector, the second connector, aluminium set and ties up Silk, first connector can be embedded in the side of first assembled wall, and second connector can be embedded in second In the side of piece assembled wall, the both ends of the aluminium set are connected with second connector of the first connector respectively by tying up silk It connects.
Further, a kind of flexible connecting device of the assembled building block wall with aluminium set of the present invention, wherein described A connection piece and the second connector are steel cable structure, and the both ends of first connector and the second connector are embedded in accordingly First assembled wall and second assembled wall side, first connector and the second connector form closing Rectangular configuration, and be distributed between first assembled wall and second assembled wall and formed in symmetry status Gap in, the closed rectangular configuration of aluminium set, the silk of tying up ties up silk for four and is divided into two groups, wherein in one group equipped with four Two tie up silk for connection between described aluminium set one end and the first connector, two in another group are tied up silk for the aluminium Cover the connection between the other end and the second connector.
Further, a kind of flexible connecting device of the assembled building block wall with aluminium set of the present invention, wherein described Multiple first connectors are embedded on side in first assembled wall relative to the gap side from top to bottom, in institute It states and is correspondingly embedded with multiple the second connectors corresponding with first connector on the side of second assembled wall, It is 4mm that wherein first connector and the second connector, which are all made of diameter, and length is that the steel cable of 400mm forms closed rectangle Structure.
The invention also discloses use the flexible connecting device of the assembled building block wall with aluminium set for build filling wall Construction method, the construction method the following steps are included:
Step 1: shifting to an earlier date prefabricated first assembled wall and second assembled wall in factory, and in first assembled Corresponding first connector and the second connector are embedded in the side of second assembled wall of wall;
Step 2: first assembled wall and second assembled wall being lifted in place at the scene, in advance prefabricated aluminium Set, and match four reinforcing bars required for being ready for building filling wall and pour the concrete material of needs;
Step 3: selection is formed by pore size phase between first assembled wall and second assembled wall Then matched steel form will be divided into two groups with four reinforcing bars got ready, wherein one group of reinforcing bar passes through from top to bottom in gap Described aluminium set one end and the first connector intersect place, and another group of reinforcing bar passes through the aluminium set other end in gap from top to bottom It intersects place with the second connector, and is located at two groups of reinforcing bars in gap in vertical state, while in the first connector, The place of intersecting is attached fixation using tying up silk respectively for two connectors, aluminium set and reinforcing bar, is allowed to form filling wall reinforced mesh;
Step 4: selected steel form being fixed on first assembled wall and second assembled wall is formed Gap two sides, then at the gap of its connection or steel form bottom install sealing material, finally in gap Casting concrete;
Step 5: when the concrete of step 4 reaches design strength, removing steel form and sealing material to get cast-in-place concrete is arrived Assembled building block fill wall.
Further, construction method of the present invention, wherein the reinforcing bar is equal in the work progress of the step 2 Use diameter for the spiral of 20mm.
Further, construction method of the present invention, wherein in the work progress of the step 3, described first When being formed by gap spacing between assembled wall and second assembled wall greater than 100mm, need two groups of reinforcing bars it Between install multiple groups built-in fitting.
Further, construction method of the present invention, wherein in the work progress of the step 4, the sealing material Material is flexible sealing material.
It is and existing using a kind of flexible connecting device and its construction method of the assembled building block wall with aluminium set of the present invention There is technology to compare, effective effect is: due to distinguishing in first assembled wall and second assembled wall It is prefabricated with corresponding first connector and the second connector in advance, after assembled building block main structure construction, by tying up Silk can will be attached fixation between the first connector, the second connector, aluminium set and reinforcing bar, just can be carried out cast in situs coagulation Soil can be realized the construction of filling wall, can reduce construction and interfere with each other, not influence the construction speed of main structure, can be effective Shorten the construction period, while also ensuring the antidetonation compatibility of deformation with main structure, built-in fitting can also be installed in gap location, this Sample can provide higher bearing capacity.Using flexible connecting device of the present invention and its construction method, solves traditional architecture Connection type between wall not only makes the gap between wall smaller, and construction is more convenient when filling wall pours, and saves material, and And but also the production of assembled building block wall and installation process are more convenient, have structure simple, construction is simple is quick, and safety is real The advantages that using.
Detailed description of the invention
The present invention is described in further detail below in conjunction with the accompanying drawings.
Fig. 1 is the structural diagram of the present invention;
Structural schematic diagram when Fig. 2 is present invention construction.
It is as shown in the figure: the first connector of 1-, the second connector of 2-, 3- aluminium set, 4- tie up silk, first assembled wall of 5-, Second assembled wall of 6-, 7- reinforcing bar.
Specific embodiment
To further illustrate design of the invention, a specific embodiment of the invention is made below with reference to attached drawing further Illustrate:
As depicted in figs. 1 and 2, a kind of flexible connecting device of the assembled building block wall with aluminium set of the present invention includes A piece of assembled wall 5 and second assembled wall 6, first assembled wall 5 and second assembled wall 6 it Between there are gap, the attachment device includes the first connector 1, the second connector 2, aluminium set 3 and ties up silk 4, it is described first connect Fitting 1 can be embedded in the side of first assembled wall 5, and second connector 2 can be embedded in second assembled wall In the side of body 6, the both ends of the aluminium set 3 are connected with first connector 1 and the second connector 2 respectively by tying up silk 4.
Further, a kind of flexible connecting device of the assembled building block wall with aluminium set of the present invention, wherein described A connection piece 1 and the second connector 2 are steel cable structure, and the both ends of first connector 1 and the second connector 2 are embedded in The side of corresponding first assembled wall 5 and second assembled wall 6, first connector 1 and the second connector 2 Closed rectangular configuration is formed, and is distributed in first assembled wall 5 and second assembled wall 6 in symmetry status Between be formed by gap, the aluminium set 3 is in closed rectangular configuration, and the silk 4 of tying up is tied up silk 4 and divided for four and be equipped with four Two groups, wherein two in one group are tied up silk 4 for connection between described 3 one end of aluminium set and the first connector 1, in another group Two are tied up silk 4 for the connection between 3 other end of aluminium set and the second connector 2.
Further, a kind of flexible connecting device of the assembled building block wall with aluminium set of the present invention, wherein described Multiple first connectors 1 are embedded on side in first assembled wall 5 relative to the gap side from top to bottom, Multiple corresponding with first connector 1 second are correspondingly embedded on the side of second assembled wall 6 to connect Fitting 2, wherein it is 4mm that first connector 1 and the second connector 2, which are all made of diameter, the steel cable that length is 400mm forms envelope The rectangular configuration closed.
It is used to build the construction party of filling wall using flexible connecting device of the assembled building block wall with aluminium set of the present invention Method, the construction method the following steps are included:
Step 1: shifting to an earlier date prefabricated first assembled wall 5 and second assembled wall 6 in factory, and assembled at first Corresponding first connector 1 and the second connector 2 are embedded in the side of formula wall 5 and second assembled wall 6;
Step 2: first assembled wall 5 and second assembled wall 6 are lifted in place at the scene, it is prefabricated in advance Aluminium set 3, and with being ready for four reinforcing bars 7 required for building filling wall and pour the concrete materials of needs, wherein institute It states reinforcing bar 7 and is all made of the spiral that diameter is 20mm;
Step 3: being formed by pore size between selection and first assembled wall 5 and second assembled wall 6 The steel form to match, then will be divided to four reinforcing bars 7 getting ready is two groups, wherein one group of reinforcing bar 7 gap from top to bottom Intersect across described 3 one end of aluminium set with the first connector 1 place, and another group of reinforcing bar 7 passes through the aluminium in gap from top to bottom It covers 3 other ends and the second connector 2 intersects place, and be located at two groups of reinforcing bars 7 in gap in vertical state, while the The place of intersecting is attached fixation using tying up silk 4 respectively for a connection piece 1, the second connector 2, aluminium set 3 and reinforcing bar 7, is allowed to be formed Fill wall reinforced mesh;
Step 4: selected steel form is fixed on 6 shapes of first assembled wall 5 and second assembled wall At gap two sides, then at the gap of its connection or steel form bottom install sealing material, finally in gap Middle casting concrete, wherein the sealing material is flexible sealing material;
Step 5: when the concrete of step 4 reaches design strength, removing steel form and sealing material to get cast-in-place concrete is arrived Assembled building block fill wall.
Further, using construction method of the present invention, for first assembled wall 5 and second assembled When being formed by gap spacing between wall 6 greater than 100mm, need that multiple groups built-in fitting is installed between two groups of reinforcing bars 7.Pass through institute Overall structural strength of the filling wall when pouring can be improved in the built-in fitting of installation.
In actual application, using flexible connecting device of the present invention, it is not only suitable for assembled building block wall Between in "-" type, T-type and L-type structure wall, be also suitable for other abnormally-structured walls.Due on chip described first With being prefabricated with corresponding first connector 1 and the second connector 2 in advance respectively in formula wall 5 and second assembled wall 6, It, can be by the first connector 1, the second connector 2, aluminium set 3 and reinforcing bar by tying up silk 4 after assembled building block main structure construction It is attached fixation between 7, after reinforcing bar 7 is fixed, just can be carried out poured in place concrete, the construction of filling wall can be realized, Construction can not only be reduced to interfere with each other, nor affect on the construction speed of main structure, while can also effectively shorten the construction period. Using the filling wall of one-piece casting structure, while also more ensure that the antidetonation compatibility of deformation with main structure, can also Built-in fitting is installed at gap, higher bearing capacity can be provided in this way.
In conclusion using flexible connecting device of the present invention and construction method, solve between traditional architecture wall Connection type, not only make the gap between wall smaller, filling wall when pouring construction it is more convenient, save material, and make Production and the installation process for obtaining assembled building block wall are more convenient, have structure simple, construction is simple is quick, safe and practical etc. excellent Point.
The foregoing is merely the preferred embodiment of the present invention, are not intended to limit the invention, for the technology of this field For personnel, there can be various modifications and variations, it is all to utilize any modification, equivalent replacement, improvement and so on of the present invention, it should all It is included within protection scope of the present invention.

Claims (7)

1. a kind of flexible connecting device of the assembled building block wall with aluminium set includes first assembled wall (5) and second Assembled wall (6), there are gap, features between first assembled wall (5) and second assembled wall (6) Be: the attachment device includes the first connector (1), the second connector (2), aluminium set (3) and ties up silk (4), described first Connector (1) can be embedded in the side of first assembled wall (5), and second connector (2) can be embedded in second In the side of assembled wall (6), the both ends of the aluminium set (3) by tie up silk (4) respectively with first connector (1) and Two connectors (2) are connected.
2. a kind of flexible connecting device of the assembled building block wall with aluminium set according to claim 1, it is characterised in that: described First connector (1) and the second connector (2) they are steel cable structure, and the two of first connector (1) and the second connector (2) End is embedded in the side of corresponding first assembled wall (5) and second assembled wall (6), first connector (1) and the second connector (2) forms closed rectangular configuration, and is distributed in first assembled wall in symmetry status (5) it is formed by gap between second assembled wall (6), the aluminium set (3) is in closed rectangular configuration, described to tie up Silk (4) is equipped with four, ties up silk (4) for four and is divided into two groups, wherein two in one group piece tie up silk (4) for the aluminium set (3) one end With the connection between the first connector (1), two in another group are tied up silk (4) for the aluminium set (3) other end and the second company Connection between fitting (2).
3. a kind of flexible connecting device of the assembled building block wall with aluminium set according to claim 1, it is characterised in that: in institute It states and is embedded with multiple first connectors from top to bottom on the side in first assembled wall (5) relative to the gap side (1), it is correspondingly embedded on the side of second assembled wall (6) multiple opposite with first connector (1) The second connector (2) answered, wherein it is 4mm that first connector (1) and the second connector (2), which are all made of diameter, length is The steel cable of 400mm forms closed rectangular configuration.
4. a kind of flexible connecting device of the assembled building block wall with aluminium set using as described in any one of claims 1 to 3 For build filling wall construction method, which is characterized in that the construction method the following steps are included:
Step 1: shifting to an earlier date prefabricated first assembled wall (5) and second assembled wall (6) in factory, and at first Corresponding first connector (1) and second is embedded in the side of assembled wall (5) and second assembled wall (6) to connect Fitting (2);
Step 2: first assembled wall (5) and second assembled wall (6) are lifted in place, in advance in advance at the scene It makes aluminium set (3), and matches four reinforcing bars (7) required for being ready for building filling wall and pour the concrete material of needs Material;
Step 3: being formed by gap between selection and first assembled wall (5) and second assembled wall (6) Then the steel form that size matches will be divided into two groups with four reinforcing bars (7) got ready, wherein one group of reinforcing bar (7) is in gap It passes through the aluminium set (3) one end and the first connector (1) from top to bottom to intersect place, another group of reinforcing bar (7) is in gap from upper It intersects place to the lower aluminium set (3) other end and the second connector (2) of passing through, and makes the perpendicular shape of two groups of reinforcing bars (7) State is located in gap, while adopting at the place of intersecting respectively in the first connector (1), the second connector (2), aluminium set (3) and reinforcing bar (7) It is attached fixation with silk (4) is tied up, is allowed to form filling wall reinforced mesh;
Step 4: selected steel form is fixed on first assembled wall (5) and second assembled wall (6) Gap two sides are formed by, then sealing material is installed at the gap of its connection or steel form bottom, finally existed Casting concrete in gap;
Step 5: when the concrete of step 4 reaches design strength, removing steel form and sealing material to get cast-in-place concrete is arrived Assembled building block fill wall.
5. construction method according to claim 4, it is characterised in that: in the work progress of the step 2, the reinforcing bar (7) it is all made of the spiral that diameter is 20mm.
6. construction method according to claim 4, it is characterised in that: in the work progress of the step 3, described first When being formed by gap spacing between piece assembled wall (5) and second assembled wall (6) greater than 100mm, need two Multiple groups built-in fitting is installed between group reinforcing bar (7).
7. construction method according to claim 4, it is characterised in that: in the work progress of the step 4, the sealing Material is flexible sealing material.
CN201910247043.2A 2019-03-29 2019-03-29 A kind of flexible connecting device and its construction method of the assembled building block wall with aluminium set Pending CN109838012A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910247043.2A CN109838012A (en) 2019-03-29 2019-03-29 A kind of flexible connecting device and its construction method of the assembled building block wall with aluminium set

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910247043.2A CN109838012A (en) 2019-03-29 2019-03-29 A kind of flexible connecting device and its construction method of the assembled building block wall with aluminium set

Publications (1)

Publication Number Publication Date
CN109838012A true CN109838012A (en) 2019-06-04

Family

ID=66886445

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910247043.2A Pending CN109838012A (en) 2019-03-29 2019-03-29 A kind of flexible connecting device and its construction method of the assembled building block wall with aluminium set

Country Status (1)

Country Link
CN (1) CN109838012A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112554139A (en) * 2020-11-27 2021-03-26 中国电建集团成都勘测设计研究院有限公司 Flexible connection structure for anti-seismic beams in dam of high earth-rock dam

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203097017U (en) * 2013-03-14 2013-07-31 沈阳建筑大学建筑设计研究院 Connecting structure between prefabricated infilled wall and prefabricated column or prefabricated shear wall
CN103556749A (en) * 2013-10-10 2014-02-05 南京工业大学 Hanging flexible connection of precast concrete infill wall
CN204081134U (en) * 2014-08-30 2015-01-07 刘家文 Precast concrete wall component
CN104727467A (en) * 2015-03-23 2015-06-24 河北联合大学 Assembly type concrete filled steel tube shear wall splitting and assembling connection structure and assembling connection method
CN209742149U (en) * 2019-03-29 2019-12-06 贵州兴贵恒远新型建材有限公司 Flexible connecting device of assembled block wall with aluminum sleeve

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203097017U (en) * 2013-03-14 2013-07-31 沈阳建筑大学建筑设计研究院 Connecting structure between prefabricated infilled wall and prefabricated column or prefabricated shear wall
CN103556749A (en) * 2013-10-10 2014-02-05 南京工业大学 Hanging flexible connection of precast concrete infill wall
CN204081134U (en) * 2014-08-30 2015-01-07 刘家文 Precast concrete wall component
CN104727467A (en) * 2015-03-23 2015-06-24 河北联合大学 Assembly type concrete filled steel tube shear wall splitting and assembling connection structure and assembling connection method
CN209742149U (en) * 2019-03-29 2019-12-06 贵州兴贵恒远新型建材有限公司 Flexible connecting device of assembled block wall with aluminum sleeve

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112554139A (en) * 2020-11-27 2021-03-26 中国电建集团成都勘测设计研究院有限公司 Flexible connection structure for anti-seismic beams in dam of high earth-rock dam

Similar Documents

Publication Publication Date Title
CN203097017U (en) Connecting structure between prefabricated infilled wall and prefabricated column or prefabricated shear wall
CN205857448U (en) A kind of assembly concrete shear wall structure
CN108442536A (en) A kind of prefabricated assembled shear wall groove slurry anchor horizontal connection construction
CN203684399U (en) Embedded-column prefabricated part connection node
CN106968381A (en) With the prefabricated shear wall and overlapping plate node of Combined grouting sleeve connection
CN204626707U (en) A kind of wall-wall horizontal connecting node of exempting from the connection of formwork erection steel plate with stem stem
CN106638486B (en) High-tech zones cut-pff wall and gallery stage construction method
CN201891133U (en) Manual assembled type self-waterproof late poured band prefabricated slab of basement outer wall
CN209040349U (en) A kind of ring muscle fastening shear wall structure being easily installed
CN109838012A (en) A kind of flexible connecting device and its construction method of the assembled building block wall with aluminium set
CN109826337A (en) A kind of assembled building block wall steel cable flexible connecting structure and its construction method
CN104652608B (en) Assembly type exterior wall and beam connecting structure
CN209723296U (en) A kind of assembled building block wall steel cable flexible connecting structure
CN208105506U (en) A kind of prefabricated assembled shear wall groove slurry anchor horizontal connection construction
CN209703727U (en) Novel steel wire rack insulation board positioning supporting part and the novel wall containing it
CN209243966U (en) A kind of connecting node of heat-insulation wall plate
CN208088563U (en) A kind of assembled compound shear wall and its with girder steel, the connecting structure of floor
CN205421710U (en) Permanent beam mold board, concrete structure component are connected to arrangement of reinforcement formula buckle
CN106087881B (en) A kind of precast concrete box-structure and cast-in-place concrete convolution Sluice Pier structure and its construction technology
CN205444565U (en) Wallboard connected node
CN211286164U (en) Self-compaction regeneration block concrete superimposed shear wall
CN209742149U (en) Flexible connecting device of assembled block wall with aluminum sleeve
CN210917937U (en) Environment-friendly light high strength wallboard
CN208441257U (en) A kind of mounting structure of assembling-type precast hybrid beam and stiffened column
CN208718210U (en) Prefabricated panel suitable for multilayer assembled architecture

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20191223

Address after: No. 8, building 5-8, future Fangzhou E3 group, yu'an'jing District, Yunyan District, Guiyang City, Guizhou Province 550001

Applicant after: Guizhou Quick Construction Technology Co., Ltd

Address before: 561000 Guizhou province Xixiu Xixiu District of Anshun City Economic Development Zone

Applicant before: Guizhou Xinggui Hengyuan new building materials Co. Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20190604

RJ01 Rejection of invention patent application after publication