CN209723296U - A kind of assembled building block wall steel cable flexible connecting structure - Google Patents
A kind of assembled building block wall steel cable flexible connecting structure Download PDFInfo
- Publication number
- CN209723296U CN209723296U CN201920417944.7U CN201920417944U CN209723296U CN 209723296 U CN209723296 U CN 209723296U CN 201920417944 U CN201920417944 U CN 201920417944U CN 209723296 U CN209723296 U CN 209723296U
- Authority
- CN
- China
- Prior art keywords
- wall
- steel cable
- blockwork
- building block
- flexible connecting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Revetment (AREA)
Abstract
The utility model discloses a kind of assembled building block wall steel cable flexible connecting structures, it include the first blockwork wall, second blockwork wall, first steel cable, second steel cable and tension rib, there are gaps between first blockwork wall and the second blockwork wall, the embedded bar for connection is embedded in the first blockwork wall and the second blockwork wall, and the first steel cable is equipped in the pre-buried embedded bar of the first blockwork wall, the second steel cable is equipped in the pre-buried embedded bar of the second blockwork wall simultaneously, it is connected between first steel cable and the second steel cable by tension rib.Using flexible connecting structure described in the utility model, solves the connection type between traditional architecture wall, not only make the gap between wall smaller, construction is more convenient when filling wall pours, material is saved, and but also the production of assembled building block wall and installation process are more convenient, has structure simple, the advantages that construction is simple is quick, safe and practical.
Description
Technical field
The utility model relates to building structure technology field, specifically a kind of assembled building block wall steel cable is flexible
Connection structure.
Background technique
Fabricated construction is the abbreviation of prefabricated concrete structure, be using prefabricated components as main bearing member through assembly and
The concrete structure being formed by connecting.With the development of modern industrial technology, build house can as machine production, in batch at
The manufacture of set ground.As long as prefabricated house component, transport to assemble in site got up at.Due to the construction speed of assembled architecture
Degree is fast, and lower production costs, promotes come all over the world rapidly.In China, according to propulsion supply side structural reform
With the requirement of novel Urbanization Progress, the assembled architectures such as steel construction, concrete are greatly developed.Therefore, assembled steel reinforced coagulation
Soil structure is one of the important directions of China's building structure development, it is conducive to the development of China's building industrialization, improves production
Efficiency is energy saving, develops Green environmental-protection building, and is conducive to improve and guarantee construction engineering quality.It is built using assembled
The major advantage built has: a large amount of building subassembly is completed the process by Workshop Production, and only needs largely to be assembled at the scene
Operation greatly reduces than original cast-in-place operation;Using building, finishing integrated design, construction, component gets over standard, production efficiency
Higher, corresponding component cost will decline, and cooperate the digital management of factory, the cost performance of entire assembled architecture can be more next
It is higher, while also being compliant with the requirement of green building.Therefore, developing assembled architecture has the larger advantage for saving resource and market
Prospect.
Filling wall is a kind of building structure, and wall is different according to structure stress situation, there is load bearing wall, non-load bearing wall.
Using building block in house building course, gap can be generated between blocks, so that filling wall construction is formed, it is main at present to use
It disengages the connection type not disengaged either to be attached, when using the method disengaged, fills and reserved between the building block of wall both ends
Gap not less than 20mm, the Out-Plane Stability Problems of filling wall are more prominent when using disengagement mode in this way.And use does not take off
There is also certain problems for the connection method opened, and at present mainly based on bar planting method, bar planting method is problem appear to is that the steel being implanted into
Muscle is insecure, and stability is poor.These problems seriously affect structure safety, so that the whole shock resistance of structure can be reduced
Can, security-hidden trouble is left to engineering.The drawbacks of to overcome rigid connection, " the masonry filler wall detail of construction " 10SG64-2
In propose flexible connection scheme between filling wall and main structure, " seismic design provision in building code " (GB50011-2011) the
13.2.1 item provides: to the building element of flexible connection, can be not counted in rigidity, masonry filler wall can not be considered to main structure
Stiffness contribution.Therefore, reduction coefficient natural vibration period for considering main structure can not be had in main structure seismic resistance calculation, it is convenient
The design application of concrete structure.However, effective flexible connection forms there is no to can solve masonry filler wall pair at present
The problems such as influence to tension rib of the stiffness contribution of main structure, masonry filler wall sedimentation and deformation.
Utility model content
The problem of the technical problems to be solved in the utility model is for background technique provides a kind of structure letter
Single, easy for construction flexible connecting device, breaks the connection type between traditional architecture wall, and filling wall is cast-in-place concrete structure
Part, two sides and assembled building block wall are flexibly connected, and filling wall can construct after the completion of assembled building block, so that assembled building block
The production of wall and installation process are more convenient, specifically a kind of assembled building block wall steel cable flexible connecting structure.
In order to solve the above technical problems, the technology employed by the present utility model is a kind of assembled building block wall steel cable
Flexible connecting structure includes the first blockwork wall, the second blockwork wall, the first steel cable, the second steel cable and tension rib, institute
State between the first blockwork wall and the second blockwork wall that there are gaps, in the first blockwork wall and the second prefabricated block
It is embedded with the embedded bar for connection in block wall, and is equipped in the pre-buried embedded bar of the first blockwork wall
First steel cable, while the second steel cable, first steel cable are equipped in the pre-buried embedded bar of the second blockwork wall
And second be connected between steel cable by tension rib.
Further, a kind of assembled building block wall steel cable flexible connecting structure described in the utility model, wherein described pre-
It buries reinforcing bar and is embedded in corresponding first blockwork wall the second blockwork coping, first steel cable and the second steel in advance respectively
Removably set is hung in corresponding embedded bar rope respectively, wherein first steel cable and the second steel cable are all made of diameter is
4mm, the steel cable that length is 400mm form enclosed construction, and the embedded bar uses diameter for the spiral of 12mm.
Using a kind of assembled building block wall steel cable flexible connecting structure described in the utility model, compared with prior art,
Its effective effect is: due to being embedded in the first blockwork wall and the second blockwork wall for connection
Embedded bar, and the first steel cable is equipped in the pre-buried embedded bar of the first blockwork wall, while described second
It is equipped with the second steel cable in the pre-buried embedded bar of blockwork wall, passes through tension rib between first steel cable and the second steel cable
It is connected.After assembled building block main structure construction, the first steel cable and the second steel cable is set to be connected by tension rib, just
It can be carried out poured in place concrete, the construction of filling wall can be realized, construction can be reduced and interfered with each other, main structure is not influenced
Construction speed, can effectively shorten the construction period, while also ensure the antidetonation compatibility of deformation with main structure, can also
Built-in fitting is installed at gap, higher bearing capacity can be provided in this way.Using flexible connecting structure described in the utility model, solve
Connection type between traditional architecture wall not only makes the gap between wall smaller, and construction is more convenient when filling wall pours, and saves
Material, and but also the production of assembled building block wall and installation process are more convenient, have structure simple, construction is simple is fast
Victory, it is safe and practical the advantages that.
Detailed description of the invention
The utility model is described in further detail with reference to the accompanying drawing.
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is structural schematic diagram when the utility model is constructed.
It is as shown in the figure: the first building block of 1- partition wall, the second building block of 2- partition wall, the first steel cable of 3-, the second steel cable of 4-, 5- drawknot
Muscle, 6- embedded bar, 7- reinforcing bar.
Specific embodiment
For the design for further illustrating the utility model, below with reference to attached drawing to specific embodiment of the present utility model
It is described further:
As depicted in figs. 1 and 2, a kind of assembled building block wall steel cable flexible connecting structure described in the utility model, including
There are the first blockwork wall 1, the second blockwork wall 2, the first steel cable 3, the second steel cable 4 and tension rib 5, the first prefabricated block
There are gaps between block wall 1 and the second blockwork wall 2, in the first blockwork wall 1 and the second blockwork wall 2
It is embedded with the embedded bar 6 for connection, and is equipped with the in the pre-buried embedded bar 6 of the first blockwork wall 1
One steel cable 3, while the second steel cable 4, first steel are equipped in the pre-buried embedded bar 6 of the second blockwork wall 2
It is connected between rope 3 and the second steel cable 4 by tension rib 5.Wherein it is prefabricated to be embedded in corresponding first in advance respectively for the embedded bar 6
Removably set is hung on relatively respectively for the top of blockwork 1 and the second blockwork wall 2, first steel cable 3 and the second steel cable 4
In the embedded bar 6 answered, wherein it is 4mm that first steel cable 3 and the second steel cable 4, which are all made of diameter, length is the steel cable of 400mm
Enclosed construction is formed, the embedded bar 4 uses diameter for the spiral of 12mm.
In actual application, using flexible connecting structure described in the utility model, it is not only suitable for assembled block
In "-" type, the wall of T-type and L-type structure between block wall, it is also suitable for other abnormally-structured walls.When for building filling
When wall, specific construction method the following steps are included:
Step 1: shifting to an earlier date prefabricated first blockwork wall 1 and the second blockwork wall 2 in factory, and respectively described
The top surface of one blockwork wall 1 and the second blockwork wall 2 is embedded with the embedded bar 6 for connection;
Step 2: the prefabricated first blockwork wall 1 and the second blockwork wall 2 being lifted in place at the scene, and mentioned
Preceding prefabricated first steel cable 3 and the second steel cable 4, the good matched tension rib 5 of simultaneous selection are ready for building in addition, also to match
Reinforcing bar 7 required for filling wall and the steel form and concrete material for pouring needs;
Step 3: prefabricated first steel cable 3 and the second steel cable 4 are socketed on respectively in corresponding embedded bar 6, then
Reinforcing bar 7 passes through from gap to first steel cable 3 and from the second steel cable 4 intersects from top to bottom, and makes the reinforcing bar 7 in hanging down
Straight state is located in gap, while being carried out at the first connector 3, the second connector 4 and 7 place of intersecting of reinforcing bar by tension rib 5
It is connected and fixed, is allowed to form the reinforced mesh of filling wall;
Step 4: first by selected steel form be fixed on the first blockwork wall 1 and the second blockwork wall 2 it
Between be formed by gap two sides, then at the gap of the two sides of steel form and bottom install sealing material, finally in gap
Middle casting concrete;Wherein the sealing material is flexible sealing material;
Step 5: when the concrete when be poured in step 4 reaches design strength, removing steel form to get cast-in-place coagulation is arrived
The masonry of soil fills wall.
In conclusion can not only carry out poured in place concrete, i.e., using flexible connecting structure described in the utility model
The construction that filling wall can be achieved, can reduce construction and interfere with each other, not influence the construction speed of main structure, can effectively shorten and apply
The work duration, while also ensuring the antidetonation compatibility of deformation with main structure, built-in fitting can also be installed in gap location, can mention in this way
For higher bearing capacity.The connection type between traditional architecture wall is also solved, not only makes the gap between wall smaller, is filled
It constructs when wall pours more convenient, saves material, and but also the production of assembled building block wall and installation process are more convenient, have
Have structure simple, construction is simple is quick, it is safe and practical the advantages that.
Above description is merely a prefered embodiment of the utility model, is not intended to limit the utility model, for ability
For the technical staff in domain, there can be various modifications and variations, it is all to utilize any modification made by the utility model, equally replace
It changes, improve, should be included within the scope of protection of this utility model.
Claims (2)
1. a kind of assembled building block wall steel cable flexible connecting structure, it is characterised in that: include the first blockwork wall (1),
Two blockwork walls (2), the first steel cable (3), the second steel cable (4) and tension rib (5), the first blockwork wall (1) and
There are gaps between two blockwork walls (2), pre- in the first blockwork wall (1) and the second blockwork wall (2)
It is embedded with the embedded bar (6) for connection, and is set in the pre-buried embedded bar (6) of the first blockwork wall (1)
Have the first steel cable (3), while being equipped with the second steel cable in the pre-buried embedded bar (6) of the second blockwork wall (2)
(4), it is connected between first steel cable (3) and the second steel cable (4) by tension rib (5).
2. a kind of assembled building block wall steel cable flexible connecting structure according to claim 1, it is characterised in that: described pre-buried
Reinforcing bar (6) is embedded in the top of corresponding first blockwork wall (1) and the second blockwork wall (2), first steel in advance respectively
Removably set is hung in corresponding embedded bar (6) respectively for rope (3) and the second steel cable (4), wherein first steel cable (3)
Being all made of diameter with the second steel cable (4) is 4mm, and the steel cable that length is 400mm forms enclosed construction, and the embedded bar is using straight
Diameter is the spiral of 12mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920417944.7U CN209723296U (en) | 2019-03-29 | 2019-03-29 | A kind of assembled building block wall steel cable flexible connecting structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920417944.7U CN209723296U (en) | 2019-03-29 | 2019-03-29 | A kind of assembled building block wall steel cable flexible connecting structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209723296U true CN209723296U (en) | 2019-12-03 |
Family
ID=68689408
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920417944.7U Expired - Fee Related CN209723296U (en) | 2019-03-29 | 2019-03-29 | A kind of assembled building block wall steel cable flexible connecting structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209723296U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109826337A (en) * | 2019-03-29 | 2019-05-31 | 贵州兴贵恒远新型建材有限公司 | A kind of assembled building block wall steel cable flexible connecting structure and its construction method |
-
2019
- 2019-03-29 CN CN201920417944.7U patent/CN209723296U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109826337A (en) * | 2019-03-29 | 2019-05-31 | 贵州兴贵恒远新型建材有限公司 | A kind of assembled building block wall steel cable flexible connecting structure and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201217847Y (en) | Plug-in type preformed hole grouting reinforcement lapping connection component | |
CN103510639B (en) | A kind of can the overlaid plate type shear wall of restore funcitons and implementation method thereof | |
CN208441231U (en) | A kind of beam column built from concrete dry method connecting node | |
CN106120542B (en) | It can be applied to the assembled pier and its construction technology of seismic fortification intensity upper zone | |
CN106638486B (en) | High-tech zones cut-pff wall and gallery stage construction method | |
CN204626707U (en) | A kind of wall-wall horizontal connecting node of exempting from the connection of formwork erection steel plate with stem stem | |
CN204311614U (en) | The fabricated shear wall of prestressing force splicing | |
CN109826337A (en) | A kind of assembled building block wall steel cable flexible connecting structure and its construction method | |
CN206570955U (en) | A kind of prefabricated post single hole provisions for grouting | |
CN209723296U (en) | A kind of assembled building block wall steel cable flexible connecting structure | |
KR101458434B1 (en) | Half precast concrete column manufacturing method using prefabricated PC panels and constructing method using the same | |
CN204356996U (en) | The U-shaped beam of prefabricated reinforced concrete with horizontal steel diaphragm | |
CN209040349U (en) | A kind of ring muscle fastening shear wall structure being easily installed | |
CN206752693U (en) | A kind of assembled steel reinforced concrete column of stirrup encryption and post splicing node | |
CN203296203U (en) | Reinforced-concrete-fitted seismic isolation node and fitted seismic isolation structure with reinforced-concrete-fitted seismic isolation node | |
CN205742550U (en) | Novel fabricated building connects node | |
CN104746434B (en) | Closure segment formwork system without dismantling outer formwork | |
CN109838012A (en) | A kind of flexible connecting device and its construction method of the assembled building block wall with aluminium set | |
CN209293197U (en) | Wall and floor connection structure and assembled arthitecutral structure system | |
CN207727762U (en) | Assembled beam-column connecting node | |
CN205557839U (en) | Brickwork infilled wall and main body frame's flexible connection mean | |
CN213062683U (en) | Anti-seismic concrete prefabricated staircase | |
CN204098220U (en) | The bottom reinforcement bars syndeton that a kind of keyway node prefabricated frame is set a roof beam in place | |
CN211286164U (en) | Self-compaction regeneration block concrete superimposed shear wall | |
CN209227784U (en) | Wall and Liangping face external link structure and assembled arthitecutral structure system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20191226 Address after: No. 8, building 5-8, future Fangzhou E3 group, yu'an'jing District, Yunyan District, Guiyang City, Guizhou Province 550001 Patentee after: Guizhou Quick Construction Technology Co.,Ltd. Address before: 561000 Guizhou province Xixiu Xixiu District of Anshun City Economic Development Zone Patentee before: GUIZHOU XINGGUI HENGYUAN NEW BUILDING MATERIAL CO.,LTD. |
|
TR01 | Transfer of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191203 |
|
CF01 | Termination of patent right due to non-payment of annual fee |