CN109736457A - A kind of double-faced waterproofing structure and processing method for pond pond body construction joint seepage treatment - Google Patents

A kind of double-faced waterproofing structure and processing method for pond pond body construction joint seepage treatment Download PDF

Info

Publication number
CN109736457A
CN109736457A CN201910138482.XA CN201910138482A CN109736457A CN 109736457 A CN109736457 A CN 109736457A CN 201910138482 A CN201910138482 A CN 201910138482A CN 109736457 A CN109736457 A CN 109736457A
Authority
CN
China
Prior art keywords
construction joint
pond body
pond
water stop
copper water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910138482.XA
Other languages
Chinese (zh)
Inventor
张君来
郭晓勇
朱德宁
黎学皓
李彬龙
段琼
胡方华
李棉巧
熊建武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group No 1 Engineering Co Ltd
Original Assignee
China Gezhouba Group No 1 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group No 1 Engineering Co Ltd filed Critical China Gezhouba Group No 1 Engineering Co Ltd
Priority to CN201910138482.XA priority Critical patent/CN109736457A/en
Publication of CN109736457A publication Critical patent/CN109736457A/en
Pending legal-status Critical Current

Links

Abstract

A kind of double-faced waterproofing structure and processing method for pond pond body construction joint seepage treatment, including Copper water stop, plugging material, pointing, finishing coat, in pond pond body construction joint breakthrough two sides, metope cuts decorative mortar and concrete surface respectively, expose reinforcing bar, clear up construction joint and concrete surface, pointing two-component polysulfide sealant is filled in construction joint, special Copper water stop is connect with reinforcement welding, finishing coat construction is carried out after blocking the concrete surface chiseled with plugging material, the construction of another side carries out processing operation using same treatment method.Using the above structure and method, the leakage problems of pond pond body be can effectively solve the problem that, cesspool service life is extended, the construction of waterproof construction is simple and direct, reasonable, and processing construction procedure is simple, at low cost.

Description

A kind of double-faced waterproofing structure and processing for pond pond body construction joint seepage treatment Method
Technical field
It is especially a kind of for the two-sided of pond pond body construction joint seepage treatment the present invention relates to sewage treatment facility field Waterproof construction and processing method.
Background technique
Municipal water supply factory, sewage treatment plant are the public utilities concerning national economy, no matter at water supply plant or sewage Factory is managed, includes multiple ponds, for large capacity, has a Gai Shuichi, when construction, inevitable to need to stay to set construction joint, construction joint Processing generally take embedding rubber fastening band, or before upper layer concrete final set, dabbing processing is carried out to contact surface, under When one layer concrete is constructed, clean out contact surface, be laid with casting concrete again after proportion mortar, no matter which kind of way, Difficulty is brought to construction, easily causes quality problems, pond is caused pond body leakage phenomenon occur, meanwhile, after pond is come into operation, The effects of due to settlement of foundation and the external environment temperature difference, also easily leads to cracking at construction joint, rubber fastening band fracture, causes pond Pond body leaks.
Construction joint seepage treatment be always in engineering insoluble problem and engineers and technicians and operating personnel without The problem of method is avoided.
Summary of the invention
A kind of double-faced waterproofing structure and processing method for pond pond body construction joint seepage treatment provided by the invention, energy It is enough effectively to solve above-mentioned deficiency in the prior art.
In order to solve the above technical problems, the technical scheme adopted by the invention is that: a kind of construction joint for pond pond body Seepage treatment double-faced waterproofing structure, including Copper water stop, plugging material and pointing, the pointing, which is filled with, to be applied In work seam, chisel is equipped with groove in the pond body of construction joint two sides, and the both ends of pointing extend to outside construction joint and are located in groove, Copper water stop is equipped in the groove of construction joint position, Copper water stop is tightly attached to groove floor and the setting of pointing bottom, copper Sealing is equipped with plugging material, and pond body is equipped with finishing coat, and finishing coat covering is arranged on construction joint.
In preferred scheme, the pointing uses two-component polysulfide sealant.
In preferred scheme, when the construction joint slit width is less than 10mm, the insert depth of the pointing with apply It is equal that work stitches slit width;
When the construction joint slit width is greater than 10mm, the insert depth of the pointing is the 50%-60% of construction joint slit width.
In preferred scheme, the groove chisel sets depth and the intracorporal pond body reinforcing bar in pond is identical to spacing between pool wall, Copper water stop between pond body reinforcing bar by being weldingly fixed in groove.
A kind of construction joint seepage treatment method for pond pond body, comprising the following steps:
1) centered on breakthrough construction joint, the pond body concrete inside and outside breakthrough construction joint is cut, width is cut Degree is 15-20cm, cuts length not less than 20cm, cuts distance of the thickness according to pond body reinforcing bar apart from pool wall and determine, complete out After digging operation and forming groove, construction joint and pond body concrete surface are cleared up;
2) Copper water stop is wherein above set in pond body on one side, is welded between the pond body reinforcing bar exposed in Copper water stop and groove;
3) pointing is filled by the construction joint of pond body another side;
4) after pointing filling is completed, Copper water stop is set on the face, and will be between Copper water stop and the pond body reinforcing bar of exposing It is welded;
5) Copper water stop of breakthrough construction joint two sides is respectively provided with finish after, plugging construction and smooth out using plugging material;
6) after plugging material reaches age, finishing coat construction is carried out on pool wall.
In preferred scheme, in the step 3), when filling pointing, guarantee former rubber fastening band integrality.
In preferred scheme, the plugging material uses pea gravel concreten identical with pond body concrete grade, blocks The slump of material is less than 10.
In preferred scheme, the finishing coat uses cement mortar identical with pond body.
In preferred scheme, the Copper water stop uses multistage bending structure, portion size of the Copper water stop perpendicular to pond body No more than the groove height that chisel is set, the partial-length that Copper water stop is contacted with pond body concrete surface, which is not more than, cuts width, Copper water stop The partial-length contacted with pointing and construction joint are of same size.
A kind of double-faced waterproofing structure and processing method for pond pond body construction joint seepage treatment provided by the present invention, By filling pointing, Copper water stop covering, plugging material closure and finishing coat construction at breakthrough construction joint, effectively solve The leakage problems of pond pond body extend cesspool service life, and the construction of waterproof construction is simple and direct, reasonable, handle construction procedure Simply, at low cost.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples:
Fig. 1 is overall structure diagram of the invention.
Fig. 2 is Copper water stop structural schematic diagram of the invention.
In figure: Copper water stop 1, plugging material 2, pointing 3, pond body reinforcing bar 4, pond body concrete 5, former rubber fastening band 6, Finishing coat 7.
Specific embodiment
Embodiment 1:
As shown in figure 1, a kind of construction joint seepage treatment double-faced waterproofing structure for pond pond body, it is characterized in that: including Copper water stop 1, plugging material 2 and pointing 3, the pointing 3 are filled in construction joint, dig in the pond body of construction joint two sides Equipped with groove, the both ends of pointing 3 extend to outside construction joint and are located in groove, are equipped in the groove of construction joint position Copper water stop 1, Copper water stop 1 is tightly attached to groove floor and the setting of 3 bottom of pointing, Copper water stop 1 are equipped with plugging material 2, pond Body is equipped with finishing coat 7, and the covering of finishing coat 7 is arranged on construction joint.
Embodiment 2:
On the basis of embodiment 1, the pointing 3 uses two-component polysulfide sealant.
In preferred scheme, when the construction joint slit width is less than 10mm, the insert depth of the pointing 3 with apply It is equal that work stitches slit width;
When the construction joint slit width is greater than 10mm, the insert depth of the pointing 3 is the 50%- of construction joint slit width 60%。
In this example, filler uses two-component polysulfide sealant, has good caking property to materials such as metal and concrete, It can keep good air-tightness and waterproofness under continuous and adjustable, vibration and temperature variations, and oil resistant, solvent resistant, durable Property it is good, the depth of two-component polysulfide sealant insertion construction joint can guarantee that it plays one's part to the full, and not waste.
Preferably, on the basis of embodiment 1, groove chisel sets depth and the intracorporal pond body reinforcing bar 4 in pond to pool wall Between spacing it is identical, Copper water stop 1 between pond body reinforcing bar 4 by being weldingly fixed in groove.
Embodiment 4:
On the basis of embodiment 1-3, a kind of construction joint seepage treatment method for pond pond body, comprising the following steps:
1) centered on breakthrough construction joint, the pond body concrete 5 inside and outside breakthrough construction joint is cut, width is cut Degree is 15-20cm, cuts length not less than 20cm, cuts distance of the thickness according to pond body reinforcing bar 4 apart from pool wall and determine, complete out After digging operation and forming groove, construction joint and 5 face of pond body concrete are cleared up;
2) Copper water stop 1 is wherein above set in pond body on one side, is welded between the pond body reinforcing bar 4 exposed in Copper water stop 1 and groove;
3) pointing 3 is filled by the construction joint of pond body another side;
4) pointing 3 filling complete after, on the face be arranged Copper water stop 1, and by Copper water stop 1 and expose pond body reinforcing bar 4) Between welded;
5) Copper water stop 1 of breakthrough construction joint two sides is respectively provided with finish after, plugging construction and smear using plugging material 2 It is flat;
6) after plugging material 2 reaches age, finishing coat 7 is carried out on pool wall and is constructed.
In preferred scheme, in the step 3), when filling pointing 3, guarantee 6 integrality of former rubber fastening band.
In this example, cutting width is 15-20cm, cuts length not less than 20cm, cuts thickness according to 4 distance of pond body reinforcing bar The distance of pool wall determines, makes width, length and the thickness of breakthrough construction joint periphery concrete chisel removal, is all larger than breakthrough model It encloses, can effectively block breakthrough, and materials'use is less, cost is relatively low, easy to operate.
Step 2-4) in, the Copper water stop 1 and pond body reinforcing bar 4 of construction joint side are welded to connect, and fill two-component in the other side Polysulfide sealant does not destroy former rubber fastening band 6, after the completion of filling, then carries out construction joint when filling two-component polysulfide sealant The special Copper water stop 1 and 4 muscle of pond body steel of the other side are welded to connect.
The construction procedure of Copper water stop 1, two-component polysulfide sealant is defined in aforesaid operations process, is conducive to double groups The determination of part polysulfide sealant poured into dosage, and be conducive to operate.
Embodiment 5:
On the basis of embodiment 4, the plugging material 2 uses pea gravel concreten identical with 5 label of pond body concrete, envelope The slump of stifled material 2 is less than 10.
In preferred scheme, the finishing coat 7 uses cement mortar identical with pond body.
Plugging material 2 and finishing coat 7 can effectively protect Copper water stop 1 and pointing 3, and can restore the appearance of mend It is consistent with other positions.
Embodiment 5:
As shown in Fig. 2, the Copper water stop 1 uses multistage bending structure, and Copper water stop 1 is perpendicular to pond on the basis of embodiment 4 Part (the 1-1,1-3) size of body is no more than the groove height that chisel is set, the part (1- of Copper water stop 1 and 5 face contact of pond body concrete 2) for length no more than width is cut, part (1-4) length and construction joint that Copper water stop 1 is contacted with pointing 3 are of same size.
Copper water stop 1 is customized according to the size for cutting concrete surface, achievees the purpose that effectively to cover entire construction joint, and be convenient for The construction of subsequent plugging material and finishing coat.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all in spirit of the invention and Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (9)

1. a kind of construction joint seepage treatment double-faced waterproofing structure for pond pond body, it is characterized in that: including Copper water stop (1), envelope Stifled material (2) and pointing (3), the pointing (3) is filled in construction joint, in the pond body of construction joint two sides Chisel is equipped with groove, and the both ends of pointing (3) extend to outside construction joint and are located in groove, in the groove of construction joint position Equipped with Copper water stop (1), Copper water stop (1) is tightly attached to groove floor and the setting of pointing (3) bottom, Copper water stop (1) are equipped with Plugging material (2), pond body are equipped with finishing coat (7), and finishing coat (7) covering is arranged on construction joint.
2. a kind of construction joint seepage treatment double-faced waterproofing structure for pond pond body according to claim 1, feature Be: the pointing (3) uses two-component polysulfide sealant.
3. a kind of construction joint seepage treatment double-faced waterproofing structure for pond pond body according to claim 1 or 2, special Sign is: when the construction joint slit width is less than 10mm, insert depth and the construction joint slit width phase of the pointing (3) Deng;
When the construction joint slit width is greater than 10mm, the insert depth of the pointing (3) is the 50%- of construction joint slit width 60%。
4. a kind of construction joint seepage treatment double-faced waterproofing structure for pond pond body according to claim 1, feature Be: the groove chisel sets depth and the intracorporal pond body reinforcing bar (4) in pond is identical to spacing between pool wall, and Copper water stop (1) passes through It is weldingly fixed in groove between pond body reinforcing bar (4).
5. a kind of construction joint seepage treatment method for pond pond body according to any one of claims 1-4, special Sign be the following steps are included:
1) centered on breakthrough construction joint, the pond body concrete (5) inside and outside breakthrough construction joint is cut, is cut Width is 15-20cm, cuts length not less than 20cm, cuts distance of the thickness according to pond body reinforcing bar (4) apart from pool wall and determine, complete At cutting operation and after forming groove, construction joint and pond body concrete (5) face are cleared up;
2) Copper water stop (1) is set pond body is wherein upper on one side, in Copper water stop (1) and groove between the pond body reinforcing bar (4) of exposing into Row welding;
3) pointing (3) are filled by the construction joint of pond body another side;
4) pointing (3) filling complete after, on the face be arranged Copper water stop (1), and by Copper water stop (1) and expose pond body Reinforcing bar is welded between (4);
5) Copper water stop (1) of breakthrough construction joint two sides is respectively provided with finish after, using plugging material (2) carry out plugging construction simultaneously It smoothes out;
6) after plugging material (2) reaches age, finishing coat (7) construction is carried out on pool wall.
6. a kind of construction joint seepage treatment method for pond pond body according to claim 5, it is characterised in that: described Step 3) in, when filling pointing (3), guarantee former rubber fastening band (6) integrality.
7. a kind of construction joint seepage treatment method for pond pond body according to claim 5, it is characterised in that: described Plugging material (2) use pea gravel concreten identical with pond body concrete (5) label, the slump of plugging material (2) is less than 10。
8. a kind of construction joint seepage treatment method for pond pond body according to claim 5, it is characterised in that: described Finishing coat (7) use cement mortar identical with pond body.
9. a kind of construction joint seepage treatment method for pond pond body according to claim 5, it is characterised in that: described Copper water stop (1) use multistage bending structure, Copper water stop (1) is high no more than the groove that sets of chisel perpendicular to the portion size of pond body The partial-length of degree, Copper water stop (1) and pond body concrete (5) face contact, which is not more than, cuts width, Copper water stop (1) and pointing (3) partial-length and construction joint contacted is of same size.
CN201910138482.XA 2019-02-25 2019-02-25 A kind of double-faced waterproofing structure and processing method for pond pond body construction joint seepage treatment Pending CN109736457A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910138482.XA CN109736457A (en) 2019-02-25 2019-02-25 A kind of double-faced waterproofing structure and processing method for pond pond body construction joint seepage treatment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910138482.XA CN109736457A (en) 2019-02-25 2019-02-25 A kind of double-faced waterproofing structure and processing method for pond pond body construction joint seepage treatment

Publications (1)

Publication Number Publication Date
CN109736457A true CN109736457A (en) 2019-05-10

Family

ID=66368333

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910138482.XA Pending CN109736457A (en) 2019-02-25 2019-02-25 A kind of double-faced waterproofing structure and processing method for pond pond body construction joint seepage treatment

Country Status (1)

Country Link
CN (1) CN109736457A (en)

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030094979A (en) * 2002-06-11 2003-12-18 김현우 Connecting member for water proofing using in concrete structure
CN2918575Y (en) * 2006-04-28 2007-07-04 曹世龙 New composite water stop
KR100805842B1 (en) * 2007-10-29 2008-02-21 고삼석 A joint device and construction method of concrete structure
CN101372840A (en) * 2007-08-21 2009-02-25 上海市建筑科学研究院(集团)有限公司 Mounting method with detachable rubber water stop mounted inside
KR200449712Y1 (en) * 2010-01-28 2010-08-03 이해선 Water protecting finishing material for concrete joint
KR20100112278A (en) * 2009-04-09 2010-10-19 씨엘엠테크(주) Repair Method for Concrete Joint Part
KR101372749B1 (en) * 2013-07-15 2014-03-11 (주)대한콜크 Multi-performance functional water stop plate with composite structure
CN203782900U (en) * 2014-04-29 2014-08-20 中铁四局集团第三建设有限公司 Deformation joint water stopping structure for ultrathin reinforced concrete tank
CN105888247A (en) * 2016-04-26 2016-08-24 中国化学工程第三建设有限公司 Construction method for expansion joint of industrial pond
CN106088364A (en) * 2016-07-25 2016-11-09 浙江万达建设集团有限公司 A kind of Novel underground room antiseep attachment structure and construction method thereof
CN208236013U (en) * 2018-02-12 2018-12-14 中国农业科学院哈尔滨兽医研究所(中国动物卫生与流行病学中心哈尔滨分中心) The airtight cracking structure of biosecurity laboratory
CN109024931A (en) * 2018-07-24 2018-12-18 云南建投第三建设有限公司 A kind of flooring expanssion joint construction process
CN109267709A (en) * 2018-11-05 2019-01-25 广东赛力克建筑技术工程有限公司 A kind of deformation joint anti-seepage drain structure and its restorative procedure
CN209723256U (en) * 2019-02-25 2019-12-03 中国葛洲坝集团第一工程有限公司 A kind of double-faced waterproofing structure for pond pond body construction joint seepage treatment
CN113279490A (en) * 2021-04-02 2021-08-20 中国十七冶集团有限公司 Leakage plugging structure for post-cast strip of basement floor of civil air defense and construction method thereof
CN113863518A (en) * 2021-10-26 2021-12-31 中铁上海工程局集团有限公司 Construction method for initiation joint of integral biochemical pool

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030094979A (en) * 2002-06-11 2003-12-18 김현우 Connecting member for water proofing using in concrete structure
CN2918575Y (en) * 2006-04-28 2007-07-04 曹世龙 New composite water stop
CN101372840A (en) * 2007-08-21 2009-02-25 上海市建筑科学研究院(集团)有限公司 Mounting method with detachable rubber water stop mounted inside
KR100805842B1 (en) * 2007-10-29 2008-02-21 고삼석 A joint device and construction method of concrete structure
KR20100112278A (en) * 2009-04-09 2010-10-19 씨엘엠테크(주) Repair Method for Concrete Joint Part
KR200449712Y1 (en) * 2010-01-28 2010-08-03 이해선 Water protecting finishing material for concrete joint
KR101372749B1 (en) * 2013-07-15 2014-03-11 (주)대한콜크 Multi-performance functional water stop plate with composite structure
CN203782900U (en) * 2014-04-29 2014-08-20 中铁四局集团第三建设有限公司 Deformation joint water stopping structure for ultrathin reinforced concrete tank
CN105888247A (en) * 2016-04-26 2016-08-24 中国化学工程第三建设有限公司 Construction method for expansion joint of industrial pond
CN106088364A (en) * 2016-07-25 2016-11-09 浙江万达建设集团有限公司 A kind of Novel underground room antiseep attachment structure and construction method thereof
CN208236013U (en) * 2018-02-12 2018-12-14 中国农业科学院哈尔滨兽医研究所(中国动物卫生与流行病学中心哈尔滨分中心) The airtight cracking structure of biosecurity laboratory
CN109024931A (en) * 2018-07-24 2018-12-18 云南建投第三建设有限公司 A kind of flooring expanssion joint construction process
CN109267709A (en) * 2018-11-05 2019-01-25 广东赛力克建筑技术工程有限公司 A kind of deformation joint anti-seepage drain structure and its restorative procedure
CN209723256U (en) * 2019-02-25 2019-12-03 中国葛洲坝集团第一工程有限公司 A kind of double-faced waterproofing structure for pond pond body construction joint seepage treatment
CN113279490A (en) * 2021-04-02 2021-08-20 中国十七冶集团有限公司 Leakage plugging structure for post-cast strip of basement floor of civil air defense and construction method thereof
CN113863518A (en) * 2021-10-26 2021-12-31 中铁上海工程局集团有限公司 Construction method for initiation joint of integral biochemical pool

Similar Documents

Publication Publication Date Title
CN206768880U (en) A kind of waterproof construction for seashore pipe gallery
CN101403218B (en) Processing method for basement water-proof concrete construction joint
CN207987983U (en) A kind of waterproof construction being used for underground engineering main body construction seam and post-cast strip
CN102758456B (en) Construction method of basement waterproofing projects
CN107489167A (en) A kind of underground pipe gallery socket joint deformation joint structure and its construction method
CN107190782A (en) A kind of poured band of outer wall of basement structure and its construction method
CN104153401A (en) Waterproof construction method for anti-floating anchor rods
CN102776897A (en) Wash apron anti-settling anti-cracking construction method and structure
CN103184747A (en) Method and structure for leakage seepage prevention construction for two-walls-in-one structure of deep-underground engineering
CN106545030B (en) Small-sized buried reservoir of one kind and preparation method thereof
CN201943086U (en) Underground building wall body
CN111705971A (en) Construction method and structure of thin-wall concrete wall of constructed wetland unit pool
CN110241806A (en) A kind of method and crust layer forming crust layer on dredging silt slurry stockyard surface
CN104652495B (en) Internal support of foundation pit column and base plate node waterproof construction technology
CN101748753A (en) Plugging construction method of reserved opening of basement soleplate and tower crane foundation and post-pouring zone reserved opening
CN209723256U (en) A kind of double-faced waterproofing structure for pond pond body construction joint seepage treatment
CN201162233Y (en) Rear irrigation zone structure with higher ground water level
CN207211188U (en) Outer wall of underground structure HCMW engineering methods overlap wall
CN110409600A (en) Unit-combination type cesspool construction method
CN207685961U (en) Spliced gutter based on bellows
CN206220277U (en) The simple type deformation joint structure of site operation
CN105756100A (en) Basement post-pouring belt system and making method thereof
CN109736457A (en) A kind of double-faced waterproofing structure and processing method for pond pond body construction joint seepage treatment
CN107326924A (en) Outer wall of underground structure HCMW engineering methods overlap wall and its construction method
CN106638544A (en) Anti-seepage and anti-cracking construction method for ultra-large reinforced concrete bio-oxidation pond in cold area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination