CN106638544A - Anti-seepage and anti-cracking construction method for ultra-large reinforced concrete bio-oxidation pond in cold area - Google Patents

Anti-seepage and anti-cracking construction method for ultra-large reinforced concrete bio-oxidation pond in cold area Download PDF

Info

Publication number
CN106638544A
CN106638544A CN201611215686.1A CN201611215686A CN106638544A CN 106638544 A CN106638544 A CN 106638544A CN 201611215686 A CN201611215686 A CN 201611215686A CN 106638544 A CN106638544 A CN 106638544A
Authority
CN
China
Prior art keywords
construction
pond
bio
wall
oxidation pond
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611215686.1A
Other languages
Chinese (zh)
Inventor
刘钰
张生雨
刘伟杰
张然
隋新
王�琦
杨俊刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201611215686.1A priority Critical patent/CN106638544A/en
Publication of CN106638544A publication Critical patent/CN106638544A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • E04B1/6806Waterstops

Abstract

The invention discloses an anti-seepage and anti-cracking construction method for an ultra-large reinforced concrete bio-oxidation pond in a cold area. The method includes the steps that 1) a foundation is treated through a replacement method suitable for a shallow layer soft soil layer and a nonuniform soil layer; 2) after foundation replacement is completed, a bottom plate is partitioned into regions, the length and width of each region do not exceed 40 m, and the bottom plate of the bio-oxidation pond is poured through a partition jump warehouse method; 3) a pond wall formwork is constructed; 4) construction of follow-up process is carried out, and finally overall construction of the bio-oxidation pond is completed. The whole foundation replacement method is adopted, the foundation settlement is changed to be flexible micro settlement, and meanwhile the degree of foundation deformation in the Alpine region is reduced; construction joints are arranged through the jump warehouse method, construction is carried out in stages, harmful cracks of concrete are effectively controlled, and the anti-cracking safety of an engineering is ensured; a water stop strip of a common wall bolt is enlarged, block pieces are arranged at the two ends of the bolt according to the width of the pond wall, the size errors of a reinforcement protective layer and the pond wall are ensured, and leakage is avoided.

Description

The seepage control and crack resistance construction method of cold district ultra-large type armored concrete bio-oxidation pond
Technical field
The present invention relates to technical field of building construction, more particularly to a kind of cold district ultra-large type armored concrete biology The construction method of oxidation pond seepage control and crack resistance.
Background technology
With the fast development of Environmental Protection in China industry and environmental improvement engineering, the construction power of macro-organism oxidation pond is increased Degree, while also increasing the technical barriers such as impervious bad, thermal cracking many in large pool work progress.Agent on crack resistance of concrete Oozing property is bad and shrinkage cracking is the principal element for affecting waterproof concrete structure performance and structure service life, it is different from So under condition element, especially extremely frigid zones, anticracking, antiseepage difficulty are bigger by contrast.The patcher caused due to seepage Make that difficulty is big, costly, success rate is low.
Under the conditions of current construction technology, larger cast-in-situ reinforced concrete pond does not set large-sized reinforced mixed with movement joint Solidifying soil base plate, if temperature is higher during concreting, plus upper plate is thicker, and inside concrete heat of hydration temperature rise is larger, makes to mix Solidifying soil internal temperature is higher.Work as concrete cooling, when internal moisture evaporation concrete produces larger contraction, be subject to ground under base plate The constraint of base, edge is subject to the strong constraint of big rigidity, when preventing base plate from freely stretching, will occur very in base plate interior Big shrinkage tensile stress, causes base plate to occur deeper, even crosscutting concern, makes structures percolating water, destroys structure Globality, affects normally using for structures.
In Concrete Engineering Cracks Producing reason, due to deformation (humiture, deformation and expansion, differential settlement) reason The crack of generation accounts for 80%, and the crack that external force reason is produced accounts for 20%.
Often there are Vertical Cracks in roomy thin-walled pond.Different in size, the width difference in crack, it is mutually discontinuous.General pool wall Intermediate cracking is closeer, wider, in 0.5mm or so, after mostly occurring in construction period or enabling soon.Open type no-top plate pond, Crack often occurs in pool wall top, in shape with wide top and narrow bottom.There is the larger collar tie beam of top board or rigidity, crack occurs in pool wall mostly Portion, in the narrow prismatic shape in middle width two ends.Sometimes wall is shown as outer wide, narrow through crack and outer surface crack, cause in wall Pool wall serious leakage water, harmfulness is very big.
The content of the invention
The purpose of the present invention is for technological deficiency present in prior art, there is provided a kind of cold district super large steel bar The construction method of concrete bio-oxidation pond seepage control and crack resistance.
For this purpose, the present invention is employed the following technical solutions:
A kind of seepage control and crack resistance construction method of cold district ultra-large type armored concrete bio-oxidation pond, including following step Suddenly,
1) with the groundsill treatment suitable for shallow poor subsoil layer and uneven soil layer;
2) after the completion of ground is changed and filled out, by base plate subregion, the length and width in each area is less than 40 meters, is jumped using subregion Storehouse method carries out pouring for bio-oxidation pond base plate;
3) pond wall moulding board construction:After completing bio-oxidation pond bottom slab concreting, pond wall moulding board construction is carried out, in pool wall circumference side To one construction joint is formed with, construction joint is apart from bio-oxidation pond base plate 600mm;Steel is set in pool wall body of wall at construction joint Plate waterstop, when bottom plate is removed, first split bolt reservation of the steel plate water-stopping under band does not fracture, in pool wall Most beneath a piece of template is supported during formwork;Adjacent pond wall moulding board leads nail and fixes temporarily using waste and old lath, upper and lower wooden model docking Place spells folder and strengthens using short flitch, and steel pipe longitudinal direction back cord is placed from top to down, depending on placing density according to rigidity requirement, installs horizontal To back cord, and fixed by split bolt and chevron card, finally, fasten split bolt, complete pond wall moulding board construction;
4) construction of subsequent handling is carried out, the integral construction of bio-oxidation pond is finally completed.
Wherein described subregion is jumped storehouse method and is comprised the following steps:
(1) rubber fastening band for being sized, shaping is manufactured according to the size in each area of base plate, rubber water-proof is utilized between each area Band connection waterproof, adjacent waterstop heat connects in succession, makes the seam of waterstop smooth firmly, without breach, degumming phenomenon;
(2) by after the completion of the concreting in a region, it is ensured that waterstop not damaged, treat that the region completes to pour 7 days After, carry out pouring for next adjacent area.
In above-mentioned steps (1), raw stock is placed between two joints of rubber fastening band, by electrothermal sulfurizing by adjacent rubber Glue waterstop is connected;In step (2), the region to having separated carries out spacer block construction, placement layer by layer, global formation.
In one embodiment of the invention, the base areas of the bio-oxidation pond are 180530mmX 75500mm, will The base plate is divided into 5X2 region, and adjacent two is interregional every pouring, and interval time is 7 days.When pouring, first can pour simultaneously 1st, 3,5,7,9 regions, interval pours the 2nd, 4,6,8,10 regions after 7 days, then simultaneously.First can also simultaneously pour the 1st, 5 regions, then the 2nd, 4 regions are poured, then simultaneously the 3rd, 7,9 regions are poured, it is last to pour the 6th, 8,10 areas simultaneously Domain.
During construction, longitudinal and transverse back cord uses steel pipe, and increases the sealing piece width of wall-crossing opposite-drawing bolt, in pool wall both sides Split bolt bar on fixed dam is installed.
Compared with prior art, the invention has the advantages that:
1st, by the construction method of the present invention, the technical requirements of pond no seepage and no leakage can be preferably reached, reduces and repair The waste of the working-day claims and manpower and materials that bring, it is cost-effective.
2nd, the present invention using jump storehouse method arrange construction joint, constructed stage by stage, can effective control concrete harmful cracks, Guarantee engineering anti-cracking safety.
3rd, the present invention integrally changes back-up sand method using ground, settlement of foundation form is changed into into flexible micro- sedimentation, while also dropping The low degree of extremely frigid zones foundation deformations.
4th, in the present invention, in length and breadth back cord adopts steel pipe supporting module, can increase rigidity, and solution pool wall is too thin, reinforcing bar Closeer, difficulty of vibrating and the easily problem of generation template deformation, are effectively reduced interior formwork, increase water-proof concrete From close property.
5th, it is of the invention by common through-wall bolt to avoid seepage because formwork reinforcement needs many through-wall bolts Sealing piece increase, bolt two ends press pool wall width setting catch, it is ensured that the scale error of cover to reinforcement and pool wall, so as to Avoid seepage.
Description of the drawings
Fig. 1 is in the method for the present invention, to jump storehouse pouring construction structural representation;
Fig. 2 is bottom of pond, the template construction structural representation of pool wall in the method for the present invention;
Fig. 3 is the structural representation of the modified split bolt adopted in the method for the present invention.
In figure:
The 21. horizontal split bolts of steel pipe back cord 23. of longitudinal steel pipe back cord 22.
The split bolt bar of 31. fixed dam, 32. enlarged sealing piece 33.
Specific embodiment
Below in conjunction with the accompanying drawings the construction method of the present invention is described in detail with specific embodiment.
The seepage control and crack resistance construction method of the cold district ultra-large type armored concrete bio-oxidation pond of the present invention includes following Step:
1) with the groundsill treatment suitable for shallow poor subsoil layer and uneven soil layer:
By taking the basement process process of a subregion as an example, earth excavation to the bearing stratum for meeting design requirement, by substrate Carry out changing after cleaning filling out, Con trolling index is filled out by calculating the limit value for changing the thickness and width filled out and being used as to change, by scene Test determines the optimum moisture content and maximum dry density of changing back-up sand for using, it is ensured that grinding compacting, reaches compacting factor.
2) after the completion of basement process, pouring for pond baseboard concrete is carried out using storehouse method is jumped, first (divides base plate subregion Section), the length and width in each area is less than 40 meters, is mixed by spacer block construction, placement layer by layer and global formation after segmentation Solidifying native pours.
By taking the embodiment of Fig. 1 as an example, base plate that can be by area for 180530mm X 75500mm is divided into 5X2 area, often The length and width in individual area is less than 40 meters.In figure, every pouring, interval time is 7 days in adjacent two interval.Can be according to progress Arrange, it is determined that order is specifically poured, for example:Can pour simultaneously the 1st in figure, 3,5,7,9th area, interval is after 7 days, then pours simultaneously Build the 2nd in figure, 4,6,8,10th area;First the 1st, 5th area can also be poured simultaneously, then pour the 2nd, 4th area, then pour the 3rd simultaneously, 7, 9th area, it is last pour the 6th simultaneously, 8,10th area.Can with meet spacer block construction under conditions of, suitably sequentially pour by other.
Rubber fastening band is set between adjacent twoth area, to prevent Seepage.Rubber fastening band is according to each area Size is sized, patterning process, and the rubber fastening band in each area is connect in succession using shaper heat.By the concreting in an area After the completion of, check waterstop, it is ensured that its not damaged, after Dai Gai areas complete to pour 7 days, carry out pouring for next adjacent region.
3) after the completion of bottom slab concreting, pool wall reinforcing bar colligation is carried out, pond wall moulding board installation is carried out after the completion of colligation.
It is biological in order to improve the surface quality of wooden model and using degree by taking the model sheetinstallat in an area as an example referring to Fig. 2 The construction of oxidation pond pond wall moulding board using 48*3.5mm steel pipes as back cord, to ensure concrete in real outer light, effectively reduce coagulation Native blibbing, increases water-proof concrete from close property.The present invention is optimized to traditional handicraft, i.e.,:Pouring biological oxidation During bottom of pond plate, one construction joint is formed with pool wall circumferencial direction, construction joint indwelling position is at base plate 600mm, in construction Steel plate water stopper is set in the pool wall body of wall at seam.When bottom plate is removed, first split bolt of steel plate water-stopping under band is protected Stay and do not fracture, be used for supporting lowermost a piece of template in pool wall formwork, up and down adjacent forms are led using waste and old lath Nail is interim fixed, and upper and lower wooden model joint is spelled folder and strengthened using short flitch, and longitudinal back cord 21 is placed from top to down, places density root Determine according to rigidity requirement calculating, horizontal back cord 22 is installed and is fixed by split bolt and chevron card, finally fasten split bolt 23, complete pond wall moulding board construction.After the completion of pond wall moulding board construction, the construction of subsequent handling is carried out, be finally completed bio-oxidation pond Integral construction.
Referring to Fig. 3, due to oxidation pond waterproof requirement it is higher, and for thin-wall construction, so the present invention increases split bolt The width of 23 sealing piece 32.Because through-wall bolt may cause leakage hidden trouble, sealing piece width is increased, can be better ensured that Its stagnant water effect.In addition, install fixed dam 31 additional in the split bolt bar 33 of pool wall both sides, to control protective layer thickness and cut Face size, prevents to produce infiltration phenomenon at split bolt.

Claims (9)

1. a kind of seepage control and crack resistance construction method of cold district ultra-large type armored concrete bio-oxidation pond, comprises the following steps,
1) with the groundsill treatment suitable for shallow poor subsoil layer and uneven soil layer;
2) after the completion of ground is changed and filled out, by base plate subregion, the length and width in each area is less than 40 meters, using subregion storehouse method is jumped Carry out pouring for bio-oxidation pond base plate;
3) pond wall moulding board construction:After completing bio-oxidation pond bottom slab concreting, pond wall moulding board construction is carried out, in pool wall circumferencial direction shape Into there is one construction joint, steel plate water stopper is set in the pool wall body of wall at construction joint, when bottom plate is removed, the steel plate First split bolt retains and does not fracture under waterstop, for supporting most beneath a piece of template in pool wall formwork;Adjacent pond Wall form leads nail and fixes temporarily using waste and old lath, and upper and lower wooden model joint spells folder reinforcement using short flitch, places from top to down Steel pipe longitudinal direction back cord, depending on placing density according to rigidity requirement, installs horizontal back cord, and is fixed by split bolt and chevron It is fixed, finally, split bolt is fastened, complete pond wall moulding board construction;
4) construction of subsequent handling is carried out, the integral construction of bio-oxidation pond is finally completed.
2. seepage control and crack resistance construction method according to claim 1, it is characterised in that the subregion jumps storehouse method includes following step Suddenly:
(1) rubber fastening band for being sized, shaping is manufactured according to the size in each area of base plate, is connected using rubber fastening band between each area Water is taken over control, adjacent waterstop heat connects in succession, make the seam of waterstop smooth firmly, without breach, degumming phenomenon;
(2) by after the completion of the concreting in a region, it is ensured that waterstop not damaged, after the region completes to pour 7 days, Carry out pouring for next adjacent area.
3. seepage control and crack resistance construction method according to claim 2, it is characterised in that:In step (1), raw stock is placed in into rubber Between two joints of glue waterstop, adjacent rubber fastening band is connected by electrothermal sulfurizing.
4. seepage control and crack resistance construction method according to claim 2, it is characterised in that:In step (2), to the region for having separated Carry out spacer block construction, placement layer by layer, global formation.
5. seepage control and crack resistance construction method according to claim 4, it is characterised in that:The base areas of the bio-oxidation pond For 180530mmX 75500mm, the base plate is divided into into 5X2 region, adjacent two is interregional every pouring, and interval time is 7 days.
6. seepage control and crack resistance construction method according to claim 5, it is characterised in that:First pour the 1st, 3,5,7,9 simultaneously Region, interval pours the 2nd, 4,6,8,10 regions after 7 days, then simultaneously.
7. seepage control and crack resistance construction method according to claim 5, it is characterised in that:First simultaneously the 1st, 5 regions are poured, then The 2nd, 4 regions are poured, then the 3rd, 7,9 regions is poured simultaneously, it is last to pour the 6th, 8,10 regions simultaneously.
8. the seepage control and crack resistance construction method according to any one of claim 1-7, it is characterised in that:During construction, the longitudinal and transverse back of the body It is stupefied to use steel pipe, and the sealing piece width of wall-crossing opposite-drawing bolt is increased, it is provided with the split bolt bar of pool wall both sides solid Determine baffle plate.
9. seepage control and crack resistance construction method according to claim 8, it is characterised in that:The construction joint is apart from bio-oxidation pond Base plate 600mm.
CN201611215686.1A 2016-12-26 2016-12-26 Anti-seepage and anti-cracking construction method for ultra-large reinforced concrete bio-oxidation pond in cold area Pending CN106638544A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611215686.1A CN106638544A (en) 2016-12-26 2016-12-26 Anti-seepage and anti-cracking construction method for ultra-large reinforced concrete bio-oxidation pond in cold area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611215686.1A CN106638544A (en) 2016-12-26 2016-12-26 Anti-seepage and anti-cracking construction method for ultra-large reinforced concrete bio-oxidation pond in cold area

Publications (1)

Publication Number Publication Date
CN106638544A true CN106638544A (en) 2017-05-10

Family

ID=58827164

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611215686.1A Pending CN106638544A (en) 2016-12-26 2016-12-26 Anti-seepage and anti-cracking construction method for ultra-large reinforced concrete bio-oxidation pond in cold area

Country Status (1)

Country Link
CN (1) CN106638544A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109740278A (en) * 2019-01-14 2019-05-10 青岛理工大学 A kind of Bracking-resistant method in the construction of top Overlong Concrete Structure
CN111911227A (en) * 2020-07-16 2020-11-10 四川省交通勘察设计研究院有限公司 Exploration design method for seasonal frozen soil highway tunnel
CN114059654A (en) * 2021-12-03 2022-02-18 河南沃克曼建设工程有限公司 Rapid construction method for improved AAO biological pond chamber jumping method of sewage treatment station

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0868103A (en) * 1994-08-31 1996-03-12 Leo Kaken Kk Corrosion-resistant execution method for water tank, etc., with concrete skeleton, corrosion-resistant panel, and formwork device
CN1455054A (en) * 2003-05-08 2003-11-12 中国第二十冶金建设公司 Ordinary concrete block bunker-jump casting crack control method
CN101086184A (en) * 2007-05-26 2007-12-12 中国建筑第七工程局第二建筑公司 Annular closure structure formwork support method
CN103321421A (en) * 2013-06-28 2013-09-25 河北省第二建筑工程公司 Construction method for one-time formation of concrete pool wall
CN203222993U (en) * 2013-04-26 2013-10-02 中化二建集团有限公司 Tool used for reinforcing steel concrete template
CN103437337A (en) * 2013-08-21 2013-12-11 国家电网公司 Method for reinforcing soft soil foundation in cushion layer replacement mode
CN103821364A (en) * 2014-02-24 2014-05-28 中国化学工程第十四建设有限公司 Method for constructing reinforced concrete pond
CN104963357A (en) * 2015-07-08 2015-10-07 中国十七冶集团有限公司 Large-area RC basement structure sequence construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0868103A (en) * 1994-08-31 1996-03-12 Leo Kaken Kk Corrosion-resistant execution method for water tank, etc., with concrete skeleton, corrosion-resistant panel, and formwork device
CN1455054A (en) * 2003-05-08 2003-11-12 中国第二十冶金建设公司 Ordinary concrete block bunker-jump casting crack control method
CN101086184A (en) * 2007-05-26 2007-12-12 中国建筑第七工程局第二建筑公司 Annular closure structure formwork support method
CN203222993U (en) * 2013-04-26 2013-10-02 中化二建集团有限公司 Tool used for reinforcing steel concrete template
CN103321421A (en) * 2013-06-28 2013-09-25 河北省第二建筑工程公司 Construction method for one-time formation of concrete pool wall
CN103437337A (en) * 2013-08-21 2013-12-11 国家电网公司 Method for reinforcing soft soil foundation in cushion layer replacement mode
CN103821364A (en) * 2014-02-24 2014-05-28 中国化学工程第十四建设有限公司 Method for constructing reinforced concrete pond
CN104963357A (en) * 2015-07-08 2015-10-07 中国十七冶集团有限公司 Large-area RC basement structure sequence construction method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
河北省第二建筑工程公司: "《污水(给水)处理厂工程施工技术》", 31 January 2009, 中国建筑工业出版社 *
都焱: "《土力学与基础工程》", 31 August 2016, 清华大学出版社 *
顾建生、徐晓红、李岩松: "《上海自然博物馆工程建设与管理》", 31 December 2014, 同济大学出版社 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109740278A (en) * 2019-01-14 2019-05-10 青岛理工大学 A kind of Bracking-resistant method in the construction of top Overlong Concrete Structure
CN109740278B (en) * 2019-01-14 2022-11-11 青岛理工大学 Anti-cracking method for construction of upper ultra-long concrete structure
CN111911227A (en) * 2020-07-16 2020-11-10 四川省交通勘察设计研究院有限公司 Exploration design method for seasonal frozen soil highway tunnel
CN114059654A (en) * 2021-12-03 2022-02-18 河南沃克曼建设工程有限公司 Rapid construction method for improved AAO biological pond chamber jumping method of sewage treatment station

Similar Documents

Publication Publication Date Title
CN102383443B (en) Connection structures between foundation pit support piles and outer walls of basement and construction method
CN103015719B (en) Preliminary work for spudding steel concrete wastewater disposal basin monobloc cast technique
CN206768880U (en) A kind of waterproof construction for seashore pipe gallery
CN101403218A (en) Processing method for basement water-proof concrete construction joint
CN107190782A (en) A kind of poured band of outer wall of basement structure and its construction method
CN203531009U (en) Macadam layer hydrophobic structure for basement base plate
CN105804410A (en) Sub-cabin pressure grouting method for vertical connection of prefabricated concrete structure
WO2023056984A1 (en) Waterproof structure and construction method for foundation pit support
CN104878783A (en) Super-long basement concrete base plate deformation joint leakage prevention and leakage treatment method
CN106545030B (en) Small-sized buried reservoir of one kind and preparation method thereof
CN106869166A (en) A kind of fabricated construction method for pipe gallery
CN106638544A (en) Anti-seepage and anti-cracking construction method for ultra-large reinforced concrete bio-oxidation pond in cold area
CN103938553B (en) The construction method of precast concrete facade panel quick-assembling reinforcing underwater structure
CN110439036A (en) A kind of poured band of outer wall of basement advance water stop construction method
CN104790436A (en) High-rise building basement roof settlement post-pouring joint advanced water stop construction method
CN103161176A (en) Tower crane foundation construction method in main building connected garage
CN104652495B (en) Internal support of foundation pit column and base plate node waterproof construction technology
CN101498136A (en) After-pouring strips structure with high underground water level
CN201162233Y (en) Rear irrigation zone structure with higher ground water level
CN105756100A (en) Basement post-pouring belt system and making method thereof
CN202347534U (en) Force transferring structure between foundation ditch support pile and basement outer wall
CN112761158A (en) Green construction method for integral outer wall (three-in-one) of reverse construction underground engineering steel concrete key pin occlusive row pile
CN106193120A (en) Basement is encorbelmented, and base plate is inverse makees structure and construction method
CN207934054U (en) A kind of prefabricated assembled raft foundation
CN207662389U (en) A kind of sedimentation and deformation observation base point using covered culvert

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510

RJ01 Rejection of invention patent application after publication