CN109702877A - A kind of concrete green body goes bottom skin stacking cycle operation device and its operational method - Google Patents
A kind of concrete green body goes bottom skin stacking cycle operation device and its operational method Download PDFInfo
- Publication number
- CN109702877A CN109702877A CN201910158908.8A CN201910158908A CN109702877A CN 109702877 A CN109702877 A CN 109702877A CN 201910158908 A CN201910158908 A CN 201910158908A CN 109702877 A CN109702877 A CN 109702877A
- Authority
- CN
- China
- Prior art keywords
- base machine
- green body
- walking
- steam
- bottom skin
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 17
- 238000010025 steaming Methods 0.000 claims abstract description 25
- 230000005540 biological transmission Effects 0.000 claims description 18
- 230000007423 decrease Effects 0.000 claims description 3
- 238000004519 manufacturing process Methods 0.000 abstract description 12
- 230000000694 effects Effects 0.000 abstract description 4
- 238000010586 diagram Methods 0.000 description 5
- 230000015271 coagulation Effects 0.000 description 2
- 238000005345 coagulation Methods 0.000 description 2
- 230000007547 defect Effects 0.000 description 2
- 238000011982 device technology Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000011454 mudbrick Substances 0.000 description 2
- 239000004035 construction material Substances 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Abstract
The invention discloses a kind of concrete green bodies to remove bottom skin stacking cycle operation device and its operational method, includes: steaming maintaining vehicle track as device, the steaming maintaining vehicle on steaming maintaining vehicle track of walking, the steam-cured soleplate being mounted on steaming maintaining vehicle;Tipper;Stacking loop wheel machine;Insert base machine and the slotting base machine track for inserting the walking of base machine;Parallel cutting waggon and the cutting conveyer track for cutting waggon walking with slotting base machine.As method the following steps are included: cutting waggon carrying steam-cured soleplate marches to slotting base station together with green body;It inserts base machine carrying steam-cured soleplate and marches to station turning together with green body;Bottom skin is removed in tipper overturning;Green body after removing bottom skin is hoisted on steaming maintaining vehicle by stacking loop wheel machine together with steam-cured soleplate.Concrete green body of the present invention goes bottom skin stacking cycle operation device and its operational method to substantially reduce the activity duration of bottom skin, stacking, improves production efficiency, promotes the raising of Business Economic Benefit.
Description
Technical field
The invention belongs to production of construction materials field more particularly to a kind of concrete green body go bottom skin stacking cycle operation device and
Its operational method.
Background technique
Currently, at home on most of air-entrained concrete building blocks and panel production line, the production for removing bottom skin, stacking of green body
Technique is: stacking loop wheel machine by cut waggon on steam-cured soleplate together with green body be hoisted to station turning carry out overturning remove bottom skin,
During bottom skin is removed in overturning, stacking loop wheel machine need to be waited in station turning, and only after green body has removed bottom skin, stacking loop wheel machine is
Steam-cured soleplate on tipper can be hoisted on steaming maintaining vehicle together with green body and carry out stacking, after stacking, then handling be gone to cut
The steam-cured soleplate and green body on waggon are cut, this production technology for fully relying on stacking loop wheel machine to convey green body exists
Production cycle is long, and ineffective defect constrains the raising of manufacturing enterprise's economic benefit.
Summary of the invention
To solve the above problems, the present invention proposes that a kind of concrete green body removes bottom skin stacking cycle operation device
And its operational method, the devices and methods therefor substantially reduce the activity duration of bottom skin, stacking, improve production efficiency, promote
Into the raising of Business Economic Benefit.
To achieve the goals above, as the device of the invention, using following scheme comprising:
Steaming maintaining vehicle track, the steaming maintaining vehicle on steaming maintaining vehicle track of walking, the steam-cured soleplate being mounted on steaming maintaining vehicle;Overturning
Machine;Across steaming maintaining vehicle, tipper and the stacking loop wheel machine being positioned above;
The apparatus for work further includes inserting base machine and the slotting base machine track for inserting the walking of base machine;On the right side of slotting base machine
And the cutting conveyer track for cutting waggon and walk for cutting waggon with slotting base machine parallel.
The slotting base machine includes rack, and the lower part of rack is equipped with walking mechanism, and the top of rack is equipped with telescoping mechanism;
The walking mechanism includes the idler wheel for being rotatably connected on rack two sides, which, which rolls, connects the slotting base machine rail
Road is connected to the walking transmission case of bottom of the frame, and the input terminal for transmission case of walking connects movable motor, walking transmission case two sides
Output end connects the sliding duplicate gear, and the end of the sliding duplicate gear connects walking gear, and walking gear engagement, which is located at, inserts base machine rail
Walking rack on the inside of road;
The telescoping mechanism includes a pair of of telescopic arm positioned at upper rack, the bottom surface connection sliding block of telescopic arm, the sliding block
The sliding rail being slidably connected in rack, the top surface of rack are connected with flexible transmission case, the flexible electricity of input terminal connection for the transmission case that stretches
The output end of machine, transmission case two sides of stretching connects telescopic propeller shaft, which rotatably connects rack, driving of stretching
The end of axis connects flexible gear, and the flexible rack gear on the flexible gear engagement telescopic arm top surface, the end of the telescopic arm is also
Equipped with lifting body.
The lifting body includes the jacking cylinder for being connected to telescopic arm tip inside, and the piston rod of jacking cylinder connects top
Lift slab.
The walking rack is connected to the bottom surface on the inside of connector along longitudinal direction, which is fixedly connected with ground.
The inside of the cutting conveyer track is equipped with the cutting hole longitudinally extended.
As method of the invention, comprising the following steps:
Cutting waggon carrying steam-cured soleplate marches to slotting base station together with green body;
The telescopic arm for inserting base machine stretches out, and raising plate is located at the both ends of green body lower part steam-cured soleplate, starts jacking cylinder support
Steam-cured soleplate is played, telescopic arm retracts;
It inserts base machine carrying steam-cured soleplate and marches to station turning together with green body;
The telescopic arm for inserting base machine stretches out, and steam-cured soleplate is placed on tipper, then by raising plate decline together with green body
Telescopic arm retracts;
Bottom skin is removed in tipper overturning, meanwhile, it inserts base machine and returns to slotting base station;
Green body after removing bottom skin is hoisted on steaming maintaining vehicle by stacking loop wheel machine together with steam-cured soleplate, meanwhile, it inserts base machine and holds again
It carries steam-cured soleplate and marches to station turning together with green body;
By parity of reasoning, repeats the above steps.
Concrete green body of the present invention goes bottom skin stacking cycle operation device and its operational method to substantially reduce coagulation sun-dried mud brick
Body goes the activity duration of bottom skin, stacking, improves production efficiency, promotes the raising of Business Economic Benefit.
Detailed description of the invention
Fig. 1 is that the present invention removes bottom skin stacking cycle operation device technology arrangement schematic diagram.
Fig. 2 is the slotting base machine schematic view of the front view of the present invention.
Fig. 3 is the overlooking structure diagram of Fig. 2.
Fig. 4 is the right side structural representation of Fig. 2.
Fig. 5 is schematic diagram when inserting base machine and cutting waggon coordinating operation.
Fig. 6 is schematic diagram when inserting base machine and tipper coordinating operation.
Fig. 7 is that original removes bottom skin stacking cycle operation device technology arrangement schematic diagram.
Specific embodiment
Have for the ease of those skilled in the art to the present invention and be further understood in detail, now goes bottom skin stacking to recycle original
Apparatus for work and its operational method are made one and are simply introduced, as shown in fig. 7, cutting conveying of the walking on cutting conveyer track 17
Green body after cutting is delivered to lifting station by vehicle 16, and stacking loop wheel machine 15 hangs the steam-cured soleplate cut on waggon together with green body
It is transported to tipper 14, stacking loop wheel machine waits tipper overturning to remove bottom skin, and after removing bottom skin, stacking loop wheel machine will be on tipper
Steam-cured soleplate 13 is hoisted to the steaming maintaining vehicle 12 walked on steaming maintaining vehicle track 11 together with green body, and then, stacking loop wheel machine returns to lifting
Station, the steam-cured soleplate and green body on handling cutting waggon, cutting hole 18 are used to store the waste material under cutting again.Thus may be used
See, this production technology for fully relying on stacking loop wheel machine to convey green body is long there are the production cycle, ineffective
Defect.
The present invention is described in further detail with reference to the accompanying drawing,
As the device of the invention, as shown in Figure 1, comprising:
Steaming maintaining vehicle track 1, the steaming maintaining vehicle 2 on steaming maintaining vehicle track of walking, the steam-cured soleplate 3 being mounted on steaming maintaining vehicle;It turns over
Favourable turn 4;Across steaming maintaining vehicle, tipper and the stacking loop wheel machine 5 being positioned above;
The apparatus for work further includes inserting base machine 6 and the slotting base machine track 7 for inserting the walking of base machine;It is right positioned at slotting base machine
Side and the cutting waggon 8 parallel with slotting base machine and the cutting conveyer track 9 walked for cutting waggon.
As shown in Figure 2, Figure 3, Figure 4, the slotting base machine includes rack 6-1, and the lower part of rack is equipped with walking mechanism, rack
Top be equipped with telescoping mechanism;
The walking mechanism includes the idler wheel 6-2 for being rotatably connected on rack two sides, which, which rolls, connects the slotting base machine
Track is connected to the walking transmission case 6-3 of bottom of the frame, and the input terminal for transmission case of walking connects movable motor, transmission case of walking
The output end of two sides connects the sliding duplicate gear 6-4, and the end of the sliding duplicate gear connects walking gear 6-5, walking gear engagement
Walking rack 6-6 on the inside of slotting base machine track;
The telescoping mechanism includes a pair of of telescopic arm 6-7, the bottom surface connection sliding block 6-8 of telescopic arm positioned at upper rack,
The sliding block is slidably connected the sliding rail 6-9 in rack, and the top surface of rack is connected with flexible transmission case 6-10, the input for the transmission case that stretches
End connection telescope motor 6-11, the output end for transmission case two sides of stretching connect telescopic propeller shaft 6-12, which can turn
Dynamic connection rack, the end of telescopic propeller shaft connect flexible gear 6-13, stretching on the flexible gear engagement telescopic arm top surface
Contracting rack gear 6-14, the end of the telescopic arm are additionally provided with lifting body.
As the preferred embodiment of the present invention, the lifting body includes the jacking cylinder for being connected to telescopic arm tip inside
The piston rod of 6-15, jacking cylinder connect raising plate 6-16.
As the preferred embodiment of the present invention, the walking rack is connected to the bottom surface on the inside of connector 6-17 along longitudinal direction,
The connector is fixedly connected with ground.
The inside of the cutting conveyer track is equipped with the cutting hole 10 longitudinally extended.
As method of the invention, as shown in Figure 5, Figure 6, comprising the following steps:
Cutting waggon 8 carries steam-cured soleplate and marches to slotting base station together with green body 20;
The telescopic arm for inserting base machine 6 stretches out, and raising plate is located at the both ends of green body lower part steam-cured soleplate, starts jacking cylinder support
Steam-cured soleplate is played, telescopic arm retracts;
It inserts base machine carrying steam-cured soleplate and marches to station turning together with green body;
The telescopic arm for inserting base machine stretches out, and steam-cured soleplate is placed on tipper 4, so by raising plate decline together with green body
Telescopic arm retracts afterwards;
Bottom skin is removed in tipper overturning, meanwhile, it inserts base machine and returns to slotting base station;
Green body after removing bottom skin is hoisted on steaming maintaining vehicle 2 by stacking loop wheel machine 5 together with steam-cured soleplate 3, meanwhile, insert base machine again
It carries steam-cured soleplate and marches to station turning together with green body;
By parity of reasoning, repeats the above steps.
Concrete green body of the present invention goes bottom skin stacking cycle operation device and its operational method to substantially reduce coagulation sun-dried mud brick
Body goes the activity duration of bottom skin, stacking, improves production efficiency, promotes the raising of Business Economic Benefit.
Claims (6)
1. a kind of concrete green body removes bottom skin stacking cycle operation device comprising steaming maintaining vehicle track (1) is walked in steam-cured track
Steaming maintaining vehicle (2) on road, the steam-cured soleplate (3) being mounted on steaming maintaining vehicle;Tipper (4);Across steaming maintaining vehicle, tipper and it is located at
Stacking loop wheel machine (5) above it;It is characterized in that, the apparatus for work further include: insert base machine (6) and for inserting the walking of base machine
Insert base machine track (7);Positioned at slotting base machine right side and the cutting waggon (8) parallel with slotting base machine and for cutting waggon walking
Cutting conveyer track (9).
2. removing bottom skin stacking cycle operation device according to claim 1, which is characterized in that the slotting base machine includes: rack
(6-1), the lower part of rack are equipped with walking mechanism, and the top of rack is equipped with telescoping mechanism;
The walking mechanism includes the idler wheel (6-2) for being rotatably connected on rack two sides, which, which rolls, connects the slotting base machine rail
Road is connected to the walking transmission case (6-3) of bottom of the frame, and the input terminal for transmission case of walking connects movable motor, transmission case of walking
The output end of two sides connects the sliding duplicate gear 6-4), the end of the sliding duplicate gear connects walking gear (6-5), which nibbles
Walking rack (6-6) of the coincidence on the inside of slotting base machine track;
The telescoping mechanism includes a pair of of telescopic arm (6-7) positioned at upper rack, the bottom surface connection sliding block (6-8) of telescopic arm,
The sliding block is slidably connected the sliding rail (6-9) in rack, and the top surface of rack is connected with flexible transmission case (6-10), and stretch transmission case
Input terminal connects telescope motor (6-11), and the output end for transmission case two sides of stretching connects telescopic propeller shaft (6-12), the flexible drive
Moving axis rotatably connects rack, and the end of telescopic propeller shaft connects flexible gear (6-13), which engages telescopic arm
Flexible rack gear (6-14) on top surface, the end of the telescopic arm is additionally provided with lifting body.
3. removing bottom skin stacking cycle operation device according to claim 2, it is characterised in that: the lifting body includes connection
Raising plate (6-16) is connected in the piston rod of the jacking cylinder (6-15) of telescopic arm tip inside, jacking cylinder.
4. removing bottom skin stacking cycle operation device according to claim 2, it is characterised in that: the walking rack connects along longitudinal direction
The bottom surface on the inside of connector (6-17) is connect, which is fixedly connected with ground.
5. removing bottom skin stacking cycle operation device according to claim 1, it is characterised in that: the cutting conveyer track
Inside is equipped with the cutting hole (10) longitudinally extended.
6. a kind of concrete green body goes bottom skin stacking cycle operation method, which is characterized in that the operational method includes following step
It is rapid:
Cutting waggon (8) carrying steam-cured soleplate marches to slotting base station together with green body (20);
The telescopic arm for inserting base machine (6) stretches out, and raising plate is located at the both ends of green body lower part steam-cured soleplate, and starting jacking cylinder is held up
Steam-cured soleplate, telescopic arm retract;
It inserts base machine carrying steam-cured soleplate and marches to station turning together with green body;
The telescopic arm for inserting base machine stretches out, and steam-cured soleplate is placed on tipper (4), then by raising plate decline together with green body
Telescopic arm retracts;
Bottom skin is removed in tipper overturning, meanwhile, it inserts base machine and returns to slotting base station;
Green body after removing bottom skin is hoisted on steaming maintaining vehicle (2) by stacking loop wheel machine (5) together with steam-cured soleplate (3), meanwhile, insert base machine again
Secondary carrying steam-cured soleplate marches to station turning together with green body;
By parity of reasoning, repeats the above steps.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910158908.8A CN109702877B (en) | 2019-03-04 | 2019-03-04 | Concrete blank bottom skin removing stacking cyclic operation device and operation method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910158908.8A CN109702877B (en) | 2019-03-04 | 2019-03-04 | Concrete blank bottom skin removing stacking cyclic operation device and operation method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109702877A true CN109702877A (en) | 2019-05-03 |
CN109702877B CN109702877B (en) | 2023-12-08 |
Family
ID=66266169
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910158908.8A Active CN109702877B (en) | 2019-03-04 | 2019-03-04 | Concrete blank bottom skin removing stacking cyclic operation device and operation method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109702877B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112792965A (en) * | 2021-02-04 | 2021-05-14 | 安徽科达机电有限公司 | Double-station semi-finished product overturning machine |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1198670A (en) * | 1997-09-24 | 1999-04-09 | Nihon Ytong Co Ltd | Underground embedded object protective block and its manufacture |
CN102862228A (en) * | 2012-10-10 | 2013-01-09 | 江苏腾宇机械制造有限公司 | Bottom cover removing device for aerated concrete |
CN103009470A (en) * | 2012-12-12 | 2013-04-03 | 福建泉工股份有限公司 | Fully-automatic trimming hanger for aerated concrete production line and trimming method |
CN104097258A (en) * | 2014-05-19 | 2014-10-15 | 安徽科达机电有限公司 | Bottom plate replacing device and method |
CN206011413U (en) * | 2016-08-26 | 2017-03-15 | 安徽科达机电有限公司 | A kind of automatic bottom skin removing overturning platform |
CN207616869U (en) * | 2017-11-30 | 2018-07-17 | 佛山市恒益环保建材有限公司 | A kind of piler automatic production line |
CN209737932U (en) * | 2019-03-04 | 2019-12-06 | 安徽科达机电有限公司 | Bottom skin removing and stacking cyclic operation device for concrete body |
-
2019
- 2019-03-04 CN CN201910158908.8A patent/CN109702877B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1198670A (en) * | 1997-09-24 | 1999-04-09 | Nihon Ytong Co Ltd | Underground embedded object protective block and its manufacture |
CN102862228A (en) * | 2012-10-10 | 2013-01-09 | 江苏腾宇机械制造有限公司 | Bottom cover removing device for aerated concrete |
CN103009470A (en) * | 2012-12-12 | 2013-04-03 | 福建泉工股份有限公司 | Fully-automatic trimming hanger for aerated concrete production line and trimming method |
CN104097258A (en) * | 2014-05-19 | 2014-10-15 | 安徽科达机电有限公司 | Bottom plate replacing device and method |
CN206011413U (en) * | 2016-08-26 | 2017-03-15 | 安徽科达机电有限公司 | A kind of automatic bottom skin removing overturning platform |
CN207616869U (en) * | 2017-11-30 | 2018-07-17 | 佛山市恒益环保建材有限公司 | A kind of piler automatic production line |
CN209737932U (en) * | 2019-03-04 | 2019-12-06 | 安徽科达机电有限公司 | Bottom skin removing and stacking cyclic operation device for concrete body |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112792965A (en) * | 2021-02-04 | 2021-05-14 | 安徽科达机电有限公司 | Double-station semi-finished product overturning machine |
Also Published As
Publication number | Publication date |
---|---|
CN109702877B (en) | 2023-12-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105804762A (en) | Station-tunneling through and turn-over device for shield tunneling machine | |
CN212049150U (en) | Self-moving tail of large-stroke belt conveyor | |
CN106593469A (en) | Trolley for construction of inverted arch | |
CN109702877A (en) | A kind of concrete green body goes bottom skin stacking cycle operation device and its operational method | |
CN105397908A (en) | Movable full-automatic somersaulting bottom skin removing device | |
CN104326371A (en) | Unpowered mold-disassembly plate moving and flipping machine | |
CN110158973A (en) | A kind of frame tube apparatus and synchronization job formula frame pipe construction method | |
CN104773527B (en) | A kind of two-way chain-bucket layering pit discharging machine and its method of work | |
CN205591850U (en) | Full -automatic oil pipe post calandria moves a tub device | |
CN209737932U (en) | Bottom skin removing and stacking cyclic operation device for concrete body | |
CN218242806U (en) | Tunnel cable laying device | |
CN111017737A (en) | Automatic simple door machine and using method thereof | |
CN207748377U (en) | A kind of dustbin for environmental sanitation refuse vehicle promotes Tilting device | |
CN216190651U (en) | Leak dropping board maintenance with upset multi-function vehicle | |
CN203515607U (en) | Adjustable steel mould trolley of tunnel widening section | |
CN213896774U (en) | Self-moving splicing device for anti-collision wall construction formwork | |
CN206015534U (en) | The self-propelled running gear of cantilever box beam Hanging Basket | |
CN213203703U (en) | Cement stabilized macadam base rolling construction device | |
CN205022430U (en) | Self - discharging truck of environmental protection brick | |
CN105756580A (en) | Full-automatic tubing string arranging and transferring apparatus | |
CN220226915U (en) | Integrative platform truck of tunnel waterproof board reinforcing bar | |
CN204875395U (en) | Receive pillow device | |
CN215796274U (en) | Road bridge prefab handling device | |
CN220505065U (en) | Safety support trolley | |
CN210418123U (en) | Feeding and discharging trolley of flanging machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: 243000 no.2887, south section of Tianmen Avenue, Ma'anshan economic and Technological Development Zone, Anhui Province Applicant after: Anhui Keda electromechanical Co.,Ltd. Address before: 243000 555 north section of Ling Xiao Road, Ma'anshan economic and Technological Development Zone, Anhui Applicant before: ANHUI KEDA INDUSTRIAL Co.,Ltd. |
|
GR01 | Patent grant | ||
GR01 | Patent grant |